ER26-1479-000 · 2026-03-16 · Maryland Office of People's Counsel
Protest of Maryland Office of People's Counsel re PJM Interconnection, L.L.C.’s compliance filing submitted on 02/23/2026
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM INTERCONNECTION, L.L.C.
DOCKET NO. ER26-1479-000
PROTEST OF THE MARYLAND OFFICE OF PEOPLE’S COUNSEL ON PJM COMPLIANCE FILING
March 16, 2026
DAVID S. LAPP
PEOPLE’S COUNSEL
William F. Fields
Deputy People’s Counsel
Philip L. Sussler
Senior Assistant People’s Counsel
Mark S. Byrd
Assistant People’s Counsel
PDF page 2
1
Pursuant to Rules 211 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure,1 the Maryland Office of People’s Counsel (“MdOPC”) respectfully submits the following protest regarding PJM Interconnection, L.L.C.’s (“PJM”) compliance filing submitted on February 23, 2026 in the above captioned proceeding (hereinafter, “February 23 Compliance Filing”) that proposes tariff revisions with respect to behind-the-meter generation, and services available for co-located load, among other proposed revisions, to implement the Commission’s December 18, 2025 compliance directives in the co-located load show-cause proceeding (“Show Cause Order”).2
INTRODUCTION
PJM’s February 23 Compliance Filing proposes tariff revisions in compliance with the Commission’s Show Cause Order, that attempt to create clarity and consistency with regard to the rates, terms, and conditions applicable to co-location arrangements. Particularly, the February 23 Compliance Filing proposes to clarify how both new and existing generation can interconnect co-location arrangements.
However, PJM’s proposed revisions are incompatible with the Statement of Principles agreed by the White House-Governors, dated January 15, 2026 (hereinafter,
1 18 C.F.R. §§ 385.211 (2025).2 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”).
PDF page 3
2
the “Statement of Principles”)3, the Ratepayer Protection Pledge4 issued by the White House dated March 4, 2026, and PJM’s recent initiative toward implementing a reliability backstop auction (“RBA”) that began after the Show Cause Order (and in response to the Statement of Principles), and which is intended to attract revenue specifically toward new generation—not existing generators.
The proposed revisions contained in PJM’s February 23 Compliance Filing
directly contradict PJM’s plan for the RBA. Whereas PJM’s proposed revisions facilitate co-location arrangements for both new and existing generators, PJM’s RBA will procure only new generation for co-located loads, not existing generation. In other words, the Statement of Principles (and the RBA intended to implement one of its pillars)
contemplates new generation to offset the adverse impact of data centers on supply- demand. But it is unclear how PJM will achieve this RBA benefit if existing generators can serve co-located load without limit. Additionally, PJM’s proposal does not clarify how residential and other ratepayers will be protected, as required by the Ratepayer Protection Pledge, from the costs of acquiring new generation to replace existing
3 With respect to a future RBA, the Statement of Principles provides in relevant part: “Provide Revenue Certainty to New Generation: Provide 15-year price certainty for new capacity resources. This can be accomplished by holding a Reliability Backstop Auction to procure new capacity resources commencing no later than September 2026” (emphasis in original). Regarding protecting residential customers, the Statement of Principles states that due to data centers’ size and risks they pose to resource adequacy, “PJM should allocate the cost of any new capacity procured through the aforementioned Reliability Backstop Auction to load serving entities (LSEs) with new data centers that have not self-procured new capacity or agreed to be curtailable. Any remaining costs should be allocated to LSEs based on their remaining net short positions”) (emphasis in original).
4 The Ratepayer Protection Pledge provides that the pledging companies agree to, in relevant part: “build, bring or buy the new generation resources needed to satisfy their new energy demands, paying the full cost of those resources whether by building or buying from, new or otherwise additive power plants.”
PDF page 4
3
generation that has chosen to shift to a co-location arrangement under the proposed tariff revisions.
Thus, rather than providing clarity and consistency as the Commission intended, intervening events have resulted in the proposed tariff contradicting PJM’s ongoing initiatives. As a result, the proposed tariff revisions are unjust and unreasonable in their present form, without addressing and avoiding their incompatibility with the Statement of Principles and Ratepayer Protection Pledge, and understanding how the proposed tariff revisions will interact with the RBA. At a minimum, the Commission should defer action on the proposed co-location framework until PJM’s RBA proposal is finalized. BACKGROUND
Show Cause Proceeding
On February 20, 2025, the Commission initiated a show cause proceeding under section 206 of the Federal Power Act to determine whether PJM’s tariff is just and reasonable and not unduly discriminatory or preferential without provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Co-Location Arrangements.5 On December 18, 2025, the Commission determined that PJM’s tariff is unjust and unreasonable, explaining that the tariff:
does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load, including generators serving Co-
Located Load in a configuration with special protection schemes to prevent the Co-Located Load from taking energy from the transmission system.65 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025).6 Show Cause Order at P 249.
