EL25-49-000 · 2026-03-25 · Enchanted Rock, LLC

Reply Brief and Protest of Enchanted Rock, LLC in response to PJM Interconnection, L.L.C.’s initial brief filed on 02/23/2026

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-located at Generating
Facilities
)
)
)

Docket No. AD24-11-000
Constellation Energy Generation, LLC
    v. PJM Interconnection, L.L.C.
)
)
)
)

Docket No. EL25-20-000

(consolidated)

)
PJM Interconnection, L.L.C.

     )

  Docket No. ER26-1479-000

REPLY BRIEF AND PROTEST OF ENCHANTED ROCK

Pursuant to Rule 2111 of the Federal Energy Regulatory Commission (“FERC” or
“Commission”)’s rules of practice and procedure, and ordering paragraphs (D) and (E) of the Order on Show Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting in Part and Denying in Part Complaint, issued by the Commission on December 18, 2025,2 Enchanted Rock, LLC (“Enchanted Rock”) hereby files this reply brief and protest (collectively, “Protest”) to: 1) respond to PJM Interconnection, L.L.C.’s (“PJM”) initial brief, submitted on February 23, 2026;3 and 2)  respond to PJM’s February 23, 2026 compliance filing submitted in response to the Commission’s December 18 Order.4

1 18 C.F.R. § 385.211 (2026).
2 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Order”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al., at 3 (Jan. 23, 2026) (granting a 7-day extension of the deadline in ordering paragraph (D) of the December 18 Order for parties to submit reply briefs). 3 Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Feb. 23, 2026) (“PJM Initial Brief”).

4 See 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al, Docket No. ER26-1479-000 (Feb. 23, 2026) (“PJM February 23 Compliance Filing”).

PDF page 2

2
This Protest challenges a limitation that PJM seeks to impose related to the provision of Interim Network Integration Transmission Service (“Interim NITS” 5).  More specifically, as described by PJM to stakeholders –  but not set forth in its Initial Brief, Illustrative Tariff or the February 23 Compliance Filing – PJM intends to prohibit Co-Located Load from receiving any capacity or energy from a Co-Located Generating Facility while the Co-Located Load is taking Interim NITS (sometimes referred to herein as the “Proposed Interim NITS Limitation”).6  For the reasons set forth below in further detail, PJM’s Proposed Interim NITS Limitation runs afoul of the Commission’s applicable findings and directives in the December 18 Order, including Commissioner Rosner’s unequivocal statements in his concurring opinion to the December 18 Order explaining that a Co-Located Load “can take service directly from the generator” while the Co-Located Load is taking Interim NITS7 (sometimes referred to herein as the “Interim Period”). Moreover, PJM’s Proposed Interim NITS Limitation, if enacted, would make it

commercially impractical for Eligible Customers to ever utilize Interim NITS to serve their Co- Located Load, thus undermining the Commission’s goals of establishing Interim NITS in order to “facilitate the timely provision of transmission service to Eligible Customers taking

5 All capitalized terms not otherwise defined herein shall have the same meaning set forth in the PJM Open Access Transmission Tariff (“PJM Tariff”), or the Illustrative Language For New Tariff (“Illustrative Tariff”) filed with the PJM Initial Brief, as applicable.

6 See PJM Staff, Co-Located Load Use Cases, at 12 (March 16, 2026),(“Co-located load taking Interim NITS service will not have rights to the capacity/energy from any specific co-located generation”), available at: https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260316/20260316-item-02--- co-located-load-use-cases---presentation.pdf (“PJM Staff March 16 Presentation”); see also PJM Staff, Preliminary/Working Draft of Concepts as of January 23, 2026: Transmission Services Proposal – High Level Overview, at 4 (Jan. 23, 2026), (“[i]f curtailed, [Eligible Customer] cannot take energy from co-located generator.”), available at: https://www.pjm.com/-/media/DotCom/committees- groups/workshops/cllsco/2026/20260126/20260126-item-01---transmission-services-concepts-for-discussion.pdf. (“PJM Staff January 23 Draft Concepts”). 7 See December 18 Order. Commissioner Rosner, Concurring at P 11 (“Rosner Concurrence”). In the December 18 Order, the Commission issued several directives to PJM related to establishing a “new interim, non-firm transmission service.”  See, e.g., December 18 Order at P 160.  PJM has proposed to define this new transmission service as “Interim NITS.”  See, e.g., PJM Initial Brief at 1.  For the sake of efficiency and clarity, Enchanted Rock will refer to this new transmission service only as “Interim NITS” herein.

