EL25-49-000 · 2026-03-25 · Advanced Energy UnitedSolar Energy Industries Association
Reply Brief of Advanced Energy United and the Solar Energy Industries Association
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C., et.al.
)
Docket Nos. EL25-49-000
)
EL25-49-001
)
Large Loads Co-Locating at Generating )
AD24-11-000
Facilities
)
)
Constellation Energy Generation, LLC
)
v.
)
EL25-20-000
PJM Interconnection, L.L.C.
)
(Consolidated)
)
REPLY BRIEF OF ADVANCED ENERGY UNITED AND THE SOLAR ENERGY
INDUSTRIES ASSOCIATION
I. Introduction
Pursuant to paragraph 219 and ordering paragraphs (D) and (E) of the Order on Show Cause Proceeding (“Co-Location Order”) Directing Compliance Filings, Establishing Paper Hearing, and Granting in Part and Denying in Part Complaint issued by the Federal Energy Regulatory Commission (“Commission”) on December 18, 2025,1 Advanced Energy United
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 219 and Ordering Paragraphs (D) and (E) (2025) (“Co- Location Order”)
PDF page 2
2
(“United”)2 and the Solar Energy Industries Association (“SEIA”)3 submit this brief in reply to PJM Interconnection, L.L.C.’s (“PJM”) February 23, 2026, Initial Brief (“PJM Brief”).4 The Commission issued the Co-Location Order in response to an unprecedented surge in requests to interconnect large co-located loads—most notably hyperscale data centers and advanced manufacturing facilities—to generating facilities within the PJM Interconnection region. The Commission found that PJM’s existing tariff was unjust and unreasonable because it lacked service options that allow customers to flexibly manage their withdrawals from the transmission system, and lacked clarity and consistency in the rates, terms, and conditions applicable to co-located load arrangements.5 The Commission recognized that the absence of a clear, accessible regulatory framework was itself a barrier to the rapid integration of new load, with significant consequences for reliability and economic development. The Commission therefore directed PJM to develop three new transmission services as permanent and transitional alternatives to existing Network Integration Transmission Service (“NITS”) for Eligible Customers serving co-located loads that are willing and able to control their withdrawals from the transmission system: Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, and Interim Network Integration Transmission Service (“Interim NITS”).62 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean and affordable. Advanced Energy United is the only industry association in the United States that represents the full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. The comments expressed in this filing represent the position of Advanced Energy United but may not represent the views of any particular member.3 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar industry, but do not necessarily reflect the views of any particular member with respect to any issue.4 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 (Feb. 23, 2026) (“PJM Brief”).5 Co-Location Order at P 2.6 Id.
PDF page 3
3
PJM submitted its initial brief on February 23, 2026, setting forth illustrative tariff language and responding to the Commission's paper hearing questions on the non-rate terms and conditions of the three new transmission services. While PJM's proposed framework represents a meaningful attempt to address the novel operational and reliability challenges associated with co- located load, PJM’s initial brief falls short of the Co-Location Order's requirements in several important respects that, if left unaddressed, would produce a framework unlikely to achieve the Commission's objectives.
First, PJM’s proposed Non-Firm Contract Demand Transmission Service departs
materially from the Commission's directives by restricting the service to periods when the co- located generating facility is on outage. This converts a service the Commission designed as a flexible, as-available option during normal operating conditions into a narrow standby product. The Commission was explicit: Non-Firm Contract Demand Transmission Service “must be available during normal operations,” with reservations available “as needed during normal, non- emergency system operating conditions.”7 PJM’s illustrative tariff contradicts this by limiting eligibility to obtain the service “only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage.”8 The Commission should reject this restriction and direct PJM to implement Non-Firm Contract Demand Transmission Service consistent with the Co-Location Order.
Second, PJM’s curtailment framework fails to provide sufficient transparency for prospective customers to make informed commercial decisions about whether to take Interim NITS or Non-Firm Contract Demand Transmission Service. PJM has offered no meaningful information about the expected frequency or duration of curtailment under real system
7 Id. at P 215.8 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2 (b).
PDF page 4
4
conditions. Moreover, PJM's curtailment language is internally inconsistent—using “may” to describe curtailment before pre-emergency demand response in one instance and “will” in another—introducing ambiguity that must be resolved.9 Without greater transparency and certainty, curtailment risk will suppress participation in these new services and frustrate the Commission’s goals.
