ER26-1479-000 · 2026-03-16 · Crusoe Energy Systems, Inc.

Comments of Crusoe Technologies LLC in response to PJM Interconnection, L.L.C.’s 60-Day Compliance Filing for Co-Located Load Related Revisions to Open…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

Docket No. ER26-1479-000

COMMENTS OF CRUSOE TECHNOLOGIES LLC

In accordance with Rules 212 and 213 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure1 Crusoe Technologies LLC (Crusoe) respectfully submits these comments in response to PJM Interconnection, L.L.C.’s (PJM) 60- Day Compliance Filing2 filed on February 23, 2026 (PJM Compliance Filing).  The PJM Compliance Filing was submitted in response to the Commission’s December 18, 2025 Order on Show Cause Proceeding,3 regarding the co-location of large loads in PJM.

I. SUMMARY OF COMMENTS
Crusoe appreciates PJM’s efforts to advance large load interconnection and its thoughtful engagement with stakeholders in developing a workable approach.  Crusoe supports policy efforts that facilitate “bring your own power” frameworks and are built on an energy- first model that allow co-located generation to enhance grid reliability, reduce ratepayer costs, and accelerate the buildout of AI infrastructure.  Crusoe believes that certain targeted revisions to PJM’s compliance filing will help ensure the Commission’s December 18 Order achieves its purpose of enabling large loads to interconnect quickly and reliably while protecting the transmission system and other ratepayers.

1 18 C.F.R. §§ 385.212, 385.213 (2025).
2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related to Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., FERC Docket No. ER26-1479-000 (Feb. 23, 2026) (PJM Compliance Filing).
3 PJM Interconnection, L.L.C., et al., 193 FERC ¶ 61,217 (2025) (December 18 Order).

PDF page 2

Docket No. ER26-1479-000

2

First, PJM’s proposed 50 MW materiality threshold for new Retail Behind-the-Meter Generation (Retail BTMG) is too low and could produce unjust and unreasonable outcomes for larger co-located loads.  The Commission should direct PJM to revise the threshold upward and calibrate it to the size of the co-located load at the relevant electrical location.  Second, while PJM’s Interim Network Integration Transmission Service (Interim NITS) is a useful tool to help facilitate large load interconnections, it should be clarified to ensure that co-located generation is able to supply co-located load during curtailment events, including while the generator is still being studied in the interconnection process.

Third, while Crusoe supports PJM’s proposed menu of three new transmission service options, the Commission should direct PJM to provide clear Tariff procedures for establishing, adjusting, and terminating Contract Demand quantities over time and clarify how point-to-point service coordinates with co-location arrangements.

Finally, a well-designed Necessary Studies process is the cornerstone of a successful Co-Located Load interconnection framework.  The Commission has a clear opportunity to establish a process that is both expeditious and predictable — one that gives developers the certainty they need to invest with confidence and move projects forward at the speed the market demands.

To realize this opportunity, the Commission should take three affirmative steps.  First, establish binding study timelines with enforceable milestones that bring discipline and accountability to the review process.  Second, focus study scope where it matters most — on reliability impacts directly attributable to non-exporting resources — ensuring reviews are targeted, efficient, and technically sound.  Third, adopt and publish a clear, transparent standard for study triggers, giving all stakeholders a common roadmap and eliminating the ambiguity

PDF page 3

Docket No. ER26-1479-000

3

that slows project development.  Together, these measures will transform the Necessary Studies process into a genuine enabler of Co-Located Load interconnection — providing the speed, transparency, and reliability that both the Commission and the market need to unlock the full potential of co-location.

II. BACKGROUND
Crusoe is a vertically integrated Artificial Intelligence (AI) infrastructure company that builds, owns, and operates data centers specifically optimized for the high-performance computing requirements of AI and machine learning workloads.  Crusoe’s “bring your own power” philosophy is founded on the goal of harnessing stranded and otherwise wasted energy to power computation.  Crusoe's business model is built on an energy-first approach—where co-located generation, when structured correctly, simultaneously advances grid reliability, reduces ratepayer costs, and accelerates AI infrastructure.  Crusoe appreciates PJM's engagement with stakeholders on this matter and recognizes that PJM's decisions here may serve as a national model.

Crusoe supports the Commission's goal of creating a clear, workable framework with optionality for interconnecting new large loads embedded in the new transmission service options.  Our goal is speed to power responsibly.  Crusoe’s guiding principle is straightforward: move the compute to the energy, not the other way around.  Traditional data center development follows the grid – waiting for interconnection approvals, straining existing infrastructure, and too often driving up electricity costs for the communities it enters.  Crusoe takes the opposite approach and instead locates AI workloads near sources of abundant, often underutilized energy – tapping into places traditional data centers do not reach.

