EL25-49-000 · 2026-03-25 · Indicated PJM Transmission Owners

Joint Response of the Indicated PJM Transmission Owners to PJM Interconnection, L.L.C.’s Initial Brief filed on 02/23/2026

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
 )
Docket No. EL25-49-000
 )
Docket No. EL25-49-001
 )
Large Loads Co-Located at Generating Facilities )
Docket No. AD24-11-000
 )
Constellation Energy Generation, LLC

 )
Docket No. EL25-20-000
v.

 )
PJM Interconnection, L.L.C.
 )
(Consolidated)
JOINT RESPONSE OF
THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to the Commission’s December 18, 2025 order in PJM Interconnection, L.L.C.,
193 FERC ¶ 61,217 (2025) (“Order”), the Indicated PJM Transmission Owners (collectively the “PJM Transmission Owners”)1 submit this joint response to the initial brief filed by PJM Interconnection, L.L.C. (“PJM”) on February 23, 2026 (“PJM Initial Brief”).

1 For the purpose of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company , and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.

PDF page 2

2
I. INTRODUCTION AND BACKGROUND
In the Order, the Commission ordered PJM to offer three new forms of transmission service under its Tariff: (i) Firm Contract Demand transmission service; (ii) Non-Firm Contract Demand transmission service and (iii) interim, non-firm transmission service under the PJM Open Access Transmission Tariff (“Tariff”) for Eligible Customers2 serving co-located load in PJM.3  The Commission also established this paper hearing process to determine the just and reasonable rates, terms, and conditions for these new transmission services.4  For the paper hearing process, the Commission provided for initial briefs, responses to initial briefs and replies to those responses.5 The PJM Transmission Owners are submitting this response in order to reply to PJM’s Initial Brief filed on February 23, 2026.

In the PJM Initial Brief, PJM addresses the paper hearing questions posed in the Order regarding non-rate terms and conditions associated with the three new transmission services required by the Commission.6  The PJM Initial Brief also contains supporting affidavits, along with illustrative tariff records (“Illustrative Tariff”), containing tariff provisions to implement PJM’s proposed terms and conditions.  The PJM Transmission Owners applaud PJM on the substantial progress it has made in a short time towards developing the non-rate terms and conditions required to effectuate the new transmission services and support the general structure for effectuating those services that PJM proposes in the PJM Initial Brief.  Moreover, assuming

2 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C..
3 Order at P 160.
4 Id. at PP 2, 194.
5 Id. at P 220.
6 Consistent with the PJM Consolidated Transmission Owners Agreement (“CTOA”), PJM’s Initial Brief appropriately defers to the PJM Transmission Owners to propose rates for the new transmission services.  See PJM Initial Brief at 1-2.

PDF page 3

3
that the new transmission services are ultimately required to be implemented, an action with which some PJM Transmission Owners strongly disagree, the PJM Transmission Owners agree that most of the modifications and new provisions that PJM proposes to include in its Tariff are just and reasonable.  This response focuses on a limited number of items that require clarification or modest changes, or where additional detail is necessary.

II. JOINT RESPONSE TO PJM’s INITIAL BRIEF
A. Issues Relating to the Interaction Between Firm Contract Demand Service
and Non-Firm Contract Demand Service.
In the PJM Initial Brief, PJM states that for an Eligible Customer taking Contract Demand Service, the portion of the Co-Located Load for which a co-located generating facility will dedicate its output may be covered by Non-Firm Contract Demand Transmission Service and any portion of the gross demand of a Co-Located Load that is not covered by a co-located generating facility must be covered by Firm Contract Demand Transmission Service.7  In total, the cumulative amount of Firm and Non-Firm Contract Demand Transmission Service must equal the entire gross demand of the Co-Located Load.8  This approach is reflected in PJM’s Illustrative Tariff, which would require an Eligible Customer applying for Contract Demand Service to apply for a combination of Firm and Non-Firm Contract Demand Transmission Service to cover the Co-Located Load’s entire gross load.9

7 PJM Initial Brief at 6-7.  In their initial brief, the PJM Transmission Owners refer to Firm and Non-Firm Contract Demand Services (“PJM Transmission Owners Initial Brief”).  For purposes of this response, the PJM Transmission Owners have adopted the terms for these services used in the PJM Initial Brief: Firm and Non-Firm Contract Demand Transmission Services.
8 PJM Initial Brief at Attachment A, Section 709.2.
9 PJM Initial Brief at Attachment A, Section 710.2.

