EL25-49-000 · 2026-03-25 · Old Dominion Electric Cooperative
Reply Brief of Old Dominion Electric Cooperative
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
2
City of Cleveland, Department of Public Utilities, Division
of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
AD24-11-000
EL25-20-000
(Consolidated)
REPLY BRIEF OF OLD DOMINION ELECTRIC COOPERATIVE
Pursuant to the Order issued in the above-referenced proceeding on December 18, 2025, 1 and the Notice of Extension of Time issued on January 23, 2026, Old Dominion Electric Cooperative (“ODEC”) submits this Reply Brief in response to the Initial Brief and Joint Responses of the PJM Transmission Owners to Paper Hearing Questions2 and the Initial Brief of PJM Interconnection, L.L.C. (“PJM”).
I. RELEVANT BACKGROUND AND SUMMARY OF POSITION
The detailed background of this proceeding is contained in the Hearing Order. In summary, the Commission determined that PJM’s Tariff is unjust and unreasonable because it lacked provisions that address with sufficient clarity or consistency the rates, terms and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.3 Among other things, the Commission
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Hearing Order”).
2 (“Indicated TOs’ Initial Brief”).3 Hearing Order at P 2.
PDF page 3
3
directed PJM to submit a compliance filing to revise its Tariff to set forth conditions for interconnection regarding Co-Located Location Arrangements. The Commission also directed PJM to revise its Tariff to require Eligible Customers taking transmission service on behalf of Co- Located Loads to take one of three transmission services: (1) Network Integration Transmission Service (“NITS”); (2) a new Firm Contract Demand transmission service; or (3) a new Non-Firm Contract Demand transmission service.4 The Commission established a paper hearing to determine the just and reasonable rates, terms and conditions for the new transmission services.5 On February 23, 2026, PJM and the Indicated PJM TOs each filed their initial briefs in this paper hearing proceeding. PJM’s Initial Brief addressed the non-rate terms and conditions for the new transmission services, in response to questions posed in the Hearing Order. The Indicated TOs submitted rates for the new services, consistent with their rights under the Consolidated Transmission Owners Agreement.
ODEC is a not-for-profit power supply electric cooperative, organized and operating under the laws of Virginia and subject to FERC jurisdiction. ODEC supplies capacity and energy to its eleven electric distribution cooperative members, all of which are located within the PJM control area. ODEC is a network transmission customer of PJM, as well as a PJM Transmission Owner. ODEC is a generation-owning utility, dependent upon the use of the transmission facilities of PJM under its Tariff to deliver the output of ODEC’s generation facilities located within PJM and to deliver periodic power purchases from third party sellers to the load of its member systems in PJM’s footprint. ODEC takes transmission service under the PJM Tariff. ODEC is also a Market Seller of energy and capacity under the PJM Tariff.
4 Id.5 Id. at PP 2, 219-220.
PDF page 4
4
As discussed herein, ODEC generally agrees with the proposals submitted by PJM and the Indicated TOs in their respective Initial Briefs. Subject to the clarifications discussed below, ODEC believes that both Initial Briefs provide just and reasonable rates, terms and conditions for the new Firm Contract Demand transmission service and Non-Firm Contract Demand transmission service. ODEC is willing to adopt the Indicated TOs’ proposed rates for the new Firm Contract Demand and Non-Firm Contract Demand, subject to these clarifications. Therefore, ODEC supports the Commission’s acceptance of both filings, subject to further compliance filings as necessary to address the following issues described in the remainder of this Reply Brief: (1) clarification of PJM’s proposed requirement that an Eligible Customer must be designated to take transmission service on behalf of a Co-Located Load and provide PJM with an authorization from its Relevant Electric Retail Regulatory Authority (“RERRA”); (2) with respect to the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the new Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the individual TOs will need to either confirm that their formula or stated rates and metrics reporting enable the direct crediting by PJM, or provide whatever revisions are necessary in order for PJM to do so; (3) PJM and the PJM Transmission Owners will need to address how to charge regulation and black start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) the Commission should consider whether any protections are needed for local utilities or TOs should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds contract demand or they are called upon for Load Shedding and Curtailment.
