Protest of Maryland Office of People's Counsel re PJM Interconnection, L.L.C.’s compliance filing submitted on 02/23/2026
Text extracted from the eLibrary original (SHA-256 d244d3d1df2d2cf0…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Byrd Assistant People’s Counsel 1 Pursuant to Rules 211 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure,1 the Maryland Office of People’s Counsel (“MdOPC”) respectfully submits the following protest regarding PJM Interconnection, L.L.C.’s (“PJM”) compliance filing…Read this passage Filed comments: Connecting load and generation
INTRODUCTION
printed heading · Topic match: Cost allocation
INTRODUCTION PJM’s February 23 Compliance Filing proposes tariff revisions in compliance with the Commission’s Show Cause Order, that attempt to create clarity and consistency with regard to the rates, terms, and conditions applicable to co-location arrangements.Read this passage Filed comments: Cost allocation
BACKGROUND
printed heading · Topic match: Connecting load and generation
P 164. 12 Proposed Tariff Revisions, Part I, Definition of Co-Located Load. 6 Additionally, the February 23 Compliance Filing proposes tariff revisions requiring that “[a] Project Developer whose planned modifications include Co-Located Load configuration shall be required to enter into a Necessary…Read this passage Filed comments: Connecting load and generation
I. PJM’s proposed tariff revisions are unjust and unreasonable because it is
printed heading · Topic match: Cost allocation
If the capacity of existing generation that shifts to serve new co-located data center load is added to the BRA, ratepayers would be saddled with enormous costs that should be assigned to the co-located load, in contravention of the Statement of Principles and the Ratepayer Protection Pledge.Read this passage Filed comments: Cost allocation
CONCLUSION
printed heading · Topic match: Cost allocation
At the very least, the Commission should defer action on the proposed revisions until PJM proposes tariff revisions to implement the RBA.Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
Dated this 16th day of March, 2026. /s/ electronic signature----_____ Mark S.Read this passage