Protest of Vistra Corp. to PJM Interconnection, L.L.C.'s 02/23/2026 compliance filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.LC.
)
)
)
)
)
Docket No. ER26-1479-000
PROTEST OF VISTRA CORP.
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) hereby submits this protest to PJM Interconnection, L.L.C.’s (“PJM”) compliance filing filed on February 23, 2026, in the above- captioned docket.2 On December 18, 2025, this Commission issued a landmark Order on Show Cause Proceedings,3 which established a clear and principled roadmap for the development of co- located facilities in PJM in a manner that ensures both the reliability and affordability of the PJM system. The Commission’s order clearly delineated a path for enabling the expeditious development and interconnection of co-located facilities. This action was a critical step toward facilitating the development of digital infrastructure in PJM—the single most important region of the country for data centers and the other infrastructure necessary to develop and maintain our world-leading artificial intelligence capabilities.
Accepting PJM’s compliance filing would be a step backward from the progress made in that order. Where the Commission required clarity, PJM has proposed ambiguity by failing to propose
1 18 C.F.R. § 385.211 (2026).2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26- 1479-000 (filed Feb. 23, 2026) (“PJM Compliance Filing”).3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Order on Show Cause Proceedings”).
PDF page 2
- 2 -
a clear transition mechanism to apply to the facilities that have diligently pursued and, in some cases, completed, the necessary study process. Similarly, where the Commission mandated speed, PJM has chosen delay, by proposing a June 1, 2029 effective date for the new transmission services and a revised necessary study process that would appear to not even begin until 2029—a lifetime when it comes to digital infrastructure. Collectively, these two elements, unless changed, could delay integration of co-location configurations until the early 2030s. And where the Commission required pragmatism, PJM has responded with a truly byzantine proposal for Capacity Interconnection Rights (“CIRs”) that is clear as mud and appears likely to limit backup resources’ ability to support resource adequacy where they can. To realize the potential of the December Order, the Commission should direct PJM to file a further compliance that resolves these fundamental flaws, as discussed further below.
I. PJM Has Not Demonstrated That the Proposed Revisions to the Necessary Study
Process Are Just and Reasonable
In its Order on Show Cause Proceedings, the Commission found the PJM tariff is unjust and unreasonable because it lacks sufficient clarity and consistency regarding how interconnection customers can serve co-located load using existing generating facilities.4 As a remedy, the Commission directed PJM to clarify that the necessary study process can facilitate the addition of co-located load behind the meter of an existing generating facility, and to propose tariff revisions to more clearly describe that process and the scope of the analysis PJM performs in such instances.5 PJM’s tariff revisions therefore must provide sufficient clarity and transparency on the steps
4 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 225.5 Id. PP 226-27. The Commission directed PJM to describe the information that the interconnection customer must provide about the co-located load for purposes of the necessary study. Id. P 227.
PDF page 3
- 3 -
needed for an existing generator to serve co-located load to remedy the unjust and unreasonable ambiguity in PJM’s tariff.6
PJM’s proposal falls well short of providing the clarity necessary to remedy PJM’s tariff in several respects. Specifically, PJM’s proposal does not: (a) contain a transition mechanism or otherwise address necessary studies that are already in progress or completed; (b) specify how PJM will calculate and study changes to CIRs; or (c) explain why existing customers with older interconnection agreements must sign an entirely new version of interconnection agreement before serving co-located load. Rather than adding clarity, PJM’s proposal introduces new sources of ambiguity that will cause additional delays and further hinder efforts to add co-located load and power digital infrastructure in PJM.
A. PJM’s Proposal Fails to Include a Transition Mechanism for Customers
Already in the Necessary Study Process
Although some existing generators have worked diligently to pursue co-location arrangements with large load customers via PJM’s existing necessary study process, PJM’s proposal would ignore those efforts altogether and press reset on significant commercial opportunities for large load customers. Indeed, PJM’s proposal does not acknowledge that some existing generators have already executed necessary study agreements and even received study results, much less address whether and how the proposed tariff revisions apply to such customers.
6 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 229.
