EL25-49-000 · 2026-03-25 · Eolian, L.P.Antora Energy LLCCalibrant Energy and 4 others

Reply Brief of Joint Co-Location Developers and Motion to Intervene Out-of-Time of Calibrant, Convergent, U.S. Energy Storage Coalition, and Versus

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)
Docket Nos. EL25-49-000
)

         EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)

         AD24-11-000
)
Constellation Energy Generation, LLC

)

         EL25-20-000
v.

)

         (Consolidated)
PJM Interconnection, L.L.C.

)

REPLY BRIEF OF JOINT CO-LOCATION DEVELOPERS AND MOTION TO
INTERVENE OUT-OF-TIME OF CALIBRANT, CONVERGENT, U.S. ENERGY
STORAGE COALITION, AND VERRUS

Pursuant to the Federal Energy Regulatory Commission’s (Commission) December 18, 2025 order (Co-Location Order),1 Eolian, L.P. (Eolian), Antora Energy, Inc., Calibrant Energy (Calibrant), Convergent Energy and Power (Convergent), Mainspring Energy, Inc. (Mainspring), U.S. Energy Storage Coalition, and Verrus, LLC (Verrus) (collectively, the Joint Co-Location Developers) submit this response to the Initial Briefs filed by PJM Interconnection, L.L.C. (PJM) and the Indicated PJM Transmission Owners (PJM TOs) on February 23, 2026. Pursuant to Rule 214 of the Commission Rules of Practice and Procedure,2 Calibrant, Convergent, U.S. Energy Storage Coalition, and Verrus also submit a motion to intervene out-of-time. The brief is supported by the affidavit of Andrew Levitt and Aniruddh Mohan of the Brattle Group on behalf of Eolian, at Attachment A.3

The Joint Co-location Developers believe in the promise of the Co-Location Order and would like to pursue business models based on the new services offered. We are deeply concerned, however, that PJM’s proposed transmission service provisions will render the new

1 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order).
2 18 C.F.R. § 385.214. 3 Attach. A, Affidavit if Andrew Levitt & Aniruddh Mohan on Behalf of Eolian, L.P. (Levitt & Mohan Aff.).

PDF page 2

2
transmission services commercially unworkable. We urge the Commission to require PJM to adopt transmission service terms that deliver on the promise of the Co-Location Order and enable customers to meet their commercial needs through co-location arrangements.

The Commission issued the Co-Location Order within the context of a broader national effort to confront the affordability, reliability, and speed-to-power challenges that rapid large load growth poses for the electricity system. The Co-Location Order promises to cut through those challenges by requiring PJM to make common-sense reforms, allowing Eligible Customers to take new “transmission services that reflect their actual impact on the transmission system” and thereby “avoid costly and inefficient transmission system buildout that may not be necessary.”4 As Commissioner Rosner summarized, the Commission’s goal was “to meet surging demand while upholding two fundamental values that underpin the electric industry in our country: first, that all customers have a right to receive electric service on a timely basis, and second, that electric service should be reliable and affordable for all customers.”5

The proposals in PJM’s Initial Brief fall short of fulfilling that promise. PJM departs from the requirements and spirit of the Co-Location Order again and again, rendering the new transmission services commercially unworkable. PJM’s response to the Commission’s demand for bold leadership largely amounts to a continuation of the “business-as-usual approach to load growth—planning for generation and load separately.”6 This “will not suffice to timely meet growing demand while also keeping prices reasonable.”7 PJM’s proposal would do little to improve reliability, avoid unnecessary infrastructure, and enable timely interconnection.

4 Co-Location Order, 193 FERC ¶ 61,217 at PP 160, 162.
5 Id. (Comm’r Rosner, concurring, at P 3).
6 Id.
7 Id.

PDF page 3

3
The Commission should reject PJM’s proposal and direct a replacement rate that delivers on the Co-Location Order’s promise. Most importantly, the Commission should direct PJM and the PJM TOs, as applicable, to make the following changes:

• Make Non-Firm Contract Demand Transmission Service (CDS) available as needed during normal operations, as the Co-Location Order required, rather than only during a generator outage, as PJM has proposed.

• Clarify that a Co-Located Load receiving Interim Network Integration Transmission Service (NITS) can take energy from its co-located generator during curtailment conditions.

• Clarify when and how Non-Firm CDS and Interim NITS will be curtailed.
• Clarify that charging of energy storage resources does not require transmission service, whether or not such resources are stand-alone resources or are part of a co-location configuration together with Co-Located Load, and as such charging of co-located storage does not apply toward customers a Non-Firm CDS customer’s Maximum Facility Output limitation.

• Offer a rate for Non-Firm CDS that reflects cost causation principles.
• Modify PJM’s draconian penalty proposal. Penalties are appropriate where a customer fails to respond to PJM’s curtailment instructions in a manner consistent with its service obligations. But penalties must balance the need to deter conduct that is harmful to the system with the need to limit excessive and unnecessary costs.

• Given the urgent need to address the impacts of load growth on the PJM system today, the Commission should require PJM to make the new tariff provisions related to the new transmission services effective sooner than June 1, 2029.

PDF page 4

4
I. JOINT CO-LOCATION DEVELOPERS’ INTEREST IN THE PROCEEDING
AND MOTION TO INTERVENE OUT-OF-TIME OF CALIBRANT, CONVERGENT,
U.S. STORAGE COALITION, AND VERRUS

Eolian develops energy generation and storage assets throughout the United States and has originated 27 GW of operating capacity to date. Eolian and its partners have developed projects supporting large loads in multiple regions across the United States, including PJM. Eolian expects to develop storage or generation assets co-located with loads. Antora is a U.S. manufacturer of thermal batteries, which are domestically built in San Jose, California, and developer of thermal storage projects for industrial facilities in the U.S. and abroad.

Calibrant develops energy generation and storage assets throughout the United States. Calibrant and its partners have developed and expect to continue to develop projects in PJM through a range of configurations, including behind-the-meter generation (BTMG) and co- located projects supporting large loads. Specifically, Calibrant has several existing BTMG projects and projects that are currently being developed worth millions of dollars that could be impacted by PJM’s proposed transmission service framework.

Convergent develops, owns, and operates distributed energy storage and storage plus solar resources for large commercial, industrial, and utility customers across North American markets, including PJM. Convergent has resources in operation and in development in PJM including behind-the-meter distribution and transmission connected battery energy storage systems, front-of-the-meter distribution connected battery energy storage systems, both with and without attached solar systems, and a 20 MW flywheel resource in Hazleton, Pennsylvania. Mainspring is a U.S.-headquartered manufacturer of modular, fuel-flexible, and dispatchable linear generators, a new type of power generator. Mainspring was founded in 2010

PDF page 5

5
and its first commercial units were deployed in 2020. The company has been rapidly scaling since 2023, deploying its innovative technology across a wide spectrum of customer types and use cases. The company’s customers include investor-owned utilities, public power utilities, municipal water treatment facilities, biogas facilities, data centers, grocery store chains, cold food storage, and hospital systems. Mainspring’s linear generators can be installed behind a customer’s utility meter or as a front of the meter grid asset. Mainspring linear generators are currently operating across multiple sites in PJM territory and are in development across additional sites.

The U.S. Energy Storage Coalition unites America’s leading grid battery manufacturers, energy storage developers, owners, and operators. The U.S. Energy Storage Coalition advances policies and solutions to ensure grid reliability amidst historic demand for power, lower energy costs for all Americans, strengthen grid capacity to support new industrial and AI infrastructure, and rapidly scale American manufacturing and minerals production.

Verrus is a developer, owner, and operator of a first-of-its-kind fleet of purpose-built, load-flexible hyperscale data centers. Verrus designs facilities from the ground up to function not only as digital infrastructure but also as grid assets—a new class of large customer capable of dynamically adjusting electricity consumption to support reliability, efficiency, and affordability. Verrus’ facilities can provide these system benefits without disrupting the critical computing workloads that increasingly underpin the modern economy. Each Verrus campus integrates on- site utility-scale battery energy storage, advanced load-management controls, and grid-aware automation that collectively enable real-time coordination with utilities and regional transmission operators.

PDF page 6

6
Joint Co-Location Developers therefore have a substantial interest in this proceeding that cannot be adequately represented by another party. The concerns that Joint Co-Location Developers raise will critically support development of Co-Located Loads and storage assets that avoid “costly and inefficient transmission system buildout.”8 Their participation is therefore in the public interest.

The Commission granted Eolian’s, Antora’s, and Mainspring’s motions to intervene at the show cause stage of this proceeding.9 Calibrant, Convergent, U.S. Energy Storage Coalition, and Verrus, however, move to intervene out-of-time for the first time here. These parties respectfully request that the Commission grant this request to intervene out-of-time.10 The posture of this proceeding has changed significantly with the Commission’s initiation of the paper hearing proceeding in a way that has crystalized these parties’ interest. These parties accept the record as it stands, and this intervention will not place any additional burden on any other party, nor will it disrupt or delay Commission proceedings in this matter, because the same brief is submitted by Eolian, Antora, and Mainspring, even absent these additional parties’ intervention.

II. ARGUMENT
A. The Co-Location Order requires that Non-Firm CDS be available as needed
during normal operations, not solely when a generator is on outage, as PJM has proposed.

PJM proposes to limit the availability of Non-Firm CDS to “the event the Co-Located Generating Facility is on outage and unable to provide any of the dedicated level of energy.”11 But the Co-Location Order made clear that Non-Firm CDS is to be available for reservation by

8 Id. P 177.
9 Id. P 157 & Appendix.
10 To the extent that the Commission denies these additional parties’ motion to intervene out-of-time, the remaining parties that are already parties submit this filing without the movants.
11 PJM Initial Brief, Illustrative Tariff, Part XI, Subpart B, § 709.2(b).

PDF page 7

7
an Eligible Customer “as needed during normal, non-emergency system operating conditions.”12 The Commission offered the scenario of a generator outage as an example of when an Eligible Customer might use Non-Firm CDS.13 But this was clearly just an example, not a limitation on the availability of the service. The Commission intended the service to function in a manner “similar to existing non-firm transmission service options in the Tariff,”14 which contain no such limitation.

Even if the Co-Location Order were unclear (which it is not), PJM has not offered an adequate rationale for limiting the availability of Non-Firm CDS to periods of generator outages.15 References to the “complexity” of providing Non-Firm CDS cannot overcome the benefits that Non-Firm CDS will create for PJM ratepayers and large load customers seeking timely interconnection.

1. PJM’s proposal is commercially unworkable.
As the Commission explained, the availability of Non-Firm CDS allows co-located resources that can control their withdrawals from the grid to interconnect in a manner that avoids unnecessary network upgrades and unnecessary procurement of capacity.16 Were PJM to follow through on the Commission’s order as drafted, it would enable a business model that has the potential to benefit ratepayers by increasing grid utilization while reducing or avoiding the cost of new infrastructure. Ensuring that Non-Firm CDS is available during non-emergency operating

12 Co-Location Order, 193 FERC ¶ 61,217 at P 215.
13 Id. P 214; see also id. (Comm’r Rosner, concurring, at P 6) (“The data center may instead elect to purchase Non- Firm Contract Demand Transmission Service if, for example, it only plans to pull energy from the grid temporarily while its co-located generator is undergoing scheduled maintenance.”). 14 Id. P 215.
15 In addition, PJM has not provided sufficient clarity on how outages are defined and whether they cover both planned and unexpected outages. If Non-Firm CDS must be reserved ahead of time, in practice Non-Firm CDS will only be useful in the event of planned outages or extended forced outages. See Attach. A, Levitt & Mohan Aff. at 6 n.4.
16 Co-Location Order, 193 FERC ¶ 61,217 at PP 162, 218.

PDF page 8

8
conditions would allow large loads to rely on generation and storage assets at the same point of interconnection to meet the loads’ needs based on grid economics, including the relative scarcity of energy during peak conditions as well as transmission congestion. While the large load customers would be responsible for ensuring that they have ample assets and load flexibility to curtail as necessary given potential constraints, the ability to rely on the system for significant periods of time would provide critical service necessary to reliably meet the load’s demand at reasonable cost while promoting the efficient utilization of existing transmission infrastructure consistent with economic dispatch and real-time system conditions.

PJM’s approach would instead require inefficient system operations. Limiting the availability of Non-Firm CDS will undermine economic efficiency by preventing Co-Located Loads from using grid power at times when wholesale energy prices are lower than the marginal cost of the co-located generator. Under PJM’s approach, a customer taking Non-Firm CDS would be required to dispatch on-site generation even during periods when LMP is negative. Use of as-available Non-Firm CDS would also allow a load relying on thermal resources to significantly decrease the number of starts required, considerably reducing reliability risks, as well as operations and maintenance needs.17 Ability to take non-firm service during non- emergency conditions is particularly critical to cost-effectively leveraging energy storage resources to serve the load, as Non-Firm CDS must be able to support load while storage is held in reserve for peak periods, is depleted, or is charging.18

17 See, e.g., Kumar et al., NREL, Power Plant Cycling Costs, at 45-46 (2012) (finding that more frequent cycling and higher ramp rates damages generation units, increasing the costs of operation).
18 See Attach. A, Levitt & Mohan Aff. at 7 (While “[b]attery storage provides particular value for co-locating with artificial intelligence data centers, given their ability to ramp instantaneously to match rapid changes in power demand for compute,” “PJM’s proposal to only allow load to reserve NFCDS during outages appears to be incompatible with co-located storage use cases, since storage is physically incapable of producing power at all times.”).

