ER26-1479-000 · 2026-03-16 · Eolian, L.P.Antora Energy LLCCalibrant Energy and 3 others
Motion to Intervene and Protest of Eolian, L.P. et al. to PJM Interconnection, L.L.C.’s proposed revisions to the PJM Open Access Transmission Tariff
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
)
MOTION TO INTERVENE AND PROTEST OF JOINT PARTIES TO COMPLIANCE
FILING
Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s
(Commission) Rules of Practice and Procedure,1 Eolian L.P. (Eolian), Antora Energy, Inc. (Antora), Calibrant Energy (Calibrant), Convergent Energy and Power (Convergent), Mainspring Energy, Inc. (Mainspring), and Verrus, LLC (Verrus) (together, Joint Parties) respectfully submit this motion to intervene and protest to PJM Interconnection, L.L.C.’s (PJM) proposed revisions to the PJM Open Access Transmission Tariff (Tariff) to comply with the Commission’s December 18, 2025 order on service to Co-Located Loads.2
Consistent with the Request for Clarification of the Co-Location Order3 and protest in PJM’s prior compliance proceeding in Docket No. ER26-1088-000 filed by several of the above parties,4 Joint Parties respectfully request that the Commission require PJM to include minor additional revisions to clarify that, in any generator interconnection process in which PJM studies the Co-Located Load’s withdrawals from the grid for purposes of identifying network upgrades, including the Necessary Studies process,5 a Co-Located Load may nominate a net
1 18 C.F.R. §§ 385.211, 385.214.2 See PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order).3 Joint Parties, Request for Clarification, Docket Nos. EL25-49-000 & 001, AD24-11-000, EL25-20-000 (filed Jan. 20, 2026).4 Joint Parties, Limited Protest, Docket No. ER26-1088-000 (filed Feb. 10, 2026).5 The PJM OATT does not resolve definitively the circumstances in which PJM will model withdrawals of a Co- Located Load in the generator interconnection process. But because we expect that PJM may choose to study the combined withdrawals of Co-Located Loads that include storage, we have filed the above-cited Request for Clarification and are filing this limited protest to ensure that any such study process advances the principles set forth in the Co-Location Order and does not result in needless network upgrades.
PDF page 2
2
withdrawal limit in the same manner that it may nominate a net injection limit. Among other potential benefits, this clarification will ensure that Co-Located Loads paired with energy storage can use their full technical capabilities to avoid unnecessary network upgrades, thereby advancing the Commission’s twin goals of protecting ratepayers and advancing speed-to-power within PJM.
In addition, Joint Parties request that the Commission reject or, at minimum, defer action on PJM’s proposed Tariff revisions that preclude loads connected to generating facilities behind- the-meter without interconnection rights from accessing the new Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, and Interim Network Integration Transmission Service (NITS) options established in the Co-Location Order. PJM must allow loads served by behind-the-meter generation (BTMG) to access the Commission’s new transmission services in order to ensure that loads with similar willingness and ability to limit withdrawals from the grid have access to similar service opportunities, and that therefore the proposed rates are just, reasonable, and not unduly discriminatory. The Commission should direct PJM to further revise its Tariff as part of the BTMG replacement rate to remove the restrictions limiting the new transmission services to loads connected to generation resources that have Interconnection Agreements with PJM.
I. MOTION TO INTERVENE
Eolian develops energy generation and storage assets throughout the United States and has originated 27 GW of operating capacity to date. Eolian and its partners have developed projects supporting large loads in multiple regions across the United States, including PJM.
PDF page 3
3
Antora is a U.S. manufacturer of thermal batteries, which are domestically built in San Jose, California, and developer of thermal storage projects for industrial facilities in the U.S. and abroad.