PDF page 5
4
The Commission found that:
the absence of such provisions leaves entities unable to determine what steps they must take to effectuate Co-Location Arrangements, which creates uncertainty that has resulted in disparate treatment in PJM, where transmission owners have taken different approaches to performing the necessary steps that apply to Interconnection Customers seeking to serve Co-Located Load through a Co-Location Arrangement, leading to no consistent understanding of entities’ responsibilities with respect to their planned Co-Location Arrangements. We also find that PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the transmission system under certain conditions. Further, we find that PJM’s Tariff is unjust and unreasonable because it does not address charges related to Co-Located Loads’ use of regulation and black start services, which introduces the risk that Co-Located Loads may benefit from regulation and black start services without contributing to cost recovery for such services and, thereby, the risk that costs may be allocated entirely to other transmission customers and passed through to residential customers, among others.7
The Commission clarified that an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its Capacity Interconnection Rights for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving NITS.8
The Commission directed PJM to revise its tariff to provide sufficient clarity regarding the responsibilities of existing interconnection customers seeking to serve co- located load using their generating facilities.9 The Commission also directed PJM to file tariff changes specifying that an interconnection customer seeking to serve co-located
7 Id. P 175.8 Id. P 230.9 Id. P 225.
PDF page 6
5
load using an existing generating facility must bear the costs of all network upgrades that PJM finds are necessary to preserve transmission system reliability for existing transmission customers.10
Furthermore, the Show Cause Order also required that PJM define “Co-Located Load” as a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.”11
February 23 Compliance Filing
PJM’s February 23 Compliance Filing generally sets forth the relative obligations of project developers seeking to serve co-located load, and PJM. The proposal defines “Co-Located Generating Facility” as “an existing or planned Generating Facility that is physically connected to a Co-Located Load,” and “Co-Located Load” as “a configuration that refers to end-use customer load that is physically connected to the facilities of an existing or planned Generating Facility on the Project Developer’s side of the Point of Change in Ownership to the Transmission Provider’s Transmission System.”12 Importantly, these definitions appear to accommodate not only new generators, but existing generators seeking to serve co-located load.
10 Id. P 176.11 Id. P 164.12 Proposed Tariff Revisions, Part I, Definition of Co-Located Load.
PDF page 7
6
Additionally, the February 23 Compliance Filing proposes tariff revisions requiring that “[a] Project Developer whose planned modifications include Co-Located Load configuration shall be required to enter into a Necessary Studies Agreement with Transmission Provider in the form set forth in Tariff, Part IX, Subpart G.”13 The proposed tariff revisions would require a Project Developer to provide the Transmission Provider with “the amount of reduction to Capacity Interconnection Rights to facilitate the Co- Located Load configuration.”14 The proposed revisions also provide that: Project Developer shall be responsible for the costs of any modifications or Network Upgrades identified by Transmission Provider, as applicable, as a result of the change to the Interconnection Service Agreement or
Generation Interconnection Agreement to serve Co-Located Load,
including to reflect any reduction in Capacity Interconnection Rights.15
“Capacity Interconnection Rights” (“CIRs”) are previously defined in PJM’s tariff as “the rights to input generation as a Generation Capacity Resource into the Transmission System at the Point of Interconnection where the generating facilities connect to the Transmission System.”16 Thus, the proposed revisions appear to accommodate new generators seeking to serve co-located load, as well as existing generators seeking to serve co-located load by reducing their CIRs, and thus their ability to input generation onto PJM’s transmission system.
13 Id. Part VIII, Subpart A, section 401.H.3.b.
14 Id. Section 401.H.3.b.i.c.15 Id. Section 401.H.3.b.iii.16 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - C - D (40.1.1).
PDF page 8
7
White House and PJM Governors Statement of Principles and White House Pledge On January 15, 2026, the National Energy Dominance Council within the White House and thirteen governors of states within PJM signed the Statement of Principles urging PJM to expeditiously file proposed tariff revisions with the Commission that reflect a set of principles for how generation capacity for data centers should be procured, and how costs should be allocated to data centers to protect residential customers.17 Specifically, under these principles, PJM should hold a RBA to procure new capacity resources, with the costs of such new capacity going primarily to load serving entities with new data centers that have not self-procured new capacity or agreed to be curtailable.18
On March 4, 2026, the White House issued the Ratepayer Protection Pledge that companies will build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants.19 The pledge also provides that where possible, these companies will also add more capacity that serves the broader public by increasing supply.2017 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.18 Id. at 1.19 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, https://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ (Mar. 4, 2026).20 See id.
