EL25-49-000 · 2026-03-25 · Constellation Energy Generation, LLC
Reply Brief of Constellation Energy Generation, LLC
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
REPLY BRIEF OF CONSTELLATION ENERGY GENERATION, LLC
Constellation submits this reply brief1 to address four issues. First, we urge the
Commission to reject PJM’s proposal to delay by three years–until June 2029,2 beyond the second Trump Administration–the implementation of Interim Network Integration Transmission Service (“Interim NITS”). There is no good reason for such a delay, which will only harm PJM’s ability to timely interconnect new data center load while any needed transmission upgrades are being constructed. Urgency, not delay, is needed. The Commission should therefore establish a separate track to promptly approve the rates and terms for Interim NITS as modified below and make them effective no later than October 1, 2026.3 Urgency was a principal motivation for the Commission’s
1 Constellation Energy Generation, LLC (“Constellation”) files this answer pursuant to Rule 211 of the Commission’s Rules of Practice and Procedure. 18 C.F.R. § 385.211 (2025). 2 Initial Brief of PJM Interconnection, L.L.C. at 79 (Feb. 23, 2026) (“PJM Initial Brief”). 3 See Constellation Apr. 23, 2025 Answer, Exhibit 1 at 9 (“Stockton Declaration”) (“Speed is of the essence for national security.”); see also Written Testimony of Laura V. Swett, Chairman, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1-2 (Feb. 3, 2026) https://www.ferc.gov/news-events/news/testimony-laura-v-swett-chairman-federal- energy-regulatory-commission-us-house (“We’re in a global energy arms race created by the rise of technology, its tremendous load growth, and our push to onshore manufacturing and jobs. I want the United States to lead that race.
PDF page 2
2
directive that PJM create the Interim NITS service in the first instance.4 An effective date three- and-a-half years later fails to meet the spirit and letter of the Commission’s December 18 Order5 and “the administration’s goals to promptly resolve large load issues.”6
Adopting Interim NITS as soon as possible—for pending and future NITS applicants—
should not be difficult, especially because the Indicated Transmission Owners do not propose a new rate methodology but instead propose to charge the same undiscounted NITS rate for Interim
This is the moment to cement America’s energy leadership.”). See also Written Testimony of Lindsay S. See, Commissioner, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 3 (Feb. 3, 2026), https://cms.ferc.gov/news- events/news/testimony-lindsay-s-see-commissioner-federal-energy-regulatory-commission
(“our
national
imperative of speed to power and winning the AI race”); Written Testimony of David LaCerte, Commissioner, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1 (Feb. 3, 2026), https://cms.ferc.gov/news-events/news/testimony-david- lacerte-commissioner-federal-energy-regulatory-commission-house ) (“[T]he AI race, and even more importantly, who ultimately wins, will also fundamentally transform how Americans engage, transact, and compete on the global stage. The AI race is here and America’s power grid is a major battlefield.”).
4 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 201 (2025) (“This willingness to curtail would potentially allow them to obtain service more quickly.”) (“December 18th Order”).5 See id. PP 200-01; see also id. (Rosner, Comm’r, concurring at PP 3-4) (“Because of this, a business-as-usual approach to load growth—planning for generation and load separately—will not suffice to timely meet growing demand while also keeping prices reasonable. Today’s order helps break the logjam.”); id. (Rosner, Comm’r, concurring at P 4) (“And co-located large loads and generators can get online faster and easier than would otherwise be the case. Grid operators like PJM should allow and encourage large loads and generators to pursue these time- and cost-saving co-location arrangements.”); FERC, Fact Sheet: FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news- events/news/fact-sheet-ferc-directs-nations-largest-grid-operator-create-new-rules-embrace?new= (“As technology leaps forward, clear and fair regulations must keep pace to support advancement ….”); FERC, News Release, FERC: Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-create-new- rules-embrace-innovation-and?new= (“‘Clarifying new rules will help release the bottleneck of large load investments across the PJM footprint,’ said Chairman Swett.”); FERC, Transcript of 1131st Commission Meeting, at 24:25 to 25:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-december-18-2025-open-meeting (“[W]hen done right co-location can be both a consumer forward tool and a critical avenue in beating our national imperative of speed to power and winning the AI race.”) (remarks of Commissioner See); id. 26:4-7 (“FERC is meeting the urgent demand for speed to power by creating flexibility for a rapidly evolving industry without sacrificing reliability and affordability.”) (remarks of Commissioner See); id. at 37:11-12 (“We can’t just pretend large loads don’t exist and wish them away.”) (remarks of Commissioner LaCerte); id. at 37:15-16 (“PJM is in dire need of leadership for their stakeholders.”) (remarks of Commissioner LaCerte); FERC, Transcript of 1132nd Commission Meeting, at 10:2-5 (Jan. 26, 2026) (“I warmly welcome engagement from great operators who share my commitment to helping ensure that datacenters can interconnect quickly and reliably.”) (remarks of Chairman Swett).6 FERC, Notice of Extension of Time, at 3 (Jan. 23, 2026).
