EL25-49-000 · 2026-03-25 · Eolian, L.P.Antora Energy LLCCalibrant Energy and 4 others

Reply Brief of Joint Co-Location Developers and Motion to Intervene Out-of-Time of Calibrant, Convergent, U.S. Energy Storage Coalition, and Versus

Text extracted from the eLibrary original (SHA-256 d312c35f5b6f624d…). Download the original from the official source.

Contents · 18 sections
  1. I. JOINT CO-LOCATION DEVELOPERS’ INTEREST IN THE PROCEEDING p. 4
  2. II. ARGUMENT p. 6
  3. A. The Co-Location Order requires that Non-Firm CDS be available as needed p. 6
  4. B. PJM should clarify that its transmission service requirements for energy p. 13
  5. C. PJM’s tariff should clarify when and how Non-Firm CDS and Interim NITS p. 17
  6. D. PJM’s tariff should clarify that a Co-Located Load receiving Interim NITS p. 18
  7. E. PJM TOs have not justified charging the same rate for Non-Firm CDS and p. 20
  8. F. PJM’s proposed penalty provisions are unjust and unreasonable. p. 23
  9. G. PJM’s proposed effective date of June 2029 is unjust and unreasonable. p. 27
  10. III. CONCLUSION p. 30
  11. Attachment A p. 34
  12. I. QUALIFICATIONS p. 36
  13. A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy p. 36
  14. II. ASSIGNMENT p. 37
  15. III. BACKGROUND p. 37
  16. IV. SUMMARY p. 38
  17. V. ASSESSMENT OF THE PJM PROPOSAL AND POTENTIAL ENHANCEMENTS p. 39
  18. A. Levitt, J. Pfeifenberger, and A. Mohan, Accelerating the Integration of New Co-located Generation and p. 41

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

But penalties must balance the need to deter conduct that is harmful to the system with the need to limit excessive and unnecessary costs. • Given the urgent need to address the impacts of load growth on the PJM system today, the Commission should require PJM to make the new tariff provisions…
Read this passage Filed comments: Connecting load and generation

I. JOINT CO-LOCATION DEVELOPERS’ INTEREST IN THE PROCEEDING

printed heading

JOINT CO-LOCATION DEVELOPERS’ INTEREST IN THE PROCEEDING AND MOTION TO INTERVENE OUT-OF-TIME OF CALIBRANT, CONVERGENT, U.S.
Read this passage

II. ARGUMENT

printed heading

II.
Read this passage

A. The Co-Location Order requires that Non-Firm CDS be available as needed

printed heading · Topic match: Reliability and curtailment

PJM proposes to limit the availability of Non-Firm CDS to “the event the Co-Located Generating Facility is on outage and unable to provide any of the dedicated level of energy.”11 But the Co-Location Order made clear that Non-Firm CDS is to be available for reservation by 8 Id.
Read this passage Filed comments: Reliability and curtailment

B. PJM should clarify that its transmission service requirements for energy

printed heading · Topic match: Connecting load and generation

See PJM Initial Brief, Illustrative Tariff, Part XI, Subpart B, § 709.2(b) (“An Eligible Customer taking service on behalf of a Co-Located Load must apply for Non-Firm Contract Demand Transmission Service equivalent to the megawatt level of the Co-Located Generating Facility dedicated to serving…
Read this passage Filed comments: Connecting load and generation

C. PJM’s tariff should clarify when and how Non-Firm CDS and Interim NITS

printed heading · Topic match: Reliability and curtailment

Because the curtailment trigger for Non-Firm CDS and Interim NITS and curtailment priority order of those services “affect rates and service significantly,” and “are realistically susceptible of specification,” they must be included in the tariff.49 48 PJM Initial Brief, Illustrative Tariff, Part…
Read this passage Filed comments: Reliability and curtailment

D. PJM’s tariff should clarify that a Co-Located Load receiving Interim NITS

printed heading · Topic match: Reliability and curtailment

To the extent that PJM does intend to limit Co-Located Loads taking Interim NITS’ abilities to be served by co-located generators, the Commission must not adopt it.
Read this passage Filed comments: Reliability and curtailment

E. PJM TOs have not justified charging the same rate for Non-Firm CDS and

printed heading · Topic match: Cost allocation

For example, to be cost competitive in serving the thermal demands of industrial customers, thermal energy storage resources must be able to take power when low-cost supply is available because low and zero marginal cost generation availability exceeds local demand (often because the generation…
Read this passage Filed comments: Cost allocation

F. PJM’s proposed penalty provisions are unjust and unreasonable.

printed heading · Topic match: Reliability and curtailment

PJM proposes a draconian penalty structure that threatens to effectively deny customers service after a single failure to curtail or shed load, regardless of the cause.
Read this passage Filed comments: Reliability and curtailment

G. PJM’s proposed effective date of June 2029 is unjust and unreasonable.

printed heading · Topic match: Reliability and curtailment

A, Levitt & Mohan Aff. at 21. 29 PJM also argues that it needs until June 2029 to “make the necessary modifications to the PJM core Markets and Operations systems.”87 PJM claims that “implementing the proposed Curtailment priorities applicable to Interim NITS and Non-Firm Contract Demand…
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION The PJM region faces significant challenges.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: March 25, 2026 /s/ Eric Stoutenburg Eric Stoutenburg Chief Development Officer Eolian L.P. 988 Howard Ave.
Read this passage

Attachment A

printed heading

Attachment A Affidavit of Andrew Levitt and Aniruddh Mohan Docket No.
Read this passage

I. QUALIFICATIONS

printed heading

QUALIFICATIONS 1 Our names are Andrew Levitt and Aniruddh Mohan.
Read this passage

A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy

printed heading

Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No.
Read this passage

II. ASSIGNMENT

printed heading · Topic match: Connecting load and generation

We assessed: the 4 proposed eligibility for Non-Firm Contract Demand Transmission Service (“Non-Firm CDS” or 5 “NFCDS”); operational requirements for NFCDS and Interim Network Integration Transmission 6 Service (“Interim NITS”); PJM interconnection study procedures for co-located load and supply 7…
Read this passage Filed comments: Connecting load and generation

III. BACKGROUND

printed heading · Topic match: Connecting load and generation

In its compliance filing, PJM proposes 19 revisions to its Open Access Transmission Tariff addressing, among other things, behind-the- 20 meter generation, necessary study procedures, and the framework for new transmission services 21 applicable to co-located load.
Read this passage Filed comments: Connecting load and generation

IV. SUMMARY

printed heading · Topic match: Connecting load and generation

To summarize, we identify these enhancements as: 10 Provide NFCDS when needed and available (i.e., not limited only to periods when the co-located 11 generator is on outage), improving efficiency and speed to power; 12 For loads that take Interim NITS, obligate curtailment to the level of net zero…
Read this passage Filed comments: Connecting load and generation

V. ASSESSMENT OF THE PJM PROPOSAL AND POTENTIAL ENHANCEMENTS

printed heading · Topic match: Reliability and curtailment

Load must request reservation of 500 MW or nothing.
Read this passage Filed comments: Reliability and curtailment

A. Levitt, J. Pfeifenberger, and A. Mohan, Accelerating the Integration of New Co-located Generation and

printed heading · Topic match: Reliability and curtailment

PJM can offer Interim NITS without unnecessary 11 curtailments by obligating curtailment to net zero 12 withdrawals and clarifying resource adequacy 13 curtailment obligations 14 PJM proposes curtailment of load taking Interim NITS not only for transmission security reasons 15 but also for resource…
Read this passage Filed comments: Reliability and curtailment