PDF page 5
5
II. REPLY TO PJM AND INDICATED TOS’ INITIAL BRIEFS
ODEC is a PJM Transmission Owner but did not participate in the Indicated TOs’ Initial Brief. ODEC submits this Reply Brief to state its support for most of the proposals in the Indicated TOs’ Initial Brief, as well as identify areas that require further consideration or clarification. Subject to the clarifications and issues raised below, ODEC is willing to adopt the Indicated TOs’ proposed rates for the new transmission services for Co-Located Loads, as described in the Indicated TOs’ Initial Brief.
Overall, ODEC agrees with the Indicated TOs’ Initial Brief and PJM’s Initial Brief. Without detailing each component of the Indicated TOs’ Initial Brief, ODEC agrees with the Indicated TOs’ principles that (1) rates for the new services ordered by the Commission must be consistent with longstanding cost allocation principles, so that existing customers do not unfairly subsidize services for Co-Located Load customers; and (2) the new transmission services must be implemented in a manner that does not compromise system reliability.6 ODEC’s comments below correspond to the questions posed in the Commission’s Hearing Order.
Questions 1 and 2:
(1) What are the appropriate rates, terms, and conditions for the new Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal firm PTPS charges to this new service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services?
(2) What are the appropriate rates, terms, and conditions for the new Non-Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal non-firm PTPS charges to this new
transmission service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services?
6 Indicated TOs’ Initial Brief at 3-5.
PDF page 6
6
A. PJM’s Proposed Conditions Precedent and Technical Requirements for Contract Demand Transmission Services
ODEC generally supports PJM’s conditions precedent to ensure that Eligible Customers taking service on behalf of Co-Located Loads preserve the reliability of the Transmission System. However, there is one aspect of PJM’s proposed conditions precedent that may need further consideration or clarification. PJM’s Initial Brief and Illustrative Tariff propose a condition precedent that the “Eligible Customer must have been designated to take transmission service on behalf of a Co-Located Load in the relevant Application, Service Agreement, or GIA for the Co- Located Generating Facility, and provide PJM with ‘an authorization or certification from its Relevant Electric Retail Regulatory Authority which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load.”7 Based on the existing PJM Tariff definitions, it appears that ODEC would be the Eligible Customer8 for at least its distribution cooperative members, as well as the RERRA.
The PJM Tariff defines and Eligible Customer as follows:
. . .any electric utility or any person generating electric energy for sale for resale, but with respect to transmission service that the Commission is prohibited from ordering by section 212(h) of the Federal Power Act, such entity is eligible only if the service is provided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner or (2) any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner.
ODEC is a generation and transmission electric cooperative. To meet the requirements of its eleven distribution cooperatives under the Third Amended and Restated Wholesale Power
7 PJM Initial Brief at 19; Illustrative Tariff. Part XI, Subpart B, section 710.1.8 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – E-F (41.0.0).
PDF page 7
7
Contracts between ODEC and each of its eleven distribution electric cooperatives, ODEC owns generating facilities and purchases Network Integration Transmission Service (“NITS”) under the PJM Open Access Transmission Tariff (“Tariff”). Thus, with respect to the definition of Eligible Customer, ODEC is the “electric utility . . . generating electric energy for resale” and ODEC takes transmission service to serve its members. As such, ODEC is the entity that would be the Eligible Customer for Co-Located Loads, at least with respect to existing generating facilities and any Planned Facilities owned by ODEC that would be used to serve the Co-Located Loads of ODEC’s members.
The PJM Tariff defines the RERRA as “an entity that has jurisdiction over and establishes prices and policies for competition for providers of retail electric service to end-customers, such as the city council for a municipal utility, the governing board of a cooperative utility, the state public utility commission or any other such entity.”9 ODEC’s members are located in Virginia, Maryland and Delaware. While the Virginia State Corporation Commission (“VSCC”) is currently the RERRA for ODEC’s member distribution cooperatives in Virginia, the individual member distribution cooperatives are the RERRA in Maryland and Delaware. It is unclear whether PJM intends that ODEC, as the Eligible Customer for Co-Located Loads located in its members’ service territories, would need to provide certification that the member has authorized ODEC to provide energy to the Co-Located Load. Alternatively, where the state regulatory agency is the RERRA, ODEC is unaware of a procedure whereby it would obtain authorization from the VSCC in order to provide energy to Co-Located Loads. ODEC requests that PJM provide clarification on this proposed requirement, as it would apply to a generation and transmission electric cooperative like ODEC.
9 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – R-S.