PDF page 9

9
This same dynamic holds true for other strategies a load customer may use to reduce reliance on the grid during critical periods, such as by modulating load. PJM’s proposed approach allows for no market-based response based on customers’ willingness to hold risk. In the Commission’s approach, by combining Non-Firm CDS with Firm CDS, customers may seek full redundancy with generation at the point of interconnection, no redundancy, or anywhere in between and tolerate curtailment risk up to the individual customer’s appetite. In PJM’s proposed approach, customers are bound to a specific level of redundancy, which will restrict competition and innovation.

In addition, PJM’s approach may inadvertently threaten reliability for other customers. PJM’s proposal to restrict Non-firm CDS to times when the co-located generator is on outage appears to be tailored to baseload resources. Given that it takes many years to develop new baseload resources, PJM’s proposal, to the extent it is workable at all, is most likely to be used by existing baseload resources (such as nuclear plants and gas-fired combined cycles), who may exit the market and enter into co-located arrangements with loads taking Non-Firm CDS.19 Finally, PJM’s filing is unclear whether customers may take Non-Firm CDS during partial outages.20 PJM’s brief states that a customer could take service “up to the MW level that the Co-Located Generating Facility is on outage,” suggesting that perhaps a partial outage is permissible.21 However, the illustrative tariff appears to require an all-or-nothing approach. The illustrative tariff indicates that Non-Firm CDS is available when the co-located generator is

19 Id. at 7-8.
20 Id. at 7 (noting that “generation facilities typically feature multiple units for economies of scale or other purposes” and that, accordingly, “physical outages would not typically cover all generation at the site, thus potentially precluding utilization of NFCDS entirely, despite potential efficiency benefits of broad availability of NFCDS”).
21 PJM Initial Brief at 32.

PDF page 10

10
“unable to provide any of the dedicated level of energy.”22 PJM should clarify this point. If PJM intends the illustrative tariff language to control, it should address the perverse incentives created by that rule, including the fact that this structure would encourage co-located generators to declare complete outages even when only a partial outage is necessary.

2. PJM’s approach is not necessary to maintain system reliability.
Restricting Non-Firm CDS to periods of generator outage is also unnecessary to maintain system reliability. To the contrary, PJM’s Interim NITS proposal demonstrates PJM’s ability to offer interruptible, non-firm service during normal conditions without the need to request reservation.23 Instead, rendering this service commercially unworkable will make it harder for new customers to connect to the system without overwhelming the grid. By stymying a Non- Firm CDS model that would encourage loads to bring their own capacity and reduce reliance on PJM system capacity, PJM’s approach would result in more loads following the status quo model that has strained PJM’s capacity market. Further, PJM’s approach could even prevent such loads from dispatching up when doing so would help to address a reliability challenge, such as when increasing consumption could mitigate a potential thermal overload on a transmission facility, or absorb excess reactive power to address high voltage conditions. In providing a service framework for dispatchable loads, PJM should leverage the capabilities of these loads to ensure system reliability. Given the fact that grid operators across the globe reliably count on energy storage resources to follow dispatch instructions, PJM does not adequately explain its reticence to rely on similarly-dispatchable loads.

22 Id., Illustrative Tariff, Part XI, Subpart B, § 709.2(b) (emphasis added). While PJM’s brief suggests that a customer could take service “up to the MW level that the Co-Located Generating Facility is on outage,” suggesting that perhaps a partial outage is permissible, the illustrative tariff language appears to require an all-or-nothing approach. PJM Initial Brief at 32.
23 See Attach. A, Levitt & Mohan Aff. at 8.

PDF page 11

11
We recommend that, in studying a request for Non-Firm CDS, PJM model the precise characteristics of the load and co-located generation, accounting for their proximity to one another, and appropriately accounting for generator outage and RAS or SPS contingencies.24 Such studies should model the load as dispatchable, examining transmission system limits and identifying transmission system conditions when Non-Firm CDS will not be made available.25 Those studies would impose limits on the use of Non-Firm CDS, but those limits need not be nearly so restrictive as the proposed limit to periods when the co-located generator is on outage. Rather, any operation restrictions would flow from system constraints. As discussed further below, similar to the study process it uses in providing for provisional interconnection service to generators, PJM can and should update such studies periodically, so as to ensure that such operating limits remain up to date.26

PJM’s position on Non-Firm CDS also does not square with its other service offerings. PJM already offers non-firm point-to-point service that is reservable whether or not the load has co-located generation, and whether or not any such generation is on outage. Like non-firm transmission service, Non-Firm CDS should be offered on an as-available basis, to be reserved on an hourly, daily, or (rolling) monthly basis. Further, PJM plans to offer non-firm Interim NITS on an as-available basis, demonstrating that it can provide for a reliable service framework that provides non-firm service during normal operating conditions.27

24 See id. § V.D (providing recommendations regarding PJM’s study processes for co-located load and generation).
25 Id. at 19.
26 See infra n.33.The Commission should encourage PJM, in carrying out such studies, to publish analysis of anticipated curtailment, based on historical data and projections accounting for system resources and infrastructure. Such analysis, if made available to prospective CDS customers when they apply for service, will inform their choice in CDS service and enhance the commercial workability of the services framework the Commission has required to facilitate speed to power while protecting existing customers.
27 See Attach. A, Levitt & Mohan Aff. at 8.

PDF page 12

12
If anything, Non-Firm CDS can more readily be offered during normal conditions than Interim NITS, because the service structure behind Non-Firm CDS allows for day-ahead reservation. As discussed in the affidavit of Levitt et al., Non-Firm CDS is granted based on both studies for interconnection, and day-ahead reservation review by PJM.28 Under this structure, PJM could provide for Non-Firm CDS to be available during normal operating conditions subject to any reservation limits identified in the interconnection study, while denying reservations to the extent that its day-ahead predictions demonstrate a particular hour (or day) to approach transmission system limits.29

Any SPS or RAS would operate only after these mechanisms are put in place, to ensure that the load does not show up on the grid unexpectedly. For example, PJM’s Matthew Wharton provides that “PJM would expect the RAS to actuate on the loss of the Co-Located Generating Facility” such that “the load served by Non-Firm Contract Demand Transmission Service or Interim NITS will automatically be removed from the system by the RAS scheme.”30 Thus, while SPS and RAS “should not be installed as a substitute for good system design or operating practices,”31 that would not be the case here were PJM to enable Non-Firm CDS across a broader range of circumstances. As with other services, RAS or SPS would operate only as a fail-safe backup after PJM’s planning measures and dispatch process provide for curtailment to the extent the transmission system is constrained.

Dr. Abdulsalam draws a distinction between Interim NITS and Non-Firm CDS in
highlighting the temporary nature of Interim NITS service, and explaining that system conditions

28 Id. at 8.
29 Id. at 8-9.
30 PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), at P 25. 31 Id. P 16.

PDF page 13

13
may change over time.32 But that distinction does not justify restrictions on Non-Firm CDS. Instead, PJM should update the operating conditions framework for Non-Firm CDS periodically as part of its transmission system planning process.33 Much as provisional service provides a generator with operating conditions under which it is allowed to discharge into the system, these studies will provide the baseline operating conditions pursuant to which a load taking Non-Firm CDS can expect to withdraw from the system.34 Those conditions should be built into the PJM operations framework, with the applicable RAS and/or SPS provided by such resource layering onto this service framework as a fail-safe to ensure reliability. While any SPS or RAS would not be the first line of defense in ensuring PJM’s reliability, we note that RASs can operate reliably and are used far more extensively by some grid operators.35 Under PJM’s tariff proposal “each and every Service Agreement for” Non-Firm CDS will “include the necessary control technologies and protection systems to ensure the reliability and stability of PJM’s Transmission System.”36

B. PJM should clarify that its transmission service requirements for energy
storage charging apply equally to storage co-located with load, and exempt
customers from the Maximum Facility Output where the customer’s load shape and characteristics are inherently flexible.

PJM studies the charging of energy storage resources through its generator
interconnection process.37 It does not require energy storage resources to take transmission service for charging, except where the storage charges during the zonal peak hour without being dispatched.38 As applied here in conjunction with the Maximum Facility Output (MFO)

32 PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), at P 10.
33 Attach. A, Levitt & Mohan Aff. at 19.
34 Id.
35 See id. § V.F.
36 PJM Initial Brief at 35.
37 Attach. A, Levitt & Mohan Aff. at 19.
38 Id.

PDF page 14

14
requirement for Non-Firm CDS to Co-Located Loads,39 and consistent with the position that PJM has taken in response to stakeholder questions,40 this service framework appears to allow the relevant Co-Located Load to take service while the co-located energy storage resource charges. However, PJM should clarify this point in its tariff, to avoid any implication that the MFO requirement prohibits such activity, which necessarily entails total combined withdrawals at the Point of Interconnection from the relevant storage resource and Co-Located Load in excess of the MFO. PJM should clarify that co-located charging loads, like standalone energy storage resources, do not require transmission service unless they charge during the zonal peak hour without being dispatched,41 and that any withdrawals for energy storage charging at the Point of Interconnection for which transmission service is not required do not count toward the MFO. In the alternative, the Commission should direct PJM to remove the MFO limit for loads co-located with energy storage resources.

PJM proposes to include a 100% MFO limit because “foreseeable conditions where the Co-Located Load is expected to withdraw power from the PJM network” will “only materialize if the generator is planned to go out of service or face operating conditions requiring its output to be derated for a relatively short timeframe,” and “[s]uch flexibility and conditions in operation can only exist if the non-firm load size can be served fully through the co-located generator (i.e., the generator is at least 100% of the non-firm load size).”42

39 PJM proposes to limit Non-Firm CDS to 100% of Maximum Facility Output (MFO) of the co-located generator. See PJM Initial Brief, Illustrative Tariff, Part XI, Subpart B, § 709.2(b) (“An Eligible Customer taking service on behalf of a Co-Located Load must apply for Non-Firm Contract Demand Transmission Service equivalent to the megawatt level of the Co-Located Generating Facility dedicated to serving the Co-Located Load.”); see also PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), at PP 13-17.
40 PJM indicated in response to a stakeholder question that charging energy would not count against a load customer’s Firm CDS.
41 See Attach. A, Levitt & Mohan Aff. at 19.
42 PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), at P 15.

PDF page 15

15
As applied to co-location configurations involving energy storage resources, this rationale only holds true to the extent that PJM clarifies (1) that charging of the co-located energy storage resource can take place without taking transmission service,43 and (2) that the limit is measured by the resource’s nameplate capacity.44 As Andrew Levitt and Anirrudh Mohan explain, PJM

should clarify that “even if a co-located facility has 0 MW of Firm CDS and 0 MW of Non-Firm CDS, a co-located storage component that has been granted an Interconnection Service

Agreement recognizing its ability to withdraw from the grid for charging may still do so as dispatched by PJM, consistent with a standalone storage facility.”45

Further, even with this clarification, PJM’s MFO limit should also not apply to inherently flexible loads that operate at low load factors, such as thermal energy storage. Such loads would not anticipate taking transmission service on an 8760 basis like many other large loads (thermal energy storage can provide 24/7 thermal output with a load factor of only 33%) and instead would plan to charge only when prices are very low at the point of delivery, because generation from low or zero marginal cost generators exceeds local demand.46 To the extent PJM is

concerned that variable transmission usage above MFO would create unmanageable scheduling

43 As Andrew Levitt and Aniruddh Mohan explain, “Storage charging in PJM does not take transmission service unless it charges during the zonal peak hour without being dispatched, in which case it is a Network Load taking NITS.” Attach. A, Levitt & Mohan Aff. at 19. However, clarification is necessary to confirm that this holds true in the context of energy storage resources that are co-located with load. PJM stated in response to a stakeholder inquiry that energy storage charging shall not count against a customer’s Firm CDS, suggesting that the same holds true with regard to Non-Firm CDS; however, the tariff should clarify that energy storage charging in a co-located configuration does not require transmission service.
44 PJM defines Maximum Facility Output as “the maximum (not nominal) net electrical power output in megawatts, specified in the Interconnection Service Agreement, after supply of any parasitic or host facility loads, that a Generation Interconnection Customer’s Customer Facility is expected to produce, provided that the specified Maximum Facility Output shall not exceed the output of the proposed Customer Facility that Transmission Provider utilized in the System Impact Study.” PJM, Intra-PJM Tariffs, L-M-N, OATT Definitions - L - M - N (41.1.1). While measuring the net electrical power output in megawatts makes sense, that amount may not correspond to the resource’s injection rights enshrined in the interconnection agreement. PJM should clarify that they refer to the technical output capability and not injection rights.
45 Attach. A, Levitt & Mohan Aff. at 20.
46 See Antora Energy LLC, Motion to Intervene and Comments, Docket Nos. EL25-49-000, EL25-20-000, & AD24- 11-000, at 4 (filed Apr. 23, 2025).