PDF page 3

3
transmission service on behalf of Co-Located Loads, while preserving reliability for other transmission customers,”8 and to address interconnection delays faced by large load interconnection customers.9

For these reasons, and the reasons set forth herein, Enchanted Rock respectfully requests that in any final order issued in the above-captioned proceedings, that the Commission 1) hold that PJM’s Proposed Interim NITS Limitation is prohibited, and 2) direct PJM to file revisions to its tariff to clarify that a Co-Located Load can be served by its Co-Located Generating Facility during the Interim Period, consistent with the applicable holdings and directives in the December 18 Order.

I. BACKGROUND
i. Justification for Interim NITS
In response to the Commission’s February 20, 2025 order to show cause,10 several parties recommended that “the Commission explore the potential to develop a new level of non-firm or interruptible transmission service that prioritizes connection of new flexible loads, regardless of whether they are co-located with generation.”11  Among these parties was Enchanted Rock, which filed extensive comments supporting the establishment of a new, interim non-firm transmission service to enable large load customers to interconnect faster while maintaining overall reliability of the transmission system.12

As the Commission recognized in its December 18 Order, “Enchanted Rock supports a transitional non-firm service where the load relies on PJM to provide energy, but where the load

8 See December 18 Order at P 201.
9 See id.
10 PJM Interconnection, et al., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
11 December 18 Order at P 80 (citations omitted).
12 See Response of Enchanted Rock, LLC, Docket Nos. EL25-49-000, et al. (Apr. 23, 2025) (“Enchanted Rock April 23 Comments”).

PDF page 4

4
is under a commitment to dispatch co-located generation during PJM curtailments.”13  The Commission further recognized that Enchanted Rock proposed that “the co-located facilities could be quickly interconnected and would only require curtailment in a small number of hours of a year, allowing more efficient use of generation resources and transmission capacity, lowering costs to customers, and buying time for new infrastructure to be built.”14 The Commission noted that in order to “facilitate more rapid interconnection and operation of Co-Located Loads” PJM and other parties discussed “the development of a new transitional service that would allow new Co-Located Load to withdraw electricity from the PJM transmission system earlier than may be otherwise achievable if those new Co-Located Loads could only be designated as Network Load and served once all of the Network Upgrades necessary to provide the requested NITS are complete.”15

ii. Commission Directives Related to Interim NITS
In response to these parties’ comments, the Commission directed PJM to “create a new interim, non-firm transmission service  . . .  [to] allow an Eligible Customer that has requested NITS on behalf of a Co-Located Load to take non-firm transmission service that can be interrupted until the Network Upgrades necessary to provide NITS are complete and the Co- Located Load can be designated as Network Load.”16  This “new interim, non-firm transmission service” is what PJM defines as “Interim NITS.”

The Commission further held that Interim NITS would help to address interconnection delays faced by large load customers by “allowing an Eligible Customer that has requested to take NITS on behalf of a Co-Located Load to, through this new transmission service, receive an

13 See December 18 Order at P 80 (citing Enchanted Rock April 23 Comments at 10-12).
14 See id.
15See id. at P 200 (citations omitted).
16 See id.