Calibrant develops energy generation and storage assets throughout the United States. Calibrant and its partners have developed and expect to continue to develop projects in PJM through a range of configurations, including BTMG and co-located projects supporting large loads. Specifically, Calibrant has several existing BTMG projects and projects that are currently being developed that will be impacted by PJM’s proposed revisions to its Retail BTMG rules. Convergent develops, owns, and operates distributed energy storage and storage plus solar resources for large commercial, industrial, and utility customers across North American markets, including PJM. Convergent has resources in operation and in development in PJM including behind-the-meter distribution and transmission connected battery energy storage systems, front-of-the-meter distribution connected battery energy storage systems, both with and without attached solar systems, and a 20 MW flywheel resource in Hazleton, Pennsylvania. Mainspring is a U.S.-headquartered manufacturer of modular, fuel-flexible, and dispatchable linear generators, a new type of power generator. Mainspring was founded in 2010 and its first commercial units were deployed in 2020. The company has been rapidly scaling since 2023, deploying its innovative technology across a wide spectrum of customer types and use cases. The company’s customers include investor-owned utilities, public power utilities, municipal water treatment facilities, biogas facilities, data centers, grocery store chains, cold food storage, and hospital systems. Mainspring’s linear generators can be installed behind a customer’s utility meter or as a front of the meter grid asset. Mainspring linear generators are currently operating across multiple sites in PJM territory and are in development across
PDF page 4
4
additional sites.Verrus is a developer, owner, and operator of a first-of-its-kind fleet of purpose- built, load-flexible hyperscale data centers. Verrus designs facilities from the ground up to function not only as digital infrastructure but also as grid assets—a new class of large customer capable of dynamically adjusting electricity consumption to support reliability, efficiency, and affordability. Verrus’ facilities can provide these system benefits without disrupting the critical computing workloads that increasingly underpin the modern economy. Each Verrus campus integrates on-site utility-scale battery energy storage, advanced load-management controls, and grid-aware automation that collectively enable real-time coordination with utilities and regional transmission operators.
Each of the Joint Parties expect to develop storage or generation assets co-located and/or behind the meter with loads. They therefore each have a substantial interest in this proceeding that cannot be adequately represented by another party. Granting this limited protest will critically support development of Co-Located Loads, storage, and BTMG assets that avoid “costly and inefficient transmission system buildout.”6 The Joint Parties’ participation is therefore in the public interest.
II. LIMITED PROTEST
A. PJM should be required to clarify that an existing interconnection customer can nominate a joint withdrawal limit in the Necessary Study process.
Joint Parties seek clarification, consistent with the Request for Clarification that the Joint Parties filed in response to the Co-Location Order,7 that PJM’s filing will allow interconnection customers serving Co-Located Loads to nominate net withdrawal limitations for purposes of these interconnection study processes. This clarification is necessary to realize the Co-Location
6 Co-Location Order, 193 FERC ¶ 61,217 at P 177.7 Joint Parties, Request for Clarification, Docket Nos EL25-49-000 & 001, AD24-11-000, EL25-20-000 (filed Jan. 20, 2026).
PDF page 5
5
Order’s stated intent of ensuring that Co-Located Loads do not pay for services that they do not use and do not trigger network upgrades that they do not need.8
The Co-Location Order is built on the concept that Co-Located Loads can control their net withdrawals from the grid, and that market structures should be in place that allow them to do so efficiently. The Co-Location Order requires PJM to develop transmission service frameworks that allow customers to take as-available service based on the use of special protection schemes that enable reliable, as-available service based on technical and engineering requirements set by PJM,9 and requires PJM to enable an interconnection customer to request the “minimum level of interconnection service it deems necessary.”10
PJM’s Tariff revisions proposed here, however, appear to remain silent as to how it will treat withdrawals in studying Co-Located Load interconnection requests. We therefore seek modest clarification from PJM that, to the extent PJM performs interconnection study steps involving withdrawal assumptions for Co-Located Loads, an energy storage interconnection customer will be able to specify limits to the injection and withdrawal rights reflecting the proposed integration of the storage and Co-Located Load facilities.
Joint Parties submit this protest to preserve their rights and to ensure that PJM does not include assumptions in interconnection studies that the load and storage resource withdrawals to charge create bluntly overlapping grid impacts (e.g. coincident withdrawals at peak), when in fact the storage resources and Co-Located Load could be managed to limit the overall withdrawal of the Co-Located Load and to avoid withdrawal when doing so would create grid
8 See, e.g., Co-Location Order, 193 FERC ¶ 61,217 at P 162 (“Collectively, the replacement rate provides pathways that recognize Co-Located Loads that limit their energy withdrawals from the transmission system, which may require fewer Network Upgrades, and therefore may result in lower Network Upgrade costs as compared to requiring all Eligible Customers taking service on behalf of Co-Located Load to take [Network Integration Transmission Service].”).9 Id. P 212.10 Id. P 232.