PDF page 16

16
or dispatch complexity, that concern can be addressed through tariff design rather than a blanket capacity cap. Specifically, PJM could require Co-Located Loads seeking Non-Firm CDS above MFO to submit day-ahead or hour-ahead transmission schedules for the incremental withdrawal, subject to curtailment that reduces withdrawals to MFO. This approach gives PJM advanced visibility into expected transmission usage, preserves its ability to curtail in real time, and avoids the need to plan or construct any incremental infrastructure. It is also workable in practice as expected withdrawals above MFO would occur predominantly during off-peak hours—precisely the conditions under which non-firm transmission capacity is most likely to be available. Similarly, if an inherently flexible large load such as a thermal energy storage resource is co-located with a generator with an MFO less than its full system draw, such a load would not plan to use the transmission system 100% of the time for the load above the generator MFO. Rather, both of these Co-Located Loads could demonstrate that they are “willing and able” to “reduce their withdrawal from the system . . . without (i) compromising the level of reliability to firm loads, or (ii) over utilizing their non-firm contract arrangements at the cost of firm service ratepayers.”47 In both cases, the customers could reliably curtail as necessary. Because firm customers would retain priority and because PJM would not plan any additional infrastructure to accommodate such customers, they would not impose costs on firm customers. In fact, such customers would be expected to reduce total system costs for firm customers because PJM TOs would collect new revenues for the non-firm service customers without building any new infrastructure to accommodate them. Flexible loads can also reduce curtailment and generator ramping and relieve transmission congestion by increasing consumption to absorb low value hours of generation when local generation exceeds local demand. Accordingly, PJM should

47 PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), at P 17.

PDF page 17

17
remove the MFO limit for loads co-located with energy storage resources, or, in the alternative, clarify that charging loads will not count toward the MFO limits.

C. PJM’s tariff should clarify when and how Non-Firm CDS and Interim NITS
will be curtailed.

PJM’s proposed tariff does not provide adequate clarity regarding when and how Non- Firm CDS and Interim NITS shall be curtailed. With regard to both services, the proposed tariff language specifies only that PJM “may curtail [such service] prior to dispatching the Pre- Emergency Load Response Program as further set forth in the PJM Manuals, or in response to a transfer capability shortage as a result of system reliability conditions.”48 While this language provides that the service will be curtailed before other procedures are drawn upon, it does not affirmatively state what the curtailment trigger shall be. This open-ended process, which theoretically allows PJM to curtail such services at any time, does not provide resource developers with sufficient certainty to understand their obligations and enter into commercial arrangements based on those obligations. At minimum, PJM must provide a book-end that allows customers taking Non-Firm CDS or Interim NITS to understand the earliest point at which they might be curtailed. Further, PJM does not clarify whether and how it will determine curtailment priority among its different classes of non-firm service: Non-Firm Point-to-Point, Non-Firm CDS, and Interim NITS, or whether such customers are accorded equal curtailment priority. Because the curtailment trigger for Non-Firm CDS and Interim NITS and curtailment priority order of those services “affect rates and service significantly,” and “are realistically susceptible of specification,” they must be included in the tariff.49

48 PJM Initial Brief, Illustrative Tariff, Part XI, Subpart B, § 705.2 & Subpart C, § 713.4
49 City and County of San Francisco v. FERC, 24 F. 4th 652, 661 (D.C. Cir. 2022) (citations omitted).

PDF page 18

18
D. PJM’s tariff should clarify that a Co-Located Load receiving Interim NITS can take energy from its co-located generator during curtailment conditions.

While the illustrative tariff is not explicit on this point, PJM stated in stakeholder meeting materials that it may prohibit Co-Located Loads taking Interim NITS from being served by co- located generators during curtailment periods. Such a requirement, if implemented, would be expressly contrary to the Co-Location Order, would serve no clear purpose, and would significantly degrade the value of Interim NITS. The Joint Co-Location Developers ask PJM to clarify that it does not plan to limit Co-Located Loads taking Interim NITS in this way, and instead intends to allow them to be served by co-located generators during curtailment conditions.

To the extent that PJM does intend to limit Co-Located Loads taking Interim NITS’ abilities to be served by co-located generators, the Commission must not adopt it. The Commission in the Co-Location Order expressly stated that “when curtailed, Eligible Customers taking [Interim NITS] on behalf of Co-Located Loads may be able to continue to take energy from the Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”50

In addition, such a limitation threatens to render Interim NITS commercially unusable.51 Limiting service from co-located generators would require Co-Located Loads to curtail even when the co-located generation facility is physically available, thereby preventing the large load from relying on Interim NITS as a flexible bridge between reliance on co-located resources and eventual permanent NITS service and denying loads the benefit of any resource adequacy value from their co-located generation.52 As a result, under PJM’s potential proposal, utilizing Interim

50 Co-Location Order, 193 FERC ¶ 61,217 at P 201.
51 See Attach. A, Levitt & Mohan Aff. at 10-12.
52 See id. at 11.

PDF page 19

19
NITS would fail to support the operational flexibility that forms a central premise of the Co- Location Order. Instead, customers would be required to procure additional transmissions services in conjunction with Interim NITS to maintain continuity of operations, undermining the commercial viability of Interim NITS as a stand-alone service. Such an outcome would be inconsistent with both the letter and the spirit of the Commission’s Co-Location Order. Allowing co-located generation to serve Co-Located Load during curtailment also reflects sound operational principles. During curtailment conditions, reliance on co-located resources reduces dependence on constrained transmission facilities by allowing energy to serve load locally rather than requiring it to be delivered across constrained portions of the grid. While PJM may seek to preserve access to co-located generation as a potential system resource during tight conditions, doing so does not justify requiring curtailment of load that can instead be served locally without increasing reliance on the transmission system.53 To the contrary, permitting co- located generation to continue serving its associated load during curtailment conditions supports more efficient use of the transmission system while preserving reliability. Prohibiting such behavior would instead force unnecessary curtailment of load even when local generation is physically available and capable of serving it, producing outcomes that are inconsistent with the purpose of Interim NITS.

PJM offers no rationale to justify the potential limitation. As long as co-located generators are not capacity resources, they should be free to serve Co-Located Loads during curtailment conditions.54

53 PJM’s proposal could even create the perverse result of encouraging co-located generation to forego interconnection entirely, such that it would be available to a Co-Located Load taking Interim NITS in the event of a PJM imposed curtailment. This would deprive the PJM system of the resource’s value at times when it is not needed to serve the Co-Located Load.
54 Attach. A, Levitt & Mohan Aff. at 13-14.

PDF page 20

20
E. PJM TOs have not justified charging the same rate for Non-Firm CDS and
Firm CDS.

The PJM TOs propose that “the Non-Firm Contract Demand Service rate will be computed in the same manner as the Firm Contract Demand Service rate.”55 Pricing Non-Firm CDS at the same rate as Firm CDS is neither consistent with the cost causation principle nor the Commission’s purpose, in establishing Non-Firm CDS, of creating a pathway to market that would avoid “costly and inefficient transmission system buildout that may not be necessary if such Eligible Customers are willing and able to take a transmission service that requires fewer Network Upgrades to provide.”56 The Commission should instead require the PJM TOs to set Non-Firm CDS rates that reflect the lesser costs that customers taking Non-Firm CDS impose on the grid.

PJM TOs’ proposed Non-Firm CDS rate is inconsistent with cost causation because it does not reflect the lesser costs caused by customers taking Non-Firm CDS nor the lesser benefits that such customers receive.57 PJM TOs’ justification for charging the NITS rate for Firm CDS implicitly demonstrates the need to charge a lower rate for Non-Firm CDS than Firm CDS. The PJM TOs explain that “[b]oth NITS and Firm Contract Demand Service are firm services for which network upgrades will be planned and constructed as necessary, with the only difference being that upgrades for NITS customers are identified based on existing and anticipated load growth while upgrades for Firm Contract Demand Service customers will be identified based on their contracted demand level.”58 PJM TOs note that “[b]ecause NITS and

55 PJM TOs Initial Brief at 10-11.
56 Co-Location Order, 193 FERC ¶ 61,217 at P 177.
57 Illinois Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).
58 PJM TOs Initial Brief at 8.

PDF page 21

21
Firm Contract Demand customers receive comparable benefits, using the same rate for NITS and Firm Contract Demand Service is consistent with the Commission’s cost allocation principles.”59 Applying this logic to Non-Firm CDS should result in a different, lower rate. Non-Firm CDS is not a firm service, Non-Firm CDS customers do not receive comparable benefits to NITS/Firm CDS customers, and the Transmission Provider will not plan and construct network upgrades to ensure the ability to provide firm service to Non-Firm CDS customers. Using the same NITS/Firm CDS rate for Non-Firm CDS is therefore not consistent with the Commission’s cost allocation principles. Rather, the cost causation principle requires discounting Non-Firm CDS relative to Firm CDS to reflect the lower transmission system costs that Non-Firm CDS customers cause, and the lesser benefit that Non-Firm CDS customers receive from a transmission system built to ensure that firm but not non-firm customers receive firm service. The PJM TOs argue that they cannot commit to offer discounts at this time because they assert that, “[b]efore determining whether a discount is appropriate for Non-Firm Contract Demand Service, and if so what level it should be set at, it is necessary for the PJM TOs to gather data on how Non-Firm Contract Demand Service customers are utilizing the service, taking into account the intended purpose of the service, and the effect of that utilization on the system.”60 But while this may be reasonable with respect to customers who schedule Non-Firm CDS but do not commit to limit its use to a certain level and who maintain the ability to draw Firm CDS or to switch to NITs, PJM TOs can have confidence today that customers who commit to using Non-Firm CDS will require fewer network upgrades.

59 Id.
60 Id. at 13.

PDF page 22

22
PJM TOs are correct that, under Order No. 888, transmission providers may charge up to the firm transmission rate for non-firm transmission service.61 In Order No. 888-A, however, the Commission clarified that “non-firm transmission prices should reflect the interruptibility of the service and should promote efficient use of the transmission system.”62 Accordingly, the Commission explained that, “while in some circumstances non-firm transmission rates may be set at the firm transmission rate level, the Commission expects that non-firm transmission rates would, in most instances, be priced below the price cap.”63 PJM TOs have not demonstrated that its proposed rates for Non-Firm CDS reflect the interruptibility of the service and promote efficient use of the transmission system—which they do not.

The PJM TOs’ proposed rate would also discourage productive industrial development, if adopted. Certain use cases for Non-Firm CDS rely on pricing that reflects the Commission’s cost causation principles. For example, to be cost competitive in serving the thermal demands of industrial customers, thermal energy storage resources must be able to take power when low-cost supply is available because low and zero marginal cost generation availability exceeds local demand (often because the generation faces congestion to reach other loads), at prices that reflect the lower cost of electricity and transmission service during such conditions. Thermal energy storage penetration can be expected to grow significantly where grid operators offer such service, supporting economic development from industrial uses that have significant thermal energy

61 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, 31,780 (1996) (cross-referenced at 75 FERC ¶ 61,080), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
62 Order No. 881-A, at 30,272.
63 Id.; see also Transmission Access Policy Study Group v. FERC, 225 F.3d at 731 (“In most cases, FERC expects that non-firm transmission rates will be priced below the firm rate.”).

PDF page 23

23
needs. Where non-firm service costs are higher than true system costs, such development will be stymied, inhibiting economic growth.

F. PJM’s proposed penalty provisions are unjust and unreasonable.
PJM proposes a draconian penalty structure that threatens to effectively deny customers service after a single failure to curtail or shed load, regardless of the cause. This penalty scheme is not “narrowly designed to balance the need to deter conduct that is harmful to the system with the need to limit excessive and unnecessary costs.”64 Instead, the Commission should adopt financial penalties as a replacement rate. In addition to relying on penalties in order to ensure that customers follow its dispatch instructions, transmission owners can manually disconnect a facility in case of potential severe reliability risk.65

PJM proposes to (1) disqualify customers who take more transmission service than they have contracted for from taking Contract Demand Transmission Service and/or Interim NITS according to “a strict liability rule that automatically applies after being triggered by one instance” of failure to curtail;66 (2) pause new transmission service availability for up to 120 days upon the first misoperation of a control technology or protection system scheme and disqualify Eligible Customers after a second misoperation;67 and (3) levy additional financial penalties for unreserved use to be explored with the PJM TOs in the future.68

Like many of the proposals discussed above, requiring an Eligible Customer to take NITS in order to continue to be served after a single unauthorized withdrawal regardless of fault

64 Mirant Kendall, LLC & Mirant Americas Energy Mktg., L.P., 110 FERC ¶ 61,272, at P 17 (2005).
65 See Attach. A, Levitt & Mohan Aff. at 16.
66 PJM Initial Brief at 41-43.
67 Id. at 43-46.
68 Id. at 50.

