EL25-49-000 · 2026-03-25 · Northern Virginia Electric Cooperative, Inc.
Response of Northern Virginia Electric Cooperative, Inc. to Initial Brief of PJM Interconnection, L.L.C. and to Initial Brief and Joint Responses of the…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
2
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
RESPONSE OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. TO
INITIAL BRIEF OF PJM INTERCONNECTION, L.L.C. AND TO INITIAL BRIEF AND
JOINT RESPONSES OF THE INDICATED PJM TRANSMISSION OWNERS TO
PAPER HEARING QUESTIONS
Pursuant to the Federal Energy Regulatory Commission’s (“Commission”) December 18, 2025 order (“Co-Location Order”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this response to the initial briefs and joint responses to the paper hearing questions submitted by PJM Interconnection, L.L.C. (“PJM”)2 and the Indicated PJM
Transmission Owners (“PJM Transmission Owners”).31 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, PP 219-20 (2025) (“Co-Location Order”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49, et al. (issued Jan. 23, 2026) (Accession No. 20260123-3062) (Extending the due date for responses to initial briefs by seven days, from March 18, 2026, to March 25, 2026).2 PJM Interconnection, L.L.C., Initial Brief, Docket Nos. EL25-49, et al. (Feb. 23, 2026) (Accession No. 20260223- 5189) (“PJM Initial Brief”).3 Indicated PJM Transmission Owners, Initial Brief and Joint Responses of the Indicated PJM Transmission Owners, Docket Nos. EL25-49, et al. (Feb. 23, 2026) (Accession No. 20260223-5190) (“PJM TO Initial Brief”).
PDF page 3
3
I. RESPONSE
A. Introduction and Background
Co-location in PJM presents contentious issues. An early proposal, based on PJM’s since- rescinded Guidance on Co-Located Load (“Guidance Document”),4 was filed in Docket No. ER24-2172 as an amended Interconnection Service Agreement (“ISA”) between Susquehanna Nuclear LLC, and PPL Electric Utilities Corporation.5 The Commission rejected the Amended ISA because PJM had not demonstrated a need to deviate from the pro forma ISA.6 Constellation Energy Generation, LLC (“Constellation”) subsequently filed a complaint to amend PJM’s Open Access Transmission Tariff (“Tariff”) to incorporate the co-location arrangements found in the Guidance Document.7
NOVEC is a not-for-profit electric distribution cooperative owned by its members. NOVEC has significant experience with serving data centers over the past 25 years. NOVEC is one of the country’s largest data center hubs and serves over 50 data center buildings.8 Based on its experience, NOVEC opposed Constellation’s complaint in substantial part because Constellation proposed to relieve the Co-Located Load of any responsibility for transmission costs, even as that load relied on the transmission system.9 NOVEC is very aware of the potential effects on cost allocation that can arise because of the size of data centers and does not agree that data centers or other large loads should be able to use the grid without contributing to its costs.
4 PJM, PJM Guidance on Co-Located Load (March 22, 2024) (updated April 17, 2024), https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx. PJM rescinded its Guidance Document pending Commission guidance in Docket No. EL25-49.5 PJM, Amendment to Susquehanna ISA, Docket No. ER24-2172-000 (filed June 3, 2024) (Accession No. 20240603-5012).6 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078, P 85 (2024).7 Constellation, Complaint, Docket No. EL25-20-000 (filed Nov. 22, 2024) (Accession No. 20241122-5285) (“Constellation Complaint”).8 NOVEC, Protest, Docket No. EL25-20-000, at 8-9 (filed Dec. 18, 2024).9 Id.
PDF page 4
4
The Commission instituted a section 206 show cause proceeding, consolidated the Constellation complaint with the new show cause proceeding, and directed interested parties to brief a series of questions regarding whether the PJM Tariff needed to be modified to accommodate co-located load and, if so, how.10
The Commission thereafter issued the Co-Location Order on December 18, 2025. The Co-Location Order found that PJM’s Tariff is not just and reasonable because it does not “contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”11 But the Commission included critical protections for existing transmission customers not present in other previous iterations of co-location service, including requiring prospective Co-Located Loads to fully fund any network upgrades before they could take service from an existing generator.12
In order to facilitate the service of Co-Located Load, the Commission described three new types of transmission service for Eligible Customers serving Co-Located Load. The Commission found that additional record evidence was needed to set the appropriate replacement rates, terms, and conditions of those new types of transmission service, so it set a paper hearing on eleven questions involving the rates, terms, and conditions of service for Firm Contract Demand transmission service, Non-Firm Contract Demand transmission service, and Interim Network Integration Transmission Service (“NITS”).13 PJM and the PJM Transmission Owners filed initial briefs in response to those questions.1410 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025).11 Co-Location Order at P 2.12 Id. P 176.13 Id. P 219.14 See PJM Initial Brief; PJM TO Initial Brief.
