ER26-1479-000 · 2026-03-16 · Energy Artisans, LLC

Comments of Energy Artisans, LLC re PJM Interconnection, L.L.C. Compliance Filing submitted on 02/23/2026

PDF page 1

1
8060 Main Street
Ellicott City, MD 21043
866-95-ENERG (36374)
Protest re: PJM Interconnection, L.L.C. Compliance Filing (Docket No. ER26-1479-000)
Date of Filing: February 23, 2026
Subject: Co-Located Load Related Revisions to Open Access Transmission Tariff
Introduction
Energy Artisans ("EA") is an established membership organization formed in 2017 that is comprised of industry experts to serve various client needs.  The group is anchored by individuals who have decades of energy market experience in general purchasing, wholesale and behind-the-meter power plant development and operation, as well as bulk and retail energy delivery, fuel purchasing and delivery, efficiency measures, and direct participation at the membership and stakeholder level in PJM.

EA respectfully submits these formal comments in protest of the Compliance Filing submitted by PJM Interconnection, L.L.C. ("PJM") on February 23, 2026. While PJM ostensibly seeks to address reliability and resource adequacy risks pursuant to the Commission’s December 18, 2025, Order to Show Cause, the proposed revisions to the Open Access Transmission Tariff ("OATT") represent a fundamental misalignment of cost and benefit.

PJM’s filing attempts to solve reliability concerns by imposing an untenable economic environment upon commercial and industrial (C&I) users through restrictive materiality thresholds and discriminatory study requirements. As currently structured, PJM’s proposal is unjust, unreasonable, and unduly discriminatory under Section 206 of the Federal Power Act. Consequently, EA urges the Commission to reject these revisions to ensure that the region’s C&I backbone does not suffer detrimental and unintended consequences for administrative convenience.

1. Evaluation of Negative Economic Impact on Commercial and Industrial Users
The proposed revisions to the Behind the Meter Generation ("BTMG") rules threaten the foundational economic stability of the PJM region. For over twenty years, C&I facilities have operated under BTMG netting rules to optimize energy efficiency and manage operational costs. PJM’s proposal to implement a 50 MW "Materiality Threshold" for Retail BTMG is an arbitrary cap that ignores the long-term, capital-intensive investment cycles of large-scale industrial facilities. By capping the ability to net at 50 MW, PJM effectively strangles the growth of high-efficiency industrial sites that were financed on the premise of netting on-site generation against total load. The financial implication of this 50 MW cap for two C&I clients we have managed would be between $7MM and $36MM/annually.  These are representative of impacts on various other clients, and are not inconsequential to their overall costs.

The financial burden is further exacerbated by the "Necessary Study Process" described in this filing. PJM seeks to force "Project Developers" (industrial users) to fund exhaustive thermal, short circuit, and stability studies. Beyond these administrative costs, the filing mandates that users bear the full expense of: Network Upgrades, identified during the study process; Complex Control Technologies and Protection Systems, allegedly required to prevent "unauthorized grid withdrawals"; and Redundant Metering Equipment necessitated by PJM’s refusal to adopt a more flexible regulatory approach.  All this for systems on end users’ property supplying their electric usage requirements.  This is a breach of fundamental privacy, and such rules are not applicable to other alternative fueled systems that provide onsite work which is backed up by potential electric use should those systems fail.

PDF page 2

2
8060 Main Street
Ellicott City, MD 21043
866-95-ENERG (36374)
Strategic Implications of the Economic Burden:
•
De Facto Penalty on Efficiency: These costs function as a punitive tax on cogeneration and Qualifying Facilities ("QFs") protected under the Public Utility Regulatory Policies Act ("PURPA"). By making it administratively and financially impossible for large QFs to operate under the new OATT, PJM undermines the economic and energy efficiency benefits inherent in waste heat recovery.

•
Forced-Exit Strategy: PJM’s rejection of a hybrid approach—which would allow facilities to net up to a threshold—on the grounds that it is cost-prohibitive is a tacit admission. PJM is essentially acknowledging that its all-or-nothing requirement is a deliberate barrier to entry designed to force large loads off of BTMG status and onto the grid.

•
Stranded Assets: Forcing decades-old facilities to undergo modern "Necessary Studies" and install previously unnecessary metering will cause many to cease operations, leading to higher Network Loads and exacerbating the resource adequacy issues PJM claims to mitigate.

