ER26-1479-000 · 2026-03-16 · Appalachian Voices

Comments or, in the Alternative, Limited Protest of Appalachian Voices in response to PJM Interconnection, L.L.C.’s 02/23/2026 compliance filing proposing…

Text extracted from the eLibrary original (SHA-256 5d576c649c51d2e0…). Download the original from the official source.

Contents · 3 sections
  1. I. BACKGROUND p. 1
  2. II. COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST p. 4
  3. III. CONCLUSION p. 5

Read topic-matched comments in ER26-1479

Topics in the text: Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

ER26-1479-000 COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST OF APPALACHIAN VOICES Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 Appalachian Voices submits these comments or, in the alternative, limited protest in…
Read this passage

I. BACKGROUND

printed heading · Topic match: Cost allocation

As a result, the Commission directed PJM to revise the BTMG provisions in its Tariff.12 The Commission acknowledged, however, that not all loads using BTMG are large enough to create reliability and resource adequacy risks.
Read this passage Filed comments: Cost allocation

II. COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST

printed heading · Topic match: Reliability and curtailment

It would create a loophole whereby load co-located with significant generation in the form of several generators under 50 MW could subtract their collective nameplate capacity from its peak load and effectively operate outside the constraints and oversight PJM proposes in the rest of its compliance…
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, Appalachian Voices respectfully requests the clarification described above.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 16th day of March 2026. /s/ Katherine L.
Read this passage