PDF page 4

4
The PJM Transmission Owners support these basic requirements but further clarification is necessary.  First, based on the materials provided in the PJM Initial Brief,10 as well as subsequent stakeholder presentations made by PJM, it appears that PJM contemplates that an Eligible Customer’s initial application for a certain amount of Non-Firm Contract Demand Transmission Service would essentially serve as a “holding” request, and the actual reservation and use of Non- Firm Contract Demand Transmission Service would require the Eligible Customer to submit individual requests for service in advance of the interval during which it wishes to obtain such service.  For instance, if an Eligible Customer’s co-located generator will be on scheduled outage for a month, the Eligible Customer would be required to request, in advance of that month, Non- Firm Contract Demand Transmission Service for that month, at which point PJM would determine whether or not the requested amount of Non-Firm service is available.  Moreover, the amount that PJM determines is available for a particular requested interval or intervals would presumably serve as the basis for determining the relevant charge to the Eligible Customer for Non-Firm Contract Demand Transmission Service.  PJM should confirm these understandings are correct and add appropriate language to its proposed Tariff provisions.

Moreover, PJM should clarify pertinent details relating to this process.  For instance, Section 710.3 of PJM’s Illustrative Tariff sets forth a study process to determine what levels of Firm and Non-Firm Contract Demand Transmission Service can be provided to an Eligible Customer.  However, it is not clear if this process is meant to cover only the initial service study, or also subsequent determinations as to available Non-Firm capacity based on specific reservation requests.  Regardless, more detail should be provided as to the process for evaluating and granting specific reservation requests for Non-Firm Contract Demand Transmission Service, including the

10 PJM Initial Brief at 9-10, Attachment B at 5-6.

PDF page 5

5
timelines associated with such requests.  For instance, PJM explains that Non-Firm Contract Demand Transmission Service is available only when a generating facility dedicated to serving Co-Located Load is on outage, but it is not clear what reservation requirements and timelines would apply to forced outages.  Based on the Order,11 the PJM Transmission Owners assume that Non-Firm Contract Demand Transmission Service will be available for periods from one month to one hour in duration, but this should be specified in the relevant PJM Tariff language.

B. The Study Process for Co-Located Load Arrangements Should be Clarified to Recognize the Priority of Load Integration Studies.

In its Initial Brief, PJM proposes a study process for Contract Demand Transmission Service whereby PJM will determine, in accordance with PJM Manuals, any studies necessary to provide the requested transmission service.12  For Interim Network Integration Transmission Service (“NITS”), PJM will determine whether additional studies beyond those required to evaluate the Eligible Customer’s request for NITS are needed for Interim NITS.13  If additional studies are required, PJM will inform the Eligible Customer and then tender to the customer an application and study agreement within 15 days.  PJM’s proposal appropriately recognizes the important role of the affected PJM Transmission Owner(s) in evaluating load interconnection requests, stating that PJM will notify the affected PJM Transmission Owner(s) after receiving an application for Contract Demand Transmission Service or Interim NITS, and specifying that if studies are required, it will consider the results of any studies conducted by the PJM Transmission Owners.14  This approach serves as a just and reasonable foundation for studying Contract Demand

11 See Order at P 215.
12 PJM Initial Brief at 24-25.
13 PJM Initial Brief at 70-71.
14 PJM Initial Brief at 24, 68.

PDF page 6

6
Transmission Service or Interim NITS requests, but more detail should be added to clarify that the load integration studies conducted by the PJM Transmission Owners will be conducted first and inform any studies required by PJM relating to an Eligible Customer’s request for transmission service and co-located generation interconnection.

As the PJM Transmission Owners explained in their initial brief, they will still need to perform load integration studies for any Co-Located Load arrangements, similar to what they do today with respect to any large load customers, but with an expanded study scope due to the addition of co-located generation.15  Nothing in PJM’s proposal prevents the PJM Transmission Owners from conducting these necessary large load analyses to ensure local reliability.  To the contrary, PJM’s Illustrative Tariff provisions specifically indicate that PJM “will coordinate with the affected Transmission Owner(s) to complete studies, including load integration studies, which will provide data relevant to the determination of whether (and to what level as applicable)” requested Firm and Non-Firm Contract Demand Transmission Service can be provided.16 The PJM Transmission Owners support this approach.  It is critically important that PJM and the PJM Transmission Owners work closely and collaboratively in order to ensure that large loads, including those co-located with generation, can be quickly and efficiently interconnected. The PJM Transmission Owners are fully committed to achieving this goal.  However, more detail is necessary as to how a PJM Transmission Owner’s load integration studies will be sequenced with Eligible Customer requests to PJM for Contract Demand and Interim NITS Transmission Services, as well as any related generator interconnection studies.  The Tariff should specify that Transmission Owners’ load integration studies will be completed first and thereby inform the

15 PJM Transmission Owners Initial Brief at 25-26.
16 PJM Initial Brief at Attachment A, Section 710.3 (emphasis added).

PDF page 7

7
determination of whether and what additional studies are necessary for purposes of an Eligible Customer’s request for transmission service on behalf of a Co-Located Load and the interconnection of any on-site generation.  Transmission Owners will always need to study new load additions to ensure that they can be reliably interconnected to the grid, regardless of the type of transmission service being requested.  Any facilities that the Transmission Owners determines are necessary to reliably interconnect the load can inform additional transmission and generation studies.  Therefore, conducting load integration studies first will maximize the speed and efficiency of the overall process and avoid potential duplication of effort and expense between the PJM Transmission Owners and PJM.