PDF page 6
6
impacts necessitating network upgrades. Accordingly, Joint Parties request that the Commission require PJM to propose narrow Tariff additions to clarify that a Co-Located Load may nominate a net withdrawal limit in the same manner that it may nominate a net injection limit. a. The Commission should require PJM to propose further
compliance revisions to ensure compliance with the Co-Location
Order
PJM here proposes Tariff revisions related to Necessary Studies and Necessary Study Agreements, including the information needed to perform Necessary Studies.11 PJM does not appear to specify in these revisions or elsewhere in the filing how it will treat energy storage withdrawals in interconnection studies, or that, to the extent that PJM includes Co-Located Load in interconnection studies, interconnection customers may provide withdrawal limits for both the energy storage resource components and the Co-Located Load. To remedy these deficiencies, the Commission should require PJM to file revisions clarifying that (1) interconnection customers may nominate joint withdrawal limits and include information in their requests to modify interconnection agreements to demonstrate the ability to operate within such limits; and (2) the determination of Network Upgrades, Interconnection Facilities, and any other infrastructure that may be required shall account for such limits.
The Co-Location Order finds the existing PJM tariff unjust and unreasonable because it lacks clear provisions to govern the “rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”12 The requested revision aims to address precisely this defect: the absence of clear rules that govern how Co-Located Load paired with storage will be
11 PJM Filing, Transmittal at 26 (citing Proposed Tariff, Part VII, Subpart A, section 401.H.3.b.i – iii).12 Co-Location Order, 193 FERC ¶ 61,217 at P 175.
PDF page 7
7
studied in the generator interconnection process. The Proposed Tariff, as currently drafted, does not specify how storage withdrawals will be modeled when a storage facility is seeking to co- locate with a large load.
This absence of clear provisions means that without clarification, there is a risk that the necessary study process could include assumptions that the load and the charging load of the storage resource create bluntly overlapping grid impacts (e.g. coincident withdrawals at peak), when in fact the storage resources and Co-Located Load could be managed to limit the overall withdrawal of the co-located resource and to avoid withdrawal when doing so would create grid impacts necessitating network upgrades. Accordingly, the Commission should require modest revisions to clarify that an interconnection customer can nominate a joint withdrawal limit to avoid uncertainty.
b. The principles set forth in the Co-Location Order require PJM
to allow interconnection customers to nominate joint withdrawal
limits
In the Co-Location Order, the Commission found that “the PJM Tariff is unjust and unreasonable because it lacks sufficient clarity and consistency with respect to the rules for Co- Location Arrangements” and directed changes to the new service request process, as well as the necessary study process for modifications to existing facilities.13 With regard to “Interconnection Customers seeking to use new generating facilities to serve Co-Located Load,” the Commission required PJM to clarify that it “shall consider requests for interconnection service below the full generating capability of the generating facility, so that an Interconnection Customer may request interconnection service at a level below its maximum facility output to serve Co-Located
13 Id. P 225.
PDF page 8
8
Load.”14 The Co-Location Order aims to minimize infrastructure needs based on interconnection customer capabilities including the Co-Located Load’s characteristics, specifying that “[t]his revision will clarify that an Interconnection Customer seeking to use a new generating facility to serve a Co-Located Load may request only the minimum level of interconnection service it deems necessary to effectuate its Co-Location Arrangement.”15
With regard to the necessary study process, the Commission required PJM “to add to the Tariff a description of the scope of the analysis that it will perform as part of the necessary study process when an Interconnection Customer seeks to use its existing generating facility to serve Co-Located Load,” which must include a description of “the information that the Interconnection Customer must provide about the Co-Located Load for purposes of the necessary study.”16 The Co-Location Order contemplates that PJM will use this information in determining “any modifications or Network Upgrades that are needed as a result of PJM’s study of the change to the ISA or GIA to allow the existing generating facility to serve Co-Located Load.”17 And the Co-Location Order explains that such upgrades should account for “special protection schemes.”18 The implication of these directives is that information about the Co-Located Load and special protection schemes may influence what modifications and Network Upgrades may be required, because the Interconnection Customer may operate the Generating Facility and Co- Located Load in a coordinated fashion so as to minimize infrastructure needs. Given the ambiguity of the tariff proposed by PJM, we urge the Commission to clarify that such information must include the ability to nominate joint withdrawal limits between the Generating
14 Id. P 232.15 Id.16 Id. P 227.17 Id. P 228.18 Id.
PDF page 9
9
Facility and Co-Located Load, as such limits may be a critical factor affecting the infrastructure that may be triggered by study results where both the Generating Facility and the Co-Located Load withdraw electric energy from the system.