PDF page 4
- 4 -
This is a critical issue in this proceeding, given the Commission’s emphasis on facilitating speed to power,7 and PJM’s replacement rate must directly address that issue to pass muster.8 Without any clear transition mechanism, PJM’s proposal could be read to require parties that have completed the necessary study process to restart that process entirely. In this way, PJM’s proposal will create further delays for parties that have already sought to pursue co-location arrangements because those parties will have no way to preserve in-progress or completed necessary studies. Such delays are not only unnecessary but simply incompatible with the nation’s urgent need for computing power. That result is also incompatible with the Commission’s Order on Show Cause Proceedings, which indicated that this compliance filing should memorialize PJM’s existing approach to necessary studies, but that any “enhance[ment]” to the necessary study process should occur in a future section 205 filing.9 There should be no need for parties that are already in the necessary study process to start over if the tariff revisions at issue here are limited to complying with the Commission’s directives. Furthermore, requiring generators with executed necessary study agreements to restart the process violates the rights of those existing generators that relied on the existing rules to pursue facility modifications for co-location opportunities.10
Further, by failing to provide a transition mechanism, PJM’s proposal represents an unexplained and unjustified departure from the Commission’s customary approach to
7 See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 200 (acknowledging that co-location arrangements can allow existing generating facilities to begin serving new large co-located loads rapidly and directing PJM to create a new interim, non-firm transmission service to facilitate more rapid interconnection and operation of co-located loads); see also id. (Rosner, Comm’r, concurring at P 11) (discussing how the new interim transmission service leverages speed).8 See Affirmed Energy, LLC v. FERC, 166 F.4th 1070,1079 (D.C. Cir. 2026) (“An agency’s decision is arbitrary and capricious if the agency entirely fails to consider an important aspect of the problem before it or ignores the reasonable reliance interests of regulated parties.”).9 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 227.10 PJM Power Providers Grp. v. FERC, 96 F.4th 390, 400 (3d Cir. 2024) (“P3”) (explaining that the Commission may not take actions that alter the legal consequences attached to past actions).
PDF page 5
- 5 -
interconnection reforms, in which the Commission regularly requires transition mechanisms to avoid disruption and stranded capital investments. Most recently, in Order No. 2023, the Commission required transmission providers to (i) tender an interconnection agreement to any customer that had received a final facilities study report before commencing transitional studies, 11 and (ii) allow late-stage interconnection customers that had already been tendered a facilities study agreement to opt to continue under a serial study process.12 The Commission explained that doing so appropriately respected the investments and expectations of interconnection customers at an advanced stage in the existing process.13 And the Commission has consistently employed these types of transition mechanisms since it first created the standardized interconnection procedures in Order No. 2003, where the Commission allowed interconnection customers with executed study agreements to choose to continue under those existing processes or transition processes.14 Given the Commission’s longstanding approach to interconnection reform, PJM’s
compliance proposal is flawed. PJM does not justify its failure to include a transition mechanism, let alone acknowledge that there are generators with executed necessary study agreements on file with the Commission. Thus, PJM has not provided the Commission with the justification it would need to accept PJM’s proposal and depart from precedent requiring a transition mechanism for
11 Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054, at P 865, order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024)).
12 Order No. 2023, 184 FERC ¶ 61,054 at PP 855, 865.13 Id. P 856.14 Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103, at P 186 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007); see also Midcontinent Indep. Sys. Operator, 164 FERC ¶ 61,234, at P 21 (2018); Midcontinent Indep. Sys. Operator, 158 FERC ¶ 61,003, at PP 45, 59 (2017); Midcontinent Indep. Sys. Operator, 166 FERC ¶ 61,187, at P 107 (2019); Sw. Power Pool, Inc., 167 FERC ¶ 61,275, at PP 19, 39 (2019); PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P 60 (2022).
