Reply Brief of Old Dominion Electric Cooperative
Text extracted from the eLibrary original (SHA-256 3973d1732844c48e…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
AD24-11-000 EL25-20-000 (Consolidated) REPLY BRIEF OF OLD DOMINION ELECTRIC COOPERATIVE Pursuant to the Order issued in the above-referenced proceeding on December 18, 2025, 1 and the Notice of Extension of Time issued on January 23, 2026, Old Dominion Electric Cooperative (“ODEC”) submits this…Read this passage Filed comments: Filing procedure
I. RELEVANT BACKGROUND AND SUMMARY OF POSITION
printed heading · Topic match: Connecting load and generation
Therefore, ODEC supports the Commission’s acceptance of both filings, subject to further compliance filings as necessary to address the following issues described in the remainder of this Reply Brief: (1) clarification of PJM’s proposed requirement that an Eligible Customer must be designated to…Read this passage Filed comments: Connecting load and generation
II. REPLY TO PJM AND INDICATED TOS’ INITIAL BRIEFS
printed heading · Topic match: Cost allocation
Without detailing each component of the Indicated TOs’ Initial Brief, ODEC agrees with the Indicated TOs’ principles that (1) rates for the new services ordered by the Commission must be consistent with longstanding cost allocation principles, so that existing customers do not unfairly subsidize…Read this passage Filed comments: Cost allocation
A. PJM’s Proposed Conditions Precedent and Technical Requirements for Contract
printed heading · Topic match: Connecting load and generation
PJM’s Initial Brief and Illustrative Tariff propose a condition precedent that the “Eligible Customer must have been designated to take transmission service on behalf of a Co-Located Load in the relevant Application, Service Agreement, or GIA for the Co- Located Generating Facility, and provide PJM…Read this passage Filed comments: Connecting load and generation
B. The Indicated TOs’ Proposed Rates for Firm and Non-Firm Contract Demand
printed heading · Topic match: Connecting load and generation
Therefore, ODEC requests that the Commission’s order on the Indicated TOs’ filing require such further compliance filings.Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading · Topic match: Connecting load and generation
Clair Jenna Cliatt Thompson Coburn LLP 1909 K Street, N.W., Suite 600 Washington, D.C. 20006-1167 (202) 585-6900 (202) 585-6969 (fax) aclair@thompsoncoburn.com jcliatt@thompsoncoburn.com Attorneys for Old Dominion Electric Cooperative Dated: March 25, 2026Read this passage Filed comments: Connecting load and generation