Comments of EDF Power Solutions, Inc. in response to the 60-Day Compliance Filing by PJM Interconnection, L.L.C. on 02/23/2026
Text extracted from the eLibrary original (SHA-256 0eb49a828c40e239…). Download the original from the official source.
Contents · 8 sections
- I. SUMMARY OF COMMENTS
- II. BACKGROUND
- III. COMMENTS
- A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG is
- B. For Retail BTMG Resources that Exceed the Materiality Threshold Size,
- C. Co-Located Retail BTMG Resources Must Be Permitted to Provide Ride-
- D. PJM’s Proposed Three New Transmission Services Should Be Accepted.
- IV. CONCLUSION
Read topic-matched comments in ER26-1479
Topics in the text: Reliability and curtailment · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. SUMMARY OF COMMENTS
printed heading · Topic match: Connecting load and generation
The Retail BTMG threshold should instead be based on 1 18 C.F.R. §§ 385.212, 385.213 (2025). 2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related to Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No.Read this passage Filed comments: Connecting load and generation
II. BACKGROUND
printed heading
Among other things, PJM proposes to adopt a revised definition of Retail BTMG to include a new 50 MW materiality threshold and to establish three new transmission service options for large loads. 3Read this passage
III. COMMENTS
printed heading
III.Read this passage
A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG is
printed heading · Topic match: Cost allocation
PJM proposes a materiality threshold of up to 50 MW for a new generator at the same electrical location as the Network Load to qualify for Retail BTMG.4 According to PJM, its proposed 50 MW threshold corresponds with the PJM Board’s definition of large load additions, which are individual loads of…Read this passage Filed comments: Cost allocation
B. For Retail BTMG Resources that Exceed the Materiality Threshold Size,
printed heading · Topic match: Cost allocation
PJM states that going forward any new large Retail BTMG that is greater than the proposed threshold would not qualify as Retail BTMG and that “a Retail BTMG cannot both net up to a certain threshold but still potentially have generation and load above that threshold which 7 Under the “beneficiary…Read this passage Filed comments: Cost allocation
C. Co-Located Retail BTMG Resources Must Be Permitted to Provide Ride-
printed heading · Topic match: Reliability and curtailment
PJM proposes that the Retail BTMG threshold excludes backup generation “at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or reliability of the PJM Region or the regional power system.”15 EDFps…Read this passage Filed comments: Reliability and curtailment
D. PJM’s Proposed Three New Transmission Services Should Be Accepted.
printed heading
PJM’s Proposed Three New Transmission Services Should Be Accepted.Read this passage
IV. CONCLUSION
printed heading · Topic match: Reliability and curtailment
To ensure the effectiveness and fairness of these proposals, PJM should (1) set a Retail BTMG materiality threshold that is based on 100% of the load; (2) allow a hybrid approach to netting of Retail BTMG resources that exceed the threshold; and (3) expressly permit co-located Retail BTMG and…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 16th day of March 2026. /s/ Emily Starobin Emily Starobin Husch Blackwell LLP 1801 Pennsylvania Ave.Read this passage