Third, while appropriate study of co-located generating facilities is necessary to protect transmission system reliability, PJM’s proposal to subject all co-located generating facilities, including those that have no intention of ever exporting power to the grid, to the full PJM interconnection queue process is unnecessarily burdensome and inconsistent with the Co- Location Order’s speed-to-power objectives. The interconnection queue was designed to study the deliverability and system impacts of exporting generators; applying it wholesale to non- exporting resources that will serve only their co-located load imposes multi-year delays and costs that are disproportionate to any reliability benefit and would further burden an interconnection queue that is already significantly backlogged, to the detriment of the broader PJM region. The Commission should direct PJM to develop a streamlined study and registration pathway for non- exporting co-located generating facilities that provides PJM with the operational visibility it needs without subjecting these resources to the full burdens of the interconnection queue. Fourth, PJM’s framework fails to honor the Co-Location Order’s directive that co-located loads curtailed from grid service under Interim NITS must be permitted to continue taking energy directly from their co-located generating facility. The Commission stated that “when curtailed, Eligible Customers taking this transmission service on behalf of Co-Located Loads may be able to continue to take energy from the Interconnection Customer with which they are
9 PJM Initial Brief at 63-64
PDF page 5
5
co-located if PJM’s Tariff otherwise allows.”10 This is the foundational commercial rationale for co-location with a new generating facility, and denying it directly conflicts with the Co-Location Order’s speed-to-power objectives.
The Commission should direct PJM to revise its proposed terms and conditions to: (1) make Non-Firm Contract Demand Transmission Service available during normal operating conditions, not solely during generating facility outages; (2) provide greater transparency regarding curtailment triggers and frequency, and resolve the ambiguity in its curtailment priority language; (3) establish a streamlined study and registration pathway for non-exporting co-located generating facilities in lieu of the full interconnection queue process; and (4) confirm that Eligible Customers taking Interim NITS may continue to take energy from their co-located generating facility during curtailment periods, so long as there are no net injections or withdrawals from the co-located facility, consistent with the Co-Location Order.
II. REPLY AND PROTEST
A. PJM’s Non-Firm Contract Demand Transmission Service Inverts the
Commission’s Intent
The Commission directed PJM to develop Non-Firm Contract Demand Transmission Service as a permanent transmission service option available to Eligible Customers seeking flexible, as-available access to the transmission system on behalf of co-located loads during normal operating conditions.11 PJM’s proposed implementation of this service departs materially from that directive by restricting its availability to periods when the co-located generating
10 Co-Location Order at P 201.11 Id. at P 215.
PDF page 6
6
facility is on outage.12 This restriction inverts the Commission’s intent, renders the service commercially unworkable for the loads it was designed to serve, and must be rejected. The Commission’s directive on Non-Firm Contract Demand Transmission Service is unambiguous. In the Co-Location Order, the Commission stated:
We find that the new Non-Firm Contract Demand transmission
service must be available during normal operations and curtailed
during emergency operations (i.e., it will be curtailed before existing
firm transmission services and the new Firm Contract Demand
Transmission Service). Under this service, Eligible Customers may
reserve transmission service on behalf of a Co-Located Load as
needed during normal, non-emergency system operating conditions.
Reservations under this service would be available only when there
is available transmission capacity, similar to existing non-firm
transmission service options in the Tariff.13
The Commission further specified that reservations under Non-Firm Contract Demand Transmission Service “shall be available for terms ranging from one hour to one month, consistent with the terms available for Non-Firm PTPS in the PJM Tariff.”14 The reference to Non-Firm Point-to-Point Transmission Service (“Non-Firm PTPS”) is instructive: Non-Firm PTPS is available on an as-available basis during normal system conditions across a range of reservation periods, and is not limited to any particular triggering event such as a generator outage as is required in PJM’s proposed tariffs.15 The Commission’s reference to Non-Firm PTPS makes clear that Non-Firm Contract Demand Transmission Service must function as a flexible, broadly available service option, not a narrow emergency backstop. After explaining that there are situations in which Co-Located Loads may withdraw energy from the transmission system from time to time when transmission capacity is available,
12 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b).13 Co-Location Order at P 215.14 Id.15 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b).
