EL25-49-000 · 2026-03-25 · PJM Industrial Customer Coalition and Industrial Energy ConsNational Railroad Passenger Corporation ("Amtrak")American Forest and Paper Association, Inc.
Responsive Brief of Industrial Customer Organizations and Amtrak
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
AD24-11-000
EL25-20-000
(Consolidated)
RESPONSIVE BRIEF OF
INDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK
Pursuant to the Order on Show Cause Proceeding, Directing Compliance Filings,
Establishing Paper Hearing, and Granting In Part and Denying In Part Complaint (“Order”) in the above-captioned dockets,1 and the January 23, 2026, Notice of Extension of Time,2 the PJM Industrial Customer Coalition (“PJMICC”), the Industrial Energy Consumers of America
(“IECA”), the American Forest and Paper Association (“AF&PA”) (collectively, “Industrials”), and the National Railroad Passenger Corporation (“Amtrak”) hereby file this Responsive Brief in response to PJM Interconnection, L.L.C.’s (“PJM”) and the Indicated PJM Transmission Owners’ (“PJM Transmission Owners”) Initial Briefs in Docket No. EL25-49, et al. (“Initial Briefs”)3, which were filed at the Federal Energy Regulatory Commission (“FERC” or “Commission”) on February 23, 2026, in the above-captioned dockets.
1 PJM Interconnection, L.L.C., et al., Order on Show Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting In Part and Denying In Part Complaint, Docket Nos. EL25-49-000, EL25-49-001, AD24- 11-000, EL25-20-000 (“Consolidated Dockets”) (Dec. 18, 2025) (“Order”).2 Notice of Extension of Time, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (Jan. 23, 2026). 3 PJM Interconnection, L.L.C., et al., Initial Brief of PJM Interconnection, L.L.C. (Feb. 23, 2026) (“PJM Initial Brief”); PJM Interconnection, L.L.C., et al., Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions (Feb. 23, 2026) (“PJM Transmission Owners Initial Brief”).
PDF page 2
2
I. EXECUTIVE SUMMARY
As retail customers with high energy consumption needs, the Industrials/Amtrak have long endorsed customer choice as a foundational principle for electric service. As such, the Industrials/Amtrak appreciate the promise of new transmission services designed to support the type and amount of service required by customers. Lessons can be learned from the optionality in the natural gas industry, while also recognizing the utility’s obligation to serve and the right of industrial, institutional, and transportation customers to receive reliable electric service under various federal and state laws. The proposed implementation of PJM’s three new transmission services (“New Services”) may yield benefits and optionality, but the New Services must be just, reasonable, and not unduly discriminatory or preferential under Section 206 of the Federal Power Act.4 Consequently, implementation of the New Services requires careful consideration of regulatory and jurisdictional issues and adherence to cost-causation principles. As the Commission develops the details for the New Services, the Industrials/Amtrak emphasize the following:
1) A just and reasonable back-up service is missing from the new transmission services structure. Back-up service provided without a default assumption that it will be used during system peaks is guaranteed to Qualifying Facilities (“QF”) under the Public Utility Regulatory Policies Act of 1978 (“PURPA”) and should be extended to other retail customers with on-site generation on a cost-causation basis, either through retail netting or through a firm, back-up service charged on a cost-causation basis (“cost-based”).
2) The outcome of PJM’s pending compliance proposal in FERC Docket No. ER26-1479 (“BTMG Compliance Docket”) regarding PJM’s retail Behind-the-Meter Generation (“BTMG”) applicability rules, including a yet-to-be-determined materiality threshold (“Retail Threshold”), directly impacts and relates to the New Services and whether the terms and conditions of the New Services are just and reasonable. While specific eligibility for retail netting is under consideration in the BTMG Compliance Docket, no firm cost- based back-up service has been proposed in the instant proceeding.
3) The Commission should incorporate incentives for Co-Located Load to bring new generation, with appropriate inducements for such generation’s reliable operation.
4 16 U.S.C. § 824e(a).
PDF page 3
3
4) The terms for New Services must respect state/federal jurisdictional boundaries and clearly translate into transparent retail rates.
Industrial retail configurations are varied, complex, and unique. Generally, in contrast to typical computational loads, industrial customers produce a physical product on-site; cannot shift load to other facilities; often must continue to operate for safety and environmental compliance reasons; and frequently have generation and load deeply integrated via cogeneration, a process that generates both electric power and useful thermal energy.5 Traditional industrial load configurations with BTMG also provide substantial benefits to the grid—this traditional, existing customer load did not trigger the current resource adequacy challenges on the grid, nor does it present the reliability risks posed by super-sized loads rapidly seeking to come online today. In the BTMG Compliance Docket, the Industrials/Amtrak submitted the Affidavit of James R. Dauphinais (“Dauphinais Affidavit”), in which Mr. Dauphinais provided testimony concerning the configurations of industrial, institutional, and transportation retail customers, particularly QFs, and the technical and regulatory basis for ensuring such customers have access to back-up power at just and reasonable rates.6
In contrast to the “traditional” load described above, computational loads (including data centers) do not generally have substantial cogeneration, typically do not operate large motors (which can help with grid stability), can turn on and off nearly instantaneously, and can reach extremely large sizes, well beyond most traditional industrial and institutional retail customers. The size and scale of the computational load currently in the planning process across PJM is
5 FERC regulations implementing PURPA define “cogeneration facility” as “equipment used to produce electric energy and forms of useful thermal energy (such as heat or steam), used for industrial, commercial, heating, or cooling purposes, through the sequential use of energy.” 18 C.F.R. § 292.202(c).6 See PJM Interconnection, L.L.C., Joint Protest and Comments of Industrial Customer Organizations and Amtrak, Docket No. ER26-1479-000 (Mar. 16, 2026) (“Industrials/Amtrak Protest”), Exhibit No. IA-1. The Dauphinais Affidavit is attached to this filing as Attachment 1 and provides support for the arguments herein.
PDF page 4
4
massive, both in the size of individual facilities and in the scale of the projects coming online across the PJM footprint.
As most planned load growth is driven by load additions greater than 300 MW, the Industrials/Amtrak proposed in the BTMG Compliance Docket a Retail Threshold of at least 200 MW, under which BTMG netting should continue.7 The Industrials/Amtrak also proposed that QFs maintain their continued eligibility for BTMG netting, in accordance with PURPA requirements.8 If the FERC accepts these proposals, it will go a long way toward resolving the concerns about back-up power in the design of the New Services. However, if the FERC denies the Industrials/Amtrak’s proposals in the BTMG Compliance Docket, the lack of back-up service in the design of the New Services becomes a heightened concern.
Retail customers represented by the Industrials/Amtrak in this docket seldom grab headlines and are often not at the center of large-load and transmission planning discussions today—yet they have operated such systems reliably for decades. The transmission system has grown up around such traditional loads, worked in concert with them, and benefited from their presence, operations, and long-term planning. As explained further in Section III, infra, these retail BTMG configurations are varied and diverse. The facts of on-site generation configurations matter and must be understood to ensure just and reasonable determinations in this proceeding. Examples are plentiful. For some retail customers, industrial processes with cogeneration and combined heat and power (“CHP”) assets may require steam heat produced from the generation, meaning if the generation goes down, the load follows. In that case, it would defy cost- causation principles to require such a facility to pay for transmission services it cannot physically
7 Industrials/Amtrak Protest at 23-33.8 Id. at 17-23.
PDF page 5
5
use (such as via a Grid Reliance Charge as proposed in the PJM Transmission Owners’ Initial Brief).9
Other industrial customers currently qualify, or could qualify, as QFs under PURPA, granting them the right to back-up and maintenance power at rates/terms that do not assume that units will be down during system peaks and do not assume that units will be down at the same time as the other QFs (unless there is data backing that assumption). Yet, as will be explained further herein, the current proposed design of the New Services in the Initial Briefs makes no allowance for back-up power at cost-based rates.
A third example is that, as a legacy of the buildout of the Northeast Corridor (NEC), Amtrak requires service at 25 Hz, which it receives, at least for some of its requirements, through a contractual arrangement with a third-party generator that is neither a small power production QF nor a cogeneration QF. This arrangement provides the only black-start capability for Amtrak’s south end of its Northeast Corridor traction power system if the 60 Hz power grid goes out of service.
Each of these configurations, plus others, is described in greater detail in Section III, infra. These configurations underscore the critical need for the FERC to consider the impact on traditional large-load configurations to ensure a just and reasonable replacement rate when authorizing a final design for the New Services. Absent a just and reasonable method of obtaining back-up power, many retail customers will face devastating economic consequences. For some, as further explained below and in the Dauphinais Affidavit, it will mean closure of generating units, exacerbating the current resource adequacy concerns in the region.
9 PJM Transmission Owners Initial Brief at 5, 11.
PDF page 6
6
With careful attention to the reasons, needs, and cost-causation basis for back-up service, this result is avoidable. The Commission can authorize the New Services while also ensuring a just and reasonable back-up service is in place for QFs and other similarly situated retail customers. Accordingly, the Industrials/Amtrak respectfully request that the Commission develop the New Services, consistent with the comments and changes recommended herein, to ensure the avoidance of unintended and irreparable damage to America’s essential manufacturing sector and institutional and transportation service providers.
II. BACKGROUND
On December 18, 2025, the Commission issued the Order, finding that the PJM Tariff is unjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and directing PJM to make several compliance and informational filings. The Order directed PJM to create three New Services, including an interim, non-firm Network Integration Transmission Service (“Interim NITS”), a Firm Contract Demand Service (“Firm CDS”), and a Non-Firm Contract Demand Service (“Non-Firm CDS”).10 Paper hearing procedures were established to evaluate the rates, terms, and conditions of the New Services. The Order also addressed PJM’s retail BTMG rules, which have long allowed for measurement of a retail customer’s transmission (as well as capacity, energy and ancillary services) cost responsibility by actual use of the system as measured at the meter. In light of its finding that “circumstances have changed since the Commission approved PJM’s retail BTMG rules,” the Commission directed PJM to implement changes to BTMG rules above a yet-to-be- determined materiality threshold (“Retail Threshold”).11 PJM, the Industrials/Amtrak, and others
10 Order at P 2.11 Order at P 186.
PDF page 7
7
have subsequently made various proposals for the Retail Threshold and other proposed terms for retail BTMG rules in the BTMG Compliance Docket.
On February 23, 2026, PJM and the PJM Transmission Owners filed Initial Briefs in the above-captioned dockets, kicking off the briefing stage of the Paper Hearing.12 PJM also convened several stakeholder workshops to solicit input on the design and pricing of the New Services.13 To provide additional perspective on issues set for the Paper Hearing, and to respond to proposals made in the Initial Briefs, the Industrials/Amtrak respectfully offer the following response for the Commission’s consideration.
III. THE INDUSTRIALS/AMTRAK
This Responsive Brief is being filed on behalf of many of the major American energy consumers in the PJM region: industrial customers that manufacture products used in everyday life and commerce; a provider of core transportation services across the nation; and institutions that offer essential medical and educational services. In many cases, these traditional institutional, industrial, and transportation customers own or operate their own generation—not because energy is their primary industry, but because their core work is energy-intensive. These customers have elected to construct or contract for retail BTMG in order to control their own energy costs, create efficiencies, and/or address reliability needs. Even though the Order was issued largely in response to the impacts of “super-sized” loads such as data centers on the grid, the resulting changes (as currently proposed in the Initial Briefs) will directly and deeply impact these traditional retail
12 Also on February 23, 2026, in the BTMG Compliance Docket, PJM filed 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25- 49, et al., Docket No. ER26-1479-000 (Feb. 23, 2026) (“Compliance Filing”).13 PJMICC and IECA (together, “Requestors”) jointly filed a Request For Clarification or, in the Alternative, Rehearing of the Industrial Customer Coalitions (“Rehearing Request”) on January 20, 2026, in Docket No. EL25- 49-000 and the other Consolidated Dockets. Nothing herein should be construed to modify the Rehearing Request. The Requestors and the Industrials/Amtrak reserve their rights to supplement or modify this Protest and Comments in response to any order on rehearing.
PDF page 8
8
customers. Like all other retail customers, manufacturers, hospitals, universities, and transportation providers have the same right to just and reasonable rates that are grounded in cost- causation principles.
The Industrials, which include several associations of leading American manufacturing companies and other energy-intensive customers, represent well over $1 trillion in sales, including thousands of manufacturing facilities and millions of family-sustaining jobs in the United States. As an industry, manufacturing is unique compared to all other sectors, employing over 15 million people in the United States14 and contributing $2.3 trillion to U.S. Gross Domestic Product (“GDP”) in 2023 (amounting to 10.2% of total U.S. GDP, measured in chained 2017 dollars).15 Manufacturers produce the raw materials and inputs necessary for sustaining commerce and our overall standard of living. Manufacturers are energy-intensive, frequently operate 24/7, are price- sensitive, and compete globally. Unlike the surge in large-load demands from data centers and computational workloads, most manufacturers are simply trying to remain competitive and keep their facilities operational and financially healthy amid ever-rising operational costs. Expansions of existing facilities are carried out over years of deliberate planning. Small changes in electricity prices can have significant impacts on the competitiveness of existing facilities and serious implications for reshoring and expanding facilities and production capabilities in the United States. Amtrak is a corporation authorized by the Rail Passenger Service Act of 1970, codified at 49 U.S.C. §§ 24101, et seq. Amtrak provides passenger rail service across the continental United States, including within the PJM footprint. Amtrak consumes substantial amounts of electricity in
14 See U.S. Bureau of Labor Statistics (2024 data), available at https://www.bls.gov/cps/cpsaat18.htm (last accessed Mar. 12, 2026).15 See U.S. Manufacturing Economy, NIST, available at https://www.nist.gov/el/applied-economics- office/manufacturing/manufacturing-economy/total-us-manufacturing (last accessed Mar. 12, 2026).
PDF page 9
9
its operations on the Northeast Corridor and requires reliable electric service to support its operations. While Amtrak is not a manufacturer, it is an industrial customer of utility services. For many years, Amtrak has harnessed retail BTMG within PJM to support its business operations and reliability imperatives. Amtrak’s interests align with the Industrials and reflect the wide-ranging types of bespoke retail BTMG arrangements that support the region’s and the nation’s economy. The issues set for Paper Hearing carry great weight for retail customers like Amtrak and members of the Industrials. If the FERC determines in the BTMG Compliance Docket that existing industrial, institutional, and transportation applications no longer qualify as BTMG and, as such, customers no longer have their cost responsibility for transmission (and possibly capacity) measured at the meter, these customers will be reliant on the FERC to ensure there are adequate transmission services, grounded in cost-causation principles, to enable these customers to remain economic. If the requirements and standards for the New Services are inadequately designed, existing concerns about resource adequacy and cost causation will deepen. Such a result would risk rendering uneconomic a vast array of existing on-site generation arrangements. This may have devastating economic impacts on industrial customers, who, as noted by PJM in the BTMG Compliance Docket, may decide to shutter their on-site generating units, exacerbating the resource adequacy challenges.16
Further impacting the cost and regulatory analysis, it is important to recognize that industrial retail configurations are varied, complex, and unique. In contrast to typical computational and data center load, industrial customers: (a) produce a physical product on-site;
(b) typically cannot shift load to other facilities; (c) often must continue to operate for safety and environmental compliance reasons; (d) frequently have generation and load deeply integrated via
16 Compliance Filing at 12-14. See also Dauphinais Affidavit at PP 42-44.
PDF page 10
10
cogeneration; and (e) often provide valuable resource adequacy and reliability benefits to the broader grid. These traditional load configurations are neither the essential cause of the current resource adequacy challenges on the grid, nor do they present the reliability risks posed by super- sized, inverter-based loads rapidly seeking to come online today. In fact, they provide substantial reliability and resource adequacy benefits to the grid.17 In contrast, the new computational loads entering the grid today do not have substantial cogeneration,18 do not typically operate large motors (which, in some cases, help with stability on the grid),19 can turn off and on nearly instantaneously, and can reach extremely large sizes (“super-sized”), well beyond most traditional industrial and institutional retail customers. As most planned load growth is driven by load greater than 300 MW, the Industrials/Amtrak proposed a Retail Threshold in the BTMG Compliance Docket of at least 200 MW, under which BTMG netting should continue.20
The above-listed characteristics of “traditional” large loads have direct implications for
how cost causation, grid risks, and other considerations should be evaluated. The Commission’s decisions in this docket will directly impact cost and access issues such as: (a) who is eligible for
17 These benefits are both 1) indirect: reducing large loads on the system and operating efficiently to reduce congestion and/or transmission system build-out; and 2) direct: being able to operate during system emergencies. Notably, the Department of Energy (“DOE”) recently issued an order indicating that it may rely on industrial customers’ generation during emergencies. See U.S. Department of Energy, Emergency Order No. 202-26-06 (issued Jan. 26, 2026).18 See Dauphinais Affidavit at P 50 (“[V]ery large computational load processes are generally not highly thermally integrated, if integrated at all, with any co-located generation facilities whose meter they may be located behind. This is because those generation facilities will either not be Cogeneration Facilities or would only be Cogeneration Facilities of greatly limited electrical capability relative to the total magnitude of the electrical load of their host retail customer.”) See also id. at PP 22-24.19 See Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads: NERC Large Loads Working Group White Paper (March 2026), at p. 29, available at https://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-of-gaps.pdf.20 See Dauphinais Affidavit at PP 65-69 (providing evidence that most load added by large load additions is by additions of 300 MW and higher). See also Interconnection of Large Loads to the Interstate Transmission System, Reply Comments of the Indicated Transmission Owners, Docket No. RM26-4-000, at 2-3 (Dec. 5, 2025) (“To the extent the Commission asserts jurisdiction over large load interconnections, it should adopt a sufficiently narrow definition of ‘large load customer’ limited to large (200 MW or greater) data center customers. It is those customers that are primarily driving load increases.”)