PDF page 9
8
PROTEST
I. PJM’s proposed tariff revisions are unjust and unreasonable because it is unclear how they will interact with PJM’s implementation of the RBA.
As explained by the Commission in the Show Cause Order, PJM’s tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co- Located Load.21 However, in light of the Statement of Principles issued jointly by the White House and thirteen governors of states within PJM, the Ratepayer Protection Pledge, and PJM’s subsequent responsive work toward instituting a RBA to be held toward the end of 2026, PJM’s tariff remains without sufficient clarity and consistency. The Statement of Principles directed PJM to hold an RBA to procure new capacity resources.22 The Statement of Principles further urges that costs of such new capacity should go primarily to load serving entities with new data centers that have not self- procured new capacity or agreed to be curtailable.23 The Ratepayer Protection Pledge also commits the major data center developers to procure new capacity resources to serve their needs. Thus, the thrust of the Statement of Principles and the Ratepayer Protection Pledge is that generally new data centers should pay for new capacity.
Under this framework, new data centers that are not served by self-procured new co-located generation could be subject to higher costs from the load serving entity as
21 See Show Cause Order at P 2.22 See Statement of Principles at 1.23 See id.
PDF page 10
9
result of the RBA. But PJM’s proposed tariff revisions do not explain how existing capacity resources that shift to co-located arrangements with new data centers would be treated relative to the RBA. For example, it is unclear whether the capacity of existing generators that enter co-location arrangements with new data center load would be added to the capacity required to be procured in the RBA, or to the capacity procured in the regular base residual auction (“BRA”).
If the capacity of existing generation that shifts to serve new co-located data center load is added to the BRA, ratepayers would be saddled with enormous costs that should be assigned to the co-located load, in contravention of the Statement of Principles and the Ratepayer Protection Pledge. For example, recent analysis by PJM’s Independent Market Monitor concluded that if 1,000 UCAP MW of nuclear capacity in Maryland was removed—due to shifting to serving a co-located load for example—total market revenues for the 2025/2026 BRA would increase by more than $3.6 billion.24 Yet PJM’s compliance filing provides no explanation as to how such costs would be paid by new co- located data center load rather than being shifted to existing ratepayers. PJM’s compliance filing thus leaves significant and fundamental questions unanswered with respect to how existing generation can serve new co-located data center load. Without providing more details regarding how the proposal will align with PJM’s plans for the RBA, PJM’s proposal remains unclear and inconsistent with the Statement
24 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 (Sep. 24, 2024) at 3, https://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf.
PDF page 11
10
of Principles underpinning the RBA. This lack of clarity and consistency causes PJM’s tariff to remain unjust and unreasonable. At a minimum, the Commission should defer action on the proposed revisions until PJM announces details regarding its planned RBA, including specifics on how the RBA will interact with co-located arrangements to ensure that new co-located loads pay the costs of any new capacity.
CONCLUSION
The issuance of the Statement of Principles by the White House and thirteen governors of states within PJM calling for an RBA to serve new data center load and the Ratepayer Protection Pledge are salient intervening events that have occurred since the Show Cause Order issued. However, despite the significance of PJM’s work toward implementing an RBA, fundamental issues surrounding how existing generators that shift to serve co-located load under PJM’s proposed tariff revisions will be treated relative to the RBA remain unaddressed. As a result, PJM’s proposed revisions do not provide the clarity and consistency required by the Show Cause Order. PJM’s proposed tariff revisions thus are unjust and unreasonable without a complete picture of how they will interact with the RBA. At the very least, the Commission should defer action on the proposed revisions until PJM proposes tariff revisions to implement the RBA.
Respectfully submitted,
DAVID S. LAPP
PEOPLE’S COUNSEL
PDF page 12
11
William F. Fields
Deputy People’s Counsel
Philip L. Sussler
Assistant People’s Counsel
/electronic signature/
Mark S. Byrd
Assistant People’s Counsel
Office of People’s Counsel
6 St. Paul Street, Suite 2102
Baltimore, Maryland 21202
(410) 767-3908
PDF page 13
12
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing pleading to be served upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated this 16th day of March, 2026.
/s/ electronic signature----_____
Mark S. Byrd