PDF page 7
7
the Commission provided an illustrative example of how Non-Firm Contract Demand Transmission Service might be used: “an Eligible Customer could seek a transmission reservation for a Co-Located Load in advance for the duration of an expected outage of the associated generator.”16 This example describes one likely and common use case. It does not define or limit the circumstances under which the service may be available. That the Commission offered one example of how the service might be used does not mean that example defines the only circumstances under which the service is available. The Co-Location Order contains no such limitation.
Contrary to the Commission’s clear directive, PJM's illustrative tariff restricts Non-Firm Contract Demand Transmission Service to a narrow set of circumstances that bear little resemblance to the service the Commission ordered. Specifically, PJM proposes that “an Eligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co- Located Generating Facility dedicated to serving the Co-Located Load is on outage.”17 PJM further characterizes the service as a “standby product” to be relied upon “under limited circumstances,”18 and states that it “anticipates that in practice, requests for Non-Firm Contract Demand Transmission Service will be at the MW level the Co-Located Generating Facility has dedicated to serving the Co-Located Load,” available “only up to the MW level that the Co- Located Generating Facility is on outage.”19
This is not the service the Commission ordered. The Co-Location Order contemplated a service available “as needed during normal, non-emergency system operating conditions,” a
16 Co-Location Order at P 214.17 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b). 18 PJM Brief at 10.19 Id. at 32.
PDF page 8
8
standard that encompasses a wide range of circumstances in which a co-located load may wish to draw supplemental energy from the transmission system, not merely periods of generator unavailability. PJM has taken an illustrative example from the Co-Location Order and elevated it into the governing rule, while discarding the broader principle the Commission established. This approach is inconsistent with the Co-Location Order and must be rejected.
The practical consequences of PJM's restriction are significant. Hybrid resources serving co-located loads, including storage paired with solar and other technologies with variable or intermittent output profiles, may require supplemental grid withdrawals not only during planned outages but during any period in which the co-located generating facility’s output is constrained, reduced, or otherwise insufficient to meet the full gross demand of the co-located load. Under PJM's proposed framework, such a customer could not access Non-Firm Contract Demand Transmission Service to cover that shortfall unless the generating facility is formally “on outage” as defined in PJM’s tariff. This creates a significant gap in service availability that would force many customers to take full NITS—with all of its associated costs and planning obligations— simply to access the flexibility that Non-Firm Contract Demand Transmission Service was designed to provide.
PJM's supporting testimony attempts to justify this restriction on operational and planning complexity grounds, pointing to the challenges of designing protection systems that adapt to varying system conditions and the risks of Remedial Action Scheme interactions in a tightly coupled network. These concerns do not support PJM’s proposed limitation. The Commission was fully aware that co-location arrangements would require novel operational accommodations when it issued the Co-Location Order; PJM had raised precisely these
PDF page 9
9
protection scheme concerns as a reason to resist non-firm service,20 and the Commission directed establishment of Non-Firm Contract Demand Transmission Service, nonetheless, finding it “just and reasonable.” 21 PJM's compliance filing is not the appropriate vehicle to relitigate that policy judgment. To the extent PJM identifies genuine implementation constraints, the appropriate response is a reasonable implementation timeline and clear Commission guidance on protection system requirements, not a fundamental narrowing of the service itself. Notably, PJM’s own testimony acknowledges that protection scheme solutions are workable in the core co-location scenario: PJM witness Wharton concedes that a Remedial Action Scheme triggered by loss of the co-located generating facility “would be overwhelmingly beneficial and would have a minimal impact on the overall grid.”22 The Commission should reject this additional restriction as inconsistent with the Co-Location Order's flexible service design.
