ER26-1479-000 · 2026-03-16 · American Municipal Power, Inc.
Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.’s 02/23/2026 Compliance filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
LIMITED PROTEST OF
AMERICAN MUNICIPAL POWER, INC.
American Municipal Power, Inc. (“AMP”) hereby protests the February 23, 2026 compliance filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1 in which PJM proposes revisions to its Open Access Transmission Tariff (“Tariff”) to comply with directives in the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) December 18, 2025 order in Docket Nos. EL25-49-000, et al.2 As discussed below, AMP’s protest is limited to one specific aspect of the PJM Filing: the proposed revised definition for Non-Retail Behind The Meter Generation (“Non-Retail BTMG”).3
I. BACKGROUND AND INTRODUCTION
Under the existing PJM Tariff, load served by all Behind the Meter Generation (“BTMG”), and more particularly, Non-Retail BTMG is, subject to certain requirements and limitations, eligible to be netted from daily load under section 34.2 of the PJM Tariff for purposes of calculating charges for Network Integration Transmission Service and other PJM charges.4 In the December 18 Order, the Commission found PJM’s existing
1 PJM, 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-1479-000 (February 23, 2026) (“PJM Filing”).2 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Order”).3 See PJM Filing, Transmittal Letter at 15-18; id. at Attachment B, p. 43.4 See, e.g., PJM Filing, Transmittal Letter at 4-6. PJM proposes to revise section 34.3 of the Tariff such that it will now be the operative provision specifying the eligibility of Non-Retail BTMG to net against Network Load. See id. at 16 & n.48.
PDF page 2
2
retail BTMG5 rules to be unjust and unreasonable, and directed PJM to revise the Tariff provisions addressing certain generating units that are classified as retail BTMG.6 The Commission made clear, however, that it was not directing PJM to make any changes to its rules for Non-Retail BTMG.7
The PJM Filing, submitted pursuant to section 206 of the Federal Power Act
(“FPA”),8 proposes a number of changes to the Tariff provisions addressing BTMG, including a retail BTMG materiality threshold of 50 MW, and a three-year transition period for existing retail BTMG.9 PJM also proposes new or revised Tariff definitions for Behind the Meter Generation, Non-Retail Behind The Meter Generation, and Retail Behind The Meter Generation.10 In accordance with the Commission’s directions in the December 18 Order, PJM indicates that it is not proposing any changes to the Tariff rules for Non-Retail BTMG.11
AMP and AMP’s load-serving utility members own and operate generating units in
the PJM region that qualify as Non-Retail BTMG. AMP therefore strongly supports the
5 The December 18 Order notes that the Commission and others apply the label of “retail BTMG” to the class of BTMG that does not qualify as Non-Retail BTMG, December 18 Order at P 7, while PJM’s filing includes a new definition of “Retail Behind The Meter Generation,” e.g., PJM Filing, Transmittal Letter at 7; Attachment B, p. 89.
6 Id. PP 179, 221-224. Specifically, the Commission directed PJM to “propose a new MW threshold for the amount of load at a particular electrical location that Network Customers may net by using BTMG.” Id. at P 221. Recognizing that customers may have relied on the existing BTMG rules, however, the Commission required PJM to maintain the current BTMG rules for customers that fall below the new MW threshold level. See id. at P 179. The Commission also adopted a transition process for “retail BTMG,” including a three-year transition period and grandfathering of certain parties with existing contracts. See id.7 See id. at P 222. The Commission found that, given the existing Tariff limitation on the amount of Non- Retail BTMG that is eligible for netting, Non-Retail BTMG does not present the same resource adequacy and reliability concerns as BTMG. Id.; see also id. at P 179.8 See PJM Filing, Transmittal Letter at 1 (citing 16 U.S.C. § 824e).9 See id. at 11-15.10 See id. at 15-18.11 Id. at 7, 15-16.
PDF page 3
3
Commission’s decision to preserve the current rules for Non-Retail BTMG. Likewise, AMP endorses PJM’s efforts to preserve the status quo as to those rules.12
As discussed below, however, and notwithstanding PJM’s stated intent to preserve its existing Non-Retail BTMG rules in conformance with the Commission’s instructions, the proposed revision to the definition of Non-Retail BTMG included in the PJM Filing could be construed as preventing generating units that are merely eligible for application of the Non-Retail BTMG rules from ever participating in PJM’s newly established Co- Located Load configurations. This literal reading would preclude a broad swath of PJM generators from supporting Co-Located Load because the set of generators eligible for treatment as Non-Retail BTMG includes, without reservation, generators “used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load.”13
Such an outcome, which PJM has indicated is not what it intended, would be unjust, unreasonable, and unduly discriminatory. Further, revising the Non-Retail BTMG definition is unnecessary and outside the scope of the Commission’s compliance directives. Even if in-scope, the proposed revised definition is at best ambiguous, and could be read to unjustifiably exclude otherwise eligible generation resources from participating in Co-Located Load configurations. Accordingly, in setting a just, reasonable, and not unduly discriminatory or preferential replacement rate in this compliance proceeding, the Commission should direct PJM to either revise the Tariff using the
12 See id. at 16 (explaining that PJM is “seeking to avoid any inadvertent changes to the substantive rules pertaining to Non-Retail Behind The Meter Generation,” and the proposed Tariff changes are intended to “preserve[] the status quo” regarding the ability of Non-Retail BTMG to net against load).13 See PJM Filing, Attachment B, p. 43.