C. PJM’s Proposed Provisions Relating to Necessary Control Technologies and
Protection Systems Should Be Clarified and Expanded.
PJM’s proposal appropriately includes requirements for necessary control technologies and protective systems in order to protect the transmission system and limit an Eligible Customer’s withdrawals.  Pursuant to these requirements, the Transmission Provider, affected Transmission Owner(s) and Eligible Customer shall establish the necessary control technologies and protection systems for each service agreement.17  The PJM Transmission Owners request two clarifications to these provisions.

First, PJM should make clear that in order for an Eligible Customer to take any form of new transmission services, whether it be Interim NITS, or Firm or Non-Firm Contract Demand, the customer must comply with requirements to implement necessary control technologies and protection systems.  Currently, PJM’s proposed Tariff language refers to such requirements in the context of Interim NITS and Non-Firm Contract Demand Transmission Service, but not Firm

17 PJM Initial Brief at Attachment A, Sections 705.5 and 713.6.

PDF page 8

8
Contract Demand Transmission Service.18  It is important, however, that each new transmission service be conditioned, as determined through studies of each individual customer’s arrangements, on the implementation of control technologies and protection systems to ensure that a Co-Located Load does not exceed its specified level of transmission service.  This is because PJM will only be planning and operating the system to reliably accommodate the contractually specified level of transmission service.

The PJM Transmission Owners appreciate that PJM’s proposal will require an Eligible Customer to take a combination of Firm and Non-Firm Contract Demand Transmission Service to cover its entire gross load when co-located generation is unavailable.  However, regardless of the type of services being taken, necessary control technology and system protections must be implemented.  Therefore, in order to avoid confusion regarding an Eligible Customer’s obligations, PJM should add language to its Illustrative Tariff provisions making clear that Interim NITS, as well as both Firm and Non-Firm Contract Demand Transmission Service, are contingent on the implementation of necessary control technologies and protection systems, where applicable. Second, PJM should modify the Illustrative Tariff provisions to make clear that necessary control technologies and protection systems may (some would say should) be required on the customer’s side or both the customer’s side and the Transmission Owner’s side of the point of interconnection.  As the PJM Transmission Owners explained in their initial brief, the use of control technologies and protection systems to protect the grid from large amounts of on-site load exceeding their contractual withdrawal limitations, whether on an instantaneous, shorter-term, or

18 See, e.g., PJM Initial Brief at Attachment A, Section 708 (“Prior to the Commencement of Service, for an Eligible Customer to take Non-Firm Contract Demand Transmission Service on behalf of a Co-Located Load, the Eligible Customer must demonstrate the implementation of the necessary control technologies and protection systems, approved by the Transmission Provider to allow the Eligible Customer to effectively limit withdrawals from the Transmission System to serve such Co-Located Load.”) (emphasis added).

PDF page 9

9
longer-term basis, rather than building more permanent transmission solutions, is novel.19  This approach will require providing Transmission Owners with flexibility to determine how best to ensure reliability on their respective systems, including whether contractual limitations agreed to by Co-Located Load customers are best secured by control technologies and protection systems on only the Co-Located Load side or on both the Co-Located Load and independently on the Transmission Owner side of the point of interconnection.  PJM’s Tariff provisions should be sufficiently broad to encompass both approaches.20

In addition to these clarifications, additional detail will need to be developed to further define the requirements associated with the control technologies and protection systems necessary to ensure that Co-Located Loads do not exceed their relevant withdrawal limitations.  The PJM Transmission Owners recognize that PJM is planning to include further details on this issue in PJM Manuals, but regardless of where this detail resides, it is important that PJM work closely with the PJM Transmission Owners and other stakeholders to develop this detail so that all parties understand their respective rights and obligations.  In their initial brief, the PJM Transmission Owners suggested a number of criteria relating to the use of control technologies and protection systems, and the PJM Transmission Owners urge PJM and the Commission to adopt these criteria, to the extent they are not already contained in PJM’s proposal.21

The PJM Transmission Owners understand that PJM is considering, in other stakeholder initiatives, questions regarding potential study priorities for large loads that bring their own

19 PJM Transmission Owners Initial Brief at 23-24.
20 See, e.g., PJM Initial Brief at Attachment A, Section 702.5 (noting that the provision of “Interim NITS” service will be conditioned upon the “Eligible Customer constructing, maintaining, and operating the facilities on its side of the Delivery Point necessary to reliably deliver capacity and energy from the Transmission Provider’s Transmission System to the Eligible Customer”).
21 PJM Transmission Owners Initial Brief at 23-24.