PDF page 11
11
the New Services; (b) how required amounts of contract demand are calculated; (c) retail cost allocation transparency; and (d) whether retail customers can access cost-based (and in many cases, legally-required) back-up service.
Industrial, institutional, and transportation customers with on-site generation are rarely in the news and are often not at the center of large load and transmission planning discussions; the reason for this is that they have operated such on-site generation systems reliably for decades. The transmission system has grown up around such traditional loads, works in concert with them, and benefits from their presence and operation. The facts of on-site generation configurations matter and must be understood to make just and reasonable determinations in this docket. The following are several examples of configurations that raise specific applicability and interpretation questions:
If a cogeneration facility and its associated manufacturing load is required to operate as a Co-Location Arrangement, the manufacturing load’s actual use of the transmission system may not equate to the actual maximum amount of load on-site, as the industrial process may require steam heat produced from the generation, meaning if the
generation goes down, the load follows—in that case, it would defy cost causation principles to require such a facility to pay for transmission services it cannot physically use (such as via a Grid Reliance Charge as proposed in the PJM Transmission Owners’ Initial Brief).21
Amtrak, a retail customer, has a contractual arrangement for retail BTMG to support its Northeast Corridor operations. As a legacy of the buildout of the Northeast Corridor, Amtrak requires service at 25 Hz, which it receives, at least for some of its
requirements, through a contractual arrangement with a third-party generator that is neither a small power production QF nor a cogeneration QF. This arrangement provides the only black-start capability for Amtrak’s south end of its Northeast Corridor traction power system if the 60 Hz power grid goes out of service.
Many industrials currently qualify, or could qualify, as QFs under PURPA, granting them the right to back-up and maintenance power at rates/terms that do not assume that
21 Mr. Dauphinais explains in the Affidavit that when an outage of a cogeneration facility occurs, “significant electric load of the host retail customer can be lost immediately following, or very shortly following, the outage.” See Dauphinais Affidavit at P 16. This can be due either to certain industrial or commercial processes “not being able to operate without thermal energy from the Cogeneration Facility if it is a Topping-Cycle facility” or due to “a thermal process being unable to operate because of the inability to dump its waste heat to the Cogeneration Facility if it is a Bottoming-Cycle facility.” Id. Put simply, the very configuration of many industrial cogeneration facilities directly limit use of the transmission system.
PDF page 12
12
units will be down during system peaks and do not assume that units will be down at the same time as the other QFs (unless there is data backing that assumption). Yet, as explained further herein, the current proposed design of the Contract Demand Services (“CDS”) in the Initial Briefs makes no allowance for back-up power at cost-based rates.
An industrial customer represented by the Industrials has several dozen combined heat and power (“CHP”) assets, totaling between 80 MW and 200 MW in production
capacity, fueled by a mixture of coal and natural gas; the CHP assets are primarily designed to meet the thermal load; thermal energy is required for industrial processes; when a significant decrease in electricity generation occurs, thermal generation also declines, resulting in a simultaneous load shedding event decreasing the need for any external electricity purchases; there are physical limitations on amounts of power that can be drawn from the grid; a standby service contract is in force, with decades of demand history informing the contract; a purchased power contract has been in effect for decades, as well, and is renewed on a year-to-year basis.22
Many other examples exist of bespoke arrangements for industrial and institutional customers that may require firm back-up needs. As explained in the Dauphinais Affidavit, some of these units, particularly cogeneration units, are highly efficient and highly reliable units, requiring limited downtime.23
Each of these configurations underscores the critical need for the FERC to consider the impact on traditional large load customers when authorizing a final design for the New Services. Due to the above examples and others, there are sound legal, regulatory, and cost-based reasons that industrial and institutional applications should qualify for cost-based back-up power options, whether through retail BTMG netting eligibility, or, alternatively, through a firm, cost-based back- up and maintenance service. Further, the New Services should be structured to support Bring Your Own New Generation initiatives and to create efficient investment signals, as the industry faces a crisis of resource adequacy. Finally, any New Services design finalized by the FERC should ensure sufficient clarity as to how cost responsibility will be assigned to retail customers, while respecting state jurisdiction over retail rates.
22 See Industrials/Amtrak Protest at 38.23 See Dauphinais Affidavit at PP 11-12, 29-35.
PDF page 13
13
To that end, the Industrials/Amtrak respectfully request that the Commission consider the following arguments in determining rates, terms, and conditions of the New Services. With the changes recommended herein, the Commission can approve rules that effectuate the goals of the Order while avoiding unintended damage to America’s essential manufacturing sector and institutional and transportation service providers.
IV. ARGUMENTS
A. A just and reasonable back-up service is missing from the new transmission services structure. A cost-based back-up service is guaranteed to Qualifying Facilities under PURPA and should be extended to other retail customers with on-site generation on a cost-causation basis.
The New Services represent a significant change to how transmission services are designed, bundled, and paid in the PJM region. However, as currently proposed, the New Services are missing a critical component. The current design lacks a back-up service that is based on cost- causation and that meets the legal requirements of PURPA. Back-up service is an essential component of energy management for many industrials and other retail customers with on-site generation, including QFs, which are guaranteed access to back-up service with specific cost-based assumptions.24
Because neither the New Services nor NITS calculated on a gross basis meet these requirements, as explained below, at a bare minimum, QFs should retain access to longstanding retail BTMG netting rules. If the FERC determines otherwise, however, the FERC should ensure QFs have access to a cost-based back-up service. Retail customers with BTMG that is not a QF should also, based on principles of cost causation, be provided with access to cost-based back-up services, either through NITS with netting or through a cost-based back-up service. Access to
24 18 C.F.R. § 292.305.
PDF page 14
14
back-up services is a critical component to allowing industrial, institutional, and transportation retail customers to continue to operate without significant economic damage, including likely closures of some BTMG generating units.
1. PURPA ensures that QFs have access to back-up and maintenance
service that meets assumptions about generator uptime, and the NITS
netting construct meets this requirement.
Congress passed PURPA in 1978 to encourage cogeneration, small power production, and geothermal energy production.25 PURPA has played an important role for manufacturers and the electric grid for nearly five decades, providing market access where none previously existed, taking strain off the grid, and supporting American industry by enabling economic means to reduce energy costs. Under PURPA, QFs fall into two broad categories: “qualifying small power production facilities,” which can be sized up to 80 MW, and “qualifying cogeneration facilities,” which have no size limit.26 Cogeneration QFs must achieve certain efficiency standards and are highly efficient in their use of input fuels. Cogeneration QFs, which produce both electricity and heat from the same fuel source, make use of the “waste heat” in their manufacturing, heating, or cooling process. As explained by Mr. Dauphinais in the attached Affidavit (which was filed in the BTMG Compliance Docket), “Cogeneration Facilities can achieve efficiencies in excess of 80%, by using waste heat and avoiding electrical losses, compared to the efficiency of approximately 50% for conventional electricity generation with a steam boiler.”27
Under FERC regulations (enacted at Congress’ direction), QFs are entitled to access to supplementary power, back-up power, maintenance power, and interruptible power, pursuant to
25 16 U.S. Code § 824a-3(a).26 16 U.S. Code § 824a-3. “Qualifying small power production facilities” are also referred to as “small power production QFs,” and “qualifying cogeneration facilities” are also referred to as “cogeneration QFs.”27 Dauphinais Affidavit at P 11.
PDF page 15
15
long-established enacting regulations.28 “Back-up power” is defined in the regulations as “electric energy or capacity supplied by an electric utility to replace energy ordinarily generated by a facility’s own generation equipment during an unscheduled outage of the facility.”29 Critically, rates for back-up or maintenance power “[s]hall not be based upon an assumption (unless supported by factual data) that forced outages or other reductions in electric output by all qualifying facilities on an electric utility’s system will occur simultaneously, or during the system peak, or both.”30 As explained by Mr. Dauphinais, the current BTMG netting construct for NITS permits QFs to receive the back-up power they are guaranteed—back-up power that is charged without a default assumption that the back-up power will be needed during peak times.31 If back-up services are needed during peak times, the current NITS design ensures customers pay for them by appropriately measuring peak usage.32 As explained by Mr. Dauphinais, “With respect to the transmission component of back-up and maintenance power, Section 34.2 of the PJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the load served by the operating behind the meter generation of a retail customer from that retail customer’s daily load for [NITS].”33 He further states:
Whether a retail customer has behind the meter generation or not, its NITS
charges are based on the demand the retail customer has historically put on the
transmission system at the time of the annual peak of the transmission pricing
zone. Given zonal transmission costs under the PJM Tariff are currently
28 18 C.F.R. § 292.305(b).29 18 C.F.R. § 292.101(b)(9) (emphasis added).30 18 C.F.R. § 292.305(c)(1).31 See Dauphinais Affidavit at P 29 (explaining that the netting approach “is consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities as it does not assume that a retail customer’s behind the meter Qualifying Facility will be experiencing an outage at the time of the annual transmission system peak and instead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time of the annual peak of the transmission pricing zone, when allocating transmission costs to the retail customer.”). See also id. at P 49.32 Id. at P 29. 33 Id. at P 28.
PDF page 16
16
allocated to load on an annual coincident peak demand basis, this netting
approach is consistent with cost causation. Furthermore, it is consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities as it does not assume that a retail customer’s behind the meter Qualifying Facility will be experiencing an outage at the time of the annual transmission system peak and instead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time of the annual peak of the transmission pricing zone, when allocating transmission costs to the retail customer.34
Because of this design, the BTMG netting construct meets the requirements of PURPA’s enacting regulations that QFs be guaranteed access to back-up and maintenance power with the cost-based assumptions required by the Regulations. To that end, in the BTMG Compliance Docket, the Industrials/Amtrak proposed that QFs be able to continue to net output and operate under longstanding/historical retail BTMG rules.35 Not only does this comport with cost-causation principles, but it also meets the legal requirements of PURPA.36
2. As currently designed, the New Services do not provide for cost-based
back-up service that meets the requirements of PURPA.
The CDS transmission services are designed to address various needs on the grid, including reserving enough transmission capacity and generating capacity to cover the firm needs of a large customer, and incorporating protections to prevent overdrawing from the grid. However, the CDS services stop short of providing back-up service on a cost basis. Back-up power is, by its nature, unplanned.3734 Id. at P 29.35 Industrials/Amtrak Protest at 17-23.36 In contrast, transitioning to a gross-only approach would negate this alignment, as it calculates cost responsibility as if the on-site generation is always off by not including it in measurement of transmission cost responsibility.37 18 C.F.R. § 292.101(b)(9).
PDF page 17
17
Mr. Dauphinais explains in the attached Affidavit the reasons neither Firm nor Non-Firm CDS provides a cost-based back-up service for cogeneration QFs and similarly-situated retail customers. As to Firm CDS, Mr. Dauphinais stated:
While Contract Demand Transmission Service would provide reliable backup
and maintenance power, it would not provide it at rates that are consistent with cost causation or FERC’s rules for the rates for the provision of backup and maintenance power to Qualifying Facilities. Specifically, it requires payments for the service based on the contracted amount. As a result, it would inherently assume, in violation of FERC’s rules for backup and maintenance power for
Qualifying Facilities, that forced outages or other reductions in electric output by all qualifying facilities on an electric utility's system will occur
simultaneously, or during the system peak, or both, without any factual data to support such an assumption. As I have discussed at length in this affidavit, this is not a reasonable assumption for Qualifying Cogeneration Facilities.38
A simplified illustration highlights how Firm CDS fails to provide a back-up service based on PURPA’s cost-based requirement. Consider an industrial load of 100 MW with 100 MW of offsetting BTMG. In this hypothetical, the BTMG experiences unplanned outages 1% of the time. If the customer is forced to obtain 100 MW of Firm CDS, it will essentially be required to pay the same as a customer that relies fully on the transmission system and uses that capacity 99% of the time (rather than 1%). Taking the illustration a bit further, consider the impact if there are ten similar configurations within one transmission zone. Collectively, those ten customers would need to reserve 1,000 MW (1 GW) of transmission capacity through Firm CDS (or, if pricing for NITS is the same on a per-MW basis, pay the equivalent through a gross NITS product). Viewed as a group, however, it would be violative of cost-causation principles to bill for and collect 1,000 MW of transmission cost responsibility when these ten customers will not use more than a small fraction of that collective reservation at one time (based on any statistical analysis). As explained by Mr. Dauphinais in the attached Affidavit, “[T]he transmission system is not planned assuming
38 Dauphinais Affidavit at P 44.
PDF page 18
18
that all Cogeneration Facilities will experience an outage at the same time or will not otherwise be running…. Furthermore, in my experience, transmission planners do not study or examine scenarios where it is assumed large numbers of Cogeneration Facilities will be offline at the same time, as there is no factual basis to support such an assumption.”39 While transmission planners must consider many variables, it would not comport with cost-causation principles to require a full Firm CDS reservation for occasional back-up power needs, particularly where the history and risk of the individual unit is well-established or has met outside standards (such as qualifying as a QF). In fact, such an approach would violate cost-causation principles and, for QFs, directly contradict the PURPA regulations.
Even more so, Non-Firm CDS would also fail to meet PURPA’s requirements for back-up service. As explained by Mr. Dauphinais:
Non-Firm Contract Demand Transmission Service would fall short in two
respects. First, it is incapable of providing backup power for forced outages of Qualifying Cogeneration Facilities because the actual usage Non-Firm Contract
Demand Transmission Service would have to be pre-scheduled with, and
approved by, PJM in advance of its use, and forced outages cannot be known
beforehand. Second, the service is not reliable and risky to use as it is only
available on an as-available basis, subject to interruption during emergencies, and subject to automated interruption. It is not a product that could be used to provide safe and environmentally compliant maintenance power to traditional
commercial, industrial and institutional retail customers with Qualifying
Cogeneration Facilities, never mind backup power to them.40
Consequently, neither Firm CDS nor Non-Firm CDS are adequate services for industrial, institutional, transportation, and other retail customers who have invested in on-site generation and who have qualified as QFs. Without clarity on how QFs will obtain back-up and maintenance
39 Id. at P 32.40 Id. at P 45.
PDF page 19
19
power across all contexts, the FERC should permit QFs to continue under the current netting regime, as requested by the Industrials/Amtrak in the BTMG Compliance Docket.
