Reply Brief of Advanced Energy United and the Solar Energy Industries Association
Text extracted from the eLibrary original (SHA-256 3f038c6528d81726…). Download the original from the official source.
Contents · 7 sections
- I. Introduction
- II. REPLY AND PROTEST
- A. PJM’s Non-Firm Contract Demand Transmission Service Inverts the
- B. Additional Certainty Regarding Potential Curtailment is Needed to Enable
- C. PJM Would Unnecessarily Subject All Co-Located Generating Facilities to a
- D. The Commission Should Direct PJM to Explicitly Allow Co-Located Loads
- III. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C., et.al. ) Docket Nos.Read this passage
I. Introduction
printed heading · Topic match: Reliability and curtailment
Moreover, PJM's curtailment language is internally inconsistent—using “may” to describe curtailment before pre-emergency demand response in one instance and “will” in another—introducing ambiguity that must be resolved.9 Without greater transparency and certainty, curtailment risk will suppress…Read this passage Filed comments: Reliability and curtailment
II. REPLY AND PROTEST
printed heading
II.Read this passage
A. PJM’s Non-Firm Contract Demand Transmission Service Inverts the
printed heading · Topic match: Connecting load and generation
In the Co-Location Order, the Commission stated: We find that the new Non-Firm Contract Demand transmission service must be available during normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing firm transmission services and the new Firm Contract…Read this passage Filed comments: Connecting load and generation
B. Additional Certainty Regarding Potential Curtailment is Needed to Enable
printed heading · Topic match: Reliability and curtailment
Additional Certainty Regarding Potential Curtailment is Needed to Enable Uptake of the Non-Firm and Interim NITS Options The Commission directed PJM to create Non-Firm Contract Demand Transmission Service and Interim NITS to accommodate co-located load arrangements, and these services must be…Read this passage Filed comments: Reliability and curtailment
C. PJM Would Unnecessarily Subject All Co-Located Generating Facilities to a
printed heading · Topic match: Connecting load and generation
PJM’s Brief undermines that objective by proposing that all co-located generating facilities—including those that have no intention of ever exporting power to the grid—must navigate the full PJM interconnection queue before they can participate in Non-Firm Contract Demand Transmission Service or…Read this passage Filed comments: Connecting load and generation
D. The Commission Should Direct PJM to Explicitly Allow Co-Located Loads
printed heading · Topic match: Reliability and curtailment
PJM is explicit that interim NITS will be among the first services curtailed during emergencies and must be prepared to shed load when system reliability requires it.39 Additionally, Interim NITS may be curtailed prior to dispatching emergency programs.40 Given the curtailment hierarchy, it is…Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, United and SEIA respectfully request that the Commission find that PJM's initial brief does not fully satisfy the requirements of the Co-Location Order and direct PJM to revise its proposed terms and conditions to address the deficiencies identified herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 25th day of March 2026. /s/ Mike HaughRead this passage