The minor revision we are requesting is necessary to ensure that “the Tariff will have sufficient clarity and consistency to facilitate Co-Location Arrangements in a just and reasonable and not unduly discriminatory or preferential manner.”19 Just as an Interconnection Customer seeking to use a new storage facility to serve a Co-Located Load “may request only the minimum level of interconnection service it deems necessary to effectuate its Co-Location Arrangement,” similar treatment of an existing Interconnection Customer requires such customers to request the minimum level of service necessary to serve the Co-Located Load when proceeding through the necessary study process.
Allowing both new and existing customers the ability to nominate joint withdrawal limits is also necessary to give the Co-Location Order’s transmission service reforms meaning. The Co- Location Order recognizes in the context of requiring PJM to offer non-firm transmission service that co-located resources can be integrated so as to “limit [the] energy withdrawals” of Co- Located Loads in order to prevent “inefficient and costly transmission buildout.”20 In requiring PJM to offer Co-Located Loads a menu of transmission service options, the Co-Location Order ensures that such loads have the opportunity to receive service that “reflect[s] their actual impact on the transmission system.”21 But the value presented by the option to obtain non-firm transmission service requires reading PJM’s interconnection service compliance requirements to avoid separately forcing Co-Located Loads to bear the cost and delay of unnecessary network
19 Id. P 229.20 Co-Location Order, 193 FERC ¶ 61,217 at P 199.21 Id. P 162.
PDF page 10
10
upgrades that do not “reflect[s] their actual impact on the transmission system.”22 To achieve the objectives of the Co-Location Order, the Commission should therefore require PJM to allow for non-firm withdrawal and integrated operation of co-located facilities including net withdrawal limits to be integrated into interconnection study assumptions because failing to do so “could necessitate inefficient and costly transmission buildout.”23
B. The Commission should reject PJM’s proposed Tariff revisions that preclude retail loads served by behind-the-meter generation from taking the new
transmission services and otherwise limit eligibility for the new transmission services to load that is connecting to a generator with interconnection rights.
PJM’s compliance filing is also unjust, unreasonable and unduly discriminatory for precluding loads connected to behind-the-meter generation without interconnection rights from taking the new Firm and Non-Firm Contract Demand Transmission Services and Interim NITS that will be offered to Co-Located Loads. These retail loads are similarly situated to Co-Located Loads in their willingness and ability to limit their energy withdrawals from the transmission system under certain conditions in the same manner as Co-Located Loads. Just, reasonable, and not unduly discriminatory treatment requires that these similarly-situated loads receive similar treatment: access to these new transmission service classes.
The Commission is requiring revisions to PJM’s Tariff with respect to certain BTMG loads because such loads “are not fully accounted for in resource adequacy planning and shift costs onto other transmission customers.”24 This directive speaks to a desire to render such loads visible to the PJM transmission system and require them to pay for transmission service used by the load customer that relies on BTMG. The Commission’s stated goals do not suggest a desire to force BTMG to move through PJM’s queue even where it does not plan to inject into the
22 Id.23 Id. P 199.24 Id. P 2.
PDF page 11
11
system, or to require purchase of more transmission service than similarly situated customers. Yet, absent removal of the eligibility restrictions proposed by PJM for the new transmission services, that is exactly the result that will occur.
PJM could remedy the deficiency of its proposed replacement rate by removing the restrictions on eligibility that allow only Co-Located Loads to access the new transmission services. Extending this transmission service eligibility will also further the Co-Location Order’s goals of ensuring that loads have the opportunity to receive service that “reflect[s] their actual impact on the transmission system”25 and preventing “inefficient and costly transmission buildout.”26
PJM’s compliance filing prohibits retail loads served by “[a]ny facility that qualifies as a Retail Behind The Meter Generation . . . from Co-Located Load configurations.”27 By proposing to restrict availability of the new transmission services to “Eligible Customers taking transmission service on behalf of Co-Located Load,”28 this provision prevents retail customers served by behind-the-meter generation lacking interconnection rights from taking the new transmission services. These customers are also excluded from new transmission service options by PJM’s proposal to define Co-Located Load as “end-use customer load that is physically connected to the facilities of an existing or planned Generating Facility on the Project Developer’s side of the Point of Change in Ownership to the Transmission Provider’s Transmission System.”29 Retail loads served by behind-the-meter generation do not qualify under this definition because Generating Facilities under the Tariff must have gone through the
25 Id. P 162.26 Id. P 199.27 PJM Filing, Transmittal at 7-8 & Proposed Tariff, Definitions – R – S. 28 PJM, Proposed Tariff, § III.29 PJM, Proposed Tariff, Definitions – A - B
PDF page 12
12
interconnection process and have injection rights, which do not apply to behind-the-meter generation.30
PJM’s compliance filing therefore excludes loads served by behind-the-meter generation that lack interconnection rights from accessing the new transmission service options despite their abilities to limit withdrawals. This result is particularly absurd in light of PJM’s proposal, in compliance with the Co-Location Order, to allow Generating Facilities connected to Co-Located Loads to nominate net injection limits below their nameplate capacity.31 These provisions would enable an interconnection customer to reduce its net injection to 1 MW and receive the new transmission services, while prohibiting a BTMG to engage in a nearly-identical arrangement that places even less strain on the grid by limiting its net injection to zero (and therefore eliminating the need an interconnection agreement for the Generating Facility).