3. To the extent netting is unavailable, a firm transmission service based
on actual use must be made available to QFs to meet the requirements
of PURPA.
As explained above, the BTMG netting construct provides a framework that is compliant with PURPA standards for QFs. However, with the changes to NITS rules initiated by the Order, NITS (with a gross load calculation) no longer meets this PURPA legal requirement. Because neither gross NITS nor Firm nor Non-Firm CDS meet the established PURPA requirements, a firm transmission service must be available for QFs to meet the requirements of PURPA based on actual use. Practically speaking, this means that transmission services must be developed that apply cost-causation standards to occasional, yet unplanned use of the transmission system. In short, if netting is no longer available to a customer with a QF, a cost-based back-up service must be available to that retail customer to ensure just and reasonable rates. Alternatively, without clarity on how QFs will obtain back-up and maintenance power across all contexts, the FERC should permit QFs to continue under the current netting regime, as requested by the Industrials/Amtrak in the BTMG Compliance Docket.41 The current retail BTMG netting structure is, quite literally, a cost-based structure based on actual use. QFs, which are either size-limited (non-cogeneration) or must meet efficiency requirements in integration with load (cogeneration), fit well within this structure, though it would also apply equally to other efficient BTMG arrangements that only need occasional back-up and maintenance power.
41 Strong operational and financial incentives exist for cogeneration facilities to operate reliably and efficiently, even above the ordinary cost-savings incentives of all generators. Further, to maintain QF status, the Regulations require cogeneration QFs (which includes any QF above 80 MW) to meet specified efficiency standards. See 16 U.S. Code § 824a-3(n); 18 C.F.R. § 292.205.
PDF page 20
20
To the extent netting is unavailable, a QF must have access to back-up and maintenance power that meets the standards of PURPA in a different way.
4. Absent a sufficiently high Retail Threshold in the BTMG Compliance
Docket, cost-causation principles dictate that the FERC should
authorize cost-based back-up service for all retail customers with
BTMG, not only QFs.
While allowing QFs to remain eligible for longstanding BTMG netting rules addresses the essential concern for QFs, many facilities operate on similar principles to QFs but do not have QF status. As Mr. Dauphinais notes, “[T]here may be some Cogeneration Facilities within the PJM footprint that fully meet FERC’s requirements to be a Qualifying Cogeneration Facility (and, thus, a Qualifying Facility), except they do not currently have a FERC-approved certification or self- certification of their Qualifying Cogeneration Facility status because they do not makes sales of excess power either at avoided cost to electric utilities or into the wholesale power market.”42 Additionally, many facilities may be eligible for QF status but did not seek or maintain such status because the existing netting construct provided these services.43 In other cases, there may be BTMG units that produce power behind-the-meter but do not meet PURPA’s technical requirements (e.g., size or efficiency standards), but still, from a cost-causation standpoint, should be given access to such services.
While PURPA regulations expressly recognize the need for QFs to occasionally draw from the grid, including for occasional unscheduled outages, that need is not limited to QFs. To function properly and under just and reasonable rates, other industrial, institutional, and transportation retail loads with on-site generation also require back-up service based on cost-causation. Absent access
42 Dauphinais Affidavit at P 48.43 In the wake of the termination of the mandatory purchase obligation, many QF-eligible customers did not seek or maintain QF status due to a combination of (1) having access to cost-based back-up power via BTMG netting rules, and (2) their utilities’ must-purchase obligations being terminated. See 16 U.S. Code § 824a-3(m).
PDF page 21
21
to retail netting, there is a sound basis to provide back-up service that recognizes the cost-causation principles of back-up and maintenance service for BTMG facilities that do not have QF status. As recognized by the D.C. Circuit Court of Appeals, the “cost-causation principle” has been
recognized “for decades” by “the Commission and the courts.”44 Under the cost-causation
principle, “costs are to be allocated to those who cause the costs to be incurred and reap the resulting benefits.”45 Cost-causation has been described by the D.C. Circuit as a principle that “burden is matched with benefit.”46
To that point, PJM noted in the BTMG Compliance Docket that existing retail BTMG
arrangements—including QFs and other BTMG arrangements with existing contracts—“have
been in place and netted against Network Loads within PJM without operational issues to date.”47 Large loads with large retail BTMG units have existed since the BTMG rules were established in 2004 in PJM.48 Further, the illustration above—showing that ten 100-MW facilities would be required under Firm CDS to reserve 1,000 MW for back-up service, when those ten facilities would never use more than a fraction of that transmission capacity—demonstrates that back-up service
44 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018). (“For decades, the Commission and the courts have understood [the ‘just and reasonable’ rate requirement] to incorporate a ‘cost-causation principle’—the rates charged for electricity should reflect the costs of providing it.”).45 Nat’l Ass’n of Reg. Util. Comm’rs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007). (See also K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); City of Lincoln v. FERC, 89 F. 4th 926, 930 (D.C. Cir. 2024); see also Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (“we evaluate compliance with this unremarkable [cost causation] principle by comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party”).46 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).47 Compliance Filing at 10.48 From the beginning, large manufacturers have operated generating facilities behind-the-meter that offset their load. At the establishment of BTMG rules in PJM over 20 years ago, large on-site generation units already existed and participated in the proceeding approving BTMG rules. For example, a refining company intervenor at the time described its on-site generation as a “60 megawatt combined cycle cogeneration facility,” and an agricultural company described its operational location as having “a combined load, net of the capabilities of [the company’s] onsite cogeneration, of between 200 and 300 MW,” implying a substantial presence of on-site generation. Motion to Intervene of Valero Refining Company – New Jersey, Docket No. ER04-608-000 (Mar. 23, 2004); Motion to Intervene of Archer-Daniels-Midland Company, Docket No. ER04-608-000 (Mar. 22, 2004).
PDF page 22
22
cannot, based on principles of cost-causation, be priced the same as Firm CDS or gross-based NITS. Consequently, a cost-based back-up rate is the primary service missing from the Commission’s set of New Services.
The economic impacts of the FERC’s decisions in this docket and in the BTMG
Compliance Docket will be profound. Industrials are already grappling with the serious implications of cost increases, resource adequacy concerns, and other economic pressures. Retail customers have developed on-site generation to minimize the load they place on the transmission system and, in many cases, to support thermal needs, such as heating facilities, operating chillers, or using steam in the manufacturing process. If continued BTMG eligibility is not granted by the FERC for members of the Industrials or Amtrak, the New Services, as designed, would force retail customers with on-site generation to a “gross load” measurement for NITS or Firm CDS for occasional back-up needs. In addition to violating cost-causation principles, this approach could seriously damage existing users’ economic viability by requiring customers to be charged for transmission (and capacity, subject to clarification) as if their BTMG were not operating. Failing to provide (either by BTMG netting applicability or by an alternative back-up service) just and reasonable transmission and/or capacity cost allocation will render those units uneconomic, forcing them to operate at a loss, close and seek power from the grid, or shutter the plant entirely. Addressing cogeneration units in particular, Mr. Dauphinais explained that if the ability to operate “in a safe and environmentally compliant manner within the bounds of what can be supported by the remaining thermal capability of the Cogeneration Facility at just and reasonable electric power rates” cannot be assured, “cogeneration may fail to be a practical and/or economic solution to the retail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the
PDF page 23
23
retail customer to become economically unviable.”49 This issue is not limited to QFs. In the Protest and Comments of Eastman Chemical Company (“Eastman”) in the BTMG Compliance Docket, Eastman explained that an arbitrarily low Retail Threshold (resulting in removal of BTMG netting) “renders Eastman’s BTMG uneconomic after almost 28 years of operations.”50
For some industrial and institutional customers, transmission and capacity cost savings are a critical factor that makes it worth the investment to build and operate generation on their premises—investments these customers have already made (sometimes over decades).51 The Industrials/Amtrak do not seek anything new that has not already been the regulatory context for these units for multiple decades; rather, the Industrials/Amtrak seek to avoid a situation where existing retail customers who have made such investments are suddenly forced to pay rates far above cost for the services upon which they depend.
B. For Co-Located Loads for which retail netting is not an option, Non-Firm CDS should be designed to maximize efficient deployment of resources and advance
incentives for large loads to “Bring Your Own New Generation.”
As set forth in the Order, Non-Firm CDS “must be available during normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing firm transmission services and the new Firm Contract Demand Transmission Service).”52 However, “[r]eservations under this service would be available only when there is available transmission capacity, similar to existing non-firm transmission service options in the Tariff.”5349 Dauphinais Affidavit at P 17.50 Protest and Comments of Eastman Chemical Company, PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-1479-000 (Mar. 16, 2026).51 See Dauphinais Affidavit at P 17.52 Order at P 215.53 Id.
PDF page 24
24
Non-Firm CDS should be designed to encourage new large loads to “Bring Your Own New Generation” and prevent cost shifts to other customers, in accordance with cost-causation principles. In furtherance of those goals, the Industrials/Amtrak recommend the following principles and practices be adopted in the final design of Non-Firm CDS:
1. Hourly, actual use calculation – no standby fee. As an as-available service, Non- Firm CDS should not be charged a standby fee. Regardless of the merits of a standby fee in context of a firm service offering, a standby fee does not make sense when it charges for “access” with no guarantee that such access will actually be available. Rather, an actual use calculation on an hourly basis would be an appropriate way to charge for Non-Firm CDS. Such an approach guarantees that retail customers pay for what they use; such revenues collected by transmission owners would go toward the revenue requirement for that transmission owner, ultimately lowering rates for Firm CDS and NITS customers.
2. No transmission planning based on Non-Firm CDS. As a non-firm, as-available service, Non-Firm CDS should not be considered as a factor in transmission planning. If transmission owners planned for additional transmission capacity for Non-Firm CDS, the costs of that transmission capacity would have to be recovered through rates. This cost recovery would have the effect of raising rates for other transmission customers, because Non-Firm CDS, by design, should be less expensive than its Firm CDS and NITS cousins.
3. Fuel contracts. Co-Located Load subscribing to Non-Firm CDS should have firm natural gas capacity or other adequate alternatives to be able to utilize Non-Firm CDS. The Commission should include such reasonable requirements to avoid misuse of the Non-Firm CDS service by generators who have the ability to operate but may want to rely on the grid when it appears to be more economical for that generator. From a resource adequacy perspective, policies surrounding Non-Firm CDS should encourage Bring Your Own New Generation, which promotes building and operating on-site generation.
4. Anti-manipulation. Non-Firm CDS should have clearly defined allowable circumstances or standards for load to reserve non-firm transmission service. To preserve and support resource adequacy on the broader grid during times of system stress, switching from use of on-site generation to grid-supplied resources via Non- Firm CDS should not be for short-term economic reasons (such as when pricing for a grid resource is lower than the on-site generation resource). Acknowledging efficiency gains from letting markets operate on economic signals, Non-Firm CDS should generally be available only if generation is unavailable for physical reasons—planned maintenance, fuel outages, etc.—especially during times of system stress.
PDF page 25
25
5. Reasonable rules surrounding special protective schemes and required amounts of Non-Firm CDS. In the Order, the Commission asked for comment on “[w]hat
interconnection requirements and operational practices are necessary for special protection schemes to maintain system reliability . . . in the event that a Co-Located Load itself or its associated generator trips offline.”54 To the extent that special protective schemes are required by the Commission for access to Non-Firm CDS, the requirements should allow for a realistic assessment of what the facility can actually draw from the grid. As explained in Section III, supra, some load/generation configurations allow only a limited amount of draw from the grid.55 The rules governing Non-Firm CDS should account for realistic on-site constraints.
C. A durable solution must provide clear direction on cost allocation while
respecting federal-state jurisdictional distinctions.
With the sweeping, transformative changes initiated by the Order, it is critical to ensure retail customers have clear, accountable, and understandable rates and terms for these services. This is particularly a concern considering interstate transmission services (the subject of this docket) are a federal-jurisdictional service, yet the service must be translated to retail rates and billed by Load-Serving Entities (“LSE”) or local distribution utilities.
Many distribution utilities across PJM’s footprint publish methodologies of how customer cost responsibility is calculated in the Attachment M-2s filed with the PJM Tariff at FERC. It is not immediately clear from the Order how the retail cost allocation will be determined. Along those lines, the FERC must ensure that transmission owners’ calculation of individual customer and zonal transmission cost allocation is transparent, whether through an Attachment M-2 filing or another publicly transparent and accountable method. Clear direction on how charges for New Services will be established is necessary for a durable final order in this proceeding. A simple example of a lack of clarity would be a transmission owner that does not post its allocation methodology in a publicly-available way.
54 Order at P 219(6).55 See also Dauphinais Affidavit at P 16.
PDF page 26
26
Further, the FERC must provide direction on how the revenue and the billing determinants for the New Services would be incorporated into the existing transmission owners’ formula rates. Both the revenue and billing determinants for Firm CDS should be treated in the same way as those for NITS. The revenue for Non-Firm CDS should be treated comparably to the revenue from existing non-firm Point-to-Point (“PTP”) service.
The end goal should be: (1) alignment with cost-causation principles; (2) clarity for retail customers and others on how those costs get translated to retail rates. During times of profound change, traditional industrial, institutional, and transportation customers need clarity to be able to operate with predictability.
In the Industrials/Amtrak’s view, changes authorized by the Commission will fall most heavily on existing retail customers. For many of these retail customers, particularly in heavy industry, energy is one of the top costs of doing business. The on-site generation facilities these customers have developed were built based on certain assumptions and have been operated under those assumptions. It is critical that these retail customers have clarity on how their needed services will be delivered and charged.
PDF page 27
27
V. CONCLUSION & REQUEST FOR RELIEF
The Industrials/Amtrak respectfully request that the Commission ensure: (1) retail customers with on-site generation have access to cost-based back-up service; (2) the new transmission services are designed to incentivize development of new generation and to avoid manipulation; and (3) costs and obligations of retail customers are clear, publicly-available, and respect federal-state jurisdictional lines.
Respectfully submitted,
By:
/s/ Susan E. Bruce
Susan E. Bruce
Kenneth R. Stark
Matthew L. Garber
McNees Wallace & Nurick LLC
100 Pine Street
Harrisburg, PA 17101
Tel: 717-232-8000
E-mail: sbruce@mcneeslaw.com
E-mail: kstark@mcneeslaw.com
E-mail: mgarber@mcneeslaw.com
Counsel to the PJM Industrial Customer Coalition,
the Industrial Energy Consumers of America, the
American Forest and Paper Association, and the
National Railroad Passenger Corporation (Amtrak)
Dated: March 25, 2026
PDF page 28
CERTIFICATE OF SERVICE
I hereby certify that I have this day served via electronic transmission the foregoing upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated this 25th day of March, 2026.