PDF page 4
4
approach suggested herein, or simply not revise the Tariff definition of Non-Retail BTMG, as discussed below.
II. PROTEST
A. PJM’s proposed definition of Non-Retail BTMG should be rejected
because it is unnecessary and could exclude otherwise eligible
generation facilities from Co-Located Load configurations.
The PJM Filing proposes the following revised Tariff definition of Non-Retail BTMG (new language underlined):
“Non-Retail Behind The Meter Generation” shall mean Behind the
Meter Generation that is used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load. Any
facility that qualifies as a Non-Retail Behind The Meter Generation
shall be excluded from Co-Located Load configurations.14
As a threshold matter, there is no evident reason to modify the definition of Non- Retail BTMG as proposed by PJM. The PJM transmittal letter is silent as to why the underlined language above has been added to the definition of Non-Retail BTMG, or why such language is needed to comply with the directives in the December 18 Order.1514 PJM Filing, Attachment B, p. 43. This definition continues to define Non-Retail BTMG with reference to the definition of BTMG, which PJM also proposes to clarify in the December 18 Order. PJM proposes the following revised definition for BTMG (new language underlined): “Behind The Meter Generation” shall mean either Retail Behind the Meter Generation or Non-Retail Behind The Meter Generation and refers to a generation unit that delivers energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent has been demonstrated to the satisfaction of the Office of the Interconnection); provided, however, that Behind The Meter Generation does not include (i) at any time, any portion of such generating unit’s capacity that is designated as a Generation Capacity Resource or DER Capacity Aggregation Resource; or (ii) in an hour, any portion of the output of such generating unit that is sold to another entity for consumption at another electrical location or into the PJM Interchange Energy Market. PJM Filing, Attachment B, p. 80.15 PJM states that similar language in the definition of Retail BTMG “is intended to provide clarity and direction to project developers about what pathways are available to serve load that is co-located, and to avoid unexpected and unintended hybrid scenarios mixing BTMG and the new transmission service
PDF page 5
5
Indeed, the Commission was clear that that it was “not direct[ing] PJM to change its rules for non-retail BTMG.”16 Accordingly, the proposed revisions to the definition of Non-Retail BTMG should be rejected as outside the scope of the compliance filing.17
Even if PJM’s proposed changes to the definition of Non-Retail BTMG are deemed to fall within the scope of its compliance obligations, the revisions are at least ambiguous and could produce a result inconsistent with PJM’s stated intent and the Commission’s directives. The problem with PJM’s proposed definition of Non-Retail BTMG arises principally from the use of the word “qualifies” in the newly added text. For practical purposes, generation capacity that is designated as Non-Retail BTMG for load netting purposes under revised section 34.3 of the Tariff and is actually utilizing such netting provisions and therefore “excluded from Co-Located Load configurations” in the event and to the extent that the generator output is netted against load, as PJM apparently intends to convey through the new definitional text, may not be denied access to relevant usable transmission service. But by triggering the exclusion from Co-Located Load configurations based on whether generation merely “qualifies” as Non-Retail BTMG (rather than focusing on whether it is actually engaged in netting and limiting the preclusion to the extent of that netting), the proposed definition sweeps too broadly. Currently, generation “qualifies” as Non-Retail BTMG under the Tariff if it: (1) meets the definition of BTMG; and (2) is “used by municipal electric systems, electric
products the Commission has directed in the [December 18 Order].” PJM Filing, Transmittal Letter at
18. As discussed herein, however, PJM’s proposed revised definition of Non-Retail BTMG would reduce the clarity of options available to generation owners and developers considering pathways to serve co- located load under the Tariff.
16 December 18 Order at P 222.17 See, e.g., PJM Interconnection, L.L.C., 173 FERC ¶ 61,244, at P 50 (2020) (explaining that “[c]ompliance filings must be limited to the specific directives ordered by the Commission,” and directing PJM to remove certain proposed Tariff provisions included in a compliance filing).
PDF page 6
6
cooperatives, or electric distribution companies to serve load.”18 Thus, any generating unit that could arguably fall within these criteria might be said to “qualify” as Non-Retail BTMG, even if the unit is not used to offset load for purposes of charges assessed under the PJM Tariff.