PDF page 10

10
generation.  Any such priority process should ensure that its interaction with the new transmission services does not create opportunities for customers to game the system; for instance, by adding de minimis amounts of co-located generation to trigger the priority, or by taking Firm Contract Demand Transmission Service equal to their entire on-site load to gain a priority over NITS customers.

Finally, it is important to recognize that, based on recent discussions at the NERC Large Load Technical Conference, regulatory expectations for emerging large loads are evolving.  At that conference, NERC and other reliability organizations indicated they are considering extending certain reliability standards currently applicable to generation owners to large load customers, reflecting their view that these facilities increasingly function as grid infrastructure rather than traditional end use customers.22  This process is of key importance because currently there is no compliance entity on the load side to tie to NERC obligations, resulting in significant potential liability and exposure to Transmission Owners and other entities with defined NERC obligations, as well as increased risks to system reliability

D. Development of Telemetry Requirements.
In its Initial Brief, PJM states that to ensure adequate reliability and stability of PJM’s Transmission System, it expects to develop telemetry requirements and require Co-Located Load to meet such requirements in order to monitor Co-Located Load’s use of the transmission system.23 The PJM Transmission Owners support PJM’s proposal to develop and implement telemetry requirements as described in the Initial Brief.24  Such requirements are an important reliability

22 See, e.g., NERC, Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads (Feb. 24, 2026), https://www.nysrc.org/wp-content/uploads/2026/03/NYSRC-LLWG-3-Att.- 1-NERC-LLWG-Tech-Conference-Presentations.pdf at 63-70.
23 PJM Initial Brief at 59.
24 PJM Initial Brief at 59-61.

PDF page 11

11
measure and are consistent with broader developments at the North American Electric Reliability Council (“NERC”), as discussed above.

E. Penalties for Unreserved Use.
In its Initial Brief, PJM proposes operational penalties for Eligible Customers taking Interim NITS or Contract Demand Service that would apply when: (i) an Eligible Customer fails to follow established Load Shedding and Curtailment procedures; or (ii) necessary control technology and protection systems misoperate.25  For the first instance of a control technology/protection system misoperation, PJM proposes a 120 day pause in service, which may be shortened or extended by mutual agreement.  The PJM Transmission Owners strongly urge  that the relevant Transmission Owner’s approval must be included in the process of allowing service to be reinstated, and this requirement should be added to the Tariff language.  Upon a second misoperation, or if an Eligible Customer fails to follow Load Shedding and Curtailment procedures even once, PJM proposes a strict liability rule resulting in the disqualification of an Interim NITS customer thereby forcing them to take traditional NITS or forcing a customer taking a Contract Demand Service to then take either Interim NITS or traditional NITS.26

As stated in their initial brief, the PJM Transmission Owners agree with PJM that the imposition of operational penalties is appropriate, but also believe that any penalty regime should rely on both operational consequences and complementary financial penalties.27  In its Initial Brief, PJM states that it supports a financial penalty for unreserved use, and intends to work with the PJM Transmission Owners to explore such a financial penalty.28  The PJM Transmission Owners

25 PJM Initial Brief at 40.
26 PJM Initial Brief at 41-46.
27 PJM Transmission Owners Initial Brief at 19-20.
28 PJM Initial Brief at 50-51.

PDF page 12

12
appreciate and agree with PJM’s comments on this issue, and propose a financial penalty charge structure with two components: (1) a base penalty charge, which applies to each individual hour in which the reserved transmission service limit is exceeded, and (2) a penalty ratchet, which applies when such exceedances occur repeatedly.  The PJM Transmission Owners provide a basic outline of this proposal below, with more details forthcoming in future filings in this proceeding. In addition to this proposed penalty for unreserved use, the PJM Transmission Owners propose to apply financial penalties in instances in which a Co-Located Load fails to curtail upon instruction. The PJM Transmission Owners will also provide additional details on this proposal in future filings.

When a Co-Located Load exceeds its reserved transmission service limit, the base penalty charge will be assessed for any hour in which at least one five-minute interval occurs during which a customer’s metered load at the point of interconnection exceeds its reserved transmission service. Such a five-minute interval is defined as an Exceedance Interval, and such an hour is defined as an Exceedance Hour.  The base penalty charge will apply to each Exceedance Hour.  The penalty rachet applies when multiple Exceedance Hours occur during a particular time period.  It is designed to discourage recurring reliance on unreserved transmission capacity. Under the penalty rachet framework, the penalty charges escalate as the frequency of unreserved transmission use increases.  Specifically, if more than one Exceedance Hour occurs on the same day, an additional daily penalty applies.  If exceedances occur on multiple days within the same week, an additional weekly penalty applies; likewise, if exceedances occur in multiple weeks within the same month, an additional monthly penalty applies.  Each of these penalties will involve escalating financial liabilities for prolonged periods of time.  By progressively increasing the economic consequences of repeated penalties, the penalty ratchet reinforces the expectation

PDF page 13

13
that Co-Located Load customers manage their load in a manner consistent with their reserved transmission service.