PDF page 4

Docket No. ER26-1479-000

4

Crusoe's primary operations involve sourcing and developing cost-effective energy, including natural gas, renewable power (e.g., wind, solar) and battery storage, to power its data center facilities.  Crusoe leverages its in-house manufacturing capabilities to rapidly deploy computing infrastructure that provides reliable, low-latency cloud services, including access to leading-edge graphics processing units (GPUs), to enterprise customers and AI developers. Through its energy-first approach, Crusoe aims to reduce both the cost and the environmental impact of utility-scale computing infrastructure.

III. COMMENTS
A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG
Should Be Revised Upward.

PJM proposes a materiality threshold of up to 50 MW for a new generator to qualify as Retail BTMG, contending that this threshold corresponds with the PJM Board’s definition of large load additions (i.e., individual loads of 50 MW or greater at a single point of interconnection).  Crusoe respectfully submits that this threshold is misaligned with the regulatory purpose it purports to serve and will undermine the very policy goals the Commission sought to advance in the December 18 Order.

The 50 MW threshold, while aligned with the PJM Board’s definition of large load additions, was designed as an administrative planning threshold, not as a bright-line test for what constitutes a reliability risk.  Applying the threshold as the sole determinant of Retail BTMG eligibility conflates two distinct regulatory purposes.  A planning metric developed to identify large load additions for administrative purposes is not, and should not become, a proxy for measuring when behind-the-meter generation creates transmission system risk.  The Commission should decline to treat these two distinct purposes as interchangeable.

PDF page 5

Docket No. ER26-1479-000

5

Large loads come in many sizes, and co-location arrangements can vary significantly. The Retail BTMG threshold should be flexible and non-discriminatory to account for these differences.  A fixed 50 MW cap raises serious concerns about disparate treatment of large loads of different sizes.  PJM’s own filing acknowledges that a lower threshold risks forcing existing BTMG resources offline during the transition period—an outcome that would increase grid burden, not reduce it, by converting currently netted load into full network load without corresponding new capacity additions.4  This outcome warrants careful consideration by the Commission, as it does not reflect a principled distinction among similarly situated customers.

Stripping a new large load of netting rights if it has Retail BTMG greater than 50 MW penalizes the very co-location configurations that can ease grid congestion.  BTMG arrangements can benefit the transmission system in many ways, such as by serving load on a streamlined basis, avoiding queue delays in the generator interconnection process, and by reducing the need for expensive grid upgrades.  These are not speculative benefits – they are the precise outcomes the Commission’s bring your own power framework was designed to produce.

The optimal sizing of Retail BTMG (such as solar plus battery energy storage systems or some other combination) to support AI data center would most certainly exceed 50 MW. Accordingly, Crusoe supports an approach that limits the size of Retail BTMG in proportion to the size of the load.

4 PJM Compliance Filing at 12 (Sec. III.A.2.c).

PDF page 6

Docket No. ER26-1479-000

6

B. PJM’s Proposed Interim NITS Framework Must Allow Co-Located
Generation and Retail BTMG to Serve Co-Located Load During
Curtailment Events on the Grid.

PJM proposes Interim NITS as a transition service until the transmission system can support the large load customer’s NITS request.5  According to PJM, “Interim NITS is premised on the notion that the Co-Located Load is willing and able to limit its energy withdrawals from the Transmission System prior to NITS being available.6  Crusoe supports Interim NITS as a bridge service where it adds genuine value: the period during which a single building or phase of a data center campus is coming online while co-locating  generation and/or Retail BTMG is still being built and interconnected.  In that context, Interim NITS provides a workable, near-term solution to allow load to operate on the transmission system. PJM’s proposed approach to implementing Interim NITS, however, appears to treat new Co-Located Generating Facilities as equivalent to full PJM Resources prior to the Co-Located Generating Facilities receiving firm Network Resource status.  It is not clear if PJM intends to prevent Co-Located Generating Facilities or Retail BTMG from supplying energy to Co- Located Load during a grid curtailment event if the Co-Located Load is at that time being served via Interim NITS.  If that is PJM’s proposal, it would create a large disincentive to large load customers from utilizing Interim NITS as an option for speedy interconnection.  If large load customers cannot rely upon their own Co-Located Generating Facilities or Retail BTMG during the Interim NITS period, it would create a significant disincentive and effectively nullify Interim NITS as a viable transmission service option and commercial pathway.

5 Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49, at 67 (Feb. 23, 2026) (PJM Brief).
6 PJM Brief at 71.

PDF page 7

Docket No. ER26-1479-000

7

This concern is not unique to Crusoe.  Large loads electing to take Interim NITS accept the risk of grid curtailment, but they should not have to completely shut down during a grid curtailment if they can rely on co-located generation or Retail BTMG without relying on the transmission grid.  The PJM tariff should allow a Co-Located Generating Facility to serve its Co-Located Load directly—without grid injection—while still being studied through the applicable generator interconnection study process.

C. PJM’s Proposed Three New Transmission Service Options Should Be
Accepted, With Additional Guidance on Contract Demand Procedures.