PDF page 5
5
The proposals set forth in the initial briefs strike an appropriate balance between recognizing the reduced usage of the transmission system for Co-Located Load while also ensuring that such load does not become a “free rider” to the extent that such load does rely on and use the transmission system, but does not pay for it. Several important principles should guide the Commission’s determination of what constitute just and reasonable rates, terms, and conditions for these new services being mandated to accommodate Co-Located Load. First, the proposed transmission rates cannot be just and reasonable unless they recover from the Co- Located Load the full costs associated with the Co-Located Load’s use of and reliance on the transmission system and do not cause or result in subsidization by existing transmission customers.
Second, meaningful financial and operational penalties are necessary. Such penalties must discourage gamesmanship, must be enforceable, and should include guard-rails such as the anti-toggling measures proposed by PJM. But penalties should also be tailored to ensure that they are not written too broadly. As more fully discussed in Section C.4 of these comments, infra at 14-15, the Commission should direct PJM to modify the penalty provisions to clarify that, in the event a single Eligible Customer is serving multiple Co-Located Loads, that the disqualification penalty would only apply to service at the Co-Located Load that disregarded curtailment instructions or whose transmission protection measures misoperated twice. Finally, workable and reliable protections for the transmission system are critical. Although neither PJM nor the PJM Transmission Owners provided specific criteria yet for the “special protection schemes” and other necessary controls, the principles they outlined are sound; the Commission should adopt them.
PDF page 6
6
Notwithstanding the progress that PJM and the PJM Transmission Owners have made in their proposals, NOVEC respectfully urges the Commission to remain flexible as PJM, the PJM Transmission Owners, and other Market Participants gain practical experience serving Co- Located Load. These are entirely new services and may require additional modifications as experience is gained or as unexpected circumstances arise. As this proceeding advances and additional details on the proposals become clear, NOVEC reserves the right to oppose the Co- Location service rates, terms, and conditions if those proposals do not adequately shield existing transmission customers from subsidizing large-load customers or if they endanger the reliability of the transmission system.
B. PJM’s and the PJM Transmission Owners’ proposals to use the NITS rate for the new Firm Contract Demand transmission service, Non-Firm Contract
Demand transmission service, and Interim NITS, impose PJM administrative
and ancillary service charges, and institute a Grid Reliance Charge are just and reasonable, and the Commission should adopt their proposals.
Above all else, the rates for the new transmission services for the Co-Located Load must not result in existing transmission customers subsidizing large-load customers. NOVEC supports the Commission’s acceptance of the proposals of PJM and the PJM Transmission Owners with respect to rates for Contract Demand transmission service and Interim NITS. NOVEC is commenting specifically to highlight how critical it is that the proposed rates appropriately reflect the use of the transmission system by these new services and protect existing transmission customers from subsidizing Eligible Customers providing transmission service to Co-Located Load.
1. Using the NITS rate for Firm Contract Demand transmission service and
Non-Firm Contract Demand transmission service is appropriate.
The NITS rate is appropriate in light of the characteristics of Firm Contract Demand transmission service. Unlike point-to-point service, Contract Demand transmission service is not
PDF page 7
7
limited to one source, one sink and one path; an Eligible Customer can draw from the transmission system in a manner comparable to that of a NITS customer. Firm Contract Demand transmission service is NITS-equivalent, just scaled down to be available for less than the Co- Located Customers’ total load. Network upgrades still must be planned and constructed as necessary, with the only difference being that Firm Contract Demand transmission service’s network upgrades are planned based on contract demand requests instead of anticipated load growth.15 Because the service otherwise is fundamentally the same, assessing the same transmission rates as that of NITS makes sense. Because Eligible Customers are receiving a service commensurate with NITS, they should pay a cost commensurate with NITS in recognition of the Commission’s cost-causation principles.