/s/ Matthew L. Garber
Matthew L. Garber
100 Pine Street
Harrisburg, PA 17101
Tel: 717-232-8000
Fax: 717-237-5433
E-mail: mgarber@mcneeslaw.com
PDF page 29
ATTACHMENT 1
Affidavit of James R. Dauphinais
Filed in Docket No. ER26-1479-000
PDF page 30
Exhibit No. IA-1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
AFFIDAVIT OF JAMES R. DAUPHINAIS
PDF page 31
Exhibit No. IA-1
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
AFFIDAVIT OF JAMES R. DAUPHINAIS
Table of Contents
I. INTRODUCTION … 1
Affiant Description … 1
II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
TRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND
COMMERCIAL RETAIL CUSTOMERS … 5
What are Cogeneration Facilities? … 5
Cogeneration Efficiency … 7
The Integration of Cogeneration with Commercial, Industrial, and Institutional
Processes and the Critical Need for Reliable Backup and Maintenance Power
at Just and Reasonable Rates … 8
III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS
USING COGENERATION ARE NOT THE SAME AS VERY LARGE
COMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER
OF GENERATION FACILITIES … 12
IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
FACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER
GENERATION PROVISIONS ARE CONSISTENT WITH COST
CAUSATION AND FERC’S OWN BACKUP AND MAINTENANCE
POWER RULES FOR QUALIFYING FACILITIES … 13
Retail BTMG Netting for Transmission … 13
Retail BTMG Netting for Capacity … 17
PDF page 32
Exhibit No. IA-1
V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND
NON-FIRM CONTRACT DEMAND TRANSMISSION SERVICE
ARE UNABLE TO PROVIDE JUST AND REASONABLE
BACKUP AND MAINTENANCE SERVICE TO QUALIFYING
COGENERATION FACILITIES … 19
VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING
CERTIFIED QUALIFYING FACILITIES AS OF DECEMBER 18, 2025
TO CONTINUE TO USE RETAIL BTMG NETTING FOR NITS
AND CAPACITY REQUIREMENTS FALLS SHORT OF BEING
JUST AND REASONABLE … 23
VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR
NON-QUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER
GENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND
REASONABLE … 26
The Proposed 50 MW Limit is Inappropriately Applied to Cumulative
Nameplate Capacity Rather than the Amount of Retail Load that can be Netted .. 29
PJM’s Proposed 50 MW Limit is Too Low … 32
VIII. CONCLUSION … 36
PDF page 33
Exhibit No. IA-1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
AFFIDAVIT OF JAMES R. DAUPHINAIS
List of Attachments
1 Qualifications of James R. Dauphinais
2
Analysis of MW Size of Consumers Energy Company Data Center Load Addition Inquiries
3
Michigan Public Service Commission Case No. U-21859, Consumers Energy Company Data Request Response U21859-DCC-CE-0045
4
Illinois Commerce Commission Docket No. 25-0677, Commonwealth Edison Company Response to Data Request NRG-ComEd 1.02
PDF page 34
Exhibit No. IA-1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
AFFIDAVIT OF JAMES R. DAUPHINAIS
Glossary of Abbreviations and Acronyms
AF&PA
American Forest and Paper Association
Amtrak
National Railroad Passenger Corporation
BAI
Brubaker & Associates, Inc.
BTMG
Behind the Meter Generation
CHP
Combined Heat and Power
ComEd
Commonwealth Edison Company
DCPZ
Zonal Daily Load
FERC
Federal Energy Regulatory Commission
FPA
Federal Power Act
IECA
Industrial Energy Consumers of America
ICC
Illinois Commerce Commission
MISO
Midcontinent Independent System Operator, Inc. MPSC
Michigan Public Service Commission
NERC
North American Electric Reliability Corporation NITS
Network Integration Transmission Service
NU
Northeast Utilities Service Company, now Eversource PJM
PJM Interconnection, L.L.C.
PJMICC
PRA
PJM Industrial Customer Coalition
Planning Resource Auction
PURPA
Public Utility Regulatory Policies Act of 1978 RAA
Reliability Assurance Agreement
RAR
Resource Adequacy Requirements
SMR
Small Modular Reactors
PDF page 35
Exhibit No. IA-1Page 1 of 38
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
AFFIDAVIT OF JAMES R. DAUPHINAIS
I. INTRODUCTION
THE UNDERSIGNED, James R. Dauphinais, of Chesterfield, Missouri having been duly sworn on oath before a Notary Public, states the following:
Affiant Description
1. I am a Managing Principal of Brubaker & Associates, Inc. (“BAI”), an energy, economic and regulatory consulting firm. My business address is 16690 Swingley Ridge Road, Suite 140, Chesterfield, Missouri 63017. I have worked in the electric utility industry for over 40 years, and during my twenty-eight (28) years of my employment by BAI I have been engaged with respect to resource planning, transmission planning, wholesale power market structure, market power, transmission access, transmission line routing, fuel cost, power procurement and rate issues throughout the United States and portions of Canada. For at least twenty (20) of my over twenty-eight (28) years with BAI, I have monitored developments in the PJM Interconnection, L.L.C. (“PJM”) stakeholder process on behalf of a group of large end-use customers in Illinois. This work has included, but not been limited to, providing recommendations with respect to various market proposals made by PJM either in the stakeholder process or in filings with the Federal Energy Regulatory Commission (“FERC”).
PDF page 36
Exhibit No. IA-1Page 2 of 38
I have also assisted end-use customers with establishing themselves as a load-serving PJM Member and understanding their obligations as a load-serving PJM Member. For at least twenty-six (26) years, I have also participated in the Midcontinent Independent System Operator, Inc. (“MISO”) stakeholder process on behalf of several large end-use customer groups.1 This has included, but not been limited to, providing extensive feedback to MISO and other MISO stakeholders during the design of MISO’s day-ahead and real-time energy markets and MISO’s Resource Adequacy Requirements (“RAR”) construct including the MISO Planning Resource Auction (“PRA”). It has also included extensive involvement with respect to treatment of Load Modifying Resources and Non-Load Modifying Resource behind the meter generation within the MISO market. During my time with BAI, I have also had over twenty-four (24) years of experience with issues related to the purchase and sale of electric power from or to Public Utility Regulatory Policies Act of 1978 (“PURPA”) Qualifying Facilities that are large industrial or institutional customer cogeneration facilities. This has included providing testimony on the utility purchase of excess electric power from such facilities at avoided cost, the sale of excess electric power by such facilities into the wholesale market, and the sale of backup and maintenance power to such facilities to serve their host load when the facilities are experiencing outages or derates. Prior to my employment with BAI, I was a Senior Engineer in the Transmission Planning Department of the Northeast Utilities Service Company (“NU,” now Eversource). During my over twelve (12) years of employment with NU, I was extensively involved with transmission planning, transmission operation and open access transmission
1 These groups have members who have facilities with traditional large industrial and institutional electric loads located in the MISO portions of Illinois, Indiana, Iowa, Louisiana, Michigan and Texas or elsewhere within the MISO footprint.
PDF page 37
Exhibit No. IA-1Page 3 of 38
service issues. I have testified previously before FERC as well as many state and provincial regulatory commissions. Attachment 1 to this Affidavit provides a more complete summary of my background and experience.
2. My firm has been retained by the PJM Industrial Customer Coalition
(“PJMICC”), the Industrial Energy Consumers of America (“IECA”), the American Forest and Paper Association (“AF&PA”) and the National Railroad Passenger Corporation (“Amtrak”) (collectively, “Industrials/Amtrak”) to: (i) provide background on the use of cogeneration facilities by traditional large industrial, commercial and institutional retail customers, (ii) explain the differences between the traditional use of cogeneration facilities by large retail customers versus co-location of very large computational loads2 behind the meter of very large generation facilities, (iii) explain how PJM’s current retail behind the meter generation provisions are consistent with cost causation for the traditional use of cogeneration facilities by large retail customers and FERC’s own longstanding rules with respect to the provision of backup and maintenance power to those retail customers, (iv) explain why the new Firm Contract Demand Service and Non-Firm Contract Demand Service options that FERC has proposed for co-location of large loads behind the meter of generation facilities do not reasonably provide for the backup and maintenance service required by traditional use of cogeneration facilities by large retail customers, (v) explain why PJM’s proposal with respect to the treatment of Qualifying Facilities
2 For purposes of this affidavit, when I use the term “computational load”, I am referring to crypto currency, data center and other large computer system electric loads including the electric load of the auxiliary systems necessary to operate the foregoing. The North American Electric Reliability Corporation (“NERC”) Large Load Task Force has focused its recent reliability impact review on computational loads, recently observing that “[t]he penetration of large loads on the [Bulk Power System] is growing, especially computational loads.” Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads: NERC Large Loads Working Group White Paper (March 2026), at p. 46, available at https://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment- of-gaps.pdf.
PDF page 38
Exhibit No. IA-1Page 4 of 38
in its compliance filing in this proceeding falls short of being just and reasonable with respect to the provision of backup and maintenance power to retail customers using cogeneration facilities, and (vi) explain why PJM’s proposed 50 MW and smaller limitation for non-Qualifying Facility retail behind the meter generation netting falls short of being just and reasonable.
3. Attachments 1 through 4 to this Affidavit were either prepared or obtained under my direction and control. They are part of my Affidavit.
4. I conclude the following in this affidavit:
Very large computational loads co-located behind the meter of generation facilities are not similarly situated to traditional large commercial, industrial, and institutional loads using Cogeneration Facilities located behind their meter, as very large computational loads generally are not highly thermally integrated with co-located generation facilities.
For traditional large loads served by Cogeneration Facilities, PJM’s current retail behind-the-meter generation netting provisions for NITS charges and capacity requirements are consistent with cost causation principles and FERC’s own backup and maintenance power rules for Qualifying Facilities, as they rely on factual data regarding each Qualifying Facility’s historical performance rather than assumptions about when outages will occur and whether they will occur simultaneously.
Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service are not capable – either alone or in tandem
– of providing reliable backup and maintenance power to traditional large retail customers that utilize Qualifying Cogeneration Facilities at rates consistent with cost causation principles and FERC’s rules for providing backup and maintenance service to Qualifying Facilities.
PJM’s proposal to limit legacy retail behind-the-meter generation treatment for Qualifying Facilities to those certified or self-certified as of December 18, 2025 falls short of being just and reasonable, and should be modified to cover all Qualifying Facilities regardless of the date they entered service or the date of their certification or self-certification.
PJM’s proposed 50 MW cumulative nameplate capacity limit for continued retail behind-the-meter generation netting for non-Qualifying Facility generation is not just and reasonable because the limit is inappropriately applied to cumulative nameplate capacity rather than to
PDF page 39
Exhibit No. IA-1Page 5 of 38
the amount of retail load that can be netted, and 50 MW is too low given
that the large computational load additions driving the Co-Located Loads
issue are overwhelmingly 300 MW or larger in size; any limit should
initially be set no lower than 200 MW (if not closer to 300 MW).
II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY
TRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND
COMMERCIAL RETAIL CUSTOMERS
What are Cogeneration Facilities?
5. FERC defines a Cogeneration Facility to be “equipment used to produce electric energy and forms of useful thermal energy (such as heat or steam), used for industrial, commercial, heating, or cooling purposes, through the sequential use of energy”.3 Given that on a combined basis these facilities provide both thermal and electric energy, cogeneration facilities are also commonly referred to as Combined Heat and Power (“CHP”) facilities.
6. There are two types of Cogeneration Facilities – Topping-Cycle Cogeneration Facilities and Bottoming-Cycle Cogeneration Facilities.
7. FERC defines a Topping-Cycle Cogeneration Facility as “a cogeneration facility in which the energy input to the facility is first used to produce useful power output, and at least some of the reject heat from the power production process is then used to provide useful thermal energy”.4 A common example of a Topping-Cycle Cogeneration Facility would be a facility with combustion turbine generation fired by natural gas, combustible waste gases, or some combination of the two, that produces electricity and provides steam for heating, cooling, and/or industrial processes via heat recovery steam generators that collect waste heat from the combustion turbine generator. Another example would be a facility with boilers fired by fossil
3 18 C.F.R. § 292.202(c).
4 18 C.F.R. § 292.202(d).
PDF page 40
Exhibit No. IA-1Page 6 of 38
fuel, combustible waste gases, other forms of combustible waste material, or some combination of the foregoing producing high pressure steam that is run through a steam turbine to produce electricity with the lower pressure steam exiting the steam turbine then being used for heating, cooling, or industrial processes. 5
8. FERC defines a Bottoming-Cycle Cogeneration Facility as “a cogeneration
facility in which the energy input to the system is first applied to a useful thermal energy application or process, and at least some of the reject heat emerging from the application or process is then used for power production”.6 A common example of a Bottoming-Cycle Cogeneration Facility would be the use of a heat recovery steam generator to recover heat from an industrial process to produce steam that is then used to generate electricity via a steam turbine.
9. Cogeneration Facilities can include some amount of Supplementary Firing.
FERC defines Supplementary Firing as “an energy input to the cogeneration facility used only in the thermal process of a topping-cycle cogeneration facility, or only in the electric generating process of a bottoming-cycle cogeneration facility”.7 An example of Supplementary Firing for a Topping-Cycle Cogeneration Facility would be the use of duct burners within the exhaust stream of a combustion turbine to increase the amount of steam that can be produced in the heat recovery steam generator associated with the combustion turbine. An example of Supplementary Firing for a Bottoming-Cycle Cogeneration Facility would be the use of duct burners to stabilize
5 It should be noted the use of Nuclear Small Modular Reactors (“SMR”) as the thermal source for Topping-Cycle Cogeneration Facilities is currently being actively explored in the industry and in at least one case in the ERCOT portion of Texas is being actively pursued by X-Energy Reactor Company, LLC at a Dow site. See https://x-energy.com/media/news-releases/dow-and-x-energy-submit-construction-permit- application-to-the-us-nuclear-regulatory-commission-for-proposed-advanced-nuclear-project-in-texas. 6 18 C.F.R. § 292.202(e).
7 18 C.F.R. § 292.202(f).
PDF page 41
Exhibit No. IA-1Page 7 of 38
the steam produced from heat recovery from a waste heat source prior to that steam being used to generate electricity via a steam turbine.
Cogeneration Efficiency
10. As I have noted, FERC’s definition of Cogeneration Facility requires the
“sequential use of energy”.8 Specifically, for a Topping-Cycle Cogeneration Facility, FERC requires “the use of reject heat from a power production process in sufficient amounts in a thermal application or process to conform to the requirements of the operating standard”,9 where the “operating standard” is “the useful thermal energy output of the facility must be no less than 5 percent of the total energy output during the 12-month period beginning with the date the facility first produces electric energy, and any calendar year subsequent to the year in which the facility first produces electric energy.”10 For a Bottoming-Cycle Cogeneration Facility, FERC requires “the use of reject heat from a thermal application or process, at least some of which is then used for power production”.
11. Cogeneration Facilities, which, as I have noted, are also commonly referred to as CHP systems, are typically highly efficient because they capture heat that would otherwise be wasted and avoid electrical losses by generating electricity at the location where it will largely, if not entirely, be consumed. Specifically, Cogeneration Facilities can achieve efficiencies in excess of 80%, by using waste heat and avoiding electrical losses, compared to the efficiency of approximately 50% for conventional electricity generation with a steam boiler.11
8 18 CFR § 292.202(c).
9 18 CFR § 292.202(s)(1).
10 18 CFR § 292.205(a)(1).11https://www.epa.gov/chp/what-chp (last accessed 3/8/2026).
PDF page 42
Exhibit No. IA-1Page 8 of 38
12. In addition, pursuant to the Federal Power Act (“FPA”),12 FERC has a rule that dictates the requirements (including requirements respecting minimum size, fuel use and fuel efficiency) for a Cogeneration Facility to be a Qualifying Cogeneration Facility pursuant to PURPA. Specifically, to be a Qualifying Cogeneration Facility, a Cogeneration Facility must meet any applicable standards and criteria specified in 18 C.F.R. §§ 292.205(a), (b) and (d) and, unless exempted, has filed with the Commission a notice of self-certification, or has filed with the Commission an application for Commission certification, that has been granted.13 Section 292.205(a) is the operating and efficiency standard for Topping-Cycle Cogeneration Facilities.14 Section 292.205(b) is the efficiency standard for Bottoming-Cycle Cogeneration Facilities.15 Section 292.205(d) applies certain additional requirements to Cogeneration Facilities that do not meet certain grandfathering requirements.16
The Integration of Cogeneration with Commercial, Industrial, and Institutional Processes and the Critical Need for Reliable Backup and Maintenance Power at Just and Reasonable Rates
13. Because of the “sequential use of energy” requirement for Cogeneration Facilities that I have discussed, Cogeneration Facilities are typically highly integrated with the industrial processes, commercial processes, heating processes and/or cooling processes of their host retail customer. This has four major implications.