2. Argument Against Discriminatory Treatment
The filing represents a clear violation of the Federal Power Act’s requirement for just and reasonable rates due to its discriminatory application. PJM establishes a 50 MW cumulative nameplate cap for "Retail BTMG" (C&I users) while maintaining a massive 3,000 MW regional cap for "Non-Retail BTMG" (municipal and cooperative systems).. Furthermore, PJM’s manipulation of the legal boundary of the site is a transparent attempt to restrict BTMG eligibility. In its filing, PJM aggressively defends the use of the Point of Change in Ownership (“PCO”) rather than the Point of Interconnection (“POI”). This technical shift is strategically designed to shrink the legal definition of the facility boundary, thereby capturing more load for grid-service billing and excluding it from the BTMG actual use category.

PJM’s filing admits that many of these industrial configurations have "been in existence without noted impact for decades". This admission renders the sudden imposition of the 50 MW cap and restrictive PCO definitions arbitrary. If no impact has been noted for twenty years, the reliability risk is clearly a manufactured pretext for cost- shifting.  We have had direct experience with customers whose BTMG was as large as 150 MW behind loads in excess of 200 MW with no adverse impacts.

3. Proposed Alternative: 200 MW Threshold and Interruptible Transmission Service
A constructive alternative exists that balances grid integrity with the industrial sector's operational reality. The PJM ICC advocates for an Interim/Alternative Materiality Threshold of 200 MW, anchored in the Actual Use principle. Prior to data centers there have been many large industrial loads with correspondingly large BTMG.  As established in the PJM ICC Request for Rehearing/Clarification in Docket EL25-49, filed on January 20, 2026, and supported by the C&I clients we represent and our direct experience, the 200 MW threshold is a far more practical solution for existing industrial and institutional loads that have long relied on their on-site investments to manage electric and other commodity costs efficiently.  For sites exceeding this 200 MW threshold, the Commission should direct PJM to utilize the proposed "Interim Network Integration Transmission Service" (Interim NITS) under the new Part XI of the Tariff. This service is non-firm and interruptible, providing PJM with the operational safety switch it needs to manage reliability during peak emergencies without forcing cost-prohibitive upgrades or complete disconnection on industrial users.  There is a corollary in natural gas: firm and interruptible service.  It is critical that interruptible gas customer cease using gas when instructed by the applicable pipeline or utility system.  Failure to do so results in extreme financial penalties and the offending customer may even be shutoff if system integrity is

PDF page 3

3
8060 Main Street
Ellicott City, MD 21043
866-95-ENERG (36374)
compromised.  We fail to see any reason why large customers above this threshold could not have an automatic shutoff of electricity for failure to comply.  In fact, numerous smaller systems and sites have been subject to transfer- trip schemes for similar reasons for decades.

Comparison: PJM Proposal vs. Industrial Alternative
Feature
Current PJM Proposal (50 MW Limit)
Industrial Alternative (200 MW +
Interruptible Tier)
Reliability
Impact
High risk of forcing efficient units offline;
increases firm demand.
Maintains stability via Interim NITS (Part XI)
for largest users.
Capital Cost to
User
Extreme; requires Network Upgrades and
redundant metering.
Minimal; grounded in the "Actual Use"
principle for existing sites.
Grid Flexibility Rigid "all or nothing" approach; forced grid-
dependency.
High; utilizes non-firm, interruptible service for
peak management.
Regulatory
Baseline
Ignores PURPA efficiency and 20-year
investment cycles.
Protects QF status and manufacturing
competitiveness.
Appeal for Commission Action
PJM has fundamentally failed to prove that a 50 MW threshold is the least cost or most equitable way to manage co-located load, especially while exempting municipal entities from similar constraints. We implore the Commission to summarily reject the February 23 Compliance Filing. At a minimum, the Commission should stay its implementation and direct a formal paper hearing to:

1. Evaluate the 200 MW threshold based on the "Actual Use" principle;
2. Mandate the inclusion of an interruptible tier using Interim NITS for all large loads;
3. Reject the restrictive "Point of Change in Ownership" definition as an arbitrary shrinking of the site boundary; and

4. Enforce PURPA protections for cogeneration facilities that PJM seeks to penalize. The Commission cannot allow PJM to undermine the industrial backbone of the region through arbitrary caps and protectionist barriers.

Respectfully submitted,

H. Bertram Wilson, CFA
Managing Director