EL25-49-000 · 2026-03-25 · Enchanted Rock, LLC

Reply Brief and Protest of Enchanted Rock, LLC in response to PJM Interconnection, L.L.C.’s initial brief filed on 02/23/2026

Text extracted from the eLibrary original (SHA-256 0c9e6d99b6eb12df…). Download the original from the official source.

Contents · 3 sections
  1. I. BACKGROUND p. 3
  2. II. PROTEST p. 7
  3. III. CONCLUSION p. 11

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Moreover, PJM’s Proposed Interim NITS Limitation, if enacted, would make it commercially impractical for Eligible Customers to ever utilize Interim NITS to serve their Co- Located Load, thus undermining the Commission’s goals of establishing Interim NITS in order to “facilitate the timely provision…
Read this passage Filed comments: Connecting load and generation

I. BACKGROUND

printed heading · Topic match: Connecting load and generation

Commission Directives Related to Interim NITS In response to these parties’ comments, the Commission directed PJM to “create a new interim, non-firm transmission service . . . [to] allow an Eligible Customer that has requested NITS on behalf of a Co-Located Load to take non-firm transmission…
Read this passage Filed comments: Connecting load and generation

II. PROTEST

printed heading · Topic match: Connecting load and generation

However, any prohibition on a Co-Located Load’s ability to be served by a Co-Located Generating Facility during the Interim Period must be specified in the PJM Tariff, as the prohibition significantly impacts how Eligible Customers taking Interim NITS must operate their Co-Located Load during…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading · Topic match: Connecting load and generation

Moreover, Enchanted Rock respectfully requests that in any final order issued in the above-captioned proceedings, that the Commission 1) hold that PJM’s Proposed Interim NITS Limitation is prohibited, and 2) direct PJM to file revisions to its tariff to clarify that a Co-Located Load can be served…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 25th day of March 2026. /s/ Steven Shparber
Read this passage