Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.’s 02/23/2026 Compliance filing
Text extracted from the eLibrary original (SHA-256 58b8a48a9b71bc7a…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
American Municipal Power, Inc. (“AMP”) hereby protests the February 23, 2026 compliance filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1 in which PJM proposes revisions to its Open Access Transmission Tariff (“Tariff”) to comply with directives in the Federal Energy…Read this passage
I. BACKGROUND AND INTRODUCTION
printed heading · Topic match: Connecting load and generation
PJM proposes to revise section 34.3 of the Tariff such that it will now be the operative provision specifying the eligibility of Non-Retail BTMG to net against Network Load.Read this passage Filed comments: Connecting load and generation
II. PROTEST
printed heading
II.Read this passage
A. PJM’s proposed definition of Non-Retail BTMG should be rejected
printed heading · Topic match: Connecting load and generation
Any facility that qualifies as a Non-Retail Behind The Meter Generation shall be excluded from Co-Located Load configurations.14 As a threshold matter, there is no evident reason to modify the definition of Non- Retail BTMG as proposed by PJM.Read this passage Filed comments: Connecting load and generation
B. Alternatively, the Commission should direct PJM to revise its
printed heading · Topic match: Cost allocation
The output from any facility that (1) qualifies as Non-Retail Behind The Meter Generation, and (2) is used for netting pursuant to Tariff, Part III, section 34.3 shall be excluded from Co-Located Load configurations, in the event of and to the extent of that netting. 8 AMP’s alternative preserves…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully requests that the Commission reject PJM’s proposal to revise the existing Tariff definition of Non-Retail BTMG as outside the scope of this compliance proceeding.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 16th day of March, 2026. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.comRead this passage