Comments or, in the Alternative, Limited Protest of Appalachian Voices in response to PJM Interconnection, L.L.C.’s 02/23/2026 compliance filing proposing…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-1479-000
COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST
OF APPALACHIAN VOICES
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or
Commission) Rules of Practice and Procedure,1 Appalachian Voices submits these comments or, in the alternative, limited protest in response to PJM Interconnection, L.L.C.’s (PJM) compliance filing proposing revisions to its Open Access Transmission Tariff (Tariff) concerning co-located load (Compliance Filing).2 The Compliance Filing addresses the Commission’s directives in its December 18, 2025 order in Docket No. EL25-49-000, et al.3 (Order Directing Compliance) by proposing, among other things, to revise the Tariff provisions applicable to retail Behind-the- Meter Generation (BTMG). For the avoidance of doubt, Appalachian Voices submits these comments to seek clarification that the Compliance Filing’s proposed 50 MW materiality threshold for BTMG applies to the aggregate capacity of all generation resources at a single customer site, rather than to each individual generating unit. If PJM intended that this threshold apply only to individual units, Appalachian Voices urges the Commission to reject this aspect of the Compliance Filing and direct further compliance.
I. BACKGROUND
The proliferation of data centers has raised difficult questions about the impacts their interconnection and the associated generation they require will have on other users of the grid,
1 18 C.F.R. § 385.211 (2025).2 PJM Interconnection, L.L.C., Compliance Filing, Transmittal Letter, at 11-12 (filed Feb. 23, 2026) (Compliance Filing).3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (Order Directing Compliance).
PDF page 2
2
particularly in the PJM region. To address some of these challenges, the Commission issued an order on February 20, 2025, directing PJM to show cause as to why its Tariff remains just and reasonable and not unduly discriminatory or preferential without specific provisions addressing service to co-location arrangements between large loads and generators.4 In response to public comment, the Commission issued the Order Directing Compliance on December 18, 2025, directing PJM to revise its Tariff to set forth specific terms and conditions for customers seeking to interconnect load co-located with generation.5
The Commission’s compliance directives included a requirement that PJM revise its Tariff provisions related to retail BTMG. PJM’s Tariff defines BTMG as “a generation unit that delivers energy to load without using the Transmission System or any distribution facilities[.]”6 Currently, the Tariff allows load serving entities that serve loads with BTMG to reduce their level of service and the associated costs by netting output from the BTMG in the calculation of their peak demand for the purpose of determining Network Integration Transmission Service charges.7 In its Order Directing Compliance, the Commission found that changed circumstances have made PJM’s existing Tariff provisions unjust and unreasonable, citing PJM’s own conclusion that the existing rules were “conceived for, and [have] been implemented for, substantially smaller loads . . . and not on the scale of large data centers.”8 Again echoing PJM, the Commission noted that “[a]llowing very large loads like data centers to net is problematic because loads in this configuration do not carry reserves.”9 Yet, because load serving entities must nevertheless serve these loads, the current rules would allow these loads to “lean on the
4 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 2 (2025).5 Order Directing Compliance at P 2. 6 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – A-B (21.0.0).7 PJM, Intra-PJM Tariffs, OATT, § III.34.2 Netting of Behind the Meter Generation (0.0.0).8 Order Directing Compliance at P 186 (citing PJM Interconnection, L.L.C., Answer, Docket No. EL25-49-000, et al., at 13 (filed Mar. 24, 2025) (PJM March 24th Answer)).9 Id. (citing PJM March 24th Answer at 36).