14. First, there is a need for very high availability from the Cogeneration Facility to meet the host retail customer’s thermal energy needs in order to assure the retail customer can operate its commercial or industrial processes that require thermal energy or to assure the retail
12 Section 3(18)(A) of the FPA.13 18 CFR § 292.203(b).14 18 CFR § 292.205(a).15 18 CFR § 292.205(b).16 18 CFR § 292.205(d).
PDF page 43
Exhibit No. IA-1Page 9 of 38
customer can operate its commercial or institutional cooling and heating systems. This has the side effect of the Cogeneration Facility operating at a high electrical capacity factor, either due to the need to produce the necessary thermal energy at a Topping-Cycle Cogeneration Facility or due to the abundance of waste (i.e., reject) heat from the need to run the retail customer’s primary thermal process at a Bottoming-Cycle Cogeneration Facility.
15. Second, the electrical output of the Cogeneration Facility can be much less than or much greater than the electrical load of the host retail customer. This is because the thermal energy needs of the retail customer typically dictate how much electric power must be produced by the Cogeneration Facility. For example, if an industrial retail customer has a very high steam need for its processes relative to its electrical needs, the Cogeneration Facility serving that customer will likely have to produce electric power well in excess of that retail customer’s needs for its electrical load. This requires there to be a reasonable outlet available to sell that excess electric power at utility-avoided cost or at just and reasonable prices in the wholesale market. In contrast, if an industrial retail customer has a very limited steam need for its processes relative to its electrical needs, the Cogeneration Facility serving that customer will likely produce electric power well below the level that the retail customer needs for its electrical load. This requires that the retail customer be able to purchase supplementary (or supplemental) electric power to cover the deficit from either a utility under a regulated retail electric service rate or from the wholesale power market through a retail supplier at just and reasonable rates where retail customer choice is available.
16. Third, when an outage of Cogeneration Facility occurs, significant electric load of the host retail customer can be lost immediately following, or very shortly following, the outage either due to certain retail customer industrial or commercial processes not being able to operate
PDF page 44
Exhibit No. IA-1Page 10 of 38
without thermal energy from the Cogeneration Facility if it is a Topping-Cycle facility or due to a thermal process being unable to operate because of the inability to dump its waste heat to the Cogeneration Facility if it is a Bottoming-Cycle facility.
17. Finally, most relevant to this current proceeding, there is a very high need for the Cogeneration Facility to be able to purchase reliable backup and maintenance electrical power for the host retail load of the Cogeneration Facility from the local utility, or from the wholesale market via a retail supplier where there is retail customer choice, at a cost that is consistent with cost causation principles. This is necessary to ensure the retail customer can, in a safe and environmentally compliant manner, continue to operate its processes at just and reasonable electric power rates within the bounds of what the remaining thermal energy capability of the Cogeneration Facility can support while it is under a full or partial outage or derate. The ability to continue operation in a safe and environmentally compliant manner within the bounds of what can be supported by the remaining thermal capability of the Cogeneration Facility at just and reasonable electric power rates is a critical requirement to ensure the retail customer can economically meet the needs of its own customers and clients. If that ability cannot be assured, cogeneration may fail to be a practical and/or economic solution to the retail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the retail customer to become economically unviable.
18. FERC’s rules recognize this critical need by requiring all electric utilities, except where exempted from doing so under FERC’s rules, to provide backup and maintenance power to Qualifying Facilities, including Qualifying Cogeneration Facilities, and placing two additional specific requirements on the rates under which that backup and maintenance power is provided in addition to generally requiring the rates be just and reasonable and in the public interest; and
PDF page 45
Exhibit No. IA-1Page 11 of 38
not discriminate against any Qualifying Facility in comparison to rates for sales to other customers served by the electric utility.17
19. FERC defines backup power as “electric energy or capacity supplied by an electric utility to replace energy ordinarily generated by a facility's own generation equipment during an unscheduled outage of the facility.”18 This is electric power beyond the host retail customer’s supplemental power consumption that is required by the host retail customer when the Cogeneration Facility experiences a full or partial forced outage or a forced deration.
20. FERC defines maintenance power as “electric energy or capacity supplied by an electric utility during scheduled outages of the qualifying facility.”19 This is electric power beyond host retail customer’s supplemental power consumption that is required by the host retail customer when the Cogeneration Facility experiences a full or partial scheduled maintenance outage or a scheduled maintenance derate.
21. Consistent with cost causation principles, the aforementioned two additional specific requirements for backup and maintenance power rates under FERC’s rules require that electric utility rates for sales of back-up power or maintenance power to Qualifying Facilities, including Qualifying Cogeneration Facilities:
(1) Shall not be based upon an assumption (unless supported by factual data) that forced outages or other reductions in electric output by all qualifying facilities on an electric utility's system will occur simultaneously, or during the system peak, or both; and
(2) Shall take into account the extent to which scheduled outages of the qualifying facilities can be usefully coordinated with scheduled outages of the utility's facilities.2017 18 CFR § 292.305.18 18 CFR § 292.101(b)(9).19 18 CFR § 292.101(b)(11).20 18 CFR § 292.305(c).
PDF page 46
Exhibit No. IA-1Page 12 of 38
III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING
COGENERATION ARE NOT THE SAME AS VERY LARGE
COMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER OF
GENERATION FACILITIES
22. Very large computational loads co-located behind the meter of generation
facilities are not similarly situated to traditional large commercial, industrial and institutional loads using Cogeneration Facilities located behind their meter.
23. In particular, very large computational loads by their very nature generally do not have a high thermal energy need relative to the magnitude of their total electric load and do not produce large amounts of waste heat relative to the magnitude of their total electrical load. As such, they are not candidates for Cogeneration Facilities beyond potentially addressing their cooling and heating needs.
24. Thus, very large computational load processes are generally not highly thermally integrated, if integrated at all, with the co-located generation facilities whose meter they may be located behind. This is because those generation facilities will either not be Cogeneration Facilities or be Cogeneration Facilities of greatly limited electrical capability relative to the total magnitude of the electrical load of their host retail customer.
25. Without such integration, the co-located generation facilities will not provide the efficiency benefits that are provided by Cogeneration Facilities in serving commercial, industrial, and institutional customers. In addition, depending on the specific nature of the co-located generation facilities, the generation may be operated only intermittently rather than at the high capacity factor typically required of Cogeneration Facilities to ensure their host retail customer thermal process needs are being reliably fully met.
PDF page 47
Exhibit No. IA-1Page 13 of 38
26. Due to these differences, from a cost causation perspective, very large
computational load co-located behind the meter of generation facilities are more akin to wholesale customer load served by utility behind the meter generation21 than traditional large commercial, industrial, and institutional load served by behind the meter Cogeneration Facilities.
IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION
FACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER
GENERATION PROVISIONS ARE CONSISTENT WITH COST CAUSATION
AND FERC’S OWN BACKUP AND MAINTENANCE POWER RULES FOR
QUALIFYING FACILITIES
27. PJM’s longstanding provisions22 for the netting of retail customer load with generation located behind the meter of those customers are consistent with cost causation for traditional large commercial, industrial, and institutional customers using Cogeneration Facilities, and consistent with FERC’s rules for backup and maintenance power for Qualifying Facilities.
Retail BTMG Netting for Transmission
28. With respect to the transmission component of backup and maintenance power, Section 34.2 of the PJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the load served by the operating behind the meter generation of a retail customer from that retail customer’s daily load for Network Integration Transmission Service (“NITS”).23 This has the
21 An example of utility behind the meter generation, also known in PJM as non-retail behind the meter generation, is a transmission dependent utility whose load is being served in part by the transmission dependent utility’s conventional generation facilities that are located on its side of the meter between it and its transmission provider.22 I have been advised by counsel that the Commission found that these provisions may be subject to change in light of the Commission’s December 18, 2025 order issued in Docket No. EL25-49-000. I am also aware that PJMICC and IECA have a pending rehearing request, filed on January 20, 2026, challenging the Commission’s determination with respect to findings concerning PJM’s rules for netting and retail behind-the-meter generation.23 PJM Tariff § 34.2 (Effective 9/17/2010 Docket No. ER10-2710-000).
PDF page 48
Exhibit No. IA-1Page 14 of 38
effect of excluding the portion of a retail customer’s load served by its operating behind the meter generation from its zonal daily load (“DCPZ”), which is the retail customer’s daily load within a transmission pricing zone coincident with the time of the annual peak of the zone.24 This nets the output of the behind the meter generation from the retail customer’s load such that the retail customer’s DCPZ is the retail customer’s demand placed on the transmission system at the time of the annual peak of the transmission pricing zone the retail customer is located within, just like it is for retail customers who do not have behind the meter generation. The DCPZ is applied to 1/365th of the annual NITS rate for the zone to determine the retail customer’s NITS charges for each day. Hence, whether a retail customer has behind the meter generation or not, its NITS charges are based on the demand the retail customer has historically put on the transmission system at the time of the annual peak of the transmission pricing zone.
29. Given zonal transmission costs under the PJM Tariff are currently allocated to load on an annual coincident peak demand basis, this netting approach is consistent with cost causation. Furthermore, it is consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities25 as it does not assume that a retail customer’s behind the meter Qualifying Facility will be experiencing an outage at the time of the annual transmission system peak and instead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time of the annual peak of the transmission pricing zone, when allocating transmission costs to the retail customer. Also consistent with FERC’s backup and maintenance rule,26 this approach inherently avoids assuming that all Qualifying Facilities will be
24 PJM Tariff § 34.1 (Effective 2/18/2020 Docket No. ER20-646-000).25 18 CFR § 292.305(c).26 Id.
PDF page 49
Exhibit No. IA-1Page 15 of 38
experiencing an outage at the same time. Again, it instead relies on factual data, in the form of the historical performance of each Qualifying Facility, not an assumption with respect to whether they will all be out of service at the same time.
30. It is also important to note the retail behind the meter generation netting approach would work under different cost allocation methods besides the annual coincident peak demand method. For example, if future facts and circumstances warranted a change from the annual zonal transmission system peak to the use of 12 monthly coincident peaks for the zone, to the top 100 transmission system demand hours for the zone, or to the evening hours of annual transmission peak day for the zone, the current retail behind the meter netting approach would still properly allocate transmission costs to retail customers based on the historical demand they place on the transmission system during the hours being used for the cost allocation consistent with using factual data, not assumptions.
31. Furthermore, given the high capacity factor typically associated with Qualifying Cogeneration Facilities that I discussed earlier, Qualifying Facility Cogeneration would not be expected to perform significantly less effectively using a larger number of hours for allocation rather than a smaller number of hours.
32. It is also important to understand that the transmission system is not planned assuming that all Cogeneration Facilities will experience an outage at the same time or will not otherwise be running. Based on my experience, consistent with their high capacity factor nature, Cogeneration Facilities are generally modeled in power flow and stability analysis as electrically producing power at the level necessary to support the thermal process needs of their retail host load, with only any stretch in electrical capability they may have through supplementary firing potentially being subject to economic dispatch. Furthermore, in my experience, transmission
PDF page 50
Exhibit No. IA-1Page 16 of 38
planners do not study or examine scenarios where it is assumed large numbers of Cogeneration Facilities will be offline at the same time, as there is no factual basis to support such an assumption. Both of these points further reinforce why transmission costs should be allocated to retail customers with Cogeneration Facilities on the basis of the net demand they place on the transmission system during the hours used for cost allocation rather than their gross load during those hours, as the sum of their individual gross loads is never under any circumstance placed on the transmission system.
33. Also from my experience, while transmission planners do consider the
contingency loss of individual generation assets at Cogeneration Facilities, when those contingencies are examined by transmission planners, those planners take into consideration how the electrical load of the host retail customer will change both immediately following the contingency and shortly thereafter due to the highly integrated nature of the Cogeneration Facility and its host retail customer. Regardless, such contingencies at best drive local transmission needs and only if the contingency is most severe generation contingency in that local area after subtracting off the electrical load that will be lost by the Cogeneration Facility’s host retail customer. As such, these contingencies are not driver of the bulk majority of transmission system costs any more than the non-coincident peak demand of individual loads is a driver of the bulk majority of transmission system costs. Instead, the bulk majority transmission system costs are driven by total system demand on the transmission system, which is why transmission costs are typically allocated to load using a coincident peak demand cost allocation method.
PDF page 51
Exhibit No. IA-1Page 17 of 38
Retail BTMG Netting for Capacity27
34. With respect to the capacity component of backup and maintenance power,
Schedule 8 of the PJM Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“PJM Reliability Assurance Agreement” or “RAA”) currently establishes the Obligation Peak Load of a party to the RAA as the daily summation of the weather-adjusted coincident summer peak, last preceding the Delivery Year, of the retail customers in the zone net of the operating behind the meter generation of those customers.28 The Daily Unforced Capacity Obligation of the party is then determined as its Obligation Peak Load multiplied by the applicable Final Zonal Reliability Pricing Model Scaling Factor and the PJM Forecast Pool Requirement.29 Thus, the PJM capacity requirement for retail customers is based on the weather adjusted demand of those customers at the time of the summer coincident peak net of the output of any behind the meter generation at that time of that summer coincident peak. This nets the output of the behind the meter generation from the retail customer’s load such that the retail customer’s capacity requirement is based the retail customer’s demand placed on the PJM market at the time of the summer coincident peak, just like it is for retail customers who do not have behind the meter generation. Hence, whether a retail customer has behind the meter generation or not, its PJM capacity requirement is based on the demand the retail customer has historically put on the PJM market at the time of the PJM summer coincident peak.
27 While PJM did not include any proposed changes to the PJM Reliability Assurance Agreement in its filing in ER26-1479-000, PJM, in Footnote 2 of the first page of its transmittal letter for its February 23, 2026 Compliance Filing, indicated it anticipates needing to make subsequent conforming clean-up filings to the PJM Reliability Assurance Agreement, among other documents, in regard to the compliance filings being submitted in response to the FERC’s Order to Show Cause in Docket No. EL25-49, et al.28 PJM RAA, Schedule 8, Section A (Effective: 8/31/2024 – Docket No. ER24-2447-003).29 Id.
PDF page 52
Exhibit No. IA-1Page 18 of 38
35. Given capacity requirements under the PJM RAA are currently allocated to load on a summer coincident peak demand basis, this netting approach is consistent with cost causation. Furthermore, like with retail behind the meter generation netting for NITS charges, it is consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities30 as it does not assume that a retail customer’s behind the meter Qualifying Facility will be experiencing an outage at the time of the summer coincident peak and instead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time of the summer coincident peak, when allocating transmission costs to the retail customer. Also consistent with FERC’s backup and maintenance rule,31 this approach inherently avoids assuming that all Qualifying Facilities will be experiencing an outage at the same time. Again, it instead again relies on factual data, in the form of the historical performance of each Qualifying Facility, not an assumption with respect to whether they will all be out of service at the same time.
36. Also, like with retail behind-the-meter netting for NITS charges, the current retail behind-the-meter generation netting approach for capacity requirements would still work under different cost allocation methods than the current summer coincident peak demand method. Specifically, regardless of the hours used for allocation, the current retail behind-the-meter netting approach would still properly allocate capacity requirements to retail customers based on the historical demand they place on the transmission system during the hours being used for the allocation of capacity requirements, consistent with using factual data, not assumptions. This sends a strong cost signal for retail behind the meter generation to operate and fully serve the
30 18 CFR § 292.305(c).31 Id.
PDF page 53
Exhibit No. IA-1Page 19 of 38
electric load of their host retail customer during times of grid stress. It does so because the times of grid stress generally align with the time periods used for cost allocation and it is at those very times that NITS billing units and capacity requirements are determined under retail behind the meter generation netting.
37. Finally, just as with retail behind-the-meter generation netting for NITS charges, given the high capacity factor typically associated with Qualifying Cogeneration Facilities that I discussed earlier above, Qualifying Facility Cogeneration would not be expected to perform significantly less effectively using a larger number of hours allocating capacity requirements rather than a smaller number of hours.