The proposal to charge Non-Firm Contract Demand transmission service at the NITS rate net of the Grid Reliance Charge multiplied by their reserved amount of demand also seems reasonable. Netting the Grid Reliance Charge prevents double recovery. Like Firm Contract Demand transmission service, Non-Firm Contract Demand transmission service bears a resemblance to NITS service. Although non-firm, it is a network-type service. In Order No. 888, the Commission capped non-firm rates at the firm rate.16 Because an Eligible Customer need only purchase Non-Firm Contract Demand transmission service when reserved, transmission costs for an Eligible Customer are lower than firm rates. Further, as the PJM Transmission Owners point out, it has a superior priority to non-firm point-to-point transmission service.17 And because these revenues are credited to the applicable transmission owner’s annual transmission
15 PJM TO Initial Brief at 8.16 Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities, Order No. 888, 75 FERC ¶ 61,080 (1996).17 PJM TO Initial Brief at 12.
PDF page 8
8
revenue requirement, this proposal prevents existing load-serving transmission customers from subsidizing Co-Located Load.
2. PJM’s administrative charges are appropriate.
The Commission asked whether it would be just and reasonable to include charges for PJM’s administrative services.18 NOVEC agrees with PJM’s proposal to assess administrative service charges on Co-Located Load.19 These charges are associated with the use of the transmission system beyond transmission service rates.20 Any entity that uses the transmission system should contribute to administrative charges associated with the transmission system. The Commission found that Co-Located Load would use the transmission system even if it did not draw power from the grid.21 It is thus entirely appropriate for PJM to assess administrative charges on Co-Located Load. Co-Located Load must bear its fair share of administrative costs.
The Commission should also accept PJM’s proposal to recover Black Start Service charges and Regulation charges based on the gross demand of the Co-Located Load for Firm Contract Demand transmission service and for Non-Firm Contract Demand transmission service. The proposal is consistent with the Commission’s finding “that Eligible Customers taking one of the new transmission services on behalf of Co-Located Load must be assessed for regulation service on a gross demand basis at the existing Tariff rate, consistent with the Commission’s cost-causation principles.”2218 Co-Location Order at P 219.19 PJM Initial Brief at 27, 36, and 73.20 Id. at 27 (“These are standard charges associated with the use of the Transmission System over and above the transmission service rates.”).21 Co-Location Order at P 183.22 Id. P 184.
PDF page 9
9
3. The Commission should accept the Grid Reliance Charge as proposed.
In the Co-Location Order, the Commission asked whether the rate paid by an Eligible Customer on behalf of a Co-Located Load that does not reserve any amount of transmission service should include, besides Regulation and Black Start Services, “an additional charge given that regulation and black start services could not be provided without the transmission system.”23 The answer to that question is an unequivocal yes. The PJM Transmission Owners have proposed a Grid Reliance Charge based on the difference between an Eligible Customer’s firm contract demand (or for Non-Firm Contract Demand customers, the amount of reserved service) and their gross on-site load.24
As a threshold matter, Eligible Customers should pay a charge that reflects the need to deliver these services to their Co-Located Load. Because all other load takes transmission service up to their gross load, their transmission rates implicitly reflect such use of the transmission system. The rates of Black Start Service and Regulation do not include a delivery component. If a Co-Located Load reserved no Firm or Non-Firm Contract Demand transmission service, its payment for those two ancillary services would not include any costs of the transmission system that are necessary to deliver those services to the Co-Located Load. Without such a charge, the Co-Located Load would be a free rider on the transmission system, benefiting from the payments of existing transmission customers to maintain the transmission system without making any contribution towards it.2523 Id. P 219(3).24 PJM TO Initial Brief at 14.25 Id. at 15 (“Even with a zero MW contract demand, a large Co‑Located Load and generation arrangement will still depend on the grid for the delivery of various ancillary services and a suite of synchronization support services, such as stable frequency, inertia, stability services (damping, angle stability), fault current capability, and ride-through and protection coordination. In short, a Co-Located Load’s net withdrawals do not fully reflect its actual reliance on the grid.”).
