ER26-1479-000 · 2026-03-16 · Crusoe Energy Systems, Inc.

Comments of Crusoe Technologies LLC in response to PJM Interconnection, L.L.C.’s 60-Day Compliance Filing for Co-Located Load Related Revisions to Open…

Text extracted from the eLibrary original (SHA-256 c7de1dfcff335f34…). Download the original from the official source.

Contents · 8 sections
  1. I. SUMMARY OF COMMENTS p. 1
  2. II. BACKGROUND p. 3
  3. III. COMMENTS p. 4
  4. A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG p. 4
  5. B. PJM’s Proposed Interim NITS Framework Must Allow Co-Located p. 6
  6. C. PJM’s Proposed Three New Transmission Service Options Should Be p. 7
  7. D. The Necessary Studies Process Must Be Expeditious and Not Become a p. 9
  8. IV. CONCLUSION p. 9

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. SUMMARY OF COMMENTS

printed heading · Topic match: Connecting load and generation

Crusoe supports policy efforts that facilitate “bring your own power” frameworks and are built on an energy- first model that allow co-located generation to enhance grid reliability, reduce ratepayer costs, and accelerate the buildout of AI infrastructure.
Read this passage Filed comments: Connecting load and generation

II. BACKGROUND

printed heading · Topic match: Cost allocation

Crusoe's business model is built on an energy-first approach—where co-located generation, when structured correctly, simultaneously advances grid reliability, reduces ratepayer costs, and accelerates AI infrastructure.
Read this passage Filed comments: Cost allocation

III. COMMENTS

printed heading

III.
Read this passage

A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG

printed heading

PJM proposes a materiality threshold of up to 50 MW for a new generator to qualify as Retail BTMG, contending that this threshold corresponds with the PJM Board’s definition of large load additions (i.e., individual loads of 50 MW or greater at a single point of interconnection).
Read this passage

B. PJM’s Proposed Interim NITS Framework Must Allow Co-Located

printed heading · Topic match: Connecting load and generation

PJM’s Proposed Interim NITS Framework Must Allow Co-Located Generation and Retail BTMG to Serve Co-Located Load During Curtailment Events on the Grid.
Read this passage Filed comments: Connecting load and generation

C. PJM’s Proposed Three New Transmission Service Options Should Be

printed heading · Topic match: Connecting load and generation

According to PJM, large load customers will have the option to take a combination of Firm and Non-Firm Contract Demand Transmission Service, so long as the combined service fully covers the co-located load's total load.7 The new transmission service options will encourage flexible co-location…
Read this passage Filed comments: Connecting load and generation

D. The Necessary Studies Process Must Be Expeditious and Not Become a

printed heading · Topic match: Connecting load and generation

The Necessary Studies Process Must Be Expeditious and Not Become a Barrier to Co-Located Load Development.
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading · Topic match: Cost allocation

ER26-1479-000 10 process, the Commission can advance its policy objectives while protecting the interests of the transmission system and ratepayers.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 16th day of March 2026. /s/ Laura Arboleda Bowie Laura Arboleda Bowie Husch Blackwell LLP 1801 Pennsylvania Ave.