PDF page 6
- 6 -
interconnection reforms.15 And by failing to include a transition mechanism that respects executed necessary study agreements on file with the Commission, PJM’s proposal appears to render those filed agreements a nullity, in violation of the filed rate doctrine.16
Requiring generators with executed necessary study agreements on file with the
Commission to restart the entire process would undermine the central goal of this proceeding: to expeditiously facilitate the co-location of generation and load in PJM.17 And the delay caused by requiring generators to restart the necessary study process is further compounded by the fact that PJM is seeking a June 1, 2029 effective date for the new transmission services, and will seek a corresponding effective date for the revisions at issue in this proceeding.18 As Vistra will describe
15 See F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“An agency may not . . . depart from a prior policy sub silentio or simply disregard rules that are still on the books. And of course the agency must show that there are good reasons for the new policy.” (citations omitted)). In the Order on Show Cause Proceedings, the Commission indicated that PJM should formalize and clarify its existing necessary study process rather than make substantive changes. See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 227. To the extent PJM is seeking to make wholesale substantive changes to the necessary study process, such as by requiring generators that have already completed the process to start the process again, it must propose such changes in a future section 205 proceeding rather than in this docket. See id. (“To the extent that PJM seeks to enhance the necessary study process . . . PJM may submit such enhancements in an FPA section 205 filing.”).16 The filed rate doctrine “bind[s] regulated entities to charge only the rates filed with FERC and to change their rates only prospectively.” Okla. Gas & Elec. Co. v. FERC, 11 F.4th 821, 829 (D.C. Cir. 2021). It applies not just to rates, but also to matters directly affecting rates. P3, 96 F.4th at 394. Existing necessary study agreements on file with the Commission are filed rates for purposes of the filed rate doctrine, and those agreements state that their terms cannot be changed without the consent of the parties. See, e.g., PJM SA No. 7476, Necessary Studies Agreement between PJM and LSP Digital (0.0.0), § 21 (“This Agreement, or any part thereof, may not be amended, modified, or waived other than by a writing signed by all Parties.”). Were PJM to require parties with existing necessary study agreements to enter new agreements, this would impermissibly alter the legal consequences that attached when those parties initially filed executed necessary agreements with the Commission. See P3, 96 F.4th at 394. And nullifying necessary study agreements would be patently unfair, as parties that have already paid for necessary studies would have to pay a second time for the same studies.17 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 200 (“[T]o facilitate more rapid interconnection and operation of Co-Located Loads . . . . [W]e direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to create a new interim, non-firm transmission.”)); Order on Show Cause Proceedings, 193 FERC ¶ 61,217 (Chang, Comm’r concurring at P 3) (explaining that the “order represents the first step to developing a package of solutions to address co-location in the PJM footprint” and that the Commission “will assess how [the] rates, terms, and conditions facilitate the efficient interconnection of co-located loads”).18 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000 et. al, at 79 (filed Feb. 23, 2026) (“PJM Paper Hearing Initial Brief”). In this proceeding, PJM proposed a 12/31/9998 effective date, which it indicated it will update to align with the effective date set in the paper hearing. PJM Compliance Filing at 35.
PDF page 7
- 7 -
further in its paper hearing brief, PJM has not shown that this lengthy delay is just and reasonable. PJM’s attempts to defend that delay based on its capacity market schedule and the need for software updates are unpersuasive. First, the 3-year forward capacity market schedule cannot justify a delay in the provision of non-firm, non-capacity backed transmission products. The capacity market schedule should not delay the provision of firm transmission products either, for that matter, given that the forecasts used in the 2027/2028 and 2028/2029 BRAs included the new large loads that are likely to come online in that timeframe.19 Second, PJM has not explained why it will take until 2029 to update its software to accommodate the new curtailment logic—or why it cannot provide a transition process in the meantime to serve customers that agree to not pull energy from the grid and therefore will not need to be curtailed.
Compounding the delay, PJM indicated that it will seek a corresponding effective date for the tariff revisions in this proceeding,20 meaning that PJM’s new necessary study procedures and new pro forma necessary study agreement would not be effective until halfway through 2029. That means that customers may need to wait until 2029 to even submit a request to begin the new necessary study process. Moreover, the pro forma necessary study agreement sets forth a study timeline of 270 days, with no consequences for study delays.21 In other words, between the study process itself and the construction of any necessary network upgrades, it is likely that no existing
19 PJM determines how much capacity to procure based on a forecast of future demand, which includes an adjustment that specifically accounts for new large loads like data centers. PJM, Load Forecast Development Process, Forecast & Reports, Long-Term Load Forecast Tables, at B-9b (Feb. 6, 2026), https://www.pjm.com/- /media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx (showing load adjustments to 2026 load forecast resulting from large load growth in transmission owner territories); see also PJM, 2026 PJM Load Forecast Report, at 5 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load- forecast/2026-load-report.pdf.20 PJM Compliance Filing at 35.21 Id., Attach. A (Revisions to the PJM Open Access Transmission Tariff) at Part IX, Subpart G (Form of Necessary Studies Agreement), § 5 (“Proposed Tariff Revisions”).