F. Comments on Specific Proposed Tariff Provisions.
In addition to the general comments set forth above, the PJM Transmission Owners have identified a number of suggested modifications or requests for clarification relating to the Illustrative Tariff records proposed by PJM.

1. Interim Network Integrated Transmission Service Provisions.
a. Section 702.4 – Technical Requirements Prior to
Commencement of Service.
Section 702.4 of PJM’s Illustrative Tariff states that the Eligible Customer must (i) install “necessary hardware and software to limit energy withdrawals, including metering equipment;”

(ii) provide PJM an operational contact and backup contact that is to be available 24 hours a day and 7 days a week, (iii) certify that it “is staffed with PJM Certified Operators pursuant to PJM Manual 40;” (iv) demonstrate “its ability to receive voice and electronic signals from [PJM];” (v) demonstrate that it “has operational control to respond to operating instructions from [PJM] to reduce or disconnect the Co-Located Load within 5 minutes or as specified in PJM Manuals;” and

(vi) demonstrate that it “has operational control of the necessary control technologies and protection systems set forth in . . . section 705, as applicable.”29

These technical requirements should also require an Eligible Customer to satisfy any applicable Transmission Owner-imposed technical requirements.  As the entities managing the load interconnection process, including any load integration studies, the PJM Transmission Owners will play a key role in ensuring the technical sufficiency of Co-Located Load connections and operations.

29 PJM Initial Brief at Attachment A, Section 702.4.

PDF page 14

14
b. Section 703.2 – New Co-Located Loads Connected with the
Transmission Provider.
Section 703.2 of PJM’s Illustrative Tariff states:
Prior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co-Located Load, the new Co-Located Load shall be studied pursuant to a new Application.30

In order to fully account for increases in the size of the designated Co-Located Load, the PJM Transmission Owners propose the following revision to Section 703.2.

Prior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co-Located Load, the new or increased Co-Located Load shall be studied pursuant to a new Application.

c. Section 703.3 – Information Updates.
Under Section 703.3 of PJM’s Illustrative Tariff, in order to maintain operational visibility by PJM of the system and thus to ensure reliability, Eligible Customers will have an ongoing obligation to provide the Transmission Provider with timely written or electronic notice of material changes in the demand characteristics of the Co-Located Load and the supply characteristics of the Co-Located Generating Facility.31  PJM, however, does not indicate how or where the term “material change” will be defined.

PJM should provide additional information as to what would constitute a “material change” in the demand characteristics of the Co-Located Load, particularly with respect to: (i) large, but foreseeable, load ramps that occur on a defined or scheduled basis; and (ii) the timing requirements for submitting a new application once such changes are anticipated or occur.

30 PJM Initial Brief at Attachment A, Section 703.2.
31 PJM Initial Brief at Attachment A, Section 703.3.

PDF page 15

15
d. Section 705.3 – Load Shedding.
PJM proposes that to the extent a contingency requires Transmission Owners and Eligible Customers taking Interim NITS to shed load, such load shedding shall occur in accordance with previously established procedures as set forth in the relevant transmission service agreement and PJM Manuals.32  There should be load shedding practice guidelines applicable to Co-Located Load arrangements established by PJM.  Such load shedding guidelines will make it less complicated and more efficient for PJM to manage Co-Located Load arrangements.  Such practices will also ensure that Co-Located Load customers will understand the relevant process when they seek to connect and their load shedding priority when they are withdrawing energy from the grid. The PJM Transmission Owners are particularly concerned with automatic load shedding schemes.  If a large load were to suddenly appear due to a forced outage of a Co-Located Load’s on-site generation, even a fast disconnection by the customer could cause issues if the disconnection is not fast enough.  With large loads rapidly looking to interconnect coupled with the retirement of synchronous generation facilities, the lack of inertia may cause sudden localized frequency decline.  If such an event occurs near a location where there is an automatic load shedding scheme, unintentional activation of the automatic load shedding scheme could result in unwanted shedding of nearby customer loads in addition to the Co-Located Load. e. Section 705.5 – Necessary Control Technologies and Protection

Systems.
Section 705.5 of PJM’s Illustrative Tariff concerns necessary control technologies and protection systems and provides:

To ensure protection of the Transmission System, and to ensure that the Eligible Customer taking Interim Network Integration Transmission Service on behalf of a Co-Located Load limits its energy withdrawals from the Transmission System to

32 PJM Initial Brief at Attachment A, Section 705.3.

PDF page 16

16
its approved level of Interim Network Integration Transmission Service, including during a period in which the Transmission Provider has directed Curtailment or Load Shedding, prior to the Service Commencement Date, the Transmission Provider, affected Transmission Owner(s), and the Eligible Customer shall establish necessary control technologies and protection systems in accordance with the PJM Manuals, which may include a Remedial Action Scheme, for each Service Agreement for Interim Network Integration Transmission Service. The necessary control technologies and protection systems must be developed in accordance with the PJM Manuals and be approved by the Transmission Provider.  The necessary control technologies and protection systems may be functionally modified from time to time in accordance with the PJM Manuals.  Any functional modification to the necessary control technologies and protection systems must be developed with the affected Transmission Owner(s) and, before taking effect, such functional modification must be approved by the Transmission Provider.33

The PJM Transmission Owners strongly agree with PJM’s proposal to impose necessary control technologies and protection systems obligations on Eligible Customers.  However, additional detail is needed on how those obligations will be determined and imposed.  For example, it is not clear whether the obligation to “establish necessary control technologies and protection systems in accordance with the PJM Manuals,” binds a Transmission Owner to install equipment itself, or just to enforce the criteria on a Eligible Customer.34  Moreover, the PJM Transmission Owners believe that the “necessary control technologies and protection systems” that must be developed in accordance with the PJM Manuals and approved by PJM should also be approved by and developed in accordance with the PJM Transmission Owners’ interconnection standards, guidelines, and practices.  In addition, to properly address modifications to the necessary control technologies and protection systems, the PJM Transmission Owners propose the following revision to Section 705.5:

Any functional modification to the necessary control technologies and protection systems must be developed with the affected Transmission Owner(s) and, before taking effect, such functional modification must be approved by the Transmission Provider and coordinated with the affected Transmission Owner(s).

33 PJM Initial Brief at Attachment A, Section 705.5.
34 Id.

PDF page 17

17
f. Section 706.2 – Redispatch Charge.
Section 706.2 of PJM’s Illustrative Tariff states that “[t]he Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in Tariff, Attachment K.”35 However, Transmission Owners should not be responsible for redispatch costs because such costs will be caused by Contract Demand Transmission Service customers.  PJM indicated that the reference to Transmission Owners in Section 706.2 is incorrect.  Accordingly, PJM should remove this reference from any filed tariff records.

In addition, this provision could result in cost shifts onto other customers because Eligible Customers may represent multiple load customers.36   Therefore, PJM should either: (1) modify the curtailment order so that Non-Firm Contract Demand Transmission Service load is curtailed prior to generation redispatch, or (2) reevaluate the applicability of its redispatch cost allocation methodology under Attachment K to better align cost responsibility with cost causation.

2. Contract Demand Transmission Service Provisions.
a. Section 708 – Provision of Contract Demand Transmission
Services.
In Section 708(c) of its Illustrative Tariff, PJM indicates that, before service begins, an Eligible Customer seeking to take Non-Firm Contract Demand Transmission Service on behalf of Co-Located Load must demonstrate that it has implemented the necessary control technologies and protection systems, approved by PJM, to allow the Eligible Customer to limit withdrawals from the transmission system to serve such Co-Located Load.37

35
PJM Initial Brief at Attachment A, Section 706.2.
36 These can include Load Serving Entities such as Electric Distribution Companies as well as other retail suppliers serving numerous retail load customers.
37 PJM Initial Brief at Attachment A, Section 708(c).

PDF page 18

18
Per the discussion above, the PJM Transmission Owners request that PJM clarify Section 708(c) because the limitation of control technologies and protections systems to Non-Firm requests for service is confusing and potentially problematic.  Appropriate control technologies and protection systems should also be required, when determined necessary upon completion of studies, for an Eligible Customer to take Firm Contract Demand Transmission Service, to ensure they do not exceed their Firm Contract Demand.

b. Section 710.1 – Conditions Precedent for Receiving Service.
In Section 710.1 of its Illustrative Tariff, PJM indicates that, subject to terms and conditions of its Illustrative Tariff, Part XI, the Transmission Provider will provide Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service or both to any Eligible Customer taking transmission service on behalf of Co-Located Load, subject to certain conditions precedent for receiving service.38

The PJM Transmission Owners request that PJM add, as a condition precedent for receiving service, that the Eligible Customer satisfy any load-connection related requirements imposed by the applicable PJM Transmission Owner(s).