V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM
CONTRACT DEMAND TRANSMISSION SERVICE ARE UNABLE TO
PROVIDE JUST AND REASONABLE BACKUP AND MAINTENANCE
SERVICE TO QUALIFYING COGENERATION FACILITIES
38. FERC in its December 18, 2025 order in Docket No. EL25-49, et al., ordered PJM to provide two new transmission services for large loads co-located behind the meter of generation facilities (“Co-Located Loads”) – who would not be permitted to take NITS based on their net load -- as an alternative to taking NITS based on their gross load: (i) Firm Contract Demand Service and (ii) Non-Firm Contract Demand Service.32 While I understand from counsel that these services are subject to the paper hearing in Docket No. EL25-49-000, these new services have direct bearing on the just and reasonableness of continued availability of retail behind-the-meter generation netting for Qualifying Facilities.
32 193 FERC ¶ 61,127 (2025), at P 193.
PDF page 54
Exhibit No. IA-1Page 20 of 38
39. Firm Contract Demand Transmission Service would allow Co-Located Loads to take firm transmission service up to a pre-specified MW quantity rather than having to take NITS based on their gross demand.33
40. Non-Firm Contract Demand Transmission Service would allow non-firm
transmission service when such service is not needed on a regular basis.34 It would need to be reserved in advance on an as-available basis during normal, non-emergency operating conditions and would be subject to curtailment during emergency conditions.35 There would be no charge for generation capacity for the portion of the load taking the service, and PJM would have no obligation to obtain generation capacity for the load.36
41. While its specific provisions for these two transmission services are the subject of a paper hearing in Docket No. EL25-49-000, PJM in its February 23, 2026 initial brief in that paper hearing (“PJM Paper Hearing Initial Brief”) in part proposed:
The entire gross load of the Co-Located Load be covered by a
combination of Firm Contract Demand Transmission Service and Non-
Firm Contract Demand Transmission Service.37
Actual deliveries of power under Non-Firm Contract Demand
Transmission Service would need to be pre-scheduled with, and approved
by, PJM.38
To the extent the Co-Located Load takes any Non-Firm Contract Demand
Service it must install control technologies, potentially in the form of a
Remedial Action Scheme (“RAS”), to assure its load can be curtailed
33 Id. at P 208 through P 213.34 Id. at P 214.35 Id. at P 215.36 Id. at P 218.37 Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, Attachment A at Section 709.2(c).38 Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026 at 9-10 and Attachment B at ¶ 12.
PDF page 55
Exhibit No. IA-1Page 21 of 38
when required by PJM and the Non-Firm Contract Demand Service taken
by the Co-Located Load does not exceed the amount approved by PJM.39
Penalties and potential disqualification that would apply when a Co-
Located Load takes Contract Demand Service in excess of that authorized
by PJM, fails to respond to load shedding and curtailment procedures, or
has a misoperation of control technologies and protection systems.40
42. Firm Contract Demand Transmission Service and Non-Firm Contract Demand
Transmission Service, neither alone nor in tandem, are capable of providing reliable backup and maintenance power to traditional large commercial, industrial and institutional retail customers that utilize Qualifying Cogeneration Facilities at a cost that is consistent with cost causation principles and FERC’s rules for providing backup and maintenance service to Qualifying Facilities.
43. As I noted earlier, reliable backup and maintenance power consistent with cost causation principles and FERC’s rules for backup and maintenance power is necessary for these retail customers to ensure they can in a safe and environmentally compliant manner continue to operate their processes at just and reasonable electric power rates within the bounds of what the remaining thermal energy capability of their Qualifying Cogeneration Facility can support while it is under a full or partial outage or derate. The ability to continue operation in a safe and environmentally compliant manner within the bounds of what can be supported by the remaining thermal capability of the Cogeneration Facility at just and reasonable electric power rates is a critical requirement to ensure the retail customer can economically meet the needs of its own customers and clients. If that ability cannot be assured, cogeneration may fail to be a practical
39 Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, Attachment A at Sections 708(c) and 713.6.40 Id. at Sections 713.7 and 713.8.
PDF page 56
Exhibit No. IA-1Page 22 of 38
and/or economic solution to the retail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the retail customer to become economically unviable.
44. While Contract Demand Transmission Service would provide reliable backup and maintenance power, it would not provide it at rates that are consistent with cost causation or FERC’s rules for the rates for the provision of backup and maintenance power to Qualifying Facilities. Specifically, it requires payments for the service based on the contracted amount. As a result, it would inherently assume, in violation of FERC’s rules for backup and maintenance power for Qualifying Facilities,41 that forced outages or other reductions in electric output by all qualifying facilities on an electric utility's system will occur simultaneously, or during the system peak, or both, without any factual data to support such an assumption. As I have discussed at length in this affidavit, this is not a reasonable assumption for Qualifying Cogeneration Facilities.
45. Non-Firm Contract Demand Transmission Service would fall short in two
respects. First, it is incapable of providing backup power for forced outages of Qualifying Cogeneration Facilities because the actual usage Non-Firm Contract Demand Transmission Service would have to be pre-scheduled with, and approved by, PJM in advance of its use, and forced outages cannot be known beforehand. Second, the service is not reliable and risky to use as it is only available on an as-available basis, subject to interruption during emergencies, and subject to automated interruption. It is not a product that could be used to provide safe and environmentally compliant maintenance power to traditional commercial, industrial and
41 18 CFR 292.305(c).
PDF page 57
Exhibit No. IA-1Page 23 of 38
institutional retail customers with Qualifying Cogeneration Facilities, never mind backup power to them.
VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED
QUALIFYING FACILITIES AS OF DECEMBER 18, 2025 TO CONTINUE TO
USE RETAIL BTMG NETTING FOR NITS AND CAPACITY REQUIREMENTS
FALLS SHORT OF BEING JUST AND REASONABLE
46. PJM in its February 23, 2026 compliance filing in this proceeding has proposed to allow all retail customer behind-the-meter generation that as of December 18, 2025 was a Qualifying Facility under PURPA to continue to be able to be netted with its load for NITS charges and capacity requirements after the completion of three-year transition period that would otherwise end such netting for this generation.42 PJM indicates it made this proposal in its compliance filing as an extension of the legacy treatment of this generation under PURPA.43 PJM also notes that given these retail behind-the-meter generation arrangements have been in place and netted against Network Loads within PJM without known operational issues to date, PJM proposes to allow such arrangements (some of which have been in place for decades) to qualify for legacy treatment and continue to be eligible to net under existing behind-the-meter generation rules.44
47. PJM’s proposal for legacy retail behind-the-meter generation treatment for retail customers with behind-the-meter generation that, as of December 18, 2025, was a Qualifying Facility is a step toward providing a just and reasonable outcome for Qualifying Cogeneration
42 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment A, Definitions R-S, Retail behind the Meter Generation.43 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a.44 Id.
PDF page 58
Exhibit No. IA-1Page 24 of 38
Facilities. However, the step falls short of providing a just and reasonable outcome for Qualifying Cogeneration Facilities in two respects.
48. First, PJM’s proposal fails to recognize there may be some Cogeneration
Facilities within the PJM footprint that fully meet FERC’s requirements to be a Qualifying Cogeneration Facility (and, thus, a Qualifying Facility), except they do not currently have a FERC-approved certification or self-certification of their Qualifying Cogeneration Facility status because they do not makes sales of excess power either at avoided cost to electric utilities or into the wholesale power market. In addition, these Cogeneration Facilities have historically not needed certification or self-certification as a Qualifying Cogeneration Facility in order for the electrical load of their host retail customer to have reliable access to backup and maintenance power through just and reasonable rates through PJM’s current retail behind the meter generation netting provisions for NITS charges and capacity requirements. To address this first shortcoming that prevents PJM’s Qualifying Facility proposal from being just and reasonable, the proposal would need to be modified to cover all Qualifying Facilities that were in service on or prior to December 18, 2025, regardless of the date of their certification or self-certification as a Qualifying Facility. This would ensure that generation facilities that were in service on December 18, 2025 that were fully able to meet FERC’s requirements to be a Qualifying Facility, except for not having a FERC-approved certification or self-certification due to not previously having a need for such certification or self-certification, would be able to remedy their lack of certification or self-certification prior to the conclusion of the proposed three-year transition period for the end of the current PJM retail behind the meter generation netting provisions in order to preserve their ability to use those provisions after the end of the transition period.
PDF page 59
Exhibit No. IA-1Page 25 of 38
49. Second, PJM has effectively erroneously concluded FERC’s rules for the provision of backup and maintenance power to Qualifying Facilities45 ceased to be applicable in PJM footprint upon FERC’s issuance of its December 18, 2025, Show Cause Order in Docket No. EL25-49-000, et al. FERC made no such finding in its December 18, 2025, Show Cause Order as it does not address its PURPA backup and maintenance power rules for Qualifying Facilities in that order. Given this, and the proposed Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service options for Co-Located Loads are unable to provide just and reasonable backup and maintenance power to Qualifying Cogeneration Facilities for the reasons I have discussed earlier in this affidavit, the proper legacy treatment for Qualifying Facilities would be to allow all Qualifying Facilities to continue to be eligible to use PJM’s current retail behind-the-meter generation netting provisions for NITS charges and capacity requirements regardless of when that Qualifying Facility entered service or was certified or self-certified as a Qualifying Facility. Therefore, to address this second shortcoming that prevents PJM’s Qualifying Facility proposal from being just and reasonable, the proposal would need to be modified to cover all Qualifying Facilities, regardless of the date they entered service or the date of their certification or self-certification as a Qualifying Facility.
50. It is important to note that providing legacy retail behind-the-meter generation netting treatment for all Qualifying Facilities would not provide a “back door” for very large computational loads to bypass the Co-Located Load provisions of FERC’s December 18, 2025, Show Cause Order in Docket No. EL25-49-000, et al. As I have discussed earlier in this affidavit, very large computational load processes are generally not highly thermally integrated,
45 18 CFR § 292.305(c).
PDF page 60
Exhibit No. IA-1Page 26 of 38
if integrated at all, with any co-located generation facilities whose meter they may be located behind. This is because those generation facilities will either not be Cogeneration Facilities or would only be Cogeneration Facilities of greatly limited electrical capability relative to the total magnitude of the electrical load of their host retail customer. Furthermore, Qualifying Small Power Production Facilities, the other type of Qualifying Facility besides Qualifying Cogeneration Facilities, are, except when a waiver is granted by FERC, limited to 80 MW in size under FERC’s rules.46 As a result, the total electrical capability of a Qualifying Small Production Facility would also be greatly limited relative to the total magnitude of a large computational load, which as I will discuss later in this affidavit, would likely be 300 MW or more. Therefore, providing legacy retail behind-the-meter generation netting treatment to all Qualifying Facilities would not provide “back door” for very large computational loads to bypass FERC’s Co-Located Load provisions of its December 18, 2025, Show Cause Order in Docket No. EL25-49-000, et al.
VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-
QUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER
GENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND
REASONABLE
51. In addition to proposing to allow all retail customer behind-the-meter generation that as of December 18, 2025 was a Qualifying Facility under PURPA to continue to be able to be netted with its load for NITS charges and capacity requirements after the completion of three- year transition period that would otherwise end such netting for this generation, PJM in its February 23, 2026 compliance filing in this proceeding is also proposing two other such
46 18 CFR §§ 292.203(a), 292.203(c) and 292.204(a).
PDF page 61
Exhibit No. IA-1Page 27 of 38
continuations of retail behind the meter generation netting for NITS charges and capacity requirements.
52. First, PJM proposes to continue to allow retail behind the meter generation netting for NITS charges and capacity requirements beyond the three-year transition period for all generation used to serve a retail load served by a Network Customer if the retail behind the meter generation is subject to contractual arrangements (including but not limited to a bilateral agreement or an interconnection agreement) that were in effect as of December 18, 2025 through the end of the term of such agreement, which may be renewed or extended per the terms of such agreement. 47 PJM indicates it made this proposal in its compliance filing pursuant to the legacy treatment of existing contractual agreements provided for by FERC under its December 18, 2025, Show Cause Order in Docket No. EL25-49-000, et al.48 PJM also notes that, given these retail behind the meter generation arrangements, like those for PURPA Qualifying Facilities, have been in place and netted against Network Loads within PJM without known operational issues to date, it proposes to allow such arrangements, which in some cases have been in place for decades, to qualify for legacy treatment and continue to be eligible to net under existing behind the meter generation rules.49 I agree with this first additional proposed extension of retail behind-the-meter generation netting beyond the three-year transition period, and also agree with PJM’s arguments with respect to it.
53. Second, PJM proposes to continue to allow retail behind the meter generation netting for NITS charges and capacity requirements beyond the three-year transition period for
47 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment A, Definitions R-S, Retail behind the Meter Generation.
48 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a.49 Id.
PDF page 62
Exhibit No. IA-1Page 28 of 38
all generation whose cumulative nameplate capacity rating is no greater than 50 MW (not including back-up generation at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or the PJM Region or the regional power system). 50 PJM justifies its proposed cumulative nameplate capacity limit for the continued retail behind the meter generation netting for generators not otherwise eligible for continuation of netting under PJM’s Qualifying Facility and existing contract proposals as not being too high when compared to a lower 10 or 20 MW limit: (i) excluding a much larger volume of retail customers whose grid impacts are small or de minimis when compared with Co- Located Loads coming online today and (ii) potentially causing loss of that generation altogether due to significant transmission upgrades that may be required for that generation to become a market resource. 51 With respect to justifying why the 50 MW limit is not too low, PJM solely relies on referencing a PJM Board letter defining large load additions as individual load additions at or above 50 MW at a single point of interconnection.52 Furthermore, PJM requests that, if its proposed Qualifying Facility continuation of retail behind-the-meter generation meeting for NITS charges and capacity requirements is not accepted, FERC accept as a potential stop gap a higher limit of possibly as high as 200 MW to avoid the same potential loss of generation capacity issue that it claims would be associated with a 10 or 20 MW limit.53 Under such an approach, PJM would commit to reviewing additional data on the size and extent of retail
50 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2. and Attachment A, Definitions R-S, Retail behind the Meter Generation.
51 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2.c.
52 Id. The January 16, 2026 PJM Board Letter does not include any factual or technical detail or support for the proposed 50 MW threshold. See Board Decisional Letter on Critical Issue Fast Path - Large Load Additions (Jan. 16, 2026) at p. 2, available at https://www.pjm.com/-/media/DotCom/about- pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large- load-additions.pdf.53 Id.
PDF page 63
Exhibit No. IA-1Page 29 of 38
behind-the-meter generation, which could inform whether the initial higher stop gap limit should be further refined through a separate future filing.54
54. PJM’s proposed 50 MW cumulative nameplate capacity limit for determining
which retail behind-the-meter generation facilities, besides those who qualify under its Qualifying Facility and existing contract proposals, would be eligible for continued retail behind the meter generation netting treatment after the three-year transition period is not just and reasonable. The proposed limit is not just and reasonable for two reasons. First, it imposes a cap based on the cumulative nameplate capacity of the generation behind the customer's meter, rather than limiting the amount of load that can be netted behind the meter. Second, the proposed threshold amount of 50 MW is too low.
The Proposed 50 MW Limit is Inappropriately Applied to Cumulative Nameplate Capacity Rather than the Amount of Retail Load that can be Netted
55. PJM’s proposal to apply its proposed 50 MW limit to cumulative nameplate
capacity rather than the amount of retail load that can be netted against generation located behind that load’s meter is not just and reasonable for at least four reasons.
56. First, nameplate capacity does not necessarily indicate the actual electrical capability of behind-the-meter generation. This can be particularly the case with generation served from a common steam system, where it is the total capability of the steam system that limits the combined electrical capability of the steam turbine generation facilities fed from it, not the cumulative (i.e., the sum of the) nameplate capacity of the steam turbines. In such situations, it would be inappropriate to apply the limit to cumulative nameplate capacity, as that amount could be significantly higher than the actual electrical capability of the generation.