PDF page 8
- 8 -
generator could add co-located load under PJM’s proposed process until 2030 or 2031. PJM’s proposal is, in effect, a 3- to 5-year moratorium on co-locating large loads with existing generators. That kind of delay in powering digital infrastructure—via the service option (i.e., co-location) that will bring speed-to-power faster than any other—is both unnecessary and directly contrary to the Administration’s efforts to ensure that the nation “has the power needed to win the global artificial intelligence [] race while continuing to meet growing demand for affordable, reliable and secure energy.”22
B. PJM Has Not Demonstrated That Its Proposal for Delisting CIRs Is Just,
Reasonable, and Not Unduly Discriminatory, or That It Is Consistent with the
Commission’s Compliance Directives
In the Order on Show Cause Proceedings, the Commission explained that “an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its CIRs for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving NITS.”23 The Commission also directed PJM to propose tariff revisions to clarify how the necessary study process works, including with regards to CIR reductions.24 While PJM claims that its proposed tariff revisions “promote clarity” by memorializing this directive,25 PJM’s proposed language, in fact, perpetuates the very ambiguity that the Commission found renders the tariff unjust and unreasonable.26 PJM would require existing generators that seek to add co-located load to submit to PJM “the amount of reduction to Capacity
22 Press Release, Dep’t of Energy, Energy Department Launches Speed to Power Initiative, Accelerating Large- Scale Grid Infrastructure Projects (Sept. 18, 2025), https://www.energy.gov/articles/energy-department-launches- speed-power-initiative-accelerating-large-scale-grid.23 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 230 (emphasis added).24 Id. P 226.25 PJM Compliance Filing at 26 n.83.26 See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 175.
PDF page 9
- 9 -
Interconnection Rights to facilitate the Co-Located Load configuration.”27 PJM’s necessary study will then “assess the impact of the reduction in Capacity Interconnection Rights.”28 But PJM does not explain how a generator should calculate the amount of the reduction of its CIRs, nor does it clarify how PJM will assess the impact of that reduction. Without these critical details, PJM’s tariff remains ambiguous—the exact issue the Commission sought to remedy in this proceeding.
1. PJM’s Proposal Is Impermissibly Vague Regarding How to Calculate
CIR Reductions and Could Be Interpreted in an Unduly
Discriminatory Manner
PJM has failed to address the Commission’s directive to “clarify its interconnection
procedures and agreements to ensure that it is clear to both new and existing Interconnection Customers how to interconnect in a Co-Location Arrangement.”29 Instead, PJM’s proposal would require existing generators to provide PJM with “the amount of reduction to Capacity
Interconnection Rights to facilitate the Co-Located Load configuration,” a mandate that is
inappropriately vague and could potentially be read to sweep far too broadly.30 Concerningly, PJM’s revisions could be read to require generators to include in their CIR reduction calculation any portion of a facility that will ever provide power to a co-located load. That would mean that
27 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)(b)(i)(c). PJM identifies the language memorializing the Commission’s directive as located in “proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.a – b.” PJM Compliance Filing at 26 n.83. PJM’s proposed revisions do not include changes to Part VII of the tariff. We assume PJM intended to reference Part VIII, but if that is the case, PJM must clarify as much in a future filing.28 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)(b)(ii).29 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 161 (emphasis added). PJM’s Paper Hearing Initial Brief attaches illustrative tariff language that states, “[t]he Eligible Customer must designate the individual Co- Located Generating Facility that will serve the individual Co-Located Load . . . and provide the megawatt level of energy from the Co-Located Generating Facility dedicated to serving the Co-Located Load.” PJM Paper Hearing Initial Brief, Attach. A, Illustrative Language for New Tariff, Part XI, Subpart B, section 711.1. PJM does not mention the illustrative language in this proceeding, but even if PJM intended for the illustrative language to guide calculation of the CIR reductions, which is something PJM has not indicated, it would not cure the ambiguity in PJM’s proposed revisions because the language does not explain what it means to be “dedicated to serv[e]” co-located load.30 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)(b)(i)(c).
