Joint Response of the Indicated PJM Transmission Owners to PJM Interconnection, L.L.C.’s Initial Brief filed on 02/23/2026
Text extracted from the eLibrary original (SHA-256 ae230a80271a0de7…). Download the original from the official source.
Contents · 13 sections
- I. INTRODUCTION AND BACKGROUND
- II. JOINT RESPONSE TO PJM’s INITIAL BRIEF
- A. Issues Relating to the Interaction Between Firm Contract Demand Service
- B. The Study Process for Co-Located Load Arrangements Should be Clarified to
- C. PJM’s Proposed Provisions Relating to Necessary Control Technologies and
- D. Development of Telemetry Requirements.
- E. Penalties for Unreserved Use.
- F. Comments on Specific Proposed Tariff Provisions.
- Attachment F-3A – Service Agreement for Regional Transmission
- Attachment F-3A provides that the Eligible Customer will comply with the necessary
- Attachment F-4 – Service Agreement for Contract Demand
- Attachment F-4 provides that only the Eligible Customer will comply with the necessary
- III. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. INTRODUCTION AND BACKGROUND
printed heading · Topic match: Connecting load and generation
The PJM Transmission Owners applaud PJM on the substantial progress it has made in a short time towards developing the non-rate terms and conditions required to effectuate the new transmission services and support the general structure for effectuating those services that PJM proposes in the PJM…Read this passage Filed comments: Connecting load and generation
II. JOINT RESPONSE TO PJM’s INITIAL BRIEF
printed heading
II.Read this passage
A. Issues Relating to the Interaction Between Firm Contract Demand Service
printed heading · Topic match: Connecting load and generation
In the PJM Initial Brief, PJM states that for an Eligible Customer taking Contract Demand Service, the portion of the Co-Located Load for which a co-located generating facility will dedicate its output may be covered by Non-Firm Contract Demand Transmission Service and any portion of the gross…Read this passage Filed comments: Connecting load and generation
B. The Study Process for Co-Located Load Arrangements Should be Clarified to
printed heading · Topic match: Connecting load and generation
In its Initial Brief, PJM proposes a study process for Contract Demand Transmission Service whereby PJM will determine, in accordance with PJM Manuals, any studies necessary to provide the requested transmission service.12 For Interim Network Integration Transmission Service (“NITS”), PJM will…Read this passage Filed comments: Connecting load and generation
C. PJM’s Proposed Provisions Relating to Necessary Control Technologies and
printed heading · Topic match: Connecting load and generation
As the PJM Transmission Owners explained in their initial brief, the use of control technologies and protection systems to protect the grid from large amounts of on-site load exceeding their contractual withdrawal limitations, whether on an instantaneous, shorter-term, or 18 See, e.g., PJM Initial…Read this passage Filed comments: Connecting load and generation
D. Development of Telemetry Requirements.
printed heading · Topic match: Connecting load and generation
In its Initial Brief, PJM states that to ensure adequate reliability and stability of PJM’s Transmission System, it expects to develop telemetry requirements and require Co-Located Load to meet such requirements in order to monitor Co-Located Load’s use of the transmission system.23 The PJM…Read this passage Filed comments: Connecting load and generation
E. Penalties for Unreserved Use.
printed heading · Topic match: Connecting load and generation
In its Initial Brief, PJM proposes operational penalties for Eligible Customers taking Interim NITS or Contract Demand Service that would apply when: (i) an Eligible Customer fails to follow established Load Shedding and Curtailment procedures; or (ii) necessary control technology and protection…Read this passage Filed comments: Connecting load and generation
F. Comments on Specific Proposed Tariff Provisions.
printed heading · Topic match: Connecting load and generation
Section 703.2 of PJM’s Illustrative Tariff states: Prior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co-Located Load, the new Co-Located Load shall be studied pursuant…Read this passage Filed comments: Connecting load and generation
Attachment F-3A – Service Agreement for Regional Transmission
printed heading · Topic match: Connecting load and generation
Attachment F-3A – Service Agreement for Regional Transmission Service And/or Interim Network Integration Transmission Service (For Co-Located Load). a.Read this passage Filed comments: Connecting load and generation
Attachment F-3A provides that the Eligible Customer will comply with the necessary
printed heading
Attachment F-3A provides that the Eligible Customer will comply with the necessary control technologies and protection systems in Tariff, Part XI, prior to the service commencement date.Read this passage
Attachment F-4 – Service Agreement for Contract Demand
printed heading · Topic match: Connecting load and generation
Attachment F-4 – Service Agreement for Contract Demand Transmission Service (For Co-Located Load). a.Read this passage Filed comments: Connecting load and generation
Attachment F-4 provides that only the Eligible Customer will comply with the necessary
printed heading
Attachment F-4 provides that only the Eligible Customer will comply with the necessary control technologies and protection systems in Illustrative Tariff, Part XI, prior to the service commencement date.55 Moreover, Section 710.4 in the Illustrative Tariff indicates that such control technologies…Read this passage
III. CONCLUSION
printed heading
CONCLUSION The PJM Transmission Owners appreciate the opportunity to submit this joint response to PJM’s Initial Brief.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 25th day of March 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005Read this passage