PDF page 10
10
So, the question becomes whether the PJM Transmission Owners’ proposed Grid Reliance Charge is just and reasonable. There are many possible ways to calculate a Grid Reliance Charge. The approach has a reasonable foundation, and the Commission should accept it because the Grid Reliance Charge as proposed is just and reasonable, with an important distinction: it is limited to depreciation and O&M, conservatively excluding a return on rate base and associated income taxes. The PJM Transmission Owners only recover their costs and not a return. Because of the novelty of the Grid Reliance Charge, taking a conservative approach initially is justifiable. Until PJM and the PJM Transmission Owners gain more experience, the Grid Reliance Charge is transparent, simple, scales with each utility’s size and cost structure, and promotes rate stability.26 In the future, the PJM Transmission Owners should explore revising the methodology to better align the costs of providing access to necessary ancillary services with the benefits of those services to ensure that Co-Located Load makes an adequate contribution to those costs. NOVEC views the current proposal as a minimum rate. In addition, because revenues earned from the Grid Reliance Charge are returned to NITS and Firm Contract Demand transmission service customers as a revenue credit, the structure avoids any risk of double recovery. The Commission should accept it as filed by the PJM Transmission Owners. The Commission may wish to consider ordering PJM to hold a stakeholder process to determine whether the rate needs to be changed in the future.
C. PJM and the PJM Transmission Owners are correct that both operational and financial penalties are necessary to ensure compliance with rules for Eligible Customers serving Co-Located Loads.
The Commission asked what is the “appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an
26 PJM TO Initial Brief, Ex. PTO-0001 at 24:17-25:14.
PDF page 11
11
Eligible Customer taking” Firm Contract Demand or Non-Firm Contract Demand transmission service on behalf of a Co-Located Load.27 PJM proposed three different penalties applicable to the three transmission services where Eligible Customers: “(i) fail to follow established Load Shedding and Curtailment procedures; (ii) rely on necessary control technologies or protection systems in accordance with the PJM Manuals, which may include a RAS, that fail (i.e., misoperate) more than once; and (iii) makes unreserved use of the PJM Transmission System.”28 Those penalties are disqualification, a pause in service, and financial penalties.
1. Disqualification is appropriate in the circumstances proposed by PJM in
order to protect the reliability of the transmission system.
Disqualification means that an Eligible Customer taking Firm Contract Demand or Non- Firm Contract Demand transmission service to serve Co-Located Load is disqualified from taking Firm Contract Demand or Non-Firm Contract Demand transmission service for that Co- Located Load.29 An Eligible Customer disqualified from taking such services for the relevant Co-Located Load may still take transmission service on behalf of the Co-Located Load by taking NITS or qualifying for Interim NITS.30 Also, an Eligible Customer taking Interim NITS may be disqualified from taking service for specific Co-Located Loads, in which case only NITS will be available once any necessary upgrades are complete.31
There are two circumstances in which PJM proposes to impose disqualification. First, in the event that there is a failure to follow Load Shedding or Curtailment procedures for the first time, the Co-Located Load will be disqualified from receiving Firm Contract Demand
27 Co-Location Order at P 219(5), (6).28 PJM Initial Brief at 40.29 Id., Attachment A, Tariff, Part XI, § 713.7(a).30 Id. at 42. As NOVEC previously commented, supra at 5, and as more fully discussed in Section C.4 of these comments, infra at 14-15, in the event a single Eligible Customer is serving multiple Co-Located Loads, the disqualification penalty should apply only to service at the Co-Located Load which disregarded curtailment instructions or whose transmission protection measures misoperated twice.31 Id. at 42-43.
PDF page 12
12
transmission service, Non-Firm Contract Demand transmission Service, or Interim NITS.32 Second, Eligible Customers will be disqualified from taking the contract demand services for the relevant Co-Located Load upon the second misoperation of necessary control technology and protection schemes.33
PJM is responsible for ensuring the provision of reliable electric service to 67 million people. Not following Load Shedding or Curtailment procedures compromises PJM’s ability to fulfill its responsibilities. Although PJM has proposed as a compromise allowing one misoperation of a “special protection scheme” before disqualification, the proposal to disqualify after repeated misoperations is also necessary to protect the integrity of the transmission system. Further, NITS remains available to any Co-Located Load that is disqualified from taking the new services. As PJM explained, the “choice to take NITS, in and of itself, decreases the likelihood of significant issues arising from failure to curtail, load shed, or misoperation of a necessary control technology or protection system.”34 Because PJM’s disqualification proposal deters conduct that threatens the integrity of the transmission system and provides a safe alternative, the Commission should find it is just and reasonable and adopt it.
2. A pause in service is an appropriate compromise for the first
misoperation of a necessary control technology or protection system.