While PJM’s compliance proposal is generally responsive to the PJM Co-location
Order’s focus on Co-Located Loads, it does not provide for a just, reasonable, and not unduly discriminatory replacement rate with regard to loads connected to behind-the-meter generation. Critically, in contrast to the services available to Co-Located Loads, PJM’s proposal does not allow customers served by behind-the-meter generation that are similarly situated to Co-Located Loads in their willingness and ability to limit withdrawals a similar pathway to use new transmission services to limit their impacts on the system.32 Under PJM’s proposal, loads served
30 See PJM, PJM Interconnection, L.L.C./Intra-PJM Tariffs, G-H, OATT Definitions - G - H (9.0.1) (defining “Generating Facilities” as “Interconnection Customer’s device for the production and/or storage for later injection of electricity identified in the Interconnection Request . . . .”).31 PJM, Filing, Docket No. ER26-1088-000, at 4 (filed Jan. 20, 2026) (citing Proposed Tariff, Part VIII, Subpart B, section 403 (A)(1)(q) (requiring Applicants, in Generation Interconnection Requests, to “[i]ndicate the level of Interconnection Service requested, including whether Project Developer requests Interconnection Service below the full generating capability of a new Generating Facility or the requested increase in generation capability of an existing Generating Facility to serve Co-Located Load.”)).32 The Commission recognized “that Co-Location Arrangements may interact with the transmission system in a similar way to BTMG arrangements,” and therefore “sought briefing on how any proposed replacement rate adopted
PDF page 13
13
by behind-the-meter generation must purchase NITS, even where the behind-the-meter
generation capabilities would allow for use of the more limited transmission services. PJM should instead make such services available to other customers with substantively the same capabilities to limit withdrawals, including customers served by behind-the-meter generation as well as others with inherently flexible demand profiles (such as thermal storage)33 or customers located adjacent to generation such that the electrical impacts of the combined load and generation are the same with respect to system curtailment needs.34
The Commission has authority to require PJM to make the new Firm Contract Demand,
Non-Firm Contract Demand, and Interim NITS services available to loads served by behind-the- meter generation. In the Co-Location Order, the Commission required PJM to develop BTMG rules that address the reliability and resource adequacy risks created by some loads using BTMG35 because such loads may “lean on the PJM system when the co-located generation is on a full or partial outage or if the load exceeds the rating of the co-located generation.”36 But in requiring revised BTMG rules, the Commission recognized “the potential impacts of the Commission changing PJM’s BTMG rules for existing BTMG customers,” and therefore
required PJM to take steps to “minimize the impact of [the BTMG rule] transition on existing BTMG customers.”37
in this proceeding would interact with existing BTMG arrangements.” Co-Location Order, 193 FERC ¶ 61,217 at P
9. Given the delays inherent to interconnecting to the PJM system, obtaining an Interconnection Agreement is likely not a viable pathway for most behind-the-meter generators. Moreover, where the load customer behind whose meter the generator is connected does not inject into the system, a generator Interconnection Agreement should not be a condition of service.
33 See Antora Energy LLC, Motion to Intervene and Comments, Docket Nos. EL25-49-000, EL25-20-000, & AD24- 11-000, at 3 (filed Apr. 23, 2025).34 See Eolian L.P., Initial Comments, Docket No. RM26-4-000, Attach. A at 8 (filed. Nov. 21, 2026) (noting that “[C]ases in which the large load is electrically close to the paired generation, metered separately, and not necessarily at the same site . . . can provide many of the same benefits as strictly on-site generation and load”). 35 Co-Location Order, 193 FERC ¶ 61,217 at P 221.36 Id. P 186.37 Id. P 222.