PDF page 10
- 10 -
a two-unit generator using one 50 MW unit to serve co-located load and one 50 MW unit to serve the grid while providing occasional, interruptible backup service to the co-located load would need to delist 100 MWs of CIRs. In other words, PJM’s proposal could potentially treat this two-unit configuration the same as a generator that serves 100 MW of co-located load, despite the fact that each configuration provides different amounts of capacity to the grid. And if read in that manner, PJM’s proposal could require generators to delist more CIRs than those associated with the “portion” of the facility that is actually dedicated to providing firm service to a co-located load. Clarity is needed to ensure that the tariff language is not read in such a broad manner. A broad reading that would require units that provide only occasional, interruptible energy to co- located load to delist their CIRs would deprive ratepayers of generation that is generally available to serve the grid when needed and risk unnecessarily increasing capacity prices. Allowing secondary units providing occasional, interruptible service to co-located load to retain their CIRs would also be consistent with other requirements in the PJM tariff. PJM’s capacity market must- offer rules excuse generators with a “financially and physically firm commitment to an external sale of [their] capacity” from the obligation to offer capacity into PJM’s market. 31 No such exception applies for generators with a non-firm commitment to sell outside of PJM. By distinguishing between firm and non-firm sales, PJM’s tariff recognizes that firm energy sales pose unique concerns for capacity market commitments, while generators providing non-firm energy sales can be expected to perform in the capacity market. The same distinction applies to generators that serve co-located loads: primary units that provide firm energy to a co-located load clearly
31 PJM Interconnection L.L.C., Open Access Transmission Tariff, Attach. DD.6, § 6.6 (Offer Requirement for Capacity Resources) (3.0.0), §§ 6.6 (a), (g); see also PJM Interconnection L.L.C., Constellation Request for Clarification or, in the Alternative, Rehearing, Docket Nos. EL25-49-000 et. al, at 4 (filed Jan. 20, 2026).
PDF page 11
- 11 -
cannot also provide capacity, but secondary units that provide only occasional, interruptible energy to co-located load can.
It would also be unduly discriminatory to require secondary units that occasionally serve co-located load on an interruptible basis to delist their CIRs. As PJM recently explained, it allows generators that export energy outside of PJM on a non-firm or recallable basis to function as capacity resources.32 Those resources must still comply with their capacity obligations, including the requirement to bid into the day-ahead market.33 But where the generator is not committed in the day-ahead market, they are not required to “sit idle.”34 Interruptible backup units in a co- located configuration should receive the same treatment. As Vistra has previously explained, secondary units that occasionally provide interruptible back-up service to a co-located load can fulfill capacity obligations and be expected to perform when needed.35 Indeed, there are commercial arrangements and associated energy offer rules that would allow such units to both be available to serve the grid during emergency conditions, while also serving as a back-up to the co- located load. There is no principled basis to treat an interruptible backup unit in a co-located configuration differently from recallable exports. But PJM’s proposal for calculating CIR reductions could do just that, if read too broadly. The Commission should reject vague tariff
32 See PJM Interconnection, L.L.C., Mot. For Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. EL25-49-000, at 6 (filed March 9, 2026).33 Id.34 Id. (citing PJM Interconnection, L.L.C., 139 FERC ¶ 61,057, at P 205 (2012)).35 As Vistra has further explained, secondary backup units are more suited to capacity market participation than the reliability must-run resources that the Commission recently approved to participate on the basis that they “can be reasonably expected to perform.” PJM Interconnection L.L.C., Comments of Vistra Corp., Docket No. EL25-49- 000, at 30-31 (filed Apr. 23, 2025) (“2025 Vistra Comments”) (citing PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 47 (2025)).
PDF page 12
- 12 -
language that could be read in an unduly discriminatory manner and could artificially restrict capacity in PJM.
Finally, as a matter of policy, there is simply no reason to ignore the valuable contribution of back-up units that only occasionally serve co-located load, as capacity resources that help the region achieve its resource adequacy needs. Ignoring those MWs will force PJM to procure additional MWs that truly are not needed and will ultimately add significant costs for ratepayers.
2. PJM Does Not Explain How It Will Study the Impact of a Reduction
in CIRs
PJM’s necessary study process aims to “determine whether a planned modification . . . will have a permanent material impact on the Transmission System.”36 While some of PJM’s proposed revisions are consistent with that aim, PJM’s proposal also indicates that PJM will “assess the impact of the reduction in CIRs associated with the Co-Located Load and Co-Located Load Generating Facility,”37 which could be interpreted to expand the scope of the necessary study process beyond what it is designed to consider. By failing to explain how it will “assess the impact of the reduction of CIRs,” PJM appears to provide itself discretion to improperly shoehorn resource adequacy considerations into the necessary study process. Vistra does not believe it is PJM’s intent to incorporate a resource adequacy assessment into its necessary study process, as such would be both inconsistent with its long-standing practice for conducting such studies, and FERC’s December Order. But PJM’s filing has introduced unnecessary ambiguity, and clarity is needed.