PDF page 24

24
threatens the commercial workability of the new transmission services.69 For customers taking Interim NITS, PJM’s proposed disqualification rules would require the Co-Located Load to cease operations while it awaits the completion of network upgrades. Ceasing operations would expose such a customer to breach of its contractual obligations while stranding hardware investments that may quickly become obsolete while the customer waits for network upgrades to be completed. And for customers taking CDS, being forced onto NITS (or Interim NITS, as applicable) could permanently undermine the commercial case behind investments made for purposes of enabling CDS (and reduced transmission reservations). The risk of such a result, especially to the extent that it could occur without fault or an ability to prevent the triggering failure, will dissuade Eligible Customers that otherwise would take the new transmission services from doing so.

As an initial matter, it is not clear that PJM’s disqualification-based penalty scheme is necessary at all, let alone “narrowly designed to balance the need to deter conduct that is harmful to the system with the need to limit excessive and unnecessary costs.”70 Transmission owners always have the ability to manually disconnect a facility in case of potential severe reliability risk.71 The threat of an extreme penalty like disqualification, especially on a strict liability basis, is therefore not needed to protect system reliability. It is also not commensurate with the penalty levied on generators that fail to curtail when ordered under similar circumstances.72 Instead, PJM

69 While PJM proposes to allow customers taking CDS to take Interim NITS in addition to NITS after a single unauthorized withdrawal, Interim NITS is only available on a temporary basis “until such time as the Network Upgrades necessary to provide NITS are complete.” PJM Initial Brief at 67-68. Many customers taking CDS will therefore be ineligible to take Interim NITS and be forced to take NITS to the extent that they are waiting for Network Upgrades to be completed. Those customers that are eligible to take Interim NITS will be required to take NITS upon completion of the relevant Network Upgrades. Those customers would also become ineligible to continue to take Interim NITS upon a subsequent unauthorized withdrawal.
70 Mirant Kendall, LLC & Mirant Americas Energy Mktg., L.P., 110 FERC ¶ 61,272 at P 17.
71 See Attach. A, Levitt & Mohan Aff. at 16.
72 Id. at 16-17 (noting also that “there appears to be no such systematic penalty on generators, although arguably there should be”).

PDF page 25

25
should adopt financial penalties sufficient to deter intentional gaming of transmission service subscription.

Meanwhile, disqualification is wildly disproportionate to the harm caused by
unauthorized withdrawal during resource adequacy-related curtailment events. From a resource adequacy perspective, failure to respond to a Load Shedding or Curtailment procedure would have a similar impact to a capacity resource failing to perform during emergency events. PJM already has a Commission-approved penalty in place to deter such an outcome: the Non- Performance Charge rate assessed to Capacity Resources that underperform during

a Performance Assessment Interval (PAI). A similar or equivalent financial penalty would be appropriate and sufficient in this context too.73 As Levitt & Mohan explain, the lost opportunity cost of shutting down a 1,000 MW data center could be three orders of magnitude higher than the equivalent Non-Performance Charge penalty for failure to curtail.74

If the Commission decides to adopt PJM’s proposal to penalize unauthorized withdrawals with disqualification, it should adopt intent (or at least fault), materiality, and repetition elements prior to disqualification. As proposed, and because PJM’s curtailment protocols allow PJM complete discretion to call curtailment events across an unpredictable range of circumstances and with as little notice as PJM deems “practicable,”75 PJM’s strict liability rule could cause an Eligible Customer to be denied future service for responding 30 seconds late to an instantaneous instruction, regardless of the cause or whether another party is at fault. And, as discussed above,

73 Id. at 15.
74 Id. at 16 (explaining that a 1,000 MW data center might cost $40 billion and provide a gross revenue of several billion dollars per year, while the PAI penalty for a 1,000 MW failure to curtail for one hour would be roughly $3 million.). 75 See PJM Initial Brief, Illustrative Tariff, Part XI, Subpart A, § 705.4 & Subpart B, § 713.5 (e.g., in relation to “making necessary adjustments to, changes in, or repairs on its lines, substations, and facilities, and in cases where the continuance of . . . [the transmission service] . . . would endanger persons or property”).

PDF page 26

26
transmission owners’ abilities to manually disconnect a facility in case of severe reliability risk76 defangs any possible justification for PJM’s proposed strict liability regime falling entirely on the Eligible Customer. Absent fault or materiality, and given the breadth of circumstances under which PJM could direct curtailment, it is not clear that the disqualification penalty sends a “signal[]” that is “actionable,” and therefore may “only result in higher costs to ratepayers”— who will share in the cost of transmission infrastructure that will need to be built to provide NITS—“without a commensurate benefit.”77 Especially when coupled with whatever financial penalties PJM and the PJM TOs ultimately adopt, which themselves could be sufficient to deter harmful conduct,78 this penalty scheme is excessive, draconian, expensive, and not just and reasonable.

These arguments apply with equal force to PJM’s proposal to disqualify Eligible Customers whose control technologies or protection system schemes misoperate for a second time.79 Disqualification is not needed to deter harmful conduct, is disproportionate given absence of fault or materiality elements and availability of financial penalties, and threatens the ability of private developers to finance projects that rely on the new transmission services the Commission required in the Co-Location Order. Disqualification for misoperation of control technologies or protection system schemes absent unauthorized withdrawal is arguably even more excessive, despite the two strikes policy PJM proposes, because misoperation without withdrawal does not in and of itself risk system harm. This proposal is unjust and unreasonable because it is “not

76 Attach. A, Levitt & Mohan Aff. at 16.
77 PJM Interconnection, L.L.C., 178 FERC ¶ 61,104, at PP 60-61 (2022).
78 Notably, the Commission and NERC regularly rely on the deterrent effect of financial penalties across a range of violations, including violations of the reliability standards involving severe risks.
79 PJM Initial Brief at 43-46.

PDF page 27

27
commensurate with any potential damage caused by the inadvertent errors which [are] de minimus,” especially if “properly reported upon discovery, and promptly fixed.”80 PJM’s proposed disqualification-based penalties are therefore not just and reasonable and should not be adopted by the Commission. Instead, the Commission should direct PJM to adopt a penalty scheme that: (1) penalizes failure to respond to resource adequacy-related curtailment instructions at the Non-Performance Charge rate assessed to Capacity Resources that underperform during a  PAI; (2) penalizes failure to respond to transmission security-related curtailment instructions with financial penalties sufficient to deter intentional gaming of transmission service subscription, or, in the alternative, with disqualification only when intentional (or at least negligent), material, and/or repeated;81 and (3) suspends service where unauthorized withdrawals reveal control technology or protection system deficiencies until those systems can be re-tested and re-certified up to 120 days.

G. PJM’s proposed effective date of June 2029 is unjust and unreasonable.
The Commission in the Co-Location Order reflected the urgent need to address resource adequacy challenges in PJM.82 In light of that urgency, the Commission should not leave the rates that it found unjust and unreasonable in the Co-Location Order in place for more than three more years. Instead, the Commission should require that (1) the Firm CDS be available within six months of an order accepting PJM’s transmission service compliance filing, and (2) the Non-

80 Direct Energy Bus., LLC, 186 FERC ¶ 61,228, at P 15 (2024); see also Idaho Power Co., 186 FERC ¶ 61,231, at P 26 (2024); Bp Energy Retail Co. California LLC, 190 FERC ¶ 61,127, at P 16 (2025); Tucson Elec. Power Co., 188 FERC ¶ 61,207, at P 22 (2024).
81 The Commission could also consider time-limiting disqualification to a specified term rather than making it permanent, if it chooses to adopt a disqualification-based penalty scheme.
82 See Co-Location Order, 193 FERC ¶ 61,217 (Comm’r Rosner, concurring, at PP 3 ( “a business-as-usual approach to load growth . . . will not suffice to timely meet growing demand while keeping prices reasonable.”) & 12 (“the solutions enabled by both [the Co-Location Order] and PJM’s ongoing initiatives to accelerate new generation are immensely important and urgent.”).

PDF page 28

28
Firm CDS and Interim NITS services be available at the earliest date technically feasible, accounting for the urgency and importance of their availability.

PJM principally justifies its proposed June 1, 2029 effective date on the assertion that three years of lead time is necessary to “integrate these transmission services into PJM’s capacity market . . . so that PJM can procure capacity for those that are capacity-backed (e.g., Firm Contract Demand Transmission Service).”83 This explanation provides no reason to delay the availability of Non-Firm CDS or Interim NITS, which are not capacity-backed.84 Nor does it offer a compelling reason to delay Firm CDS—which is likely to present nearly identical capacity requirements as NITS. PJM does not explain why a customer taking NITS would be reflected in its capacity market demand forecast but a customer taking Firm CDS would not. Nor does PJM explain why an Eligible Customer should not be allowed to transition in the immediate term from NITS to Firm CDS, which would, if anything, have a lesser resource adequacy impact. In fact, because Firm CDS enables customers to reduce their impact on resource adequacy, and co-located generation to potentially offer capacity into the market, making Firm CDS available more immediately can serve to help address PJM’s immediate capacity shortage.85 To the extent that PJM’s concern stems from a potential planning need associated with existing capacity resources de-registering to provide service to Co-Located Loads that take Non-Firm CDS or a lesser amount of Firm CDS, then PJM should propose a delayed implementation limited to those particular use cases, while allowing faster implementation for customers using new generation or resources not currently participating in the capacity market.86

83 PJM Initial Brief at 79.
84 See Attach. A, Levitt & Mohan Aff. at 20.
85 See id.; see also PJM, 2027/2028 Base Residual Auction Reserve Target Shortfall Report, at 1-2 (Feb. 9, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-reserve- target-shortfall-report.pdf (explaining that PJM’s Base Residual Auction for the 2027/2028 Delivery Year cleared 6,517 MW short of the Installed Reserve Margin).
86 See Attach. A, Levitt & Mohan Aff. at 21.

PDF page 29

29
PJM also argues that it needs until June 2029 to “make the necessary modifications to the PJM core Markets and Operations systems.”87 PJM claims that “implementing the proposed Curtailment priorities applicable to Interim NITS and Non-Firm Contract Demand Transmission Services,” “[i]n particular,” “will require PJM to work with vendors to develop system automation that will avoid non-optimal, untimely, and inefficient outcomes.”88 Again, this explanation is incomplete on its own terms, and does not address at all why additional software must be developed to provide Firm CDS to customers in a manner that is similar to providing NITS to a smaller customer. In addition, neither PJM’s brief nor the supporting testimony specifically support its claim that the software changes will require three years specifically to implement.

This silence is notable given evidence that curtailable products can be implemented in other context on much faster timelines. PJM has announced, for example, that it plans to adopt and implement by the end of 2026 a “Connect and Manage” proposal under which certain new loads in regions experiencing shortfalls would be curtailed prior to the deployment of pre- emergency Demand Response89—i.e., in a manner similar to resource adequacy-related curtailment instructions for Non-Firm CDS or Interim NITS. Similarly, just two weeks before PJM filed its Initial Brief, SPP proposed to offer Conditional High Impact Large Load Service similar in critical components (including curtailment requirements) to the non-firm conditional transmission services at issue here effective on July 1, 2026—nearly three full years before the effective date proposed by PJM.90 It is not clear why PJM will be able to implement its Connect

87 PJM Initial Brief at 79.
88 Id. at 81. 89 See PJM, Board Decisional Letter on Critical Issue Fast Path – Large Load Additions, at 4, 8 (Jan. 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter- re-results-of-the-cifp-process-large-load-additions.pdf.
90 SPP, Filing, Docket No. ER26-1323-000, at 1-2 (filed Feb. 10, 2026).

PDF page 30

30
and Manage proposal and SPP will be able to make non-firm conditional transmission service available this year while PJM claims to need 40 months to implement the new transmission services at issue in this proceeding. In addition, Mr. Levitt and Dr. Mohan note in the attached testimony that leveraging price responsive demand modifications to security constrained economic dispatch (SCED) could allow PJM to faster implement any SCED changes for non- firm loads.91

Finally, PJM posits that, because generation intended to serve Co-Located Loads is unlikely to be operational before June 1, 2029, its proposed effective date “will not be a limiting factor.”92 To the contrary, there are likely to be projects in development in a position to avail themselves of these new services—particularly those using energy storage systems. The Commission should therefore reject PJM’s proposed effective date, and direct PJM to propose an effective date that is as early as technically feasible for each individual transmission service offered. For Firm CDS, which is unlikely to require software updates, the Commission should direct an effective date within six months of an order accepting PJM’s compliance filing to establish the service. For Non-Firm CDS and Interim NITS, the Commission should direct PJM to adopt an effective date as soon as practicable, based on a detailed projection of project schedule components, moving with urgency.