PDF page 8
8
B. The Indicated TOs’ Proposed Rates for Firm and Non-Firm Contract Demand
Transmission Services
With respect to Indicated TOs’ proposed rates for the new transmission services ordered by the Commission, ODEC generally agrees with the Indicated TOs’ proposed rate design as well as the terms and conditions for each service. More specifically, ODEC agrees that it is reasonable to charge the same rate for Firm Contract Demand Service and NITS, as well as the Indicated TOs’ proposal to use the same Firm Contract Demand Service rate for purposes of establishing the maximum rate for Non-Firm Contract Demand Service. ODEC also agrees that it is reasonable for PJM to charge Firm Contract Demand Service customers and Non-Firm Contract Demand Service customers for applicable PJM administrative charges consistent with PJM’s charges to existing transmission customers.
One component of the Indicated TOs’ Initial Brief that may require further compliance filings is the issue of bill credits for NITS and Firm Contract Demand Service customers. ODEC supports the Indicated TOs’ expectation that PJM will provide bill credits to NITS and Firm Contract Demand Service customers directly in their monthly invoices, to reflect credits for revenues associated with the new Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service.10 In addition to its status as a Transmission Owner, ODEC is a transmission customer under the PJM OATT, as ODEC takes NITS service and pays the NITS rates for several Transmission Owners in order to meet ODEC’s obligations to provide service to its eleven member distribution cooperatives.11 It is important that the Commission have assurance from PJM that it
10 Id. at 7, 9.11 ODEC takes transmission service and pays the transmission revenue requirement for the following TOs: Virginia Electric and Power Company d/b/a Dominion Energy Virginia; American Electric Power Service Corporation (Appalachian Power Company); Exelon Corporation (Delmarva Power & Light Company); and FirstEnergy Service Company (The Potomac Edison Company, Monongahela Power Company, and Keystone Appalachian Transmission Company).
PDF page 9
9
will provide the bill credits as envisioned by the Indicated TOs, so that ODEC and other NITS customers are not subject to paying duplicative charges for the same revenue requirement amount. The assurance from PJM is also important because the Indicated TOs’ statement that load-serving entities will perform their current roles of submitting the metrics that PJM uses to calculate transmission, capacity, and energy charges that as a transmission customer taking NITS service, may not be consistent among the Indicated TOs. For example, although ODEC is a load-serving entity, as a transmission customer ODEC does not submit metrics to PJM for calculation of ODEC’s charges for transmission, capacity, and energy. Instead, those metrics are provided to PJM by the Transmission Owner(s) for the zones where ODEC takes transmission service.12 Further, ODEC is a customer of AEP affiliate Appalachian Power Company (“APCo”) under a full-requirements agreement dated August 1, 2017. Such stated rate agreements should ensure that customers such as ODEC receive credits for revenues received by APCo for the Grid Reliance Charge and Non-Firm Contract Demand transmission service, so that ODEC is not paying costs that are already recovered by APCo through these new charges. In order to ensure that rates for the new Firm Contract Demand Service are just and reasonable, the individual TOs will need to either confirm that their formula or stated rates and metrics reporting enable direct crediting by PJM, or provide whatever revisions are necessary in order to do so. Therefore, ODEC requests that the Commission’s order on the Indicated TOs’ filing require such further compliance filings. Questions 3 and 4:
(3) As noted above, a Co-Location Arrangement is synchronized to the transmission system.13 Should the rate paid by an Eligible Customer on behalf of a Co-Located
12 See, e.g., Attachments M-1 and M-2 to the PJM Tariff; see also, the Settlements Agreement between The Potomac Edison Company (“Potomac Edison”) and ODEC, Service Agreement No. 4453, providing that Potomac Edison calculates and reports to PJM the Total Hourly Energy Obligation (energy), Peak Load Contribution (capacity) and Network Service Peak Load (transmission) on behalf of LSEs in the PJM APS Zone.13 See also PJM March 24 Response at 42-43.
PDF page 10
10
Load taking only the new Non-Firm Contract Demand transmission service that elects to not reserve any amount of that service for a period of time (e.g., one month) reflect not only charges for regulation and black start services, but also an additional charge given that regulation and black start services could not be provided without the transmission system? If so, how should that additional charge be determined?