Moreover, from a resource adequacy and reliability perspective, there is no basis for restricting Non-Firm Contract Demand Transmission Service to outage periods. Non-Firm Contract Demand Transmission Service is by design curtailed before firm transmission services and before NITS in the curtailment hierarchy and is available only when transmission capacity exists.23 These safeguards already ensure that Non-Firm Contract Demand Transmission Service does not displace higher-priority service or impose undue reliability burdens on the system. Arbitrarily restricting availability to outage periods provides no additional reliability protection, it simply reduces the utility of the service without any corresponding system benefit. PJM's proposed restriction of Non-Firm Contract Demand Transmission Service to generating facility outage periods is inconsistent with the Co-Location Order and must be
20 “Answer of PJM Interconnection, L.L.C.” Docket No. EL25-49-000 (March 24, 2025) at pages 13-15. 21 Co-Location Order at P205 and 215.22 PJM Brief, Attachment C “Affidavit of Matthew Wharton on Behalf of PJM, Interconnection, L.L.C.” at P 25.23 Co-Location Order at P 215.
PDF page 10
10
rejected. The Commission should direct PJM to revise and file illustrative Tariff, Part XI, Subpart B, section 709.2(b) to remove the outage-only limitation and replace it with language consistent with the Co-Location Order's directive that the service be available as needed during normal, non-emergency system operating conditions, subject to available transmission capacity and the curtailment priority established in the Co-Location Order. This revision would restore the service to the form the Commission intended: A flexible, as-available transmission option that gives co-located loads a meaningful and commercially viable alternative to full NITS. The Commission should find PJM’s outage-only restriction on Non-Firm Contract Demand Transmission Service to be unjust and unreasonable and direct PJM to revise its illustrative tariff accordingly.
B. Additional Certainty Regarding Potential Curtailment is Needed to Enable
Uptake of the Non-Firm and Interim NITS Options
The Commission directed PJM to create Non-Firm Contract Demand Transmission
Service and Interim NITS to accommodate co-located load arrangements, and these services must be genuinely accessible and commercially viable alternatives to full NITS for co-located loads willing and able to limit their grid withdrawals.24 For these services to achieve that purpose, prospective customers must be able to make informed business decisions about whether to take service, and that requires a clear, consistent, and transparent curtailment framework. PJM’s initial brief fails on both counts: it introduces internal inconsistency in the curtailment priority hierarchy, and it provides no meaningful information about the conditions under which curtailment will occur in practice. The Commission should direct PJM to resolve these deficiencies before these services are implemented.
24 Id at P214-215.
PDF page 11
11
1. PJM's Curtailment Priority Language Is Internally Inconsistent and
Must Be Clarified
The Co-Location Order established a clear curtailment hierarchy: Interim NITS and Non- Firm Contract Demand Transmission Service are to be curtailed before firm transmission services and existing NITS, and before pre-emergency demand response resources are dispatched.25 This hierarchy is a critical feature of the new services, making them compatible with system reliability and defining the conditions under which co-located loads can expect their service to be interrupted.
PJM’s Brief implements this hierarchy but does so in contradictory terms that must be clarified and reconciled to confirm consistency with the Commission’s directive. In describing curtailment procedures applicable to both Interim NITS and Non-Firm Contract Demand Transmission Service, PJM states that “the Transmission Provider may also curtail Interim NITS or Non-Firm Contract Demand Transmission Service prior to dispatching the Pre-Emergency Load Response Program.”26 Yet in the very next sentence, PJM states that “this effectively means that Interim NITS and Non-Firm Contract Demand Transmission Service will be curtailed before Demand Response resources are called upon to reduce load.”27 PJM uses the same contradictory language its discussion of the same curtailment trigger later in the brief when discussing Interim NITS curtailment procedures.28
This inconsistency may be unintentional but must be resolved. The difference between a discretionary curtailment authority (“may”) and a mandatory curtailment obligation (“will”) has material consequences for how co-located loads plan their operations and evaluate their