NOVEC supports PJM’s proposal to implement a pause of 120 days from taking
transmission service or withdrawing energy from the transmission system after the first misoperation of the necessary control technology or protection system.35 Allowing a pause to
32 Id. at 41, Table 1.33 Id. at 45.34 Id. at 48-49.35 Id. at 44-45.
PDF page 13
13
evaluate, investigate, and remedy failures of the necessary control technology is appropriate and will help develop new procedures and experience to more reliably manage Co-Location.
3. Additional financial penalties are warranted.
NOVEC agrees with PJM and the PJM Transmission Owners that a penalty for
unreserved use in addition to disqualification and pause-in-service rules is appropriate.36 In the current environment, PJM is correct that “many, if not most, Eligible Customers taking service on behalf of a Co-Located Load could foreseeably elect to absorb financial penalties for unreserved use rather than follow Curtailment or Load Shed procedures or avoid misoperation of the protective technology or system.”37 Financial penalties alone would not be sufficient to ensure that Co-located Loads and co-located generating facilities comply, through the relevant Eligible Customers, with their obligations. But that is not sufficient reason to dispense with a financial penalty.
A complementary financial penalty should be an additional deterrent that would help make sure that “the market and other ratepayers are made whole if a Co-Located Load customer exceeds its contract demand.”38 At this time, neither PJM nor the PJM Transmission Owners have a specific concept for the Commission to consider, but have committed to working together to explore penalty options. NOVEC supports those efforts and supports the principle that a financial penalty should compensate other customers for any harm caused by the Eligible Customer’s departure from Co-Location requirements or, if there is no harm, that the financial penalty should be set at a level sufficient to encourage compliance with the PJM Tariff’s scheduling requirements.
36 Id. at 50; PJM TO Initial Brief at 20.37 PJM Initial Brief at 50.38 PJM TO Initial Brief at 20.
PDF page 14
14
4. PJM’s penalty language should be revised to account for conditions
where an Eligible Customer serves multiple Co-Located Loads.
At present, the Illustrative Tariff provides that, when one of the disqualifying events happens, the Eligible Customer “shall be disqualified from taking Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.”39 PJM has crafted this language with the assumption that either the generator serving the Co-Located Load or the Co-Located Load itself would be the Eligible Customer. But the Co-Location Order contemplates that “any electric utility” could be an Eligible Customer.40 That leaves open the possibility that the generator, the Co-Located Load, and the Eligible Customer could each be separate entities. Under those circumstances, the Eligible Customer could reasonably have to rely upon the Co-Located Load and the co-located generating facility for compliance with curtailment instructions from PJM and maintenance of equipment to implement the “special protection schemes.” A third-party Eligible Customer would have limited operational control over the site.
As drafted, the Illustrative Tariff could result in a third-party Eligible Customer being disqualified from serving Co-Located Load entirely because of the actions of the Co-Located Load or the co-located generating facility. This would unreasonably harm the Eligible Customer. If the Eligible Customer were a Load Serving Entity acting as an Eligible Customer for multiple Co-Located Loads, it would unreasonably harm those other Co-Located Loads as well. Accordingly, the Illustrative Tariff should be revised to specify that when a third-party Eligible Customer is not responsible for a disqualifying event, only the culpable Co-Located Load (and
39 See PJM Initial Brief, Attachment A, Tariff, Part XI, § 713.7(b).40 Co-Location Order at P 10; see also Co-Location Order at n.404 (“An Eligible Customer could be, for example, any person generating electric energy for resale or any retail customer taking unbundled transmission service under certain conditions. For the full definition of Eligible Customer, see Part I.C.”) (italics added).
PDF page 15
15
not the Eligible Customer) will be disqualified from Firm and Non-Firm Contract Demand transmission service.
D. PJM’s two-pronged approach to implementing an anti-toggling feature for Firm Contract Demand transmission service is reasonable and should be accepted.