III. CONCLUSION
The PJM region faces significant challenges. Addressing those challenges will require leadership. The Commission demonstrated that leadership in issuing the Co-Location Order, breaking from a “business-as-usual approach” to “help[] break the logjam.”93 PJM’s and the PJM

91 Attach. A, Levitt & Mohan Aff. at 21-22.
92 PJM Initial Brief at 82.
93 Co-Location Order, 193 FERC ¶ 61,217 (Comm’r Rosner, concurring, at P 4).

PDF page 31

31
TOs’ initial briefs, however, do not match the Commission’s leadership in the Co-Location Order. Rather, they propose the minimum possible ambition to offer non-firm and contract transmission services after letting the problems plaguing the PJM system worsen for several years. The Commission should not allow this attempt to water down the Co-Location Order, which would prevent it from realizing its goals. Rather, the Commission should direct PJM to timely implement commercially workable Firm CDS, Non-Firm CDS, and Interim NITS as contemplated in the Co-Location Order. Anything less will fail to meet this critical moment.

Respectfully submitted,
/s/ Eric Stoutenburg
Eric Stoutenburg

Chief Development Officer

Eolian L.P.

988 Howard Ave. Suite 200
Burlingame, CA 94010

eric.stoutenburg@eolianenergy.com
/s/ Noah Long
Noah Long
Director, State and Regulatory Affairs
Antora Energy, Inc.
200 West De Vargas St
Santa Fe, NM 87501
noah.long@antora.com

/s/ Matt Barnes
Matt Barnes
Chief Commercial Officer
Calibrant Energy
4830 W. Kennedy Blvd, Suite 600
Tampa, Florida 33609
matthew.barnes@calibrantenergy.com

PDF page 32

32
/s/ Katie Guerry
Katie Guerry
SVP Regulatory and Government Affairs
Convergent Energy and Power
7 Time Square, Suite 3504
NY, NY 10036
kguerry@convergentep.com

/s/ Brian Kauffman
Brian Kauffman
Director, Wholesale Market Development
Mainspring Energy, Inc.
3601 Haven Ave.
Menlo Park, CA 94025
brian.kauffman@mainspringenergy.com

/s/ Noah Roberts
Noah Roberts
Executive Director
U.S. Energy Storage Coalition
1299 Pennsylvania Ave NW
Washington, D.C. 20004
noah@energystorage.org

/s/ Jeff Bladen
Jeff Bladen
Head of Energy
Verrus, LLC
918 N Rengstorff Ave.

Mountain View, CA 94043

bladen@verrusdata.com

PDF page 33

33
CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.

Dated: March 25, 2026
/s/ Eric Stoutenburg
Eric Stoutenburg

Chief Development Officer

Eolian L.P.

988 Howard Ave. Suite 200
Burlingame, CA 94010

eric.stoutenburg@eolianenergy.com

PDF page 34

Attachment A

PDF page 35

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 1 of 25

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION Large Loads Co-Located at Generating Facilities

Docket No. EL25-49-000 et al.
AFFIDAVIT OF
ANDREW LEVITT AND ANIRUDDH MOHAN
ON BEHALF OF
EOLIAN, L.P.
March 25, 2026

PDF page 36

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 2 of 25
I. QUALIFICATIONS
1
Our names are Andrew Levitt and Aniruddh Mohan. Mr. Levitt is a Senior Consultant and Dr. 2

Mohan is an Energy Associate at The Brattle Group (Brattle).
3
Mr. Levitt is an expert on wholesale market design and reliability implications of changes in the 4

power system. He has consulted to Independent System Operators and Regional Transmission 5

Organizations (ISO/RTOs) such as the Midcontinent Independent System Operator (MISO), the 6

New York Independent System Operator (NYISO), the Alberta Electric System Operator 7

(AESO), and the Independent Electricity System Operator (IESO) of Ontario, and helped other 8

clients navigate ISO/RTO changes nationwide. Prior to joining Brattle in 2022, Mr. Levitt was 9

on staff at PJM for seven years (most recently as Lead Market Designer), where he developed 10

reforms to reliably integrate new resource types. Mr. Levitt holds an MMP from the University 11

of Delaware and a BSc in physics from the University of Toronto.
12
Dr. Mohan specializes in the evaluation of energy technologies at a systems level, with expertise 13

in electricity markets, techno-economic analysis, and energy policy. He has expertise in 14

optimization models that support both resource and transmission planning and has published 15

peer-reviewed research in leading academic journals on energy systems. He holds a PhD in 16

Engineering & Public Policy from Carnegie Mellon University.
17
We have worked extensively on the benefits of co-located (“hybrid”) loads and generation and 18

how that option should be facilitated to reduce costs, achieve faster connection of new loads and 19

generation, and ensure reliability. This includes co-authored affidavits and reports in prior filings 20

before the Federal Energy Regulatory Commission (“FERC” or “Commission”) on co-location 21

including an affidavit on behalf of Eolian in FERC Docket No. RM26-4-000 on Interconnection 22

of Large Loads to the Interstate Transmission System and a report on behalf of Bloom Energy in 23

this Docket EL25-49-000 on Accelerating the Integration of New Co-located Generation and 24

Loads.1
25

1 Affidavit of Andrew Levitt, Aniruddh Mohan, Ryan Quint, and Sirisha Tanneeru on Behalf of Eolian Energy, Inc., before the Federal Energy Regulatory Commission in the matter of Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, November 21, 2025; A. Levitt, J. Pfeifenberger, and
A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No. EL25-49-000, April 23, 2025.

PDF page 37

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 3 of 25
II. ASSIGNMENT
1
We were asked by Eolian, L.P. to assess the efficiency and reliability effects of PJM’s 2

compliance filing in Dockets EL25-49-000 et al. on new transmission services for loads co- 3

locating with generation resources, and to identify potential enhancements. We assessed: the 4

proposed eligibility for Non-Firm Contract Demand Transmission Service (“Non-Firm CDS” or 5

“NFCDS”); operational requirements for NFCDS and Interim Network Integration Transmission 6

Service (“Interim NITS”); PJM interconnection study procedures for co-located load and supply 7

resources; and PJM’s proposed timeline for implementation of the proposed reforms. 8

III. BACKGROUND
9
In February 2025, the Federal Energy Regulatory Commission (FERC) initiated a show cause 10

proceeding into whether sections of PJM’s tariff on co-location of generation with loads are just, 11

reasonable, and not unduly discriminatory or preferential. FERC’s subsequent Order in Docket 12

EL25-49-000 on December 18, 2025 found that PJM’s Tariff did not address with sufficient 13

clarity and consistency the rates, terms, and conditions applicable to generators serving co- 14

located load and to eligible customers taking transmission service on behalf of such load.2 FERC 15

therefore directed PJM to revise its Tariff, required PJM to establish three new transmission 16

service options for co-located load arrangements, and set the matter for further paper-hearing 17

proceedings on the appropriate rates, terms, and conditions.
18
PJM’s filings are its response to those directives. In its compliance filing, PJM proposes 19

revisions to its Open Access Transmission Tariff addressing, among other things, behind-the- 20

meter generation, necessary study procedures, and the framework for new transmission services 21

applicable to co-located load. In its accompanying Initial Brief, which is the subject of this 22

affidavit, PJM sets out illustrative tariff language and supporting positions for three new service 23

categories: Interim NITS, Firm CDS, and Non-Firm CDS. PJM also submitted supporting 24

affidavits addressing planning, operations, market design, and implementation timing. We 25

submit this affidavit in response to this Initial Brief and its accompanying affidavits, and the 26

issues they place before the Commission.
27

2 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order).

PDF page 38

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 4 of 25
IV. SUMMARY
1
We appreciate the steps PJM has taken in its Initial Brief and compliance filing to create new 2

transmission services for co-located loads that can reduce their withdrawals from the grid when 3

needed. PJM has undertaken considerable work to outline a number of pathways that we believe 4

will help facilitate faster entry of new large loads, new generation resources, and more flexible 5

contractual arrangements. These reforms are well positioned to be fully realized, and the benefits 6

fully unlocked, with relatively minor enhancements.
7
In this affidavit, we assess the proposal PJM has made in its Initial Brief in Docket EL25-49-000 8

and identify enhancements that will enable it to achieve the full scope and ambition indicated in 9

the Co-Location Order. To summarize, we identify these enhancements as:
10
Provide NFCDS when needed and available (i.e., not limited only to periods when the co-located 11

generator is on outage), improving efficiency and speed to power;
12
For loads that take Interim NITS, obligate curtailment to the level of net zero withdrawals from 13

the transmission system to avoid additional unnecessary curtailment of load supplied by local 14

generation (with narrow exceptions discussed below) while ensuring no or minimal impact 15

on the transmission system;
16
Use penalties that are proportional to the system impact and commensurate with similar penalties 17

faced by generators today; apply penalties that distinguish between failing to curtail during 18

resource adequacy events versus transmission security events;
19
Provide more detail on the interconnection studies required for co-located load and supply 20

resources, including how each component will be modeled in the studies of the other 21

component(s); study non-firm load as dispatchable in order to achieve maximum speed to 22

power benefits; and clarify treatment of the co-location of load with storage resources, 23

including allowing co-located load and energy storage resources to nominate joint 24

withdrawal limits in order to enable flexible and technology-neutral co-location 25

arrangements;
26
Accelerate the target implementation of significant portions of the new transmission services to 27

enable energization of new large loads; and
28

PDF page 39

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 5 of 25
Deploy remedial action schemes (RAS) more extensively to increase the utilization of the 1

existing transmission grid.
2
Taken together, we believe these modifications to PJM’s proposal will significantly expand the 3

commercial opportunities for co-located load and generation resources in PJM, consistent with 4

the outlined priorities of the US Department of Energy and FERC to accelerate energization of 5

new large loads, while improving and expanding the efficiency benefits of the PJM energy 6

market, making it more attractive for new loads to bring new generation, and reducing the 7

transmission upgrades and interconnection timelines necessary to integrate new loads. 8

We note that the scope of our affidavit is restricted to the items described above. We do not 9

address the proposed prices for the new non-firm transmission services, while acknowledging 10

that such pricing should be consistent with other non-firm transmission services already provided 11

by PJM to ensure that customers pay for a fair share of the transmission system they are using. 12

V. ASSESSMENT OF THE PJM PROPOSAL AND POTENTIAL ENHANCEMENTS
13
V.A.
Making Non-Firm CDS Available as Needed Improves
14
Efficiency and Speed to Power
15
V.A.1.
The benefit of Non-Firm Contract Demand Service is
16
unnecessarily limited as it only contemplates load
17
withdrawals when co-located generation is on outage
18
PJM has proposed to limit the availability of Non-Firm CDS to “the event the Co-Located 19

Generating Facility is on outage and unable to provide any of the dedicated level of energy.”3 20

3 PJM Illustrative Tariff § 709.2(b).

PDF page 40

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 6 of 25
PJM’s implementation therefore seems to envisage a load that is 100% self-supplied by its co- 1

located generation unit for almost the entire year, except for periods of generator outages.4 2

PJM’s proposed implementation is unreasonable and inefficient as it is far narrower than 3

necessary. If implemented as proposed, it would introduce potentially significant economic 4

inefficiencies by precluding the load from accessing the PJM energy market when doing so 5

would be lower cost than dispatching the co-located generation, assuming of course that such 6

withdrawals would be limited to when the transmission network could reliably deliver that 7

energy. For example, consider the case of a load taking NFCDS that is co-located with a natural 8

gas peaker plant. Under PJM’s proposed implementation, the load would have to rely on its 9

peaker plant for all the hours of the year in which the plant is physically available (i.e., not on 10

outage). This would be necessary (and reasonable) only if the transmission network were unable 11

to deliver market energy for the entire year. As proposed, loads would not be able to request non- 12

firm CDS and PJM would not even check for the availability of non-firm transmission unless the 13

co-located generator is on outage. Assuming non-firm transmission capability would indeed be 14

available in many hours of the year, PJM’s proposal would result in unnecessarily high costs 15

(and unnecessarily high fuel consumption and emissions) for supplying the load compared to 16

allowing access to PJM’s market resources whenever non-firm transmission is available. This is 17

because a co-located peaking unit would only be cost competitive during a portion of all hours 18

when the unit is available (i.e., not on outage).
19

4 We note that even if PJM’s proposed restriction of NFCDS to periods where co-located Generation is on outage were necessary and beneficial, which it is not, PJM has not provided sufficient clarity on how outages are defined and whether this covers both planned and unexpected outages or both. Given the need for reserving NFCDS ahead of time, it is likely in practice that this would only be used for planned outages or extended forced outages. By definition, unexpected outages cannot be anticipated and fully reserved for in advance

PJM’s implementation also does not specify how multiple units are to be treated for outages. For example, in the Illustrative Tariff § 709.2(b) it says NFCDS would be allowed in “the event the Co-Located Generating Facility is on outage and unable to provide any of the dedicated level of energy.” Take the case of a 500 MW load co-located with 2 × 250 MW generators that takes NFCDS. The use of the word “any” suggests that PJM would not allow the 500 MW load to take NFCDS unless all 500 MW of the generation, i.e. both units, were fully on outage. Load must request reservation of 500 MW or nothing. However, in its Initial Brief, p. 32, PJM says “The Eligible Customer may then, on any given day, reserve Non-Firm Contract Demand Transmission Service up to the amount specified in the Service Agreement (but only up to the MW level that the Co-Located Generating Facility is on outage).” The phrase “only up to the MW level” would suggest that in the example, load may take NFCDS up to 250 MW if one of its generation units were offline. This is clearly inconsistent. In Attachment B (Affidavit of Dr. Sami Abdulsalam), p.6 it also says that “An Eligible Customer would only need to take non-firm transmission service under limited circumstances—e.g., if the co-located generator is unavailable or operating at a reduced capacity.” The phrase “reduced capacity” contradicts the use of the word “any” in PJM’s Illustrative Tariff provision.