PDF page 5

5
interruptible transmission service before the Network Upgrades necessary to designate and serve the Co-Located Load as Network Load are complete.”17   Moreover, the Commission held that “when curtailed, Eligible Customers taking this transmission service on behalf of Co-Located Loads may be able to continue to take energy from the Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”18  The Commission directed PJM to file tariff revisions implementing this new service.19

Notably, in his concurring opinion to the December 18 Order, Commission Rosner described the Commission’s rationale behind ordering the establishment of Interim NITS in further detail, as well as how it is intended to be implemented in practice: today’s order directs PJM to establish a new interim service (see Figure 4) to provide a bridge while the infrastructure needed to serve a large load with traditional front-of-meter network transmission service is being built.  This interim service leverages speed in the near-term and unlocks the benefits of a full grid connection in the long-term.  It will allow co-located loads and generators seeking front-of-meter service to access the grid faster than they can today.  In exchange for increased speed, these loads will bear the risk of being curtailed when the grid is constrained until the transmission upgrades needed to provide service are constructed.  But that doesn’t mean that the load will always have to shut down completely during peak periods.  Rather, if the co-located load is paired with a new generator, and that generator is still waiting to begin its own front-of-meter service, the load can take service directly from the generator in the interim until both “graduate” to full, front-of-meter service.  This pathway is important because traditional, front-of-meter network transmission service provides the broadest benefits to both load and generators—a network load can be served by any generator on the grid, and a network generator can sell its power to any customer on the grid.20

Additionally, in Commissioner Rosner’s Figure 4 describing Interim NITS, it states that the “Generator can serve load while awaiting grid connection or when grid is unavailable.”21

17 See December 18 Order at P 201.
18 Id.
19 See id.
20 Rosner Concurrence at P 11(emphasis removed, emphasis added).
21 See Rosner Concurrence, Figure 4.

PDF page 6

6
Accordingly, as made unequivocally clear by Commissioner Rosner’s concurring statements, the Commission intended for a Co-Located Load taking Interim NITS to be able to utilize energy and capacity provided by a Co-Located Generating Facility during the period in which the Co- Located Load and Co-Located Generating Facility are being studied for full NITS (i.e., during the temporary Interim Period).  This makes sense, as large load customers (particularly data centers), cannot bear commercial risks associated with being fully offline for any material amount of time, meaning that in order to utilize Interim NITS, Co-Located Load will need to be served by their Co-Located Generating Facilities during periods in which they may be curtailed.

iii. PJM’s Proposed Implementation of Interim NITS
In response to the Commission’s directives related to Interim NITS in the December 18 Order, PJM filed the February 23 Compliance Filing (which provided a “shell” of Tariff, Part XI, to show that Interim NITS will be housed in a new Part XI of PJM’s Tariff22), and its Initial Brief, including the Illustrative Tariff.23  Sections 700-707 of Subpart A, Part IX of PJM’s Illustrative Tariff contain the non-rate terms and conditions related to PJM’s proposed implementation of Interim NITS.

Notably, nowhere in PJM’s February 23 Compliance Filing, Initial Brief or applicable sections of its Illustrative Tariff does PJM make any mention of Proposed Interim NITS Limitation.  Notwithstanding this fact, PJM has clearly indicated to its stakeholders that when it actually implements Interim NITS, it intends to ensure that “Co-located load taking Interim NITS service will not have rights to the capacity/energy from any specific co-located

22 See PJM February 23 Compliance Filing at 19.
23 PJM noted that its proposed tariff language is “illustrative” because it was filed as part of the paper hearing record and PJM is not formally filing it until the Commission rules on the record. See PJM Initial Brief at 2.

PDF page 7

7
generation,”24 and that (“[i]f curtailed, [Eligible Customer] cannot take energy from co-located generator.”25

II. PROTEST
i. The Proposed Interim NITS Limitation Cannot Be Imposed by PJM Because it is
Not Part of PJM’s Filed Rate

While none of PJM’s February 23 Compliance Filing, its Initial Brief or Illustrative Tariff make any mention of Proposed Interim NITS Limitation,26 PJM instead seeks to impose the