54 Id.
PDF page 64
Exhibit No. IA-1Page 30 of 38
57. Second, the cumulative nameplate capacity of the behind-the-meter generation, even when it does indicate the actual electrical capability of that behind-the-meter generation, may be intentionally much larger than the retail load at its location in order to provide redundancy with respect to serving that load. In this situation, it would also be inappropriate to apply the limit to the cumulative nameplate capacity of the generation as that amount could be significantly higher than the actual retail load being served by that generation solely due to the redundancy being provided to improve the reliability of serving that load with behind the meter generation.
58. Third, the proposal to use the cumulative nameplate capacity of the behind-the- meter generation fails to account for a critical operational limitation. Specifically, the generation could not be operated in excess of the retail load it is serving behind the meter unless the generation has an interconnection agreement with PJM or the applicable transmission owner that allows it to put its power in excess of the retail load it is serving behind the meter onto the transmission system. Without such an agreement, the generation is effectively constrained to serving only the retail load behind the meter. When limited in this matter, the largest generation contingency the generator could place onto the PJM transmission system is a loss of generation equal to the amount of retail load the behind-the-meter generation is serving, not its cumulative nameplate capacity. Furthermore, this concept is readily extendable to a situation where there is a limit on the amount of retail load that can be served behind the meter by limiting the output of the generation to the lesser of: (i) the current demand of the retail load or (ii) the MW limit placed on retail behind the meter generation netting.
59. Finally, the proposal fails to consider a large portion of behind the meter generation may not be associated with serving the electrical load of the host retail customer
PDF page 65
Exhibit No. IA-1Page 31 of 38
behind that customer’s meter but rather associated with either PURPA Qualifying Facility sales at avoided cost to an electric utility or sales into the wholesale market within the bounds the generation facility’s interconnection agreement. As I noted earlier in this affidavit, this situation is not uncommon for Qualifying Cogeneration Facilities with a host retail customer that has a very large steam need as the level of electric power production necessary by the Cogeneration Facility to produce the heat needed to meet the steam requirement of the host retail customer may be much higher than the electrical load of the Cogeneration Facility’s host retail customer.55 In addition, for non-Cogeneration Facilities, this situation can exist due the economy of scale benefits of constructing a generation facility to not only serve the electrical load of the host retail customer behind the meter but to also make wholesale power sales. Regardless of why the behind the meter generation facility makes avoided cost or wholesale market sales, it is important to note the loss of the total electrical capability of the generation facility, less any electrical load of the host retail customer that is lost with the loss of that electrical capability, has already been considered as a generation contingency in determining the transmission upgrades that were necessary to allow interconnection of the generation facility, and, as a result, the transmission system has been built to accommodate that level of generation contingency. Therefore, provided the generation operates within the bounds of its interconnection agreement and the bounds of PJM’s wholesale market rules, retail behind the meter generation with excess power sales does not introduce any circumstances that should preclude it from still being able to utilize retail behind the meter generation netting for NITS charges and capacity requirements for
55 As an aside, it is important to note FERC’s rules for backup and maintenance power must be met for all Qualifying Facilities regardless of whether a Qualifying Facility has any excess power sales either at avoided cost to an electric utility or into the wholesale power market.
PDF page 66
Exhibit No. IA-1Page 32 of 38
its host retail customer up to any MW limit on such netting. This would be accomplished by calculating the output of the generation to the PJM market (including any avoided costs sales to an electric utility) as the gross output of the generation less the lower of: (i) the current demand of the retail load being served by the generation behind the meter or (ii) the MW limit placed on retail behind the meter generation netting.
60. For the above reasons, the MW limit that is ultimately approved by FERC should be a limit on the maximum MW of retail load that can be netted with behind-the-meter generation when determining NITS charges and capacity requirements for that retail load. It should not be a cumulative nameplate capacity limit that determines which locations where retail behind-the-meter generation netting will be allowed, as proposed by PJM.
PJM’s Proposed 50 MW Limit is Too Low
61. PJM’s proposed 50 MW limit is too low for at least four reasons.
62. First, PJM is solely relying on the PJM Board’s definition of large load additions as 50 MW at a single site to justify its proposed 50 MW limit as not being too low. The PJM Board is not a regulatory body that has made a finding of fact that 50 MW is the appropriate limit for retail behind-the-meter generation netting. Furthermore, the PJM Board did not develop its large load definition in the context of establishing a limit on retail behind-the-meter generation netting. As such, it should be given no weight with respect to setting a limit on retail behind-the-meter netting.
63. Second, PJM has not provided any evidence that the concerns it expressed with respect to a limit of 10 or 20 MW – (i) excluding a large volume of retail customers whose grid impacts are small or de minimis when compared with Co-Located Loads coming online today and (ii) potentially causing a loss of that generation altogether due to significant transmission
PDF page 67
Exhibit No. IA-1Page 33 of 38
upgrades that may be required for them to become market resources – are not still present with a 50 MW limit. Also, it appears PJM is concerned its 50 MW limit may be too low in this respect, particularly if its proposal for Qualifying Facilities is not accepted by FERC. Specifically, as I noted earlier in this affidavit, PJM has requested that FERC adopt a higher limit, potentially as high as 200 MW, as a stopgap if FERC chooses not to accept PJM’s proposal with respect to Qualifying Facilities.56
64. Third, PJM, in its February 23, 2026 compliance filing in this proceeding, indicated that Qualifying Facility retail behind the meter generation and retail behind the meter generation with existing contracts have been in place and netted against Network Loads within PJM without known operational issues to date, and in some cases have been in place for decades. While I certainly agree this is true for Qualifying Facilities and retail behind the generation with existing contracts, it must also be generally true for all other existing retail behind-the-meter generation that has been in place for many years within the PJM footprint. Furthermore, its existence suggests that retail behind-the-meter generation netting at the MW level for individual retail customer locations for which it has historically occurred is something that can be readily accommodated in normal transmission planning and transmission operations such that it does not need extraordinary treatment, such as prohibiting it. This in turn suggests that a better basis for developing a limit on how much retail behind the meter generation netting should be permitted behind each retail customer’s meter would be to examine the largest amount of retail behind the meter generation netting that has been readily accommodated in recent years and comparing that
56 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.c.
PDF page 68
Exhibit No. IA-1Page 34 of 38
to the typical size of the very large computational load additions that have triggered the need to consider the Co-Located Loads issue in the first place.
65. Finally, there is evidence that the typical size of very large computational load additions, which are the load additions driving the need to examine the Co-Located Loads issue, is much larger than 50 MW.
66. For example, in the context of FERC’s Advanced Notice of Proposed Rulemaking in Docket No. RM26-4-000, Indicated PJM Transmission Owners stated:
To the extent the Commission asserts jurisdiction over large load
interconnections, it should adopt a sufficiently narrow definition of ‘large load customer’ limited to large (200 MW or greater) data center customers. It is those customers that are primarily driving load increases.57
67. In addition, in early July 2025, in Michigan Public Service Commission
(“MPSC”) Case No. U-21859, I performed and presented in rebuttal testimony an analysis of the MW size of the data center load addition inquiries that Consumers Energy Company had received up to that point in time. A summary of the results of that analysis is presented in Attachment 2 of this affidavit, and the raw data upon which it was performed is provided in Attachment 3 of this affidavit.58 As shown in Attachment 2, my analysis indicated that the sum of the MWs of potential data center load addition inquiries Consumers Energy Company had received associated with a MW size of 300 MW or less makes up less than 7% (1,049 MW) of the 15,249 MW in total large data center load addition inquiries that it had received. In other words, over 93% (14,200 MW) of the total MWs of large data center load addition inquiries Consumers Energy Company had received were from load additions greater than or equal to 300
57 Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000 (Dec. 5, 2025) at 2-3.58 The workpaper used to produce Attachment 2 of this affidavit is available on request to parties in this current proceeding from Industrials/Amtrak Counsel.
PDF page 69
Exhibit No. IA-1Page 35 of 38
MW in size. While Consumers Energy Company is located within MISO rather than PJM, there is no reason to believe the results for Consumers Energy Company are not indicative of what a similar analysis would likely show for similar large electric utilities in PJM. In other words, the large load additions to be concerned with are not all large load additions 50 MW and larger, but rather those 300 MW or higher, as evidenced by my analysis, since they make up the vast majority of what is being proposed. Accordingly, more concrete evidence exists to support a 300 MW threshold than a 50 MW threshold.
68. In addition, in September 2025, subsequent to the performance of my early July 2025 analysis based on Consumers Energy Company data, I became involved in Illinois Commerce Commission (“ICC”) Docket No. 25-0677. That Illinois proceeding concerned Commonwealth Edison Company (“ComEd”) – a very large Illinois electric utility located within PJM. In that proceeding, ComEd Witness Max Leichtman in direct testimony indicated “the average size of a unique large demand project that began the process of obtaining electric service from ComEd in the last twelve months is approximately 700 MWs, roughly the equivalent of 1,400 big box stores.”59 Furthermore, in response to discovery in that proceeding, ComEd provided a data request response that publicly disclosed the MW size of each of the aforementioned projects.60 A copy of this ComEd discovery response in ICC Docket No. 25- 0677 is provided as Attachment 4 to my affidavit. As can be seen in Attachment 4, in 2025, through the August 29, 2025 date of the ComEd discovery response, twelve (12) load additions began the process of obtaining electric service from ComEd. Ten (10) of the twelve (12) proposed load additions, representing 8,212 MW (98.86%) of the total of 8,307 MW of requested
59 ICC Docket No. 25-0677, ComEd Ex. 1.0, Direct Testimony of Max Leichtman at 6.60 ICC Docket No. 25-0677, ComEd Response to Data Request No. NRG-ComEd 1.02.
PDF page 70
Exhibit No. IA-1Page 36 of 38
electric service, were from proposed loads with a magnitude of 300 MW or greater. This provides further concrete evidence to support a 300 MW threshold rather than a 50 MW threshold.
69. For the foregoing reasons, PJM’s proposed limit of 50 MW is too low. Concrete evidence exists to support a 300 MW threshold, and any limit should instead initially be set no lower than 200 MW (if not closer to 300 MW), regardless of whether PJM’s proposal for Qualifying Facilities is accepted or that proposal is modified as I have recommended earlier in this affidavit.
VIII. CONCLUSION
70. In summary, I conclude the following:
Very large computational loads co-located behind the meter of generation facilities are not similarly situated to traditional large commercial, industrial, and institutional loads using Cogeneration Facilities located behind their meter, as very large computational loads generally are not highly thermally integrated with any co-located generation facilities.
For traditional large loads served by Cogeneration Facilities, PJM’s current retail behind-the-meter generation netting provisions for NITS charges and capacity requirements are consistent with cost causation principles and FERC’s own backup and maintenance power rules for Qualifying Facilities, as they rely on factual data regarding each Qualifying Facility’s historical performance rather than assumptions about when outages will occur and whether they will occur simultaneously.
Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service are not capable – either alone or in tandem
– of providing reliable backup and maintenance power to traditional large retail customers that utilize Qualifying Cogeneration Facilities at rates consistent with cost causation principles and FERC’s rules for providing backup and maintenance service to Qualifying Facilities.
PJM’s proposal to limit legacy retail behind-the-meter generation treatment for Qualifying Facilities to those certified or self-certified as of December 18, 2025 falls short of being just and reasonable, and should be
PDF page 71
Exhibit No. IA-1Page 37 of 38
modified to cover all Qualifying Facilities regardless of the date they entered service or the date of their certification or self-certification.
PJM’s proposed 50 MW cumulative nameplate capacity limit for continued retail behind-the-meter generation netting for non-Qualifying Facility generation is not just and reasonable because the limit is inappropriately applied to cumulative nameplate capacity rather than to the amount of retail load that can be netted, and 50 MW is too low given that the large computational load additions driving the Co-Located Loads issue are overwhelmingly 300 MW or larger in size; any limit should initially be set no lower than 200 MW (if not closer to 300 MW).
71. Further Affiant sayeth naught.
PDF page 72
Exhibit No.IA-1
Page 38 of38
es R. Dauph
STATE OF'MISSOURI
COUNTY OF ST. LOUIS
Subscribed and sworn to before me this 16th day of March,2026. Notary Public
)
)
)
SS
Notary Public - Notary Soal
STATE OF MISSOURI
Jetferson County
Commission Expiresr Mar, 22,2029
My
# 21989987
ADRIENNE J.
PDF page 73
Exhibit No. IA-1
Attachment 1
Page 1 of 6
BRUBAKER & ASSOCIATES, INC.
Qualifications of James R. Dauphinais
Q
PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
1
A
James R. Dauphinais. My business address is 16690 Swingley Ridge Road, Suite 140, 2
Chesterfield, MO 63017, USA.
3
Q
PLEASE STATE YOUR OCCUPATION.
4
A
I am a consultant in the field of public utility regulation and a Managing Principal with 5
the firm of Brubaker & Associates, Inc. (“BAI”), energy, economic and regulatory 6
consultants.
7
Q
PLEASE SUMMARIZE YOUR EDUCATIONAL BACKGROUND AND
8
EXPERIENCE.
9
A
I graduated from Hartford State Technical College in 1983 with an Associate's Degree 10
in Electrical Engineering Technology. Subsequent to graduation, I was employed by 11
the Transmission Planning Department of the Northeast Utilities Service Company1 as 12
an Engineering Technician.
13
While employed as an Engineering Technician, I completed undergraduate 14
studies at the University of Hartford. I graduated in 1990 with a Bachelor's Degree in 15
Electrical Engineering. Subsequent to graduation, I was promoted to the position of 16
Associate Engineer. Between 1993 and 1994, I completed graduate level courses in the 17
study of power system analysis, power system transients and power system protection 18
1In 2015, Northeast Utilities changed its name to Eversource Energy.
PDF page 74
Exhibit No. IA-1
Attachment 1
Page 2 of 6
BRUBAKER & ASSOCIATES, INC.
through the Engineering Outreach Program of the University of Idaho. By 1996 I had 1
been promoted to the position of Senior Engineer.
2
In the employment of the Northeast Utilities Service Company, I was
3
responsible for conducting thermal, voltage and stability analyses of the Northeast 4
Utilities' transmission system to support planning and operating decisions. This 5
involved the use of load flow, power system stability and production cost computer 6
simulations. It also involved examination of potential solutions to operational and 7
planning problems including, but not limited to, transmission line solutions and the 8
routes that might be utilized by such transmission line solutions. Among the most 9
notable achievements I had in this area include the solution of a transient stability 10
problem near Millstone Nuclear Power Station, and the solution of a small signal (or 11
dynamic) stability problem near Seabrook Nuclear Power Station. In 1993 I was 12
awarded the Chairman's Award, Northeast Utilities’ highest employee award, for my 13
work involving stability analysis in the vicinity of Millstone Nuclear Power Station. 14
From 1990 to 1996, I represented Northeast Utilities on the New England Power 15
Pool Stability Task Force. I also represented Northeast Utilities on several other 16
technical working groups within the New England Power Pool (“NEPOOL”) and the 17
Northeast Power Coordinating Council (“NPCC”), including the 1992-1996 New York- 18
New England Transmission Working Group, the Southeastern Massachusetts/Rhode 19
Island Transmission Working Group, the NPCC CPSS-2 Working Group on Extreme 20
Disturbances and the NPCC SS-38 Working Group on Interarea Dynamic Analysis. 21
This latter working group also included participation from a number of ECAR, PJM and 22
VACAR utilities.
23
PDF page 75
Exhibit No. IA-1
Attachment 1
Page 3 of 6
BRUBAKER & ASSOCIATES, INC.
From 1990 to 1995, I also acted as an internal consultant to the
1
Nuclear Electrical Engineering Department of Northeast Utilities. This included 2
interactions with the electrical engineering personnel of the Connecticut Yankee, 3
Millstone and Seabrook nuclear generation stations and inspectors from the Nuclear 4
Regulatory Commission (“NRC”).