PDF page 3
3
NITS.7 Constellation does not protest that rate treatment given the urgency of getting data centers in service, but crafting an identical rate cannot possibly take over three years.
As set forth below, the Commission can allow more time if needed, on a separate track, to establish the rates and terms of new Contract Demand Services.8 Additional time is not needed for Interim NITS, which is “[g]enerally speaking” the same as NITS.9
Second, the Commission should reject PJM’s unilateral attempt to restrict availability of Non-Firm Contract Demand Service. PJM proposes to make this service available only when the Co-Located Generating Facility is on outage. The Commission, however, did not limit Non-Firm Contract Demand Service in this way. Nor, contrary to PJM’s proposal, did the Commission require Eligible Customers to take Firm Contract Demand Service for all Co-located Load not served by a generator. PJM needs to stop resisting the innovative Co-Located Load arrangements10 endorsed by the Commission and start looking for solutions. “Saying no to innovation is not a winning strategy.”117 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners, Exh. No. PTO-0001 at 16:12-14 (Feb. 23, 2026) (“Indicated TO Initial Brief”). The Indicated PJM Transmission Owners are a subset of Transmission Owners in PJM, excluding Old Dominion Electric Cooperative, for example.8 Contract Demand Services refers collectively to Firm Contract Demand Transmission Service (“Firm Contract Demand Service”) and Non-Firm Contract Demand Transmission Service (“Non-Firm Contract Demand Service”).9 PJM Initial Brief at 67.10 See, e.g., id. at 48 (“Since at least its establishment as an Independent System Operator in 1997, PJM’s processes have been built around the long-held practice and expectation that load internal to PJM will receive NITS. This has significant implications for PJM’s planning, markets, and operations functions, which are focused on serving Network Load.”).11 December 18th Order, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 1). See also Judy W. Chang, et. al, It’s all one system: Integrate transmission and interconnection planning to support load growth, UTILITY DIVE (Sept. 26, 2025), https://www.utilitydive.com/news/its-all-one-system-integrate-transmission-and-interconnection- planning-Judy-Chang/761240 (“Generational change is occurring in the nation’s energy sector. While FERC is considering urgent short-term fixes, it also must evaluate longer-term solutions that shape the sector.”).
PDF page 4
4
Third, the Commission should reject PJM’s and Indicated Transmission Owners’12 proposals that restrict, delay, discriminate against or otherwise discourage the use of the Commission’s new Interim NITS and Contract Demand Services. The Federal Power Act prohibits “unreasonable differences” in services.13 Moreover, the Commission did not establish these “major new transmission” services—“the first time since the 90’s”—for them to be so limited and burdensome that few would want to take them.14 The whole purpose of these services is to “release the bottleneck of large load investments across the PJM footprint.”15
We specifically challenge the following:
• the lack of a transitional mechanism for large loads within pending NITS
applications to apply for Interim NITS;16
• the ambiguity of PJM’s proposed studies and lack of mechanisms to prevent delay and discrimination by Transmission Owners;17
• the absence of a proposed penalty charge to comment on and the proposed
suspension and disqualification of Eligible Customers for unreserved use of the transmission system;18
• unreasonable and discriminatory system protection scheme requirements, including the Transmission Owners’ recommendation for a double system protection
scheme;1912 Indicated TO Initial Brief at 5 n.13.13 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission … maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”).14 FERC, 1131st Commission Meeting Transcript, at 34:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript- december-18-2025-open-meeting (remarks of Commissioner LaCerte).15 FERC, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator- create-new-rules-embrace-innovation-and?new= (quoting Chairman Swett).16 See infra at 14.17 See infra at 14-18.18 See infra at 18-21.19 See infra at 21-25.
PDF page 5
5
• the lack of a cost-based Grid Reliance Charge;20
• the requirement that an Eligible Customer provide PJM authorization or
certification from the Relevant Electric Retail Regulatory Authority;21 and
• the requirement to construct different feeders to take the new services.22