Studying resource adequacy in the necessary study process would be inconsistent with the purpose of the necessary study process, which is designed to evaluate the impacts of a change to
36 PJM Compliance Filing at 27 n.87. 37 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3).
PDF page 13
- 13 -
an interconnection on the transmission system. Its goal is to address engineering concerns and identify transmission network upgrades needed to accommodate the modification, not address PJM-wide policy issues beyond the scope of interconnection service. And it is unclear how PJM would have the authority to consider resource adequacy issues in the necessary study process given that PJM cannot require a generator to sell its capacity into PJM’s market.38
It would also be unduly discriminatory to consider resource adequacy in the necessary
study process for existing generators that are required to delist CIRs but not for other similarly situated interconnection customers, because resource adequacy considerations associated with large load interconnection are not unique to co-location.39 For example, a retiring generator would have the same impact on capacity prices as a generator that delists CIRs to serve co-located load because the capacity market would incorporate either change as a shift in the supply curve. Similarly, a new large load seeking to co-locate would have a similar (but lower) capacity price impact as a new large load seeking to connect in front-of-the-meter.40 In both cases, the retiring generator and front-of-the-meter large load would impact capacity prices in a manner similar to a generator seeking to co-located as load, such that these entities are all similarly situated with respect to their impact on the capacity market.41 It would therefore be unduly discriminatory to
38 See PJM Interconnection, L.L.C., 178 FERC ¶ 61,121, at P 97 (2022) (“If a seller deems PJM’s capacity market rules undesirable, it can elect to pursue selling its capacity through other avenues, including via bilateral contracts within PJM, external sales outside of PJM, and other arrangements.”).39 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 85 (2025) (“Show Cause Order”); see also 2025 Vistra Comments, Attach. A, Affidavit of Dr. Roy J. Shanker, PhD, at 21 (“2025 Shanker Affidavit”) (“Without reason, many people assume that if there were no co-location, the co-located load would not exist. There is no reason to make this assumption.”).40 2025 Shanker Affidavit at 34.41 See N.Y. Indep. Sys. Operator, 162 FERC ¶ 61,124, at P 10 (2018) (“To say that entities are similarly situated does not mean that there are no differences between them; rather, it means that there are no differences that are material to the inquiry at hand.”). In fact, the front-of-the-meter load would have a larger impact on capacity prices because
PDF page 14
- 14 -
consider resource adequacy only for the interconnection of co-located load and not for these other scenarios that have a similar (or more significant) impact on capacity prices.
C. PJM Has Not Justified the Requirement to Update Old Generator
Interconnection Agreements or Explained How the Requirement Will Work in
Practice
Other aspects of PJM’s proposal appear to be entirely unresponsive to the Commission’s
compliance directives, would inject further ambiguity into the tariff, and could slow down the necessary study process and the integration of new large loads.
As a threshold matter, while PJM states that the proposed revisions to the necessary process are “intended to apply uniformly to all existing customers,”42 it is unclear whether that would be true in practice. This is because PJM proposes to place the necessary study revisions in Part VIII of the tariff, which by its plain terms applies only to generating facilities that submitted new service requests on or after October 1, 2021.43 Needless to say, to the extent that generators that began the interconnection process before October 1, 2021 cannot use the necessary process described in
PJM would accommodate the co-located load by shifting its supply curve by the size of the reduction in CIRs, while PJM would accommodate the front-of-the-meter load by shifting its demand curve by the size of the additional demand plus its planning reserve margin. See 2025 Shanker Affidavit at 29-30, 34. Nevertheless, PJM does not study the resource adequacy impacts of front-of-the-meter large load additions.
42 PJM Compliance Filing at 24-25 (“These proposed revisions are intended to uniformly to all existing customers regardless of whether they have presently effective interconnection agreements issued pursuant to Parts IV, VI, VII, or VIII of the Tariff.”).
43 PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part VIII, Subpart A, section 401 (Applications for Cycle Process Introduction) (2.0.0). PJM’s proposed changes to the necessary study process are included under Part VIII, section 401(H), which states that “[i]n connection with interconnection with the Transmission System pursuant to Tariff, Part VIII, Project Developer may be required, or may elect, to enter into one or more of the following interconnection-related agreements,” including the necessary study agreement. Id., section 404(H) (emphasis added).