Proposed Interim NITS Limitation through means not specified in the PJM Tariff.  However, any prohibition on a Co-Located Load’s ability to be served by a Co-Located Generating Facility during the Interim Period must be specified in the PJM Tariff, as the prohibition significantly impacts how Eligible Customers taking Interim NITS must operate their Co-Located Load

during periods in which they are curtailed, and as discussed further below in Section II.ii, renders Interim NITS entirely unworkable.  Therefore, because the Proposed Interim NITS Limitation is certainly a practice “that affect[s] rates and service significantly, that [is]

reasonably susceptible of specification, and that [is] not so generally understood in any contractual arrangement as to render recitation superfluous,” it must be included within the PJM Tariff (i.e., PJM’s filed rate) in order to be effectuated.27  PJM has not included any language

24 See PJM Staff March 16 Presentation at 12.
25 See PJM Staff January 23 Draft Concepts at 4.
26 Importantly, Section 701.3 of PJM’s Illustrative Tariff, which is entitled “Restrictions on Use of Service”, contains no language that would implement the Proposed Interim NITS Limitation.
27 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,003, at P 69 & n.113 (2017) (citations and internal quotes omitted).  See also Sw. Power Pool, Inc., 170 FERC ¶ 61,125, at PP 35-36 & n.92 (2020) (noting that the filed rate doctrine “entitles customers to rely upon what is in a tariff, regardless of any ‘one-way’ assertions made by the utility outside of Commission filings.” (citing W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 24 (D.C. Cir. 2014) (rejecting the Commission’s argument that interconnection studies provided notice for financial responsibility for upgrades because the Commission provided “‘no reasoned explanation for expanding the notice exception to encompass such one-way assertions, especially since generators have no apparent way to challenge any costs such studies purport to assign’”)); Old Dominion Elec. Coop. v. FERC, 892 F.3d 1223, 1232 (D.C. Cir. 2018) (finding that a website statement at issue was not filed with the Commission, which “is required for all rate changes”)).

PDF page 8

8
intended to implement the Proposed Interim NITS Limitation in its Illustrative Tariff, meaning that it cannot be imposed by PJM.

ii. PJM’s Proposed Interim NITS Limitation Would Render Interim NITS
Unworkable and Conflicts With the Commission’s Directives in the
December 18 Order

As noted previously, the Commission established Interim NITS in order to allow “an Eligible Customer that has requested to take NITS on behalf of a Co-Located Load to . . .receive an interruptible transmission service before the Network Upgrades necessary to designate and serve the Co-Located Load as Network Load are complete.”28  The core purpose of Interim NITS is to allow a large load customer to interconnect faster in exchange for being interruptible (i.e., curtailable) when the transmission system is stressed and firm transmission service must be prioritized for Network Customers taking NITS.  Importantly, Interim NITS is designed to be temporary,29 and only be in place until Network Upgrades are constructed, and both the Co- Located Load and Co-Located Generating Facility can take or provide full Network Service, respectively. This is reflected clearly in Commissioner Rosner’s concurrence to the December 18 Order, in which he stated that “if the co-located load is paired with a new generator, and that generator is still waiting to begin its own front-of-meter service, the load can take service directly from the generator in the interim until both ‘graduate’ to full, front-of-meter service.”30 PJM’s Proposed Interim NITS Limitation would prohibit Co-Located Generating

Facilities from serving Co-Located Load during the Interim Period, which would mean that the Co-Located Load would be exposed to actual shutdowns when curtailed.  Absent the ability to be

28 See December 18 Order at P 201.
29 See, e.g., December 18 Order at P 200. Enchanted Rock has no objection to Co-Located Generating Facilities being prohibited from serving their Co-Located Loads that have previously obtained Interim NITS once both the generator and load have been studied as full, front-of-the-meter Network Resources, following the Interim Period.
30 See Rosner Concurrence at P 11.