It is possible that owners of generation resources including municipal electric systems, electric cooperatives, or electric distribution companies (“EDCs”) with generator capacity that is not netted against load (i.e., are not serving in whole or in part as Non- Retail BTMG) may seek to serve Co-Located Load, to the extent such resources are otherwise eligible to do so under the PJM Tariff. Significantly, Part VIII, Subpart E, section 415 of the currently effective Tariff allows Non-Retail BTMG resources to be partially treated as Non-Retail BTMG and also to obtain Capacity Resource or Energy Resource status in PJM’s markets. Given that, there does not seem to be a valid rationale for excluding these resources from a Co-Located Load configuration.
But to the extent that such resources might still be said to “qualify” as Non-Retail BTMG under the Tariff, these resources could be needlessly excluded from Co-Located Load arrangements under PJM’s proposed revisions to the Non-Retail BTMG definition. PJM identifies no rationale for excluding otherwise eligible non-netting generation owned by municipal electric systems, electric cooperatives, or EDCs from participation in Co- Located Load configurations simply because they might be deemed to “qualify” as Non- Retail BTMG. Such an (apparently unintentional) exclusion would frustrate the objective of making the three proposed new transmission service options available in these
18 See PJM Filing, Attachment B, p. 43.
PDF page 7
7
circumstances to serve Co-Located Load, thereby restricting Co-Located Load from accessing service from this broad set of PJM generators.
Finally, it is not clear that PJM’s proposed exclusionary language is needed in principle. To the extent that all or a portion of a municipal, cooperative, or EDC generator is engaged in netting under the existing Non-Retail BTMG Tariff provisions, the netted portion of its output necessarily will not need access to one of the three newly proposed types of transmission service. Furthermore, PJM has not explained on the record why it would be reasonable to prohibit, for example, a municipal generating unit from serving a portion of a Co-Located Load, while the balance of that load is served from other generating resources or market purchases that are supported by any of the three new types of transmission service. Absent PJM’s proposed modification of the Non-Retail BTMG definition, it seems that the balance of PJM’s proposal, coupled with existing Tariff provisions, would permit such a supply combination. Thus, without a rational explanation in the record, the Commission should reject PJM’s revisions to the Non-Retail BTMG definition as unduly discriminatory and inconsistent with the Commission’s directives in the December 18 Order.
B. Alternatively, the Commission should direct PJM to revise its
proposed definition of Non-Retail BTMG.
If the Commission does not outright reject PJM’s revisions to the definition of Non- Retail BTMG, AMP proposes the following revised definition in lieu of PJM’s proposal: “Non-Retail Behind The Meter Generation” shall mean Behind the
Meter Generation that is used by municipal electric systems, electric
cooperatives, or electric distribution companies to serve load. The
output from any facility that (1) qualifies as Non-Retail Behind The
Meter Generation, and (2) is used for netting pursuant to Tariff, Part
III,
section
34.3 shall
be
excluded
from
Co-Located
Load
configurations, in the event of and to the extent of that netting.
PDF page 8
8
AMP’s alternative preserves PJM’s apparent intent that generating capacity designated as Non-Retail BTMG for netting purposes should not be eligible for Co-Located Load configurations, while making clear that the mere fact that a generator, as a conceptual matter, might qualify as Non-Retail BTMG does not render the generator wholly ineligible to participate in such configurations, to the extent it otherwise qualifies under the Tariff.
Directing PJM to revise its proposal as described above is well within the
Commission’s authority. PJM submitted its filing in this docket pursuant to FPA section 206 for the purpose of establishing a just and reasonable replacement rate given the Commission’s finding that certain aspects of the existing PJM Tariff were unjust, unreasonable, and unduly discriminatory or preferential. The Commission has the obligation to fix the just and reasonable replacement rate,19 and it is not restricted to accepting or rejecting PJM’s compliance proposal submitted under FPA section 206.20
19 See, e.g., 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. 2017) (citation modified) (“When the Commission changes an existing filed rate under section 206, it is the Commission’s burden to prove the reasonableness of its change in methodology.”). 20 See, e.g., Bldg. for the Future Through Elec. Reg’l Transmission Planning and Cost Allocation, Order No. 1920-B, 191 FERC ¶ 61,026, at PP 46-51 (2025) (rejecting arguments that compliance filings in a FPA section 206 proceeding implicate public utilities’ FPA section 205 filing rights).
PDF page 9
9
III. CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc.
respectfully requests that the Commission reject PJM’s proposal to revise the existing Tariff definition of Non-Retail BTMG as outside the scope of this compliance proceeding. Even if PJM’s proposed revisions to the Non-Retail BTMG definition are deemed to be within the scope of this proceeding, the Commission should direct PJM to revise the proposed definition of Non-Retail BTMG as described herein.
Respectfully submitted,
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com
DATED: March 16, 2026
/s/ Gerit F. Hull
Lisa G. McAlister
Senior Vice President & General Counsel
Gerit F. Hull
Deputy General Counsel for Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
lmcalister@amppartners.org
ghull@amppartners.org
PDF page 10
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 16th day of March, 2026.
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com