(4) As noted above, a Co-Location Arrangement is synchronized to the transmission system.14 Should the rate paid by an Eligible Customer on behalf of a Co-Located Load taking only a de minimis amount of the new Firm or Non-Firm Contract Demand transmission services reflect not only (i) charges for regulation and black start service and (ii) the transmission service charges for that de minimis amount of service, but also an additional charge reflecting that the Co-Location Arrangement is physically connected and synchronized to the PJM transmission system? If so, how should that additional charge be determined?
ODEC supports the Indicated TOs’ proposal for a Grid Reliance Charge to be applied to customers taking Firm Contract Demand Service and Non-Firm Contract Demand Service.15 As described by the Indicated TOs, the Grid Reliance Charge appropriately reflects the fact that Co- Located Load are synchronized with the transmission grid and rely on the transmission grid. Consistent with the Commission’s determination that transmission customers should be protected against cost-shifts under the new transmission service framework for Co-Located Loads, the Grid Reliance Charge ensures that Co-Located Loads pay their “fair share” of costs that are commensurate with the benefits Co-Located Loads receive from the transmission system including the costs associated with delivery of black start and regulation services.16 In its Initial Brief, PJM did not address these questions but indicated that it may provide additional perspectives in its reply brief, based on review of the PJM Transmission Owners’ brief.17 ODEC believes that in addition to the rates for the cost of regulation and black start services, the charges for individual Co-Located Loads will need to be determined on some basis
14 Id.15 Indicated TO’s Initial Brief at 14-18.16 Id.17 PJM Initial Brief at 38.
PDF page 11
11
of the Eligible Customer’s actual or proxy usage on behalf of Co-Located Loads. ODEC expects that in order to assess charges for black start and regulation service, there must be individual meters on the Co-Located Loads. PJM and the PJM Transmission Owners will need to address how to charge regulation and black start service to an Eligible Customer taking service on behalf of Co- Located Load.
Questions 5 and 6:
(5) What is the appropriate remedy or other remedial action that PJM should take to address unreserved use of the PJM transmission system for an Eligible Customer taking Firm Contract Demand transmission service on behalf of a Co-Located
Load? What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Non-Firm Contract Demand transmission service on
behalf of a Co-Located Load?
(6) What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Non-Firm Contract Demand transmission service on behalf of
Co-Located Load?
ODEC agrees with PJM’s proposal for escalating penalties in the form of disqualification and pauses in service for Eligible Customers failing to shed load or curtail, as well as for failures in control technology, and/or protection system misoperation.18 ODEC agrees with PJM that financial penalties alone will be insufficient to address and/or prevent the threats to system reliability posed by Eligible Customers who fail to control their withdrawals from the transmission system. ODEC will review the financial penalties being considered by PJM and the Indicated TOs when they are submitted to the Commission and may offer further comments at that time. Additionally, ODEC suggests that the Commission consider whether any protections are needed for local utilities or TOs should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible
18 Id. at 40-50.
PDF page 12
12
Customer’s use of the transmission system exceeds contract demand or are called upon for Load Shedding and Curtailment. In such instances, the local utility or TO should not be liable for legal, financial or other damages that might be experienced by an Eligible Customer.
III. CONCLUSION
WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider this Reply Brief and condition acceptance of the PJM and Indicated TOs’ proposals for transmission service to Co-Located Loads on further compliance filings as necessary to address the following (1) clarification of PJM’s proposed requirement that an Eligible Customer must be designated to take transmission service on behalf of a Co-Located Load and provide PJM with an authorization from its RERRA; (2) with respect to the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the new Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the individual TOs will need to either confirm that their formula or stated rates and metrics reporting enable the direct crediting by PJM, or provide whatever revisions are necessary in order to do so; (3) PJM and the PJM TOs will need to address how to charge regulation and black start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) the Commission consider whether any protections are needed for local utilities or TOs should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds contract demand or are called upon for Load Shedding and Curtailment.
PDF page 13
13
Respectfully submitted,
/s/ Adrienne E. Clair
Adrienne E. Clair
Jenna Cliatt
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
(202) 585-6900
(202) 585-6969 (fax)
aclair@thompsoncoburn.com
jcliatt@thompsoncoburn.com
Attorneys for Old Dominion Electric
Cooperative
Dated: March 25, 2026
PDF page 14
CERTIFICATE OF SERVICE
I hereby certify that on this 25th day of March 2026, I have caused a copy of the foregoing to be served upon each party designated on the Commission’s Official Service List for this proceeding.
/s/Adrienne E. Clair