ER26-1479-000 · 2026-03-16 · Vistra Corp.

Protest of Vistra Corp. to PJM Interconnection, L.L.C.'s 02/23/2026 compliance filing

Text extracted from the eLibrary original (SHA-256 9ebe34cc313d4cf1…). Download the original from the official source.

Contents · 6 sections
  1. I. PJM Has Not Demonstrated That the Proposed Revisions to the Necessary Study p. 2
  2. A. PJM’s Proposal Fails to Include a Transition Mechanism for Customers p. 3
  3. B. PJM Has Not Demonstrated That Its Proposal for Delisting CIRs Is Just, p. 8
  4. C. PJM Has Not Justified the Requirement to Update Old Generator p. 14
  5. II. PJM’s Proposal to Use of “Point of Change in Ownership” Versus “Point of p. 17
  6. III. Conclusion p. 19

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Where the Commission required clarity, PJM has proposed ambiguity by failing to propose 1 18 C.F.R. § 385.211 (2026). 2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No.
Read this passage Filed comments: Connecting load and generation

I. PJM Has Not Demonstrated That the Proposed Revisions to the Necessary Study

printed heading · Topic match: Connecting load and generation

The Commission directed PJM to describe the information that the interconnection customer must provide about the co-located load for purposes of the necessary study.
Read this passage Filed comments: Connecting load and generation

A. PJM’s Proposal Fails to Include a Transition Mechanism for Customers

printed heading · Topic match: Connecting load and generation

Indeed, PJM’s proposal does not acknowledge that some existing generators have already executed necessary study agreements and even received study results, much less address whether and how the proposed tariff revisions apply to such customers. 6 Order on Show Cause Proceedings, 193 FERC ¶ 61,217…
Read this passage Filed comments: Connecting load and generation

B. PJM Has Not Demonstrated That Its Proposal for Delisting CIRs Is Just,

printed heading · Topic match: Connecting load and generation

PJM’s Paper Hearing Initial Brief attaches illustrative tariff language that states, “[t]he Eligible Customer must designate the individual Co- Located Generating Facility that will serve the individual Co-Located Load . . . and provide the megawatt level of energy from the Co-Located Generating…
Read this passage Filed comments: Connecting load and generation

C. PJM Has Not Justified the Requirement to Update Old Generator

printed heading · Topic match: Connecting load and generation

This is because PJM proposes to place the necessary study revisions in Part VIII of the tariff, which by its plain terms applies only to generating facilities that submitted new service requests on or after October 1, 2021.43 Needless to say, to the extent that generators that began the…
Read this passage Filed comments: Connecting load and generation

II. PJM’s Proposal to Use of “Point of Change in Ownership” Versus “Point of

printed heading · Topic match: Connecting load and generation

O, App. 2, § 2.1 (Scope of Service) (0.0.0) (“The location of the Point of Interconnection shall be mutually agreed by the Interconnected Entities, provided, however, that if the Interconnected Entities are unable to agree on the Point of Interconnection, [PJM] shall determine the Point of…
Read this passage Filed comments: Connecting load and generation

III. Conclusion

printed heading

In the Order on Show Cause Proceedings, the Commission gave PJM straightforward directions for how it must revise its tariff to ensure that existing interconnection customers seeking to serve co-located understand their responsibilities.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: March 16, 2026 Washington, D.C. /s/ Sarah Greenberg Sarah Greenberg Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006