PDF page 15
- 15 -
this filing, then the proposal would be unduly discriminatory and inconsistent with the
Commission’s directives.44
In a similar vein, PJM also fails to justify its proposal to require generation developers with older interconnection agreements—i.e., interconnection agreements for executed by generators that initiated PJM’s interconnection process before October 1, 2021—to instead enter the new pro forma GIA housed in Part IX of the tariff.45 It is not clear whether PJM’s proposal would require that such interconnection customers enter into new GIAs before they could initiate the necessary study process or whether PJM would require them to enter new GIAs after the necessary study
process.46 In any event, under PJM’s proposal, it appears that generation owners with older forms of interconnection agreements would be unable to simply modify their existing interconnection agreement to serve co-located loads and would instead need to obtain an entirely new form of interconnection agreement. PJM fails to demonstrate how its proposal is consistent with the Commission’s directive to create a process for modifying existing agreements for interconnection customers seeking to serve co-located loads.4744 Under PJM’s proposal, generation facilities the initiated the PJM interconnection process after October 1, 2021 would need to follow a process for amending their GIAs to serve co-located load that is different from the process followed by generators that initiated the PJM interconnection process prior to October 1, 2021. But there is no material difference to justify that selective treatment.45 PJM Compliance Filing at 25; Proposed Tariff Revisions at Part III (General). PJM states that “[i]f there is an Existing Interconnection Customer that desires to serve Co-Located Load with a Service Agreement issued pursuant to Tariff, Parts IV and VI, proposed revisions to Part III of the Tariff will require such customers to begin the process of amending such service agreements by following the tariffed necessary study process in Part VIII.” PJM Compliance Filing at 25. But PJM does not explain how such interconnection customers can begin the necessary study process in Part VIII.46 To the extent PJM intends to impose this requirement at the beginning of the necessary study process, it has not explained how generators can obtain the new form of GIA. It may be that PJM’s intent is purely formalistic, such that when it amends an interconnection agreement (ISA or GIA) after the necessary study process, it will merely update the interconnection customer’s GIA to a more recent version of PJM’s GIA. If this is what PJM intends, it must say so clearly.47 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 226.
PDF page 16
- 16 -
Even if PJM’s proposal is read as merely requiring PJM to use the updated pro forma GIA
at the conclusion of the necessary study process—a reading that is not readily apparent from the proposed tariff language—PJM has not justified that requirement, which appears entirely unrelated to the Commission’s compliance directives. And PJM’s proposal could lead to further disputes about whether and how provisions in the updated pro forma GIA should apply to older generators. For instance, the most recent pro forma GIA includes certain power factor,48 primary frequency response,49 and ride-through requirements,50 that are not present in some older interconnection agreements. It is not clear whether PJM intends to impose these new requirements on older
existing generators. Imposing new requirements on older existing generators would have far- reaching impacts. The Commission very purposely exempted resources with existing signed
generator interconnection agreements from many of these new requirements based on the cost
existing generators would incur to come into compliance.51 PJM appears to be proposing to disrupt long-standing Commission precedent with no justification.
48 PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part IX, Subpart B (Form of GIA Combined with CSA), § 12 (3.0.0).49 Id., app. 2 (Standard Terms and Conditions), § 4.6.2 (Primary Frequency Response) (1.0.0).50 Id., app. 2 (Standard Terms and Conditions), § 4.7 (Under- and Over-Frequency and Under- and Over- Voltage Conditions) (1.0.0).51 Order No. 2023, 184 FERC ¶ 61,054 at P 1725 (explaining that new ride-through requirements would apply only prospectively to customers that execute a GIA after the effective date because the requirement was not intended to “impos[e] potentially significant retrofit or equipment costs on existing nonsynchronous generating facilities.”); Essential Reliability Services & the Evolving Bulk-Power System -- Primary Frequency Response, Order No. 842, 162 FERC ¶ 61,128, at P 143, order on reh’g and clarification, 164 FERC ¶ 61,135 (2018) (“We will not impose primary frequency response requirements on existing generating facilities that do not submit new interconnection requests that result in an executed or unexecuted interconnection agreement. We conclude that applying the proposed requirements only to newly interconnecting generating facilities will adequately address the Commission’s concerns regarding primary frequency response. We are persuaded by commenters that requiring existing generating facilities that have not submitted a new interconnection request to install and operate governors or equivalent controls would be overly expensive and unnecessarily burdensome.”).
PDF page 17
- 17 -
PJM’s proposal injects unnecessary uncertainty into the necessary study process, especially for generators that initiated PJM’s interconnection process prior to October 1, 2021. Such uncertainty will further delay the pace at which generators in PJM can serve critical digital infrastructure.