c. Section 710.2 – Application Procedures.
Section 710.2 of PJM’s Illustrative Tariff provides in part that “[i]f requested by the Transmission Provider, an application for Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service shall provide all of the information included in 18 C.F.R. § 2.20, including but not limited to:

(iii) A demonstration that the Co-Located Load on behalf of which the Eligible Customer is seeking to obtain service and the Co-Located Generating Facility are located on the same

38 PJM Initial Brief at Attachment A, Section 710.1.

PDF page 19

19
side of the Delivery Point to the Transmission Provider’s Transmission System as the Co- Located Load.”39

The PJM Transmission Owners request clarification from PJM regarding whether use of the term “Delivery Point” is appropriate here.  Specifically, it seems potentially inconsistent with PJM’s proposed definition of Co-Located Load, which is based on facilities located on the same side of the Point of Change in Ownership.  If there is an inconsistency, PJM should conform the language in this section with its proposed Co-Located Load definition, or if consistent, explain how the use of the term “Delivery Point” is consistent with the proposed definition of Co-Located Load.

In addition, the PJM Transmission Owners request that PJM add language to the list of information to be provided in an application for Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service to the effect that the customer has met applicable load interconnection study obligations.  The addition of this language is necessary to supplement the language in Section 710.3 related to the coordination of the Transmission Provider and affected Transmission Owner to complete studies, including load integration studies.40 d. Section 710.5 – Eligible Customer Facilities and Network

Facilities.
In Section 710.5 of its Illustrative Tariff, PJM provides in part that “[t]he provision of Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, shall be conditioned upon the Eligible Customer constructing, maintaining, and operating the facilities (i) on its side of the Delivery Point41 necessary to reliably deliver and receive energy

39 PJM Initial Brief at Attachment A, Section 710.2.
40 See PJM Initial Brief at Attachment A, Section 710.3.
41 As with Section 710.2, the PJM Transmission Owners request clarification from PJM regarding whether use of the term “Delivery Point” is appropriate here, or whether this provision should refer to the “Point of Change of Ownership” consistent with PJM’s definition of Co-Located Load.

PDF page 20

20
and capacity; and (ii) only in the case of Non-Firm Contract Demand Transmission Service, to implement the necessary control technologies and protection systems required pursuant to Tariff, Part XI, Subpart B, section 713 and specified in the Service Agreement for Contract Demand Transmission Service, as Transmission Provider may require.”42

PJM should modify the language in Section 710.5 to make it more generic to ensure that it does not preclude the concept of required Transmission Owner-side protections, which may include facilities such as control technologies and protection systems constructed, maintained, and operated by the applicable PJM Transmission Owner(s).

As discussed above, the implementation of necessary control technologies and protection systems should also not be limited to Non-Firm Contract Demand Transmission Service.43 Therefore, the PJM Transmission Owners propose to strike the language “only in the case of Non- Firm Contract Demand Transmission Service” from subclause (ii) of Section 710.5. e. Section 711.3 – Information Updates.

In Section 711.3 of its Illustrative Tariff, PJM provides that the Eligible Customer must submit annual updates to the Transmission Provider regarding (i) the demand characteristics of the co-located load, and (ii) the supply characteristics of the designated co-located generating facility, consistent with the information included in its application for Contract Demand Transmission Service.44  The Eligible Customer must also provide timely written or electronic notice of any material changes to that information, as well as any other information listed in Tariff, Part XI,

42 PJM Initial Brief at Attachment A, Section 710.5.
43 See supra Section II.C.
44 PJM Initial Brief at Attachment A, Section 711.3.

PDF page 21

21
Subpart B, Section 710, or included in its application or otherwise affecting the Transmission Provider’s ability to provide reliable service.45

PJM should clarify in Section 711.3 what constitutes “material changes,” or indicate that PJM will provide additional detail in a PJM Manual regarding what constitutes a material change for purposes of this section.  PJM should also revise Section 711.3 to require that notice of material changes to the demand and supply characteristics of Co-Located Load be provided to both the Transmission Provider and the affected PJM Transmission Owner(s).  Providing notice to both entities is required to help the Transmission Owner(s) better understand any technical changes that could affect the interconnection from a load perspective, and will facilitate effective coordination with PJM.

f. Section 712.2 – Study Procedures for Non-Firm Contract
Demand Transmission Service.
Section 712.2 of PJM’s Illustrative Tariff sets forth the study procedures for Non-Firm Contract Demand Service.46  PJM should revise Section 712.2, as indicated below, to affirmatively require PJM to notify the affected PJM Transmission Owner(s) of any request for Non-Firm Contract Demand Service.  It is appropriate that PJM Transmission Owners be notified of such requests given the role PJM Transmission Owners play in studying Co-Located Loads. Transmission Provider may will notify the affected Transmission Owner of such request for Non-Firm Contract Demand Transmission Service, and the Transmission Provider will also consider the results of any studies conducted by the affected Transmission Owner(s).47