PDF page 41

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 7 of 25
As a second example, consider a co-located battery storage facility. Battery storage provides 1

particular value for co-locating with artificial intelligence data centers, given the batteries’ ability 2

to ramp instantaneously to match rapid changes in computing load. PJM’s proposal to only allow 3

loads to reserve NFCDS during outages appears to be incompatible with co-located storage use 4

cases, since storage is physically incapable of producing power at all times. Given that storage is 5

capable of working in concert with load curtailment to accelerate grid connection of a co-located 6

facility via non-firm transmission service, PJM’s proposal would unnecessarily shut out this use 7

case.5 This precludes taking advantage of the benefits of battery storage for addressing the 8

infrastructure challenge that is the subject of FERC and PJM’s policy effort in this docket. Those 9

benefits include the fast-ramping loads mentioned above, as well as rapid deployment, a robust 10

supply chain, lower permitting requirements, and lower emissions.
11
In addition, generation facilities typically feature multiple units for economies of scale, local 12

redundancy, or other purposes. PJM would benefit if new co-located facilities are designed with 13

redundancy offered by multiple units, which in some cases could be dozens or more units at a 14

single site able to offer extremely high availability and commensurate reliability benefits.6 In 15

such cases, physical generation outages would not typically cover all generation at the site, thus 16

potentially precluding utilization of NFCDS entirely, despite the efficiency benefits that broad 17

availability of Non-Firm CDS would offer. As long as non-firm capacity is available on the PJM 18

grid, customers should be able to reserve the service.
19
PJM’s proposed implementation would create economic and technical barriers to loads that wish 20

to take NFCDS to contract with any resources other than low-energy-cost baseload resources. 21

PJM’s proposed implementation of NFCDS would thus not be technology neutral, and PJM 22

offers no explanation for why such a restrictive operational envelope for Non-Firm CDS is 23

necessary. Finally, by creating conditions in which co-location is limited to baseload resources 24

(that may require many years to develop), PJM’s proposal would create the unintended outcome 25

of providing a strong incentive to existing baseload resources (such as nuclear plants and gas- 26

5 Affidavit of Andrew Levitt, Aniruddh Mohan, Ryan Quint, and Sirisha Tanneeru on Behalf of Eolian Energy, Inc., before the Federal Energy Regulatory Commission in the matter of Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, November 21, 2025.
6 A. Levitt, J. Pfeifenberger, and A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No. EL25-49-000, April 23, 2025.

PDF page 42

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 8 of 25
fired combined cycles) to exit the PJM market so they can enter into co-location arrangements 1

with loads taking NFCDS. These are also the resources with the highest capacity market 2

accreditation, whose exit would have the highest adverse impact on the PJM capacity market. 3

Creating such incentives is undesirable at a time in which the PJM capacity market is falling 4

short of its reliability requirement and capacity prices are at the cap.
5
V.A.2.
PJM can leverage the same tools for Interim NITS and
6
for Non-Firm CDS to ensure reliability
7
Consistent with FERC’s Order, PJM has structured NFCDS such that it has the authority and 8

capability to evaluate and deny requested reservations based on expected operational 9

considerations ahead of time.7 Further, in real time operations, even after granting reservation of 10

NFCDS, PJM has the ability to curtail withdrawals consistent with the nature of non-firm 11

service. We find merit with PJM’s proposed structure for reservations and operational 12

evaluations. Given that PJM proposes to evaluate operations when it receives a reservation 13

request, it stands to reason that PJM could also evaluate conditions for NFCDS requests when 14

the co-located generation is not on outage. PJM has not provided a justification for why the 15

NFCDS reservation process should be limited to when the co-located generator is on outage. 16

Further, PJM has already proposed to offer interruptible non-firm access to withdrawals at all 17

hours to load taking Interim NITS, even without the need to request reservation. PJM should 18

therefore be able to offer non-firm, as-available service to Non-Firm CDS customers whenever 19

the request can be served reliably (understanding that the service can be curtailed in real time). 20

We conclude that NFCDS should be offered upon request whenever non-firm transmission 21

capability is available. Since PJM can deny a service request based on PJM’s operational 22

evaluation and curtail the service in real time if needed, doing so would be at least as reliable and 23

7 For example, PJM in its Initial Brief, pp. 32–33 notes that “requests for Non-Firm service shall only be granted when PJM has determined there is available transmission capacity.” PJM also notes that studies for NFCDS “relate only to the maximum amount of Non-Firm Contract Demand Transmission Service that would be allowed under a specific Service Agreement. PJM expects to perform different evaluations to actually use such service on the Transmission System on any given day.” Further, in PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam, p. 6) Dr. Abdulsalam notes that “The order also requires Non-Firm Contract Demand Transmission Service to be requested ahead of time and on a relatively short duration basis (one hour to one month). This forward request for service implies foreseeable conditions where the Co-Located Load is expected to withdraw power from the PJM network.”

PDF page 43

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 9 of 25
practical to operationalize as Interim NITS.8 Limiting Non-Firm CDS to periods during which 1

the co-located generator is on outage would be unnecessary, unreasonable, inefficient, and create 2

a significant or unworkable barrier for co-locating loads with many types of the generation 3

resources, including batteries and gas-fired peaking units.
4
V.A.3.
PJM’s implementation would be more efficient and
5
accelerate speed to power if NFCDS were broadly
6
available when requested
7
Expanding availability of Non-Firm CDS reservations to whenever it is requested and non-firm 8

grid capacity is available removes barriers to use of the NFCDS construct for generators that are 9

not baseload. This would significantly improve the economic efficiency offered by the service 10

and accelerate speed to power. Allowing customers with NFCDS to apply for reservations for 11

non-firm service in all hours of the year at their nominated levels would maximize economic 12

efficiency and allow loads to co-locate with a wide variety of technologies depending on their 13

needs and technology availability. In this expanded implementation, PJM would still have the 14

ability to deny reservations for non-firm service if expected grid conditions do not permit 15

reliably serving the load on a non-firm basis. And, if unforeseen conditions occur in real time, a 16

curtailment order could be issued, and the load would follow instructions to curtail its net 17

withdrawals from the grid to the level ordered by PJM.
18
Expanding NFCDS would enable large loads to make commercial investments with this service, 19

avoiding major transmission upgrades (and reducing the associated cost) and achieving the speed 20

8 PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam) distinguishes between the reliability implications of Interim NITS and NFCDS by noting that Interim NITS is temporary (see p. 4). However, PJM has not provided any time frame to limit the expected period of Interim service. Transmission upgrades required to enable full NITS for load may take many years to be completed. Further, the transmission system is changing continuously due to new generation, load, and transmission upgrades, making it unclear why temporary Interim NITS is reliable for its entire duration while NFCDS, which allows for continuous operational evaluations, is not.

Further, the Affidavit, p. 5 also acknowledges that operational screening by PJM for NFCDS will reduce the number of protection schemes necessary: “For Non-Firm Contract Demand Transmission Service, PJM will be offering and managing these pre-scheduled services “operationally” and ensure that permanent monitoring and aggressive, fast-acting protections are in place if conditions arise that may compromise reliable system operations. This approach allows for more reliable system operation, reduces the number of permanent protection systems on the system, thereby reducing the likelihood of unintended protection system misoperation that could lead to cascading events.”

PDF page 44

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 10 of 25
to power priorities of FERC and the US administration. It would also increase the attractiveness 1

of co-located arrangements under which large new loads voluntarily bring their own new 2

generation, reducing PJM’s reliance on other efforts (i.e., the Reliability Backstop Auction) to 3

assure generation adequacy through administrative mandates or cost allocations. Finally, by 4

incentivizing transmission customers to develop load curtailment as a backstop to generator 5

availability, it increases the operational reliability tools available to PJM. 6

While the immediate benefits of speed to power and avoided transmission upgrades for Non- 7

Firm CDS match those benefits for Interim NITS, Non-Firm CDS has the added benefit of: (1) 8

being a permanent service (as opposed to Interim NITS); (2) indicating to PJM exactly how 9

much load the customer is willing to curtail as a backstop for its co-located generator, and (3) 10

explicitly indicating to PJM and the transmission owner that the customer intends to primarily 11

rely on its own generator for a specified portion of its firm supply, setting a clear benchmark for 12

PJM to plan towards.
13
V.B.
PJM’s Proposal to Curtail Interim NITS Loads to Zero
14
Gross Consumption Results in Unnecessary Curtailment
15
V.B.1.
PJM’s proposal to fully curtail all load of Interim
16
NITS customers results in unnecessary curtailment
17
and renders Interim NITS commercially unworkable
18
for many applications
19
PJM has stated in its stakeholder meetings that load customers taking Interim NITS service 20

(which is appropriately interruptible and non-firm until the customer transitions to firm NITS) 21

would be required to curtail their entire load to zero MW when ordered to do so by PJM.9 During 22

system conditions demanding curtailment, PJM would not allow load to net its consumption 23

against its co-located generation resource. Instead, PJM would curtail the entire load even when 24

its co-located generator is producing. Curtailing customer load to levels beyond what is needed 25

9 While not explicit in its tariff filing, PJM in stakeholder materials has said that load would not be allowed to net its load with its co-located generation resource during system conditions that require curtailment. “If curtailed, EC cannot take energy from co-located generator (no netting under system conditions that required curtailment).”

PDF page 45

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 11 of 25
to achieve zero withdrawals from the grid (i.e., to less than the generation output of the co- 1

located generation) is unreasonable and inefficient in most use cases.
2
PJM does not explain why the load would need to curtail beyond the level at which zero MW are 3

withdrawn from the transmission system to the co-located facility (i.e., when some or all of the 4

load is consuming but is physically taking power entirely from the co-located generation). In 5

other words, PJM does not explain why the load could not take power from its co-located 6

generator without physically flowing power over the transmission network.
7
Since PJM proposes that co-located loads taking Interim NITS curtail not only when needed for 8

transmission security, but also for resource adequacy reasons (prior to deployment of Pre- 9

Emergency Demand Response), PJM’s proposal denies the load the benefit of any resource 10

adequacy value from its co-located generation.10 This would result in unnecessary curtailments 11

and render the Interim NITS proposal commercially unworkable for loads that develop their own 12

new generation, since the purpose of the co-location arrangement is to increase the firmness of 13

power availability to the load by way of the co-located generator.
14
For example, consider a 300 MW generator with full injection rights and a 300 MW load with 15

interim NITS, with the generator running at maximum output. If system conditions require 16

curtailment from the grid, PJM proposes to curtail the load to 0 MW while the 300 MW 17

generation resource would still be injecting into the grid. This would mean the co-located facility 18

would now be injecting 300 MW into the grid, instead of simply obligating co-located generation 19

and load to limit their net withdrawals to 0 MW. Doing so would be reasonable only if the co- 20

location involves (1) existing generators with PJM capacity market obligations prior to taking 21

advantage of the co-location opportunity and (2) the generator had no intention to retire the 22

facility absent the co-location opportunity. In any other cases, such as when new load is co- 23

located with owned or contracted new generation, curtailments should be limited to zero net 24

withdrawals from the grid.
25

10  We refer to the proposed provision to curtail prior to pre-emergency Demand Response as a resource-adequacy related curtailment.