25 Co-Location Order at P 215; see also PJM Brief at 63.26 PJM Brief at 63 (emphasis added).27 Id at 63-64.28 Id at 72.
PDF page 12
12
curtailment exposure. A customer deciding whether to take Non-Firm Contract Demand Transmission Service or Interim NITS needs to know whether curtailment before pre-emergency demand response is a certainty or a possibility. Likewise, demand response providers require certainty as to how their obligations will be impacted by the new Non-Firm Contract Demand Transmission Service and Interim NITS: Will customers on these non-firm services always be curtailed prior to pre-emergency demand response? PJM's Brief answers both simultaneously and inconsistently, leaving the customer no clearer on their actual exposure than before. The Commission should direct PJM to resolve this inconsistency in its revised filing and confirm unambiguously whether curtailment prior to pre-emergency demand response dispatch is mandatory or discretionary.
2. PJM's Curtailment Framework Provides Insufficient Transparency for
Customers to Make Informed Commercial Decisions
Beyond the readily fixable “may/will” inconsistency, PJM’s curtailment framework suffers from a deeper transparency problem: PJM has provided no information about the conditions that would actually trigger curtailment of Interim NITS or Non-Firm Contract Demand Transmission Service in practice. These are novel services for which no historical curtailment data currently exists. There is no modeling of expected curtailment frequency or duration under the proposed framework, and no examples of how the curtailment process would operate for a hypothetical co-located arrangement.
This information must be provided for customers to make informed business decisions on the transmission service that best serves their operational and commercial needs. The decision to take Non-Firm Contract Demand Transmission Service or Interim NITS rather than full NITS is fundamentally a commercial decision about the tradeoff between lower service costs and potentially faster interconnection timelines and higher curtailment exposure. A co-located load
PDF page 13
13
cannot make an informed decision without understanding how often and under what conditions its service is likely to be interrupted. Without that information, the perceived risk of curtailment will likely far outstrip the probable reality, and prospective customers will default to full NITS simply to avoid uncertainty. The result would be exactly the opposite of what the Commission intended: Rather than expanding the range of viable service options for co-located loads, the new services would go largely unused.
The Commission has long recognized that transparency is a prerequisite for competitive, well-functioning markets. The same principle applies here. Just and reasonable rates, terms, and conditions are not merely those that are technically correct on paper, they must be sufficiently clear and transparent to enable customers to make informed decisions about whether and how to participate.29 PJM’s curtailment framework, as proposed, does not meet that standard.
3. The Commission Should Direct PJM to Provide Curtailment
Transparency Mechanisms Prior to Implementation
While uncertainty cannot be entirely avoided for customers selecting the Non-Firm Contract Demand Transmission Service and Interim NITS, it can be minimized. The Commission should direct PJM to take concrete steps to provide prospective customers with the information they need to evaluate their curtailment exposure under Non-Firm Contract Demand Transmission Service and Interim NITS before these services are implemented.
First, the Commission should require PJM to resolve the “may/will” inconsistency in its curtailment priority language and confirm the specific conditions under which Interim NITS and Non-Firm Contract Demand Transmission Service will be curtailed relative to pre-emergency demand response dispatch and other system conditions.
29 “Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities”, FERC Order No. 888, FERC Stats. & Regs. ¶ 31,036, 61 Fed. Reg. 21,540 (1996).
PDF page 14
14
Second, the Commission should require PJM to develop and publish historical analysis and forward-looking modeling of curtailment frequency and duration for Interim NITS and Non- Firm Contract Demand Transmission Service, informed by historical system conditions in PJM broken down by zone, where available. This analysis should be made available to prospective customers and developers as part of the service application process so that they can evaluate their curtailment exposure prior to committing to service.
