EL25-49-000 · 2026-03-25 · Northern Virginia Electric Cooperative, Inc.

Response of Northern Virginia Electric Cooperative, Inc. to Initial Brief of PJM Interconnection, L.L.C. and to Initial Brief and Joint Responses of the…

Text extracted from the eLibrary original (SHA-256 d9c2e61ca76f6ac3…). Download the original from the official source.

Contents · 8 sections
  1. I. RESPONSE p. 3
  2. A. Introduction and Background p. 3
  3. B. PJM’s and the PJM Transmission Owners’ proposals to use the NITS rate for p. 6
  4. C. PJM and the PJM Transmission Owners are correct that both operational and p. 10
  5. D. PJM’s two-pronged approach to implementing an anti-toggling feature for Firm p. 15
  6. E. The Commission should ensure that any “special protection schemes” are robust p. 16
  7. F. The Commission should approve PJM’s proposed effective date. p. 17
  8. II. CONCLUSION p. 18

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

AND TO INITIAL BRIEF AND JOINT RESPONSES OF THE INDICATED PJM TRANSMISSION OWNERS TO PAPER HEARING QUESTIONS Pursuant to the Federal Energy Regulatory Commission’s (“Commission”) December 18, 2025 order (“Co-Location Order”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully…
Read this passage Filed comments: Filing procedure

I. RESPONSE

printed heading

I.
Read this passage

A. Introduction and Background

printed heading · Topic match: Connecting load and generation

Such penalties must discourage gamesmanship, must be enforceable, and should include guard-rails such as the anti-toggling measures proposed by PJM.
Read this passage Filed comments: Connecting load and generation

B. PJM’s and the PJM Transmission Owners’ proposals to use the NITS rate for

printed heading · Topic match: Connecting load and generation

Above all else, the rates for the new transmission services for the Co-Located Load must not result in existing transmission customers subsidizing large-load customers.
Read this passage Filed comments: Connecting load and generation

C. PJM and the PJM Transmission Owners are correct that both operational and

printed heading · Topic match: Connecting load and generation

At present, the Illustrative Tariff provides that, when one of the disqualifying events happens, the Eligible Customer “shall be disqualified from taking Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.”39 PJM has crafted this language with the assumption…
Read this passage Filed comments: Connecting load and generation

D. PJM’s two-pronged approach to implementing an anti-toggling feature for Firm

printed heading · Topic match: Connecting load and generation

First, Section 709.4 of its Illustrative Tariff provides that the portion of Co-Located Load served by Firm Contract Demand transmission service is not eligible to be served by Non-Firm Contract Demand transmission service for “five years following the effective date of the Service Agreement for…
Read this passage Filed comments: Connecting load and generation

E. The Commission should ensure that any “special protection schemes” are robust

printed heading · Topic match: Connecting load and generation

In particular, NOVEC agrees that the “special protection schemes” should be fully redundant and that the applicable PJM Transmission Owner should be able to establish technical criteria for the interconnection of Co-Located Load.
Read this passage Filed comments: Connecting load and generation

F. The Commission should approve PJM’s proposed effective date.

printed heading · Topic match: Connecting load and generation

Horger’s explanation that it is no longer possible to implement necessary changes to the 2028/2029 Reliability Pricing Model to account for the new transmission services is well-founded.52 The further explanations that there are necessary software modifications that must be designed and implemented…
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission accept this response to the initial briefs of PJM and the PJM Transmission Owners and adopt a replacement rate consistent with the PJM and PJM Transmission Owners’ proposals and NOVEC’s comments on…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 25th day of March, 2026. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.com