PDF page 46

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 12 of 25
Consider another case in which a 300 MW generator has minimal net injection rights (i.e., it is 1

limited in its interconnection agreement to almost exclusively provide power for the co-located 2

load, consistent with the Co-Location Order, with only e.g. 20 MW of allowed injections) and is 3

sited with a 300 MW load. With the load at 280 MW and the generation at 300 MW, PJM’s 4

proposal would be to curtail the load to 0 MW prior to a Pre-Emergency Demand Response 5

event. This would result in the generator also curtailing such that it injected at its maximum of 20 6

MW. The result would be to incur great opportunity cost through the curtailment yet yielding no 7

net gain in power balance during the scarcity condition. This is inefficient and unnecessary and 8

may also reduce reliability as the reactive power and stability benefits of the generator would no 9

longer be available due to its curtailment.
10
V.B.2.
PJM can offer Interim NITS without unnecessary
11
curtailments by obligating curtailment to net zero
12
withdrawals and clarifying resource adequacy
13
curtailment obligations
14
PJM proposes curtailment of load taking Interim NITS not only for transmission security reasons 15

but also for resource adequacy purposes (as evidenced by the requirement of Interim NITS 16

customers to curtail before Demand Response customers are curtailed). Curtailment for 17

transmission security is natural given the interruptible, non-firm nature of the Interim NITS 18

transmission service. However, the extent of obligatory curtailment is greater than necessary, and 19

the application to resource adequacy is insufficiently specified with respect to capacity 20

arrangements for the load and generation, leading to inefficient, unnecessary curtailments of 21

loads. Reliability would be maintained while minimizing unnecessary curtailment and offering a 22

workable Interim NITS construct if PJM limited the curtailment of net grid withdrawals only to 23

(a) the level necessary for transmission security, and (b) the level appropriate to the resource 24

adequacy circumstance the customer is in (as explained below).
25
Putting aside transmission security considerations related to existing generators (where addition 26

of new load without new generation can adversely impact transmission security for existing 27

customers), it is evident that load co-located with new generation does not generally impact 28

transmission security for existing customers once net withdrawals have been reduced to zero and 29

PDF page 47

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 13 of 25
the customer is no longer taking any power from the transmission system. In some cases, even 1

curtailing to net zero withdrawals is more than necessary, especially when multiple customers 2

taking non-firm transmission service can respond to mitigate the same issue.
3
The exception to limiting load curtailments to net zero grid withdrawals is for facilities with 4

large generation unit or load module components for which a trip of the large component could 5

cause inadvertent inflows or outflows, which would need to be addressed by reducing the output 6

or consumption of the component.11 This can be remedied with a relay or simple RAS 7

monitoring flows at the point of connection to the grid. Indeed, PJM recognizes the value of RAS 8

for the Interim NITS case in preventing accidental load withdrawals from the grid.12 In case no 9

RAS is available and post-contingency flows are insecure, curtailment obligations for Interim 10

NITS customer loads can be made by exception, rather than setting a standing obligation to 11

curtail the entire load to zero even if co-located generation supplies all or some of the load. This 12

would clarify that unnecessary curtailments are not expected.
13
Curtailments of load to ensure resource adequacy for co-location arrangements with new 14

generators should also be limited to net zero grid withdrawals (putting aside the use case 15

involving existing generator arrangements with capacity market obligations). When the 16

co-located new generator is not selling capacity to PJM and, instead, provides capacity to the co- 17

located load customer, it would be unreasonable and unnecessary to curtail load below net zero 18

grid withdrawals from the co-located facilities. In other words, even under Interim NITS, loads 19

co-located with dedicated new generation should not be curtailed for resource adequacy events if 20

there are no net withdrawals from the grid.
21

11  We note that the simplest solution to this issue is to avoid large units/modules in the design of such facilities, which is not uncommon for new large load co-location arrangements.
12  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), at p. 9. “There is one scenario where a RAS would be overwhelmingly beneficial and would have a minimal impact on the overall grid. A RAS will be required for the loss of the Co-Located Generating Facility. In this instance, PJM would expect the RAS to actuate on the loss of the Co-Located Generating Facility and the load served by Non-Firm Contract Demand Transmission Service or Interim NITS will automatically be removed from the system by the RAS scheme. In other words, after the co-located generator is offline, only the NITS or Firm Contract Demand Transmission Service will remain connected and served by PJM. At that point, PJM could evaluate if additional non-firm load could be supported after the loss of generation occurs.”

PDF page 48

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 14 of 25
Only if the co-located load is not buying capacity from PJM but the co-located generator is 1

selling capacity to PJM (and is therefore not available to serve the co-located load) is it logical 2

and necessary to curtail the load for resource adequacy events (e.g., prior to Demand Response 3

deployment, or otherwise as appropriate).
4
V.B.3.
The benefits of limiting curtailments only to net zero
5
withdrawals under Interim NITS are significant
6
For all cases in which generation does not have a PJM capacity market obligation, significant 7

benefits would accrue by allowing the co-located generation to provide capacity to Interim NITS 8

load and power that load during resource adequacy and transmission security events. PJM has 9

indicated that the highest level of reliability for loads seeking transmission service is to take 10

NITS, a service which will be provided to all Interim NITS customers once the necessary grid 11

upgrades have been completed. Enabling energization of new loads on an expedited basis 12

through co-location supports national economic competitiveness and national security priorities 13

for artificial intelligence. The Interim NITS framework established by FERC was directed at 14

addressing both the need for reliability (via eventual NITS) as well as energization of load on an 15

accelerated basis while upgrades required to provide full NITS were built out. Allowing the co- 16

located generation to provide resource adequacy benefits to its co-located load while avoiding 17

unnecessary curtailments for transmission security events increases reliability for loads that elect 18

to come online faster under Interim NITS. This speed to market advantage is particularly 19

important if the load served by Interim NITS is co-located with new generation that is able to 20

serve the load with lower (or no) net grid injections. In that case, the generation could be 21

developed more quickly with fewer delays in PJM’s generator interconnection process. Enabling 22

that use case would make the Interim NITS framework significantly more attractive for major 23

capital investments and help achieve FERC’s and DOE’s policy objectives.
24

PDF page 49

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 15 of 25
V.C.
The Proposed Penalty for Failure to Curtail Is
1
Disproportionate to the Impact and Should Distinguish
2
Types of Events
3
PJM has proposed a strict liability rule for a customer taking NFCDS or Interim NITS that “fails 4

to respond to established Load Shedding and Curtailment procedures.”13 Such a customer would 5

be disqualified from taking the service after a single failure to respond. For customers that have 6

an equipment malfunction, i.e. a protection scheme not operating as intended, PJM proposes a 7

suspension of service for up to 120 days on the first failure, to analyze the operation of the 8

protection scheme.14 On the second failure, PJM proposes a disqualification of service.15 9

Loads taking Non-Firm CDS or Interim NITS do not have firm transmission service nor benefit 10

from a resource adequacy obligation from PJM. These two attributes (transmission security and 11

resource adequacy) have distinct functions and values, and PJM’s curtailment of loads has 12

different implications for resource inadequacy or transmission related events. Penalties for 13

failure to comply with these two types of curtailments are most effectively applied when they are 14

commensurate with the reliability and cost implications of that failure. Importantly, these 15

penalties should be equivalent to the penalties paid by generators that cannot meet their capacity 16

obligations, or that cause transmission reliability impacts due to their failure to comply with PJM 17

dispatch orders.
18
Generators and demand response resources with a capacity market obligation that fail to perform 19

during a resource adequacy event are assessed as a Non-Performance Charge during every 20

Performance Assessment Interval (PAI) in which they cannot perform as committed. This charge 21

reflects the cost of the failure to perform during resource adequacy events. A similar or 22

equivalent financial penalty would appropriately be applied for load under NFCDS or Interim 23

NITS that fails to curtail for resource adequacy events. In contrast, the penalty proposed by PJM 24

(permanently discontinuing non-firm transmission service and effectively shutting down the 25

customer facility not for hours, but for many months or years) is many thousands of times more 26

13  PJM Initial Brief pp. 41–42
14  PJM Initial Brief, pp. 43–45
15  PJM Initial Brief, pp. 45–46

PDF page 50

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 16 of 25
costly than the system cost for resource adequacy failures implied by the PAI performance 1

penalties imposed on generators. For example, the PAI penalty for a 1,000 MW failure to curtail 2

for one hour might be roughly $2-3 million based on PJM’s formula.16 PJM’s Interim NITS and 3

NFCDS penalty proposal to shut down a load customer until transmission upgrades are 4

completed would have a far higher cost. A 1,000 MW data center might provide a gross revenue 5

of several billion dollars per year, much or most of it profit, in addition to contributing to 6

national priorities for deployment of artificial intelligence.17 Shutting it down for several years 7

until firm NITS can be provided due to a failure to curtail its grid withdrawals to net zero during 8

a resource adequacy event likely represents a lost opportunity cost on the order of many billion 9

dollars, or three orders of magnitude higher than the equivalent PAI penalty. PJM’s proposed 10

penalty is therefore unnecessarily high, not commensurate with the system impact of the failure 11

to curtail during resource adequacy events, and discriminatory relative to the treatment of PJM 12

generators for non-performance during resource adequacy events.
13
Failure to curtail for a transmission-security-related event could in principle result in severe, 14

potentially catastrophic reliability problems. A more substantial penalty may therefore be 15

appropriate to the scale of the risk. A similar circumstance holds for generators that fail to curtail 16

when transmission system overloads are at risk. Because the consequence of continued 17

withdrawals (or, for generators, injections) can be so high, in the case of both load and generator 18

failures to curtail as instructed, transmission owners often retain the ability to manually 19

disconnect a facility if needed to avoid potential severe reliability risk. It therefore stands to 20

reason that such overriding “forced curtailment” action would be available as a backstop in case 21

of failed load curtailment to limit the extent of actual reliability impact. Therefore, the severe 22

penalty proposed by PJM (discontinuing non-firm transmission service) is unnecessarily high for 23

transmission-related curtailment failure. It is also not commensurate with the penalty levied on 24

16  PJM, Manual 18, Section 3A.6.2, Revision 65, effective December 17, 2025 specifies the PAI charge for an interval = Performance Shortfall (MW)×Non-Performance Charge Rate. The Non-Performance Charge Rate is estimated based on Net CONE.
17  CoreWeave, CoreWeave Reports Strong Fourth Quarter and Fiscal Year 2025 Results, February 26, 2026 (stating that the company “became the fastest cloud in history to reach $5 billion in annual revenue”); CoreWeave, Annual Report on Form 10-K for the year ended December 31, 2025 (filed February 26, 2026) (stating that, as of December 31, 2025, CoreWeave operated “43 data centers with over 850 MW of active power”). Scaling those figures proportionally implies approximately $5.9 billion of annual revenue per 1 GW of active power.

PDF page 51

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 17 of 25
generators that fail to curtail when ordered under similar circumstances (there appears to be no 1

such systematic penalty on generators, although arguably there should be).
2
V.D.
PJM should study co-located resources independently but in
3
the presence of one another and consider load as
4
dispatchable to maximize speed to power benefits
5
V.D.1.
PJM has not provided sufficient detail on study design
6
for co-located resources
7
PJM has provided limited details in its filing on how studies for transmission service for loads 8

co-located with supply resources will proceed. For example, in its section on Study Procedures 9

for load taking NFCDS, PJM says only that it will coordinate with the Transmission Owners to 10

identify appropriate studies.18 Similarly, for Interim NITS, PJM says that it will determine 11

whether additional studies beyond what is required to evaluate the Customer’s request for NITS 12

are needed.
13
The design of studies for large load interconnection is the critical factor in determining the scale 14

of upgrades required for energization of new large loads under all scenarios including co-located 15

NITS, Interim NITS, NFCDS, and firm CDS. As explained in detail in a prior filing in the same 16

docket, it is important for study processes to capture both the co-located load and generation 17

(rather than netting them against one another prior to implementing the components in the study 18

model), but the study process for load must account for the presence of the generation 19

resource(s) and vice versa.19 This ensures that co-located load and generation are both present in 20

18  On p.33 of its Initial Brief PJM says “As discussed, PJM will not study transmission service requests alone, but rather will coordinate and consult with any affected Transmission Owners to determine whether and how the requested transmission service may be provided. Thus, upon receipt of a request for Non-Firm Contract Demand Transmission Service, PJM will notify the affected Transmission Owner(s) of such request.108 PJM and the affected Transmission Owner(s) will determine whether additional studies are required ‘to assess whether the Transmission System has sufficient available capacity to provide Non-Firm Contract Demand Transmission Service, and if so, which studies are appropriate.’”
19  A. Levitt, J. Pfeifenberger, and A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No. EL25-49-000, April 23, 2025.

PDF page 52

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 18 of 25
the study model, therefore offering the option to effectively self-supply and impose zero or de 1

minimis impacts on the transmission system.
2
V.D.2.
Studying co-located load and generation in the
3
presence of each other achieves speed to power
4
For example, take the case of a 500 MW load and a 500 MW co-located generator. If in the study 5

model, the presence of the co-located generator is ignored (e.g., because it does not yet have an 6

Interconnection Service Agreement), the 500 MW load is withdrawing from the system in the 7

steady state case, and the transmission service must be firm enough to support it, including after 8

removing any two components in the N-1-1 study cases. However, if both generation and load 9

are present, the 500 MW generator can support the load, ensuring that net withdrawals from the 10

transmission system are effectively zero in the base case. We recognize that contingency analysis 11

would still require stress testing one component to be tripped offline while the other is online, as 12

is the case with all elements on the transmission system. However, the addition of the new 13

generation still reduces the need for system upgrades identified in the transmission network 14

planning studies, because only so many network facilities are removed from service in 15

contingency planning cases. Further, for cases that utilize a RAS, it would ensure that the co- 16

located load never shows up on the transmission system if the generation unit were to trip offline 17

due to an unexpected outage, therefore further mitigating any impact of contingency events.20 18

Such a study model would generally identify significantly lower upgrades relative to studies that 19

do not consider both generation and load in the presence of each other.
20

20  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), at p.9. “There is one scenario where a RAS would be overwhelmingly beneficial and would have a minimal impact on the overall grid. A RAS will be required for the loss of the Co-Located Generating Facility. In this instance, PJM would expect the RAS to actuate on the loss of the Co-Located Generating Facility and the load served by Non-Firm Contract Demand Transmission Service or Interim NITS will automatically be removed from the system by the RAS scheme. In other words, after the co-located generator is offline, only the NITS or Firm Contract Demand Transmission Service will remain connected and served by PJM. At that point, PJM could evaluate if additional non-firm load could be supported after the loss of generation occurs.”