Third, PJM should dedicate time at a stakeholder meeting prior to implementation to walk through the curtailment study process with a hypothetical co-located arrangement. This exercise would give the market a concrete, practical understanding of how curtailment decisions are made, what triggers them, and what a customer can expect in terms of frequency and duration under a range of system conditions. As a predicate to that stakeholder engagement, PJM should set out in its reply brief a written explanation of how it intends to operationalize curtailment for Non-Firm Contract Demand Transmission Service, including the criteria PJM will use to determine when curtailment is warranted, the sequence in which co-located loads will be curtailed relative to other non-firm services, and the mechanism by which curtailment instructions will be communicated and enforced. Without that written explanation in this proceeding and, ultimately, in PJM’s Business Practice Manuals, neither the Commission nor affected parties can evaluate whether PJM's proposed curtailment framework is consistent with the Co-Location Order’s requirement that Non-Firm Contract Demand Transmission Service be available “as needed during normal, non-emergency system operating conditions.”30 Greater transparency at this stage will enable informed market participation and reduce the uncertainty that would otherwise suppress uptake of these new services.
30 Co-Location Order at P 215.
PDF page 15
15
PJM routinely gives market participants the information they need to evaluate the costs and risks of participating in other PJM services,31 and the novelty of these new transmission services makes the need for upfront transparency a necessity. The Commission should ensure that PJM’s implementation plan includes these transparency measures so that Non-Firm Contract Demand Transmission Service and Interim NITS can fulfill their intended purpose as genuinely accessible, commercially viable alternatives to full NITS for co-located loads across the PJM region.
C. PJM Would Unnecessarily Subject All Co-Located Generating Facilities to a Full Interconnection Study.
The Co-Location Order was designed to accelerate the integration of new load and new generation into the PJM region at a time of unprecedented demand growth. PJM’s Brief undermines that objective by proposing that all co-located generating facilities—including those that have no intention of ever exporting power to the grid—must navigate the full PJM interconnection queue before they can participate in Non-Firm Contract Demand Transmission Service or Interim NITS. While PJM indisputably requires sufficient information about both exporting and non-exporting co-located generating facilities to reliably plan and operate the transmission system, subjecting non-exporting resources to the full interconnection queue imposes costs, delays, and administrative burdens that are wholly disproportionate to the reliability benefits achieved. This outcome would further strain an interconnection queue that is already significantly backlogged, all to the detriment of the broader PJM region and the customers it serves.
31 Such as the Base Residual Auction’s planning parameters and load forecasts, the interconnection queue with cluster study reports and cost estimates, and historical dispatch data for demand response customers.
PDF page 16
16
PJM’s proposal appears to require all co-located generating facilities participating in the new transmission services will be required to go through PJM’s interconnection queue, and it acknowledges that this will contribute to delays in the availability of the new transmission services. PJM states that “the process of an Eligible Customer's generation getting through the interconnection queue, being constructed, and becoming operational will likely take more than three years, particularly in light of current supply chain issues, Transmission Owner and PJM queue requirements, and RPM auction timelines.”32 PJM makes no distinction between generating facilities that intend to export power to the grid and those that are dedicated exclusively to serving their co-located load.
This one-size-fits-all approach is fundamentally misaligned with the purpose of the interconnection queue and the objective of achieving speed-to-power. PJM’s interconnection process was designed to study the deliverability and system impact of generating facilities that intend to inject power into the transmission system and participate in PJM’s energy and capacity markets. The interconnection studies include network upgrades analysis, deliverability assessments, and capacity market participation determinations and are premised on the assumption that the generator will export power to the grid and that the grid must be capable of receiving and delivering that power to load. These assumptions do not apply to a non-exporting co-located generating facility whose output is dedicated entirely to serving its co-located load and that will never inject power into the system.
Requiring non-exporting co-located generating facilities to undergo this process does not make the transmission system more reliable, it simply foists multi-year delays and significant costs on resources that pose none of the deliverability risks the interconnection queue was
32 PJM Brief at 82.
PDF page 17
17
designed to address. As was argued in the related proceeding in Docket No. ER26-1479, non- exporting resources “do not require deliverability given their intent to serve only the co-located load” and will “rarely, if ever, trigger network upgrades,” making the full interconnection study process a “purely administrative hurdle with no technical or reliability benefit.”33 The consequences of PJM’s approach extend beyond the individual customer. PJM itself acknowledges that its interconnection queue has been severely backlogged—it effectively closed the queue to new applicants in 2022 and will not initiate the first cluster study of new requests until later this year.34 Forcing non-exporting co-located generating facilities into that queue would artificially inflate the number of projects competing for study resources and queue positions, further delaying all projects in the queue, including the exporting generators whose deliverability the interconnection process was actually designed to assess. This is precisely the kind of outcome the Co-Location Order sought to avoid.
