Comments of Invenergy Renewables LLC et al. in response to PJM Interconnection, L.L.C.’s Initial Brief in the Order to Show Cause Proceeding and Compliance…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
COMMENTS OF INVENERGY RENEWABLES LLC AND
INVENERGY THERMAL LLC
Invenergy Renewables LLC and Invenergy Thermal LLC (collectively, “Invenergy”) respectfully submit these comments in response to PJM Interconnection, L.L.C.’s (“PJM”) Initial Brief in the Order to Show Cause Proceeding,1 as well as PJM’s Compliance Filing submitted in Docket No. ER26-1479-000.2 Invenergy seeks clarification regarding the study processes for generator interconnection and transmission service, as well as the definition of Eligible Customer. The Show Cause proceeding is a needed first step to address the growing demand from manufacturing, data centers, and artificial intelligence. Invenergy applauds PJM for its considerable work to date and raises the following issues in the interest of crafting durable and workable rules for co-located generation and load.
Specifically, while the purpose of PJM’s multiple filings is to facilitate co-located projects,
1 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 (Feb. 23, 2026) (“Initial Brief”). 2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff, Docket No. ER26-1479-000 (Feb. 23, 2026) (“Compliance Filing”).
PDF page 2
2
PJM’s Initial Brief and compliance filings would continue to treat generator interconnection studies and transmission service studies for co-located projects as distinct processes operating on different timelines, rather than as a synchronized process that must be coordinated to finance and timely construct co-located projects. As Invenergy explained in its initial comments in Docket EL25-49, coordinating generator interconnection and transmission service studies can reduce systemwide costs by matching generation with load, resulting in a common set of network upgrades to accommodate both requests, and reduce the likelihood that uncoordinated study processes result in potentially unneeded network upgrades. Synchronizing the generator interconnection and transmission study processes would therefore provide practical benefits to developers, who could more easily finance and bring projects online more quickly, and save ratepayers money.
I. COMMENTS
A. PJM Should Adopt a Coordinated Study Process for Co-Located Loads and
Generation.
In response to the Commission’s directive to provide clear and consistent procedures for generation serving co-located load,3 PJM submitted tariff revisions to: (1) clarify the necessary study process for existing generation seeking to serve co-located load,4 (2) address the types of interconnection services generators may request, including provisional5 and surplus interconnection service,6 (3) clarify that generators may request interconnection service below
3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 226, 232, 233, 234 (2025) (“Replacement Rate Order”).4 See Compliance Filing at 24-28; id., Proposed Tariff, Parts III and VII.5 See PJM Interconnection, L.L.C., 30-Day Compliance Filing With Order on Show Cause at 2, 5-7, Docket No. ER26-1088-000 (Jan. 20, 2026) (“Interconnection Filing”); id., Proposed Tariff, Part I, section 1, Definitions – O – P – Q; id., Part VII, Subpart A, section 300, Definitions P; id., Part VIII, Subpart A, section 400, Definitions P.6 See Interconnection Filing at 2, 5; id., Proposed Tariff, Part VIII, Subpart A, section 401(C); id., Part VIII, Subpart E, section 414(A).
PDF page 3
3
their full maximum output,7 and (4) permit generators to use existing study processes to accelerate new service requests that do not have to pay for network upgrades.8 PJM in its Initial Brief has separately proposed the non-rate terms of service for the new firm contract, non-firm contract, and interim NITS transmission services, including the study processes for each.9
With limited exceptions,10 PJM’s filings perpetuate a bifurcated study process for generator interconnection and transmission service requests. There is no requirement that the studies be done in concert, on similar time frames, or using similar study assumptions. As a result, the distinct studies may identify duplicative or unnecessary network upgrades, and co-located generators and their associated load will each have to execute generator interconnection agreements or transmission service agreements without knowing the outcome of the other study process. A co- located generator could, for instance, be required to execute a generator interconnection agreement without knowing whether its associated load can get transmission service at all, much less the expected costs of any upgrades required to serve that load. Likewise, a co-located load may be required to contract for transmission service without knowing whether the associated generation will materialize. Given that PJM’s proposed transmission products in part anticipate co-located loads netting their co-located generation from their transmission service requests, the failure to coordinate these study processes may result in a cascade of restudies should load execute transmission service agreements only to discover that the associated co-located generator cannot
7 Interconnection Filing at 2, 4; id., Proposed Tariff, Part VIII, Subpart B, section 403(A)(1)(q); id, Part VIII, Subpart E, section 413; id., Part VIII, Subpart C, sections 404(A)(2)(a)(v), (A)(7).8 Interconnection Filing at 2, 5; id., Proposed Tariff, Part VIII, Subpart C, sections 406(A)(2), 408(A)(2)(d).9 Initial Brief at 5-13, 24-25, 30-31, 33-34, 66-68, 70-71.10 Generation customers must identify the Eligible Customer and type of transmission service in their interconnection agreements and study requests. See Proposed Tariff Revisions, Part VIII, Subpart A, section 401(H)(3)(b)(i) – (iii). The Eligible Customer must also identify details about the co-located generator in its transmission service request. See Proposed Tariff, Part XI, Subpart B, section 710.2(iii)-(iv).
PDF page 4
4
timely interconnect, or those loads will have to draw power exclusively from the grid, thereby stressing the system in exactly the manner this proceeding is intended to prevent.