5
In addition to my technical responsibilities, from 1995 to 1997, I was also 6
responsible for oversight of the day-to-day administration of Northeast Utilities' Open 7
Access Transmission Tariff. This included the creation of Northeast Utilities' pre-FERC 8
Order No. 889 transmission electronic bulletin board and the coordination of Northeast 9
Utilities' transmission tariff filings prior to and after the issuance of Federal Energy 10
Regulatory Commission (“FERC” or “Commission”) FERC Order No. 888. I was also 11
responsible for spearheading the implementation of Northeast Utilities' Open Access 12
Same-Time Information System and Northeast Utilities’ Standard of Conduct under 13
FERC Order No. 889. During this time, I represented Northeast Utilities on the Federal 14
Energy Regulatory Commission's "What" Working Group on Real-Time Information 15
Networks. Later I served as Vice Chairman of the NEPOOL OASIS Working Group 16
and Co-Chair of the Joint Transmission Services Information Network Functional 17
Process Committee. I also served for a brief time on the Electric Power Research 18
Institute facilitated "How" Working Group on OASIS and the North American Electric 19
Reliability Council facilitated Commercial Practices Working Group. 20
In 1997 I joined the firm of Brubaker & Associates, Inc. The firm includes 21
consultants with backgrounds in accounting, engineering, economics, mathematics, 22
computer science and business. Since my employment with the firm, I have filed or 23
PDF page 76
Exhibit No. IA-1
Attachment 1
Page 4 of 6
BRUBAKER & ASSOCIATES, INC.
presented testimony before the Federal Energy Regulatory Commission in Consumers 1
Energy Company, Docket No. OA96-77-000; Midwest Independent Transmission 2
System Operator, Inc., Docket No. ER98-1438-000; Montana Power Company, Docket 3
No. ER98-2382-000; Inquiry Concerning the Commission’s Policy on Independent 4
System Operators, Docket No. PL98-5-003; SkyGen Energy LLC v. Southern Company 5
Services, Inc., Docket No. EL00-77-000; Alliance Companies, et al., Docket No. EL02- 6
65-000, et al.; Entergy Services, Inc., Docket No. ER01-2201-000; Remedying Undue 7
Discrimination through Open Access Transmission Service, Standard Electricity 8
Market Design, Docket No. RM01-12-000; Midwest Independent Transmission System 9
Operator, Inc., Docket No. ER10-1791-000; NorthWestern Corporation, Docket No. 10
ER10-1138-001, et al.; Illinois Industrial Energy Consumers v. Midcontinent 11
Independent System Operator, Inc., Docket No. EL15-82-000; Midcontinent 12
Independent System Operator, Inc., Docket No. ER16-833-000; Midcontinent 13
Independent System Operator, Inc., Docket No. ER17-284-000; and Midcontinent 14
Independent System Operator, Inc. and Ameren Services Company Docket No. ER18- 15
463-000. I have also filed or presented testimony before the Alberta Utilities 16
Commission, the California Public Utilities Commission, the Colorado Public Utilities 17
Commission, the Connecticut Department of Public Utility Control, the Florida Public 18
Service Commission, the Idaho Public Service Commission, the Illinois Commerce 19
Commission, the Indiana Utility Regulatory Commission, the Iowa Utilities Board, the 20
Kentucky Public Service Commission, the Louisiana Public Service Commission, the 21
Michigan Public Service Commission, the Missouri Public Service Commission, the 22
Montana Public Service Commission, the Nevada Public Utilities Commission, the New 23
PDF page 77
Exhibit No. IA-1
Attachment 1
Page 5 of 6
BRUBAKER & ASSOCIATES, INC.
Mexico Public Regulation Commission, the Council of the City of New Orleans, the 1
State of New York Public Service Commission, the Oklahoma Corporation 2
Commission, the Public Utility Commission of Texas, the Public Service Commission 3
of Utah, the Virginia State Corporation Commission, the Wisconsin Public Service 4
Commission, the Wyoming Public Service Commission, Federal District Court and 5
various committees of the Illinois, Missouri and South Carolina state legislatures. This 6
testimony has been given regarding a wide variety of issues including, but not limited 7
to, ancillary service rates, avoided cost calculations, certification of public convenience 8
and necessity, class cost of service, cost allocation, fuel adjustment clauses, fuel costs, 9
generation interconnection, interruptible rates, market power, market structure, 10
off-system sales, prudency, purchased power costs, resource adequacy, resource 11
planning, rate design, retail open access, standby rates, transmission losses, transmission 12
planning, transmission rates and transmission line routing.
13
I have also participated on behalf of clients in the Southwest Power Pool 14
Congestion Management System Working Group, the Alliance Market Development 15
Advisory Group and several committees and working groups of the Midcontinent 16
Independent System Operator, Inc. (“MISO”), including the Congestion Management 17
Working Group; Economic Planning Users Group; Loss of Load Expectation Working 18
Group; Market Subcommittee; Michigan Transmission Studies Task Force; Planning 19
Subcommittee; Regional Expansion, Criteria and Benefits Working Group; Resource 20
Adequacy Subcommittee (formerly the Supply Adequacy Working Group); and 21
Reliability Subcommittee. I am currently a member of the MISO Advisory Committee 22
in the end-use customer sector on behalf of industrial customer groups in Illinois, 23
PDF page 78
Exhibit No. IA-1
Attachment 1
Page 6 of 6
BRUBAKER & ASSOCIATES, INC.
Louisiana, Michigan and Texas. I am also the past Chairman of the Issues/Solutions 1
Subgroup of the MISO Revenue Sufficiency Guarantee (“RSG”) Task Force. 2
In 2009, I completed the University of Wisconsin-Madison High Voltage Direct 3
Current (“HVDC”) Transmission course for Planners that was sponsored by MISO. I 4
am a member of the Power and Energy Society (“PES”) of the Institute of Electrical and 5
Electronics Engineers (“IEEE”).
6
PDF page 79
Exhibit No. IA-1
Atatchment 2
Page 1 of 1
<100 MW
< 150 MW
< 200 MW
< 250 MW
< 300 MW
< 350 MW
< 400 MW
< 1,000 MW <= 1,200 MW
Uknown MW
Total # of Load Inquiries
2
5
5
7
8
16
16
26
32
6
Total Amount of MW
54
399
399
799
1,049
3,449
3,449
9,049
15,249
% of 15,249 MW
0.35%
2.62%
2.62%
5.24%
6.88%
22.62%
22.62%
59.34%
100.00%
% of 15,249 MW above
99.65%
97.38%
97.38%
94.76%
93.12%
77.38%
77.38%
40.66%
0.00%
Source: Attachment to Consumers' Data Request Response U21859-DCC-CE-0045 (Exhibit No. IA-1, Attachment 3) Analysis of MW Size of Consumers' Large Data Center Load Addition Inquiries
PDF page 80
U21859-DCC-CE-0045
Page 1 of 1
Question:
21859-DCC-CE-0013. Please refer to Connolly Direct at 4:7-8. “The Company has data center inquiries that total over 15 gigawatts of electric load in the economic development pipeline.” Please provide a spreadsheet or other document listing each of the referenced “data center inquiries,” and identify, for each inquiry: a) the proposed location; b) the associated electric load and/or contract capacity; and c) the timeline for energization and delivery of requested capacity, including any proposed load ramp. Response:
See attached
Witness: Laura M. Connolly
Date: May 13, 2025
Exhibit No. IA-1
Attachment 3
Page 1 of 3
PDF page 81
1
Description
Date of Inquiry
Peak demand
reached year
50% of peak year
Requested in-
service year
Load
(MW)
Location
Id
Data Center
10/7/2024
Unknown
Unknown
As soon as possible
400
East Central Region
A
Data Center
10/4/2024
Q1 2040
Q2 2033
Q1 2026
1,000
South Central Region
B
Data Center
11/6/2024
Unknown
Unknown
Unknown
300
Unknown
C
Data Center
7/15/2024
Unknown
Unknown
As soon as possible
300
East Central Region
D
Data Center
5/7/2024
Within 36 months
Unknown
As soon as possible
200
Unknown
E
Data Center
12/3/2024
Unknown
Unknown
Unknown
Unknown
Southwest Region
F
Data Center
11/19/2024
Unknown
Unknown
Unknown
200
Unknown
G
Data Center
3/10/2025
Unknown
Unknown
As soon as possible
250
Unknown
H
Data Center
2/26/2025
Within 36 months
Unknown
As soon as possible
1,000
East Central Region
I
Data Center
3/1/2024
Q4 2033
Q4 2030
Q1 2029
300
West Region
J
Data Center
6/6/2024
Q4 2033
Q2 2030
Q4 2029
300
Unknown
K
Data Center
1/9/2025
Unknown
Unknown
Unknown
100
East Region
L
Data Center
12/4/2024
Q1 2030
Unknown
Unknown
300
Unknown
M
Data Center
2/4/2025
Unknown
Unknown
Unknown
700
East Region
N
Data Center
2/28/2025
Within 5-10 years
Unknown
Within 2-3 years
1,000
Unknown
O
Data Center
3/10/2025
Unknown
Unknown
Unknown
300
East Central Region
P
Data Center
7/29/2024
Unknown
Unknown
Unknown
Unknown
Unknown
Q
Data Center
8/7/2024
Unknown
Unknown
Unknown
500
Unknown
R
Data Center
10/4/2024
Unknown
Unknown
Unknown
100
South Central Region
S
Data Center
10/31/2024
Q1 2031
Unknown
Q1 2027
Unknown
Unknown
T
Data Center
12/19/2024
Unknown
Unknown
Unknown
50
Southwest Region
U
Data Center
10/16/2024
Q4 2030
Q2 2029
Q1 2028
1,200
Unknown
V
Data Center
8/19/2024
Unknown
Unknown
Unknown
300
Unknown
W
Exhibit No. IA-1
Attachment 3
Page 2 of 3
PDF page 82
2
Description
Date of Inquiry
Peak demand
reached year
50% of peak year
Requested in-service
year
Load
(MW)
Location
Id
Data Center
7/25/2024
2024
2024
2024
4
Southwest Region
X
Data Center
1/15/2025
Unknown
Unknown
Unknown
300
Unknown
Y
Data Center
10/31/2024
Unknown
Unknown
Unknown
Unknown
Unknown
Z
Data Center
9/10/2024
Unknown
Unknown
Unknown
500
Unknown
AA
Data Center
10/31/2024
Unknown
Unknown
Q1 2029
1,000
Unknown
AB
Data Center
7/12/2024
Q1 2029
Unknown
Q1 2026
500
Unknown
AC
Data Center
10/29/2024
Unknown
Unknown
Unknown
Unknown
Unknown
AD
Data Center
7/25/2024
Q3 2029
Q3 2027
Q3 2026
500
Unknown
AE
Data Center
10/10/2024
Unknown
Unknown
Unknown
500
Unknown
AF
Data Center
12/11/2024
2030
Unknown
Q4 2027
600
Unknown
AG
Data Center
7/31/2024
Unknown
Unknown
Unknown
145
Unknown
AH
Data Center
2/4/2025
Unknown
Unknown
2027
1,000
Unknown
AI
Data Center
1/6/2025
Q1 2029
Unknown
Unknown
500
Southeasterly Region
AJ
Data Center
9/11/2024
Q4 2029
Q4 2028
Q4 2027
900
Unknown
AK
Data Center
11/21/2024
Unknown
Unknown
Unknown
Unknown
East Central
AL
Exhibit No. IA-1
Attachment 3
Page 3 of 3
PDF page 83
ICC Docket Nos. 25-0677 & 25-0679 (Cons.)
Commonwealth Edison Company’s Response to
NRG Energy, Inc. (“NRG”) Information Requests
NRG-ComEd 1.01-NRG-ComEd 1.20
Date Received: August 22, 2025
Date Served: August 29, 2025
REQUEST NO. NRG-ComEd 1.02:
Please provide all workpapers, analyses, data, and information used or relied upon by Max Leichtman in relation to ComEd Ex. 1.0, the Direct Testimony of Max Leichtman. RESPONSE:
ComEd objects to this request as overly broad and unduly burdensome to the extent it seeks “all … data and information … relied upon” by ComEd witness Leichtman, and to the extent that much of the “data and information” is not relevant and not calculated to lead to the discovery of relevant and admissible evidence. Subject to and without waiving those objections, ComEd responds as follows:
See NRG-ComEd 1.02_Attach 1 for the data supporting Figure 1 in the direct testimony of Max Leichtman (ComEd Ex. 1.0) at lines 122-123. There are no other workpapers supporting Mr. Leichtman’s testimony.
2025LLT 0000007
Exhibit No. IA-1
Attachment 4
Page 1 of 4
PDF page 84
Year
New/Expansion
ComEd New
Ultimate
2018
New
2.000
2018
New
14.000
2018
New
22.000
2018
New
24.000
2018
New
4.000
2018
Expansion
24.000
2018
New
3.500
2018 Total
93.500
2019
New
4.100
2019
New
4.050
2019
Expansion
3.000
2019
Expansion
4.100
2019
Expansion
12.310
2019
Expansion
2.700
2019
New
5.370
2019
Expansion
1.200
2019
New
5.000
2019
New
37.787
2019 Total
79.617
2020
New
13.70
2020
New
0.10
2020
New
2.00
2020
New
71.80
2020
New
68.30
2020
New
48.00
2020
New
28.98
2020
New
16.00
2020
Expansion
5.00
2020
New
5.30
2020
New
4.00
2020
New
1.25
2020
New
12.29
2020
New
5.80
2020
New
11.25
2020
New
15.70
2020
New
7.70
2020
New
208.00
2020 Total
525.16
2021
New
108.00
2021
New
4.00
-
-
ICC Dkt Nos. 25-0677 / 25-0679 (Cons.)
NRG-ComEd 1.02_Attach 1
Page 1 of 3
2025LLT 0000008
Exhibit No. IA-1
Attachment 4
Page 2 of 4
PDF page 85
2021
New
250.00
2021
Expansion
10.00
2021
New
34.00
2021
New
3.00
2021
New
2.10
2021
New/Expansion
4.00
2021
New
24.00
2021
New
10.00
2021
New
24.00
2021
New
1.00
2021
New
6.50
2021
New
5.20
2021
New
8.00
2021
New
5.00
2021 Total
498.80
2022
New
24.00
2022
New
5.00
2022
New
120.00
2022
New
250.00
2022
Expansion
135.00
2022
New
2.00
2022
Expansion
92.00
2022
New
5.00
2022
New
3.00
2022
New
8.00
2022
New
2.00
2022
New
5.50
2022 Total
651.50
2023
New
612.00
2023
New
288.00
2023
New
378.00
2023
New
325.00
2023
New
7.00
2023
Expansion
24.00
2023
Expansion
12.00
2023
Expansion
11.00
2023
New
250.00
2023
New
135.00
2023
New
6.50
2023
New
110.00
2023
New
2.00
2023
New
12.00
-
-
ICC Dkt Nos. 25-0677 / 25-0679 (Cons.)
NRG-ComEd 1.02_Attach 1
Page 2 of 3
2025LLT 0000009
Exhibit No. IA-1
Attachment 4
Page 3 of 4
PDF page 86
2023
New
49.00
2023 Total
2221.50
2024
New
16.00
2024
New
1500.00
2024
New
45.00
2024
New
94.00
2024
New
587.00
2024
New
480.00
2024
New
350.00
2024
New
600.00
2024
Expansion
20.00
2024
Expansion
40.00
2024
Expansion
60.00
2024
New
10.00
2024
Expansion
25.00
2024
New
50.00
2024
New
54.00
2024 Total
3931.00
2025
New
600.00
2025
New
505.00
2025
Attraction
300.00
2025
Attraction
860.00
2025
Attraction
1000.00
2025
Attraction
750.00
2025
Attraction
1296.00
2025
Attraction
600.00
2025
Expansion
1870.00
2025
Attraction
431.00
2025
Attraction
54.00
2025
Attraction
41.00
2025 Total
8307.00
Grand Total
16308.08
-
-
ICC Dkt Nos. 25-0677 / 25-0679 (Cons.)
NRG-ComEd 1.02_Attach 1
Page 3 of 3
2025LLT 0000010
Exhibit No. IA-1
Attachment 4
Page 4 of 4