45 Id.
46 PJM Initial Brief at Attachment A, Section 712.2.
47 Id.

PDF page 22

22
g. Section 713 – Load Shedding and Curtailments for Contract
Demand Transmission Service.
Section 713.1 of PJM’s Illustrative Tariff provides, in part, that to the extent practicable, PJM will notify the Eligible Customer of any curtailment in a timely manner.48  PJM should revise Section 713.1 to require that notice of any curtailment also be provided to any affected PJM Transmission Owner or Electric Distribution Company, as both entities play key roles in implementing any load curtailments.

h. Section 713.6 – Necessary Control Technologies and Protection
Systems for Non-Firm Contract Demand Transmission
Service.
Section 713.6 of PJM’s Illustrative Tariff provides that, prior to service commencement date, PJM, the affected transmission owner(s), and the Eligible Customer shall establish control technologies and protection systems consistent with the PJM Manuals, which can include remedial RAS, for each service agreement for Non-Firm Contract Demand Transmission Service.49  As discussed above, PJM should not limit the establishment of necessary control technologies and protection systems to Non-Firm Contract Demand Transmission Service.50

i. Section 714.3 – Redispatch Charge.
Section 714.3 of PJM’s Illustrative Tariff provides that the Eligible Customer and each Transmission Owner shall pay any redispatch costs set forth in Tariff, Attachment K.51  The PJM Transmission Owners reiterate their prior comments regarding the elimination of the reference to Transmission Owners here.52

48 PJM Initial Brief at Attachment A, Section 713.1.
49 PJM Initial Brief at Attachment A, Section 713.6.
50 See supra Sections II.C and II.F.2.d. 51 PJM Initial Brief at Attachment A, Section 714.3.
52 See supra Section II.F.1.f (discussion of Section 706.2 – Redispatch Charge).

PDF page 23

23
j. Section 715.1 – Monthly Demand Charge.
The PJM Transmission Owners note that PJM has reserved Section 715.1 related to the Monthly Demand Charge for Non-Firm Contract Demand Transmission Service, which would be provided by the PJM Transmission Owners as the entities with filing rights with respect to the new transmission services.53  This placeholder may be unnecessary as the PJM Transmission Owners anticipate establishing a separate schedule for Non-Firm Contract Demand Transmission Service.

3. Attachment F-3A – Service Agreement for Regional Transmission
Service And/or Interim Network Integration Transmission Service
(For Co-Located Load).
a. Section 2.0.
The PJM Transmission Owners propose the following revision to correct what appears to be a typo in Section 2.0:

“Until the facilities listed above are completed, the Transmission Owner provides a Notice of Completion to PJM, and the facilities listed above are in service, the Eligible Customer may not only receive Interim Regional Network Integration Transmission Service subject to the conditions of Part XI of the Tariff.”

b. Section 4.0.
Attachment F-3A provides that the Eligible Customer will comply with the necessary control technologies and protection systems in Tariff, Part XI, prior to the service commencement date.  Moreover, Section 705.5 in the Illustrative Tariff indicates that such control technologies and protection systems will be established “for each Service Agreement for Interim [NITS].”54 However, Attachment F-3A does not contain a section or other placeholder where the customer’s required control technologies or protection systems will be listed.  PJM should add an appropriate section or placeholder where such facilities and systems can be listed.

53 PJM Initial Brief at Attachment A, Section 715.1. 54 PJM Initial Brief at Attachment A, Section 705.5.

PDF page 24

24
4. Attachment F-4 – Service Agreement for Contract Demand
Transmission Service (For Co-Located Load).
a. Section 5.0.
Attachment F-4 provides that only the Eligible Customer will comply with the necessary control technologies and protection systems in Illustrative Tariff, Part XI, prior to the service commencement date.55  Moreover, Section 710.4 in the Illustrative Tariff indicates that such control technologies and protection systems will be “set forth in the Service Agreement for Contract Demand Transmission Service.”56  However, Attachment F-4 does not contain a section or other placeholder where the customer’s required control technologies or protection systems will be listed.  PJM should add an appropriate section or placeholder where such facilities and systems can be listed.

55 PJM Initial Brief at Attachment A, Att. F-4.
56 PJM Initial Brief at Attachment A, Section 710.4.

PDF page 25

25
III. CONCLUSION
The PJM Transmission Owners appreciate the opportunity to submit this joint response to PJM’s Initial Brief.  The PJM Transmission Owners respectfully request that any subsequent Commission orders addressing these issues consider the recommendations set forth herein. Respectfully Submitted,

/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling

Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the PJM
  Transmission Owners
Dated:  March 25, 2026

PDF page 26

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, D.C., this 25th day of March 2026.

/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005