The Commission sought comment on the appropriate mechanisms for an anti-toggling feature for Firm Contract Demand transmission service, including a minimum service period and minimum notice period.41 The Commission explained that without an anti-toggling feature, Eligible Customers taking transmission service on behalf of Co-Located Loads “may attempt to switch between the two new transmission services based on expected capacity market conditions.”42
PJM proposed a two-pronged approach. First, Section 709.4 of its Illustrative Tariff provides that the portion of Co-Located Load served by Firm Contract Demand transmission service is not eligible to be served by Non-Firm Contract Demand transmission service for “five years following the effective date of the Service Agreement for Contract Demand Transmission Service.”43 There is an exception for physical changes to the Co-Located generating facility or the Co-Located Load that would materially alter the MW-level of power or MW-level of gross demand.44 The second anti-toggling feature is PJM’s proposed 42-month notice of termination.45
Both of these proposals are just and reasonable and should be accepted. PJM will have to procure capacity resources for Firm Contract Demand, and there may be network upgrades necessary to serve a request for Firm Contract Demand transmission service.46 Setting a minimum service commitment of five years ensures that timely price signals are sent to the
41 Id. P 219(7).42 Id. P 213.43 PJM Initial Brief at 53 (quoting PJM Initial Brief, Attachment A, Tariff, Part XI, § 709.4).44 Id. at 54.45 Id. at 54-55.46 PJM TO Initial Brief at 21.
PDF page 16
16
capacity market and enhances market stability. The five-year period also minimizes the risk of Co-Located Load causing network upgrades and then withdrawing, leaving other load with the obligation to fund those upgrades. With respect to the notice-of-termination period, as the PJM Transmission Owners point out, it is identical to the requirements for termination of NITS.47 The notice period will help address any cost-shifting concerns by preventing Co-Located Loads from avoiding capacity charges incurred on their behalf by prematurely terminating their agreement.48
E. The Commission should ensure that any “special protection schemes” are robust enough to ensure system reliability.
The Commission asked what interconnection requirements and operational practices are necessary for “special protection schemes” to maintain system reliability.49 In response, PJM stated that “[t]he interconnection requirements and operational practices necessary for necessary control technologies and protection systems to maintain system reliability in the event that a Co- Located Load or associated generator trips offline will be set forth in the PJM Manuals and, as applicable, [North American Electric Reliability Corporation] reliability standards.”50 At a minimum, PJM’s proposal to incorporate North American Electric Reliability Corporation (“NERC”) reliability standards is just and reasonable.
The Commission should ensure that there are high reliability standards so that no retail customers are harmed by the failure of “special protection schemes” of large-load customers. Retail customers do not have the option to take a lower-quality service to economize. Under no circumstances should large-load customers choosing a lower-quality service be permitted to
47 Id. at 21-22.48 PJM Initial Brief at 55.49 Co-Location Order at P 219(8).50 PJM Initial Brief at 57.
PDF page 17
17
reduce the reliability of retail customers’ services. The PJM Transmission Owners elucidated several possible guideposts to consider that would help meet this goal.51
NOVEC supports those principles. In particular, NOVEC agrees that the “special protection schemes” should be fully redundant and that the applicable PJM Transmission Owner should be able to establish technical criteria for the interconnection of Co-Located Load. Transmission Owners are familiar with the operating characteristics of their own systems, and any criteria should be flexible enough to include reasonable requirements the Transmission Owners believe are necessary to protect the transmission system. NOVEC also agrees with the PJM Transmission Owners that the Commission should direct NERC to establish registration requirements for Co-Located Loads so that they can be responsible for meeting NERC reliability standards.
F. The Commission should approve PJM’s proposed effective date.
NOVEC agrees with PJM that a reasonable effective date is June 1, 2029. Mr. Horger’s explanation that it is no longer possible to implement necessary changes to the 2028/2029 Reliability Pricing Model to account for the new transmission services is well-founded.52 The further explanations that there are necessary software modifications that must be designed and implemented and that no customers would likely be able to interconnect before then because of PJM’s interconnection queue further support the June 1, 2029 effective date.
Besides the impact on PJM, other affected entities must prepare for these new transmission services to accommodate Co-Located Loads. Any electric utility that may have to serve a Co-Located Load as an Eligible Customer, or even simply have one in its service territory, will have to prepare both as an operational matter and consider appropriate regulatory
51 PJM TO Initial Brief at 23-24.52 PJM Initial Brief, Attachment D, Affidavit of Timothy Horger at PP 6-14.
PDF page 18
18
and billing changes to ensure that costs reflect cost-causation principles. That takes time and PJM’s proposed date provides an opportunity to make these changes systematically and efficiently.
II. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission accept this response to the initial briefs of PJM and the PJM Transmission Owners and adopt a replacement rate consistent with the PJM and PJM Transmission Owners’ proposals and NOVEC’s comments on those proposals as set forth herein.
Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to Northern Virginia Electric Cooperative, Inc.
Dated: March 25, 2026.
PDF page 19
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated at Washington, D.C. this 25th day of March, 2026.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com