PDF page 14
14
Importantly, unlike the Commission’s other findings in the Co-Location Order that were limited to Co-Located Loads, the Commission’s finding with respect to the BTMG rules “applies to all Network Load.”38 The replacement rate must therefore provide for just, reasonable, and not unduly discriminatory BTMG rules for all Network Load. This broad finding both requires and permits the Commission to require PJM’s replacement rate to allow retail customers who can limit withdrawals but who are nevertheless not connected to “Generating Facilities” with interconnection rights under the Tariff to take the new transmission services. Alternately, the Commission could provide for the same result by granting the PJM Industrial Consumer Coalitions pending request for clarification or, in the alternative, rehearing seeking to clarify that “[n]ew transmission services outlined in the Order will be made available to retail BTMG customers and load-only customers, not just Co-Located Load.”39 Or, the Commission could ensure non-discriminatory eligibility for the new transmission services in the Commission’s pending paper hearing proceeding in Docket No. EL25-49 et al. to develop the new transmission service replacement rate.40
In the instant proceeding, however, the Commission may not approve PJM’s proposed unjust, unreasonable, and unduly discriminatory compliance filing that allows some loads that can limit withdrawals to take the new transmission services but denies the same opportunities to others with the same technical abilities. Rather, the Commission should reject PJM’s compliance filing and direct PJM to allow customers with generation behind their load to access transmission services that match their ability to limit withdrawals, similar to customers with load connected to Generating Facilities. In the alternative, or in addition, the Commission could defer action on this
38 Id. P 186.39 PJM Industrial Customer Coalition et al., Request for Rehearing, Docket Nos. EL25-49-000 & 001, AD24-11,000, & EL25-20-000, at 7 (filed Jan. 20, 2026).40 Co-Location Order, 193 FERC ¶ 61,217 at P 207.
PDF page 15
15
compliance filing and grant the request for clarification or rehearing arguing that the new transmission services must be available to Retail BTMG and load-only customers41 and accept this compliance filing after PJM has proposed other revisions to ensure similar transmission service access for similarly situated customers.
III. CONCLUSION
For the foregoing reasons, the Commission should reject PJM’s compliance filing and require PJM to: (1) clarify that, in any generator interconnection study process in which PJM studies the Co-Located Load’s withdrawals from the grid for purposes of identifying network upgrades, including the necessary study process, a Co-Located Load may nominate a net withdrawal limit in the same manner that it may nominate a net injection limit; and (2) allow loads that can limit their withdrawals similarly to Co-Located Loads to have access to the same Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, and Interim NITS that PJM proposes to provide to Co-Located Loads.
Respectfully submitted,
/s/ Eric Stoutenburg
/s/ Miles Farmer
Eric Stoutenburg
Miles Farmer
Chief Development Officer
Sam Walsh
Eolian L.P.
Nathan Lobel
988 Howard Ave. Suite 200
Roselle LLP
Burlingame, CA 94010
300 New Jersey Ave. NW, Suite 300
eric.stoutenburg@eolianenergy.com
Washington, DC 20001
miles.farmer@rosellellp.com
/s/ Noah Long
sam.walsh@rosellellp.com
Noah Long
nathan.lobel@rosellellp.com
Director, State and Regulatory Affairs
Antora Energy, Inc.
200 West De Vargas St
Santa Fe, NM 87501
41 PJM Industrial Customer Coalition et al., Request for Rehearing, Docket Nos. EL25-49-000 & 001, AD24-11,000, & EL25-20-000, at 7 (filed Jan. 20, 2026).
PDF page 16
16
noah.long@antora.com
/s/ Matt Barnes
Matt Barnes
Chief Commercial Officer
Calibrant Energy
4830 W. Kennedy Blvd, Suite 600
Tampa, Florida 33609
matthew.barnes@calibrantenergy.com
/s/ Katie Guerry
Katie Guerry
SVP Regulatory and Government Affairs
Convergent Energy and Power
7 Time Square, Suite 3504
NY, NY 10036
kguerry@convergentep.com
/s/ Brian Kauffman
Brian Kauffman
Direct, Wholesale Market Development
Mainspring Energy, Inc.
3601 Haven Ave.
Menlo Park, CA 94025
brian.kauffman@mainspringenergy.com
/s/ Jeff Bladen
Jeff Bladen
Head of Energy
Verrus, LLC
918 N Rengstorff Ave.
Mountain View, CA 94043
bladen@verrusdata.com
PDF page 17
17
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated: March 16, 2026
/s/ Nathan Lobel
Nathan Lobel