PDF page 3
3
PJM system when the co-located generation is on a full or partial outage or if the load exceeds the rating of the co-located generation.”10 The Commission concluded, therefore, that because PJM’s existing rules do not limit the amount of qualifying load that a Network Customer may net by using BTMG, PJM’s operative Tariff provisions “are no longer consistent with cost causation principles, because large loads configured in a BTMG arrangement with significant generation will raise cost shifting concerns compared to loads pursuing smaller amounts of netting.”11 The Commission concluded that this could create reliability and resource adequacy risks. As a result, the Commission directed PJM to revise the BTMG provisions in its Tariff.12 The Commission acknowledged, however, that not all loads using BTMG are large enough to create reliability and resource adequacy risks. The Commission therefore directed PJM “to propose a new MW threshold for the amount of load at a particular electrical location that Network Customers may net by using” BTMG.13
On February 23, 2026, PJM submitted its Compliance Filing. As relevant here, in its transmittal letter, PJM proposed “to establish a materiality threshold of up to 50 MW for a generator at the same electrical location as the Network Load for generation units to qualify as Retail BTMG.”14 PJM proposed the following Tariff language to effectuate its materiality threshold: “‘Retail Behind The Meter Generation’ shall refer to Behind The Meter Generation that is used to serve a retail load served by a Network Customer located at the same electrical location, where such generation has a cumulative nameplate rating of no greater than 50 MW[.]”15
10 Id. (citing PJM March 24th Answer at 13 n.5).11 Id.12 Id. at P 221.13 Id.14 Compliance Filing, Transmittal Letter, at 11-12. 15 Id., Attach. A at 51.
PDF page 4
4
II. COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST
PJM’s proposed Tariff language sets the materiality threshold for BTMG at “a cumulative nameplate rating of no greater than 50 MW[.]”16 This would appear to subject all generation at a single customer site to a collective threshold of 50 MW for BTMG purposes, in keeping with the Order Directing Compliance’s requirements. However, PJM’s transmittal letter injects uncertainty into this application by stating that the 50 MW threshold applies to “a generator at the same electrical location as the Network Load[.]”17 These equivocal descriptions make it unclear whether PJM intends the 50 MW threshold to apply to the aggregate nameplate ratings of all generation at a single site or only to each individual generator at the same electrical location as network load.
Applying the latter interpretation would undermine the Commission’s purpose in requiring a materiality threshold in the first place. The Commission required PJM to propose a materiality threshold “because large loads configured in a BTMG arrangement with significant generation will raise cost shifting concerns compared to loads pursuing smaller amounts of netting[,]”18 which, in turn, could create reliability and resource adequacy risks. Applying the 50 MW materiality threshold separately to multiple, individual BTMG facilities at the same electrical location as Network Load would not address this concern. It would create a loophole whereby load co-located with significant generation in the form of several generators under 50 MW could subtract their collective nameplate capacity from its peak load and effectively operate outside the constraints and oversight PJM proposes in the rest of its compliance filing. This
16 Id., Attach. A at 51 (emphasis added).
17 Id., Transmittal Letter, at 11-12 (applying the 50 MW threshold to “a generator at the same electrical location as the Network Load[.]”).
18 Id.
PDF page 5
5
would unjustly and unreasonably shift costs and exacerbate the reliability and resource adequacy risks the Commission has already identified.
Accordingly, for the avoidance of doubt, Appalachian Voices seeks clarification that PJM’s proposed Tariff language would establish a materiality threshold for Retail BTMG of no more than 50 MW, inclusive of all generation at the same electrical location, despite the ambiguous language in its transmittal letter.19 In the alternative, to the extent PJM’s proposed materiality threshold of 50 MW would apply individually to multiple generators at the same electrical location, Appalachian Voices requests that the Commission reject PJM’s proposal and require further compliance.
III. CONCLUSION
For the foregoing reasons, Appalachian Voices respectfully requests the clarification described above. In the alternative, Appalachian Voices respectfully asks that the Commission reject this aspect of PJM’s Compliance Filing and require further compliance.
Respectfully submitted,
/s/ Nicholas J. Guidi
Nicholas J. Guidi
Senior Attorney
Southern Environmental Law Center
500 New Jersey Ave NW, Suite 600
Washington, DC 20001
nguidi@selc.org
/s/ Katherine L. Rogers
Katherine L. Rogers
Associate Attorney
Southern Environmental Law Center
500 New Jersey Ave NW, Suite 600
19 See PJM Interconnection, L.L.C., 164 FERC ¶ 61,170, at P 37 (2018) (“Commission precedent is clear that in the event of a conflict between pleadings and proposed tariff language, the tariff language controls.”) (internal citations omitted)).
PDF page 6
6
Washington, DC 20001
krogers@selc.org
Counsel for Appalachian Voices
Date: March 16, 2026
PDF page 7
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, I hereby certify that I have this day served a copy of the foregoing on all persons designated on the official service list compiled by the Secretary in this proceeding.
Dated this 16th day of March 2026.
/s/ Katherine L. Rogers
Katherine L. Rogers