The Co-Location Order’s objective is not merely a commercial convenience for
individual customers, it reflects the Commission’s recognition that the PJM region faces urgent resource adequacy challenges that require new generation and new load to come online as quickly as possible.35 Nevertheless, the Commission should not exempt non-exporting co-located generating facilities from all study or registration requirements. PJM needs sufficient information about these resources to model them accurately, ensure the reliability and stability of the transmission system, and establish the necessary systems required under the new transmission services. Those are legitimate operational needs.
33 “Limited Protest of Advanced Energy United and the Solar Energy Industries Association,” Docket No. ER26- 1479-000, at 24 (Mar. 16, 2026).34 See PJM Interconnection, L.L.C., PJM Completes Interconnection Reform Transition Cycle 1 Studies (Sept. 22, 2025), https://insidelines.pjm.com/pjm-completes-interconnection-reform-transition-cycle-1-studies/.35 Co-Location Order at P 200
PDF page 18
18
The Commission should instead direct PJM to develop a study and registration pathway that is proportional to the actual technical impact that non-exporting resources have on the transmission system. This process should provide PJM with the information it needs without subjecting non-exporting resources to the full burdens of the interconnection queue. Such a pathway could include, at a minimum, standardized submission of key technical data including nameplate capacity, generation profile and operational parameters, a binding non-export commitment enforceable through the service agreement, telemetry and metering capabilities sufficient to support PJM's real-time operational visibility, and single-line diagram and delivery point information. These requirements would give PJM the information it needs to reliably incorporate non-exporting co-located generating facilities into its planning and operations without the multi-year delays and costs associated with a full interconnection study. This approach is consistent with the Commission's broader policy of tailoring
interconnection requirements to the actual system impacts of the resource seeking interconnection.36 It is also consistent with the position advanced in the related proceeding in Docket No. ER26-1479, where United and SEIA explained that PJM should “establish a streamlined, expedited process specifically for resources that do not intend to export to the grid” with requirements “proportional to the actual technical impact the resources have on the grid.”37 This same logic has been used on other regions. In another proceeding Commissioner Rosner highlighted SPP’s approach of limiting a generator’s grid output to match co-located load demand as a model worth emulating because, when generation is matched to load, “the impacts of adding load and generation to the transmission system effectively cancel each other out, which
36 “Reform of Generator Interconnection Procedures and Agreements,” Order No. 845, 163 FERC ¶ 61,043 (2018)37 “Limited Protest of Advanced Energy United and the Solar Energy Industries Association,” Docket No. ER26- 1479-000, at 24 (Mar. 16, 2026)
PDF page 19
19
minimizes the need for time-consuming transmission upgrades.”38 A non-exporting co-located generator presents an even more clear-cut example of this principle, and PJM's interconnection requirements should reflect it. The Commission should adopt that principle here and direct PJM to develop and implement a streamlined registration and study pathway for non-exporting co- located generating facilities as part of its revised terms and conditions for the new transmission services.
D. The Commission Should Direct PJM to Explicitly Allow Co-Located Loads
Under New Transmission Service to Access On-site Generation During
System Constraint Periods
The Interim NITS as currently proposed leaves unclear whether co-located loads may access on-site generation during system constraint periods. PJM’s brief outlines significant operational complexities and restrictions for Co-Location but is unclear on the use of on-site generation post-curtailment. This ambiguity creates uncertainty, which almost certainly will deter loads from considering Interim NITS. To provide clarity, encourage fair access, and align with the Commission’s Order, the Commission should direct PJM to explicitly allow co-located loads employing Interim NITS to use on-site generation during system constraints. PJM is explicit that interim NITS will be among the first services curtailed during emergencies and must be prepared to shed load when system reliability requires it.39 Additionally, Interim NITS may be curtailed prior to dispatching emergency programs.40 Given the curtailment hierarchy, it is likely that interim NITS will be curtailed from the grid early and often during system constraints to shed load and ensure reliability. However, it is unclear
38 Southwest Power Pool, Inc. 194 FERC ¶ 61,031, Rosner Concurrence at P 2.39 Initial brief at 63. (Response to Question 11, § A: Under the illustrative Tariff provisions, Interim NITS and Non- Firm Contract Demand Transmission Service will be curtailed before Firm Contract Demand Transmission Service and NITS.”)40 PJM brief at 63.