Crusoe strongly supports the Commission’s decision to create a menu of transmission service options.  The ability to right-size transmission service to actual grid dependence is a smart policy approach that aligns cost of transmission service with actual usage.  Crusoe supports PJM’s proposed three new transmission service options that will benefit large load customers.  According to PJM, large load customers will have the option to take a combination of Firm and Non-Firm Contract Demand Transmission Service, so long as the combined service fully covers the co-located load's total load.7  The new transmission service options will encourage flexible co-location structures that will enable speedy and reliable interconnection for large loads.

Firm Contract Demand Transmission Service is the appropriate long-term service for data centers that have stable, predictable on-site generation and limited grid draw.  Non-Firm Contract Demand provides valuable optionality for sites where grid dependence varies.  This is especially true for Crusoe’s phased campus development model, where generation and load come online in stages.  The three-service menu allows Crusoe to right-size its transmission

7 Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 at 7 (Feb. 23, 2026).

PDF page 8

Docket No. ER26-1479-000

8

service obligations as each phase matures, avoiding unnecessary costs during buildout while ensuring the grid is protected at every stage.

However, the illustrative Tariff language in the PJM Brief leaves certain critical questions unanswered regarding how the contract demand MW quantity is established and modified over time.8  The compliance filing does not (1) explain how the initial contract demand quantity is determined (i.e., whether by customer request, as determined by study, or by some other mechanism), (2) address whether contract demand quantities can be adjusted as load grows in phases or (3) specify how point-to-point transmission service interacts with co- location arrangements where both generation and load sit on the developer's side of the Point of Change in Ownership.

These are important implementation details for a multi-gigawatt campus developer like Crusoe.  An inability to adjust contract demand quantities in step with phased load growth would require either over-purchasing transmission service in early phases or risk non- compliance as load grows.  The Commission should ensure that the final Tariff language does not place large load customers in this position by directing PJM to provide detailed procedures for establishing, adjusting, and terminating Contract Demand quantities, and to clarify how point-to-point transmission service coordinates with co-location configurations in the final Tariff language.

8 PJM Brief, Attachment A, Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions.

PDF page 9

Docket No. ER26-1479-000

9

D. The Necessary Studies Process Must Be Expeditious and Not Become a
Barrier to Co-Located Load Development.

The Necessary Studies process must be fast, predictable, and not become a barrier to interconnecting new Co-Located Load.  A Necessary Studies process that introduces open- ended timelines, redundant review of generation resources that are not being injected into the grid, or unclear criteria for what triggers a study will directly undermine this goal.  The PJM Necessary Studies should be designed with stakeholders and practical timelines in mind. Crusoe recommends a series of workshops with industry to design these timelines.  In this regard, PJM should  (1) establish binding timelines for the completion of Necessary Studies applicable to Co-Located Load; (2) limit the scope of Necessary Studies where new generation resources are not interconnecting to the transmission system to reliability impacts only; and (3) create a clear, published standard for what triggers a Necessary Study so that developers can plan with certainty.  Speed and certainty in the Necessary Studies process are not in tension with reliability, they are prerequisites for delivering the AI infrastructure capacity the nation requires at the pace the market demands.

IV. CONCLUSION
For the reasons discussed above, Crusoe Technologies LLC respectfully urges the Commission to adopt targeted revisions to PJM’s compliance filing that will facilitate the reliable and timely interconnection of large loads, support the development of flexible co- location arrangements, and ensure that necessary studies and tariff procedures do not create unnecessary barriers for innovative energy-first data center models. By refining the materiality threshold for Retail BTMG, clarifying the application of Interim NITS, providing detailed guidance for contract demand procedures, and ensuring an expeditious and transparent studies

PDF page 10

Docket No. ER26-1479-000

10

process, the Commission can advance its policy objectives while protecting the interests of the transmission system and ratepayers. Crusoe appreciates the Commission’s and PJM’s ongoing engagement with stakeholders and looks forward to continued collaboration in building a robust framework for the next generation of AI infrastructure.

Respectfully submitted,

______________________
Sara Axelrod

Carrie Collier-Brown
Bharath Ravulapati

Linda Walsh
Crusoe Technologies LLC

Michael Blackwell
255 Fillmore Street

Husch Blackwell LLP
Denver, CO 80202

1801 Pennsylvania Ave., NW, Suite 1000
ssteele@crusoe.ai

Washington, DC  20006
bravulapati@crusoe.ai

Tel: (202) 378-2308

linda.walsh@huschblackwell.com

michael.blackwell@huschblackwell.com

Counsel to Crusoe Technologies LLC
Dated: March 16, 2026

PDF page 11

CERTIFICATE OF SERVICE

Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C. this 16th day of March 2026.

/s/ Laura Arboleda Bowie

Laura Arboleda Bowie
Husch Blackwell LLP