PDF page 53

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 19 of 25
V.D.3.
Studying load under NFCDS and Interim NITS as
1
dispatchable will improve system accuracy
2
While studying and evaluating the load for NFCDS and Interim NITS, PJM’s models would 3

need to consider the load to be curtailable in order to reflect its non-firm nature. This is 4

comparable to the way in which generators are modeled as dispatchable. Dispatchable load will 5

be incorporated into real-time operations (for example using security constrained economic 6

dispatch or SCED to curtail when needed for reliability), and modeling details are most accurate 7

when they reflect these operational capabilities. The studies can identify operating limits for 8

NFCDS and Interim NITS and provide customers with guidance on expected curtailment levels. 9

These can be updated on a periodic basis based on changes to the transmission system, consistent 10

with provisional interconnection service to generators. Just as provisional service can provide 11

generators with a view on operating conditions under which it may be allowed to inject into the 12

PJM grid, studies for NFCDS and Interim NITS can provide customers with a view on the 13

conditions in which withdrawals would be permitted.
14
V.D.4.
PJM should clarify that storage charging is studied
15
distinctly from load, and allow co-located load and
16
energy storage resources to nominate joint withdrawal
17
limits
18
Storage charging in PJM does not take transmission service unless it charges during the zonal 19

peak hour without being dispatched, in which case it is a Network Load taking NITS.21 Storage 20

charging is therefore not studied as a new NITS customer, but rather using its own distinctive 21

study process that is incorporated into the interconnection queue.22 Because storage can be co- 22

located generation, it will be helpful and possibly necessary for regulatory certainty for PJM to 23

21  PJM Manual 28, Operating Agreement Accounting, Sections 22.1 and 22.2, Revision 104, effective March 1, 2026, pp. 154-156
22  PJM, Manual 14B, Attachment C, Section C.3.1.3, Revision 58, effective December 17, 2025, p. 95. (“For each flowgate, group the Generation Capacity Resources based on whether the distribution factor is positive, in which case increases in the generator’s output contribute to the loading on the flowgate and the generator is considered a “Harmer” or negative, in which case increases in the generator’s output reduce the loading on the flowgate and the generator is considered a “Helper”. Note that the light load test considers pumped storage units in the pumping mode and batteries in both the discharging and charging mode and the appropriate mode to ramp will be based on whether the distribution factor is positive for that mode.”) .

PDF page 54

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 20 of 25
clarify that the treatment for studying storage charging at such a co-located facility is distinct 1

from the studies for the load taking Interim NITS or Contract Demand Service. It will be 2

similarly helpful or necessary to clarify that, even if a co-located facility has 0 MW of Firm CDS 3

and has reserved 0 MW of Non-Firm CDS, a co-located storage component that has been granted 4

an Interconnection Service Agreement recognizing its ability to withdraw from the grid for 5

charging may still do so as dispatched by PJM, consistent with a standalone storage facility. Any 6

RAS at the facility would need to be developed with such use cases in mind, including 7

potentially interrupting storage charging withdrawals prior to a PJM dispatch to reduce storage 8

charging under certain contingencies.
9
Further, the use case of co-located storage would feature enhanced efficiency and speed to power 10

if PJM allows loads in such arrangements taking NFCDS or Interim NITS to nominate a joint 11

withdrawal limit. This would allow for maximum flexibility and innovation for the pair of 12

resources which can decide how to use their joint withdrawal limits for serving load or charging 13

storage, or both, as appropriate. This joint limit would then be respected in the storage 14

withdrawal studies as well as in the load integration studies and NFCDS reservation evaluations. 15

V.E.
PJM can achieve implementation of all three services faster
16
than proposed
17
V.E.1.
Timeline for implementation of the new tariff services
18
does not need to be fully linked to the capacity market
19
PJM cites capacity market timing in justifying its proposed implementation date of June 1, 2029. 20

Under two of the three transmission services, PJM appears to contemplate loads that do not buy 21

capacity from the market. This includes Interim NITS and NFCDS. Therefore, they cannot have 22

an impact on the load forecast for use in the capacity market. New generators serving Interim 23

NITS and NFCDS customers may choose to not offer capacity into the market but instead 24

contract for capacity directly with co-located load. In that case, the new load and new generation 25

both would result in no changes to the Base Residual Auction in the capacity market. If the new 26

co-located generation sells capacity to the market, this would presumably be a helpful outcome 27

in today’s environment that would be desirable as soon as possible. Therefore, PJM’s 28

PDF page 55

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 21 of 25
justifications for delaying implementation until 2029 appear not to apply to co-location cases 1

with new generation.
2
Impacts on the BRA could occur in the case of existing generators leaving the capacity market to 3

provide dedicated output to co-located loads. But these reconciliations would be necessary 4

whether PJM implemented the proposal sooner or later, making it unclear why PJM proposes to 5

wait until June 1, 2029 to implement the proposal. Any such impacts would need to be and can 6

be reconciled in incremental auctions regardless of the implementation date. 7

If PJM’s concern regarding a capacity market shock that cannot be covered through an 8

incremental auction is focused on existing co-located generation withdrawing from the capacity 9

market, it should delay only that use case, while accelerating other use cases (i.e., co-location 10

with new generation facilities). We observe that accelerating new generation and co-located load 11

options eases concerns with reliability and affordability or at least reduces burden on PJM’s 12

other efforts to address those concerns, and should be implemented as quickly as possible. 13

V.E.2.
PJM can build on existing SCED capabilities for Price
14
Responsive Demand to achieve a faster timeline
15
We are encouraged that PJM expects to modify Intermediate and Real-Time SCED tools for 16

operationalizing the three new transmission services. This important function warrants deliberate 17

and careful design and thorough testing, which will take time. However, PJM can build on the 18

existing capability of its nodal Price Responsive Demand (PRD) implementation in SCED for 19

transmission-driven curtailments when needed for local exigencies such as avoiding post- 20

contingency transmission overloads or cascading failures. Because PRD is nodal, real-time, and 21

uses SCED’s real-time capabilities via Contingency Analysis and the other parts of the Energy 22

Management System, it can provide the functionality needed for executing needed reliability 23

curtailments for the non-firm transmission services in order to maintain transmission security as 24

conditions change in real-time. Since PRD has already been developed and tested, and has been 25

deployed in operations for several years, PJM could implement this particularly challenging 26

aspect of the non-firm transmission services in less time. Southwest Power Pool’s recent 27

proposal to implement non-firm transmission service for load (CHILLS) by July 1, 2026 offers 28

PDF page 56

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 22 of 25
further evidence that such changes to dispatch can be implemented faster than envisaged by 1

PJM.23
2
V.F.
PJM Could Rely on Remedial Action Schemes (RAS) More
3
Extensively
4
A Remedial Action Scheme (RAS) allows grid operators to ensure reliable system security while 5

utilizing the capability of transmission lines more fully. A RAS monitors for certain failures and 6

responds immediately with a remedial change to ensure the failure does not cause problems. 7

RASs must be carefully designed to avoid introducing unmanaged complexities and are not 8

appropriate in all circumstances.
9
Mr. Wharton in his affidavit states that
10
A RAS should not be installed as a substitute for good system design or operating 11

practices. PJM Manuals reflect this caution of relying on such schemes on a permanent 12

basis. The implementation of a RAS is generally limited to temporary conditions 13

involving the outage of critical equipment.24
14
We were not able to identify a North American Electric Reliability Corporation (NERC) 15

requirement or guideline that RAS be limited to temporary conditions related to outages. We 16

observe that other grid operators utilize RAS as an alternative to new transmission, rather than as 17

a temporary solution. For example, the California Independent System Operator (CAISO) states 18

that:
19
The primary reasons why RAS might be selected over building new transmission 20

facilities are that RAS can normally be implemented much more quickly and at a much 21

lower cost than constructing new infrastructure. In addition, RAS can increase the 22

utilization of the existing transmission facilities, make better use of scarce transmission 23

resources and maintain system reliability. Due to these advantages, use of a RAS is a 24

commonly considered alternative to building new infrastructure in an effort to keep costs 25

23  SPP, Filing, Docket No. ER26-1323-000, at 1-2 (filed Feb. 10, 2026).
24  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), p.6.

PDF page 57

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 23 of 25
down when integrating new generation into the grid and/or addressing reliability
1
concerns under multiple contingency conditions.25
2
CAISO acknowledges the potential complexity of RASs and reliability concerns if not properly 3

managed and therefore has issued a RAS Planning Standard guideline to ensure their reliable 4

utilization.26 CAISO states that:
5
These reliability concerns necessarily dictate that guidelines and standards be established 6

to ensure that performance of all RASs are consistent across the ISO controlled grid. It is 7

the intent of these guidelines and standards to allow the use of RASs to maximize the 8

capability of existing transmission facilities while maintaining system reliability and 9

optimizing operability of the ISO controlled grid. Needless to say, with the large number 10

of generator interconnections that are occurring on the ISO controlled grid, the need for 11

these guidelines and standards has become more critical.27
12
We observe that other grid operators also have extensive standalone RAS planning guides, but 13

PJM does not.28 If PJM utilized RAS more extensively, putting into place the necessary protocols 14

to ensure reliable development and operations, it could more effectively accomplish speed to 15

power for large loads in appropriate areas while lowering the cost of new transmission. 16

More extensive use of RAS would require administrative and engineering effort by PJM to 17

ensure RAS are properly designed and only deployed where appropriate. Mr. Wharton states 18

that, given that PJM has areas in which it is a tightly coupled network, “…having multiple RASs 19

within a single area increases the likelihood of a misoperation.”29 Avoiding multiple RASs in a 20

single area does not preclude use of RAS as a permanent solution across appropriate parts of the 21

25  California ISO, California ISO Planning Standards, effective February 2, 2023.
26  California ISO cites the following potential reliability considerations associated with RAS: “With the increased transmission system utilization that comes with application of RAS, there can be increased exposure to not meeting system performance criteria if the RAS fails or inadvertently operates. Transmission outages can become more difficult to schedule due to increased flows across a larger portion of the year; and/or the system can become more difficult to operate because of the independent nature of the RAS. If there are a large number of RAS, it may become difficult to assess the interdependency of these various schemes on system reliability. In addition, as RAS has become progressively increasing in complexity, it is necessary to consider the level of logic complexity through combining multiple features that were acceptable individually but that could compound to a level that cannot be integrated into market operation.”  California ISO, California ISO Planning Standards, effective February 2, 2023, p. 11.
27  California ISO, California ISO Planning Standards, effective February 2, 2023, p. 11.
28  AEMO, Remedial Action Scheme Guidelines; Western Electricity Coordinating Council (WECC) Relay Work Group, Remedial Action Scheme Review Subcommittee, Remedial Action Scheme Design Guide, July 2022.
29  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), p.7.

PDF page 58

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 24 of 25
PJM footprint (much of which is less dense than the Northern Virginia example that Mr. 1

Wharton cites). PJM could implement this principle in a RAS guideline, similar to CAISO’s 2

guideline that “[o]verlapping RAS (i.e., two different RAS monitoring one or more of the same 3

elements or contingencies) is not allowed.”30 Further, a given RAS can only monitor a limited 4

number of conditions (e.g., contingencies on specified elements). As Mr. Wharton points out, 5

“Since the PJM network is tightly coupled with multiple transmission lines, the RAS or multiple 6

RASs will need to monitor and activate for a multitude of conditions. Typically, a RAS monitors 7

one specific condition and is armed to respond to one condition.” PJM could implement such a 8

limit in a RAS standard, similar to CAISO’s provision that “There should be no more than 6 9

contingencies (P1–P7) that would trigger the operation of a RAS” and “The RAS should not be 10

monitoring more than 4 system elements or variables.”31 (We note that CAISO appears to allow 11

broader monitoring than Mr. Wharton suggests is typical in PJM).

12

30  California ISO, California ISO Planning Standards, effective February 2, 2023, p. 13.
31  California ISO, California ISO Planning Standards, effective February 2, 2023, p. 12.

PDF page 59

Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 25 of 25
Affidavit of Andrew Levitt

I, Andrew Levitt, do hereby swear that I have co-authored the Affidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true and accurate to the best of my knowledge and belief.

Andrew Levitt

Date: March 25, 2026
Affidavit of Aniruddh Mohan

I, Aniruddh Mohan, do hereby swear that I have co-authored the Affidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true and accurate to the best of my knowledge and belief.

Aniruddh Mohan

Date: March 25, 2026