PDF page 9

9
served by the Co-Located Generating Facility, the Co-Located Load would in fact “always have to shut down completely during peak periods,”31 – which is the precise outcome that the Commission sought to avoid by seeking to instead enable the “[co-located] load [] [to] take service directly from the generator in the [I]nterim [Period].”32

Based on Enchanted Rock’s experience, large load customers, which Interim NITS is designed to serve, will accept the risk of being curtailed in exchange for faster interconnection. However, these customers cannot commercially bear the risk of being completely shut down when curtailed.  Data centers and similar critical infrastructure facilities typically operate under contractual reliability requirements demanding continuous uptime of 99.999% or greater. Market rules that would require these customers’ Co-Located Loads to be curtailed, but that would allow a Co-Located Generating Facility to serve the Co-Located Load while it is being curtailed, would be operationally and commercially manageable. However, PJM’s Proposed Interim NITS Limitation forecloses that option and would effectively force large load customers taking Interim NITS to risk actually being shut down during periods in which they are curtailed, rendering Interim NITS commercially impractical and unworkable.

Other parties agree with Enchanted Rock’s assessment of PJM’s Proposed Interim NITS Limitation.  As noted by the Data Center Coalition (“DCC”) in their answer to PJM’s February 23 Compliance Filing, the DCC stated that the Proposed Interim NITS Limitation “is unworkable because curtailment should limit use of the grid, not prevent the customer from using the co- located resource it supplied, which supports Interim NITS in the first place. If the customer cannot use that generation during curtailment, Interim NITS provides no practical value.”33

31 See id.
32 See id.
33 See Comments of the Data Center Coalition, Docket No. ER26-1479-000, at 6 (Mar. 16, 2026) (emphasis added).

PDF page 10

10
Similarly, Crusoe Technologies LLC noted that “[i]f large load customers cannot rely upon their own Co-Located Generating Facilities . . . during the Interim NITS period, it would create a significant disincentive and effectively nullify Interim NITS as a viable transmission service option and commercial pathway.”34

For the foregoing reasons, the Proposed Interim NITS Limitation plainly conflicts with
the Commission’s holdings and directives related to Interim NITS in the December 18 Order and undermines the entire Interim NITS market construct. For these additional reasons, the Proposed Interim NITS Limitation is not just and reasonable and must not be permitted to stand by the Commission.35

34 Comments of Crusoe Technologies, LLC, Docket No. ER26-1479-000, at 6 (Mar. 16, 2026).
35 See also PJM Interconnection, L.L.C., 175 FERC ¶ 61,084 (2021) (rejecting an FPA Section 205 filing as unjust and unreasonable where the proposed tariff changes did not achieve PJM’s stated reliability objective and therefore failed to accomplish its purpose); NRG Power Mktg., LLC v. FERC, 430 U.S. App. D.C. 224, 226, 862 F.3d 108, 110 (2017) (noting that FERC cannot accept a proposal that results in a fundamentally different rate design than what was proposed, particularly if it fails to resolve the issues it aimed to address).

PDF page 11

11
III. CONCLUSION
For the foregoing reasons, Enchanted Rock respectfully requests that the Commission consider this Protest.  Moreover, Enchanted Rock respectfully requests that in any final order issued in the above-captioned proceedings, that the Commission 1) hold that PJM’s Proposed Interim NITS Limitation is prohibited, and 2) direct PJM to file revisions to its tariff to clarify that a Co-Located Load can be served by its Co-Located Generating Facility during the Interim Period, consistent with the applicable holdings and directives in the December 18 Order.

Joel Yu
Senior Vice President, Policy & External Affairs
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002

Jyu@enchantedrock.com

James Huang

Director, Wholesale Markets Policy
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002
Jhuang@enchantedrock.com

Respectfully submitted,

/s/ Steven Shparber

Steven Shparber
Omar Bustami
Nakia Arrington
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo, P.C.
555 12th Street NW, Suite 1100
Washington, D.C. 20004
(202) 434-7417

SShparber@mintz.com

OBustami@mintz.com
NLArrington@mintz.com

Counsel to Enchanted Rock, LLC

  Dated: March 25, 2026

PDF page 12

CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing and its attachments to be served upon each person designated on the official service list compiled by the Secretary in the captioned proceeding.

Dated at Washington, D.C., this 25th day of March 2026.
/s/ Steven Shparber