Moreover, as a practical matter, few generation and load developers will be willing to
execute generator interconnection or transmission service agreements—and thereby commit tens, if not hundreds of millions of dollars, to develop a project—without knowing whether it has a reasonable prospect of moving forward; and the banks financing such projects will also be loathe to commit capital without reviewing both generator interconnection and transmission service study results articulating the expected cost of the project. The co-location study processes should be designed to limit uncertainty,11 not exacerbate it. Without reforms to coordinate these study processes, the benefits of co-location will never materialize at scale.
Beyond these practical realities, coordinating interconnection and transmission service
studies will enhance reliability and make more efficient use of the transmission system. If transmission service and generation interconnection are studied under two separate processes, they could use a different set of study assumptions, models, and timelines, and therefore may each identify network upgrades that would not be necessary were these processes coordinated.
Synchronizing the two study processes therefore comports with FERC’s goals of promoting
11 Replacement Rate Order at PP 225-29, 231-35 (directing PJM to revise generator interconnection processes for co-located load in order to “clarify” the steps necessary to effectuate co-location arrangements); see Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054, at P 18 (2023) (“Order No. 2023”) (describing FERC’s interconnection goals to “establish a faster and more efficient interconnection queueing process, and promote a more efficient and cost-effective allocation of network upgrade costs”); e.g. cf. EDF Renewable Energy, Inc. v. MISO, 168 FERC ¶ 61,173, at P 20 (2019) (finding the lack of transparency in affected system studies coordination processes resulted in cost uncertainty, presenting a “significant obstacle to the development of new resources” and “hinder[ing] the timely development of new resources”, which resulted in an unjust and unreasonable tariff); see also N. Indiana Pub. Serv. Co., 155 FERC ¶ 61,058, at P 60 (2016) (directing PJM and MISO to inform stakeholders on how transmission planning in each region interacts, which will improve coordination and reduce risks like planning and financing, thereby increasing the likelihood that the projects successfully navigate the study process and get built).
PDF page 5
5
efficiency and speed,12 and the Show Cause proceeding’s directive to enhance the clarity of the co-location processes.13
Although the Commission did not require PJM to combine transmission service and interconnection studies into a single queue, coordination between the two processes is necessary to effectuate the co-location arrangements contemplated by the Show Cause Order and Replacement Rate Order. Invenergy therefore requests that the Commission and PJM clarify as part of this proceeding how such transmission and generator interconnection study processes, including the study processes for interconnecting new generation and modifying existing generation, can work in tandem to provide the certainty to generators and load that is necessary to ensure these processes work as the Commission intended.
B. Eligible Customer Definition As Applied Should Be Clarified.
Consistent with the pro forma Open Access Transmission Tariff, PJM’s Tariff defines Eligible Customer:
(i) Any electric utility (including any Transmission Owner and any power marketer), Federal power marketing agency, or any person generating electric energy for sale for resale is an Eligible Customer under the Tariff. Electric energy sold or produced by such entity may be electric energy produced in the United States, Canada or Mexico. However, with respect to transmission service that the Commission is prohibited from ordering by Section 212(h) of the Federal Power Act, such entity is eligible only if the service is provided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner.
(ii) Any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission
Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner, is an Eligible Customer under the Tariff. As used in Tariff, Part VI, Eligible Customer shall mean only
12 See Order No. 2023, 184 FERC ¶ 61,054 at P 18.13 Replacement Rate Order, 193 FERC ¶ 61,217 at PP 225, 231.
PDF page 6
6
those Eligible Customers that have submitted a Completed Application.14
Invenergy seeks confirmation on how the Commission and PJM view this definition when applied to the co-located generator and co-located load. In Order No. 888, the Commission noted that Eligible Customers could include municipal utilities, cooperatives, investor-owned utilities, independent power producers, and qualifying facilities, among others.15
While the Commission cannot mandate wheeling directly to end-use customers under Section 212(h) of the FPA, the Commission has determined that its jurisdiction extends to all unbundled transmission in interstate commerce by public utilities.16 Thus, as provided in the definition of Eligible Customer, where a state retail choice program results in unbundled retail access, customers may take transmission service as an Eligible Customer.17 It is therefore Invenergy’s understanding that a co-located load could qualify as an Eligible Customer in a retail choice jurisdiction. In addition, Invenergy seeks clarity on the following questions:
(1) In the context of co-location arrangements, would a co-located generator
qualify as an Eligible Customer on behalf of the co-located load?
(2) Does a co-located generator’s status as an Eligible Customer depend on whether the co-location arrangement is in a jurisdiction that has mandated retail choice?
II. CONCLUSION
Invenergy respectfully requests that PJM and the Commission consider these comments and make such adjustments as necessary to ensure just and reasonable rates, terms, and conditions for co-located arrangements.
14 Tariff, Part I, section 1, Definitions – E – F.15 Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,688 (1996).16 Id. at 31,689.17 Id.
PDF page 7
7
Respectfully submitted,
March 16, 2026
/s/ Tyler O’Connor
Tyler O’Connor
Kathryn Douglass
Crowell & Moring LLP
1001 Pennsylvania Avenue, NW
Washington, DC 20004
202-624-2500
toconnor@crowell.com
kdouglass@crowell.com
William Borders
Executive Vice President, Legal & Chief
Compliance Officer
Invenergy
One South Wacker Drive, Ste. 1500
Chicago, IL 60606
wborders@invenergy.com
Counsel for Invenergy Renewables LLC
and Invenergy Thermal LLC
PDF page 8
8
CERTIFICATE OF SERVICE
I hereby certify that on this 16th day of March, 2026, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding.
/s/ Kathryn Douglass
Kathryn Douglass
Crowell & Moring LLP
1601 Wewatta Street, Ste. 815
Denver, CO 80202
kdouglass@crowell.com