PDF page 20
20
whether loads taking interim NITS will be able to rely on their own co-located generating facility during these times of curtailment. PJM’s filing makes no clear statement on restricting on-site generation; however, PJM was clear in stakeholder discussions that, if curtailed, interim NITS customers “cannot take energy from co-located generator (no netting under system conditions that required curtailment).”41 Such a restrictive approach is inconsistent with the Co-Location Order, which clearly states: “when curtailed, Eligible Customers taking this transmission service on behalf of Co-Located Loads may be able to continue to take energy from the Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”42 If PJM intends to restrict co-located loads from accessing on-site generation while using interim NITS, this would be a fundamental flaw in the Interim NITS framework and a direct violation of the Commission’s order.
During system constraints, without clearer tariff language, co-located loads could be restricted from both the grid and on-site generation to serve their load. This removes the benefit of co-locating with a generator. On-site generation resources are critical tools for customers to manage their energy needs and enhance reliability. One of the main benefits of the Interim NITS option for co-located loads comes from being able to connect to on-site generation quickly while still meeting reliability needs. The grid benefits from adding load that does not impact system reliability, if the generation serving the load is new generation. While PJM's concern about existing generation being repurposed to serve new loads is understandable, the proposed framework would confine on-site generation resources during curtailment, undermining the operational flexibility that Non-Firm Demand and Interim NITS should provide.
41 PJM Staff Preliminary/Working Draft of Concepts as of January 23, 2026, 4 (Jan. 23, 2026). https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260126/20260126-item-01--- transmission-services-concepts-for-discussion.pdf42 Co-Location Order at P 201.
PDF page 21
21
This on-site generation should be allowed to serve the load and the load, in turn, should be allowed to be interim NITS provided: (1) it is new generation that has not previously been in the capacity market; and (2) the load is not consuming from the grid during these curtailment periods. By disallowing on-site generation to serve load under the proposed interim NITS, PJM would undermine the utility of the interim NITS service. The Commission should direct PJM to revise its interim NITS proposal to explicitly allow Eligible Customers to use on-site generation to serve load continuously, consistent with the Order, provided that the generation is new and has not previously participated in PJM’s capacity market and that the co-located load does not simultaneously withdraw energy from the transmission system. This clarity will ensure compliance with the Order and support speed to power while maintaining reliability and affordability for all customers.
III. CONCLUSION
For the foregoing reasons, United and SEIA respectfully request that the Commission find that PJM's initial brief does not fully satisfy the requirements of the Co-Location Order and direct PJM to revise its proposed terms and conditions to address the deficiencies identified herein. The Commission's prompt action on these issues is essential to ensure that the new transmission services established by the Co-Location Order fulfill their intended purpose of delivering reliable, flexible, and affordable energy service to co-located loads across the PJM region.
PDF page 22
22
Respectfully submitted,
/s/ Mike Haugh
Caitlin Marquis, Managing Director Mike Haugh, Director
Kelsey Koenig
Advanced Energy United
1801 Pennsylvania Ave. N.W., Suite 410 Washington, D.C. 20006
cmarquis@advancedenergyunited.org mhaugh@advancedenergyunited.org
kkoenig@advancedenergyunited.org
/s/ Melissa Alfano
Melissa Alfano
Senior Director of Energy Markets Counsel Greg Giunta
Senior Manager of Regulatory Affairs and Counsel
Solar Energy Industries Association 1425 K St NW Ste. 1000
Washington, DC 20005
(202) 566-2873
malfano@seia.org
ggiunta@seia.org
PDF page 23
23
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated this 25th day of March 2026.
/s/ Mike Haugh