II. PJM’s Proposal to Use of “Point of Change in Ownership” Versus “Point of Interconnection” in Co-Located Load Definition Creates New Opportunities for Undue Discrimination
In the Order on Show Cause Proceedings, the Commission defined co-located load as a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the interconnection customer’s side of the Point of Interconnection to the PJM Transmission System.”52 The Commission correctly reasoned that this definition is proper because it “reflects the fact that the Co-Location Arrangement is physically connected to and synchronized to the transmission system” and that “this relationship, and specifically the interconnection of the generator to the transmission system, is critical to the determinations” that the Commission made in its Order on Show Cause Proceedings.53 The Commission directed PJM to incorporate this definition into its tariff.54
The Commission should reject PJM’s proposal to revise the Commission’s definition of co-located load to refer to “Point of Change in Ownership” (“POCO”) instead of “Point of Interconnection” (“POI”).55 The change in term breeds uncertainty and creates an opportunity for transmission owners to unduly discriminate against certain customers because the transmission owners retain significantly more control over the designation of the POCO compared to the POI.
52 Show Cause Order, 190 FERC ¶ 61,115 at P 3 & n.4.53 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 164.54 Id. PP 163-164.55 See PJM Compliance Filing at 31.
PDF page 18
- 18 -
Specifically, PJM’s tariff requires the transmission owner and project developer to mutually agree on the POCO, with no specific timeline for doing so and no specific process for handling disagreements.56 To contrast, PJM has discretion to determine the POI if the parties cannot agree.57 By defining co-located load by reference to the POCO, transmission owners could delay large load interconnections by refusing to cooperate on the designation of the POCO. For instance, transmission owners could refuse to designate the POCO unless the load agrees to take certain services. Transmission owners could also strategically manipulate the location of the POCO to favor their preferred configurations and prevent some loads from meeting the definition of a co- located load.
Nothing in PJM’s tariff would prevent transmission owners from exercising their discretion in unduly discriminatory ways because there are no consistent or reliable standards by which the transmission owners decide whether to agree to a certain POCO. That clear opportunity for undue discrimination will perpetuate the “uncertainty that has resulted in disparate treatment in PJM, where transmission owners have taken different approaches to performing the necessary steps that apply to Interconnection Customers seeking to serve Co-Located Load Arrangement.”58 If the Commission accepts PJM’s new definition of co-located load, then it should direct further compliance to prevent undue discrimination. First, the Commission should direct PJM to revise its tariff to include clear timelines for mutual agreement on the POCO. Providing a distinct
56 See PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part VII, Subpart A, 300 Definitions “P” (2.0.0) (defining the Point of Change in Ownership as to be specified in the GIA); Id., Part VIII, Subpart A, 400 Definitions “P” (2.0.0) (same).57 PJM, Open Access Transmission Tariff, Attach. O, App. 2, § 2.1 (Scope of Service) (0.0.0) (“The location of the Point of Interconnection shall be mutually agreed by the Interconnected Entities, provided, however, that if the Interconnected Entities are unable to agree on the Point of Interconnection, [PJM] shall determine the Point of Interconnection . . . .”).58 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 159.
PDF page 19
- 19 -
deadline avoids unnecessary delays and encourages competitive open access. Second, the Commission should allow PJM to provide a final determination should the parties fail to come to a mutual agreement, consistent with PJM’s practice for POIs. Finally, the Commission should establish guidelines that prohibit transmission owners from effectuating discrimination and needless delay against large loads that do not suit their preference. These measures are necessary to avoid undue discrimination and ensure that PJM and the transmission owners meet the goals of the Order on Show Cause Proceedings by “reduc[ing] both technical and financial barriers to building new generation and efficiently connect[ing] large loads.”59
III. Conclusion
PJM’s compliance proposal threatens to impose a 3- to 5-year moratorium on co-location and thereby throttle the development of digital infrastructure at the very moment that the nation needs to rapidly build and energize the computing power needed to win the AI race. In the Order on Show Cause Proceedings, the Commission gave PJM straightforward directions for how it must revise its tariff to ensure that existing interconnection customers seeking to serve co-located understand their responsibilities. Rather than follow those directions for clarifying the necessary study process, PJM inexplicably veered in the opposite direction with its compliance filing, by impeding co-location opportunities and muddying the waters to make it even more challenging for interconnection customers to discern how to revise their existing interconnection agreements to serve co-located loads. The Commission must reject PJM’s counterproductive proposal and ensure that PJM complies with the Commission’s clear and common-sense mandates from the Order on Show Cause Proceedings.
59 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 (Rosner, Comm’r concurring at P 3).
PDF page 20
- 20 -
Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
Nicholas M. Gladd
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
Counsel for Vistra Corp.
Dated: March 16, 2026
PDF page 21
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: March 16, 2026
Washington, D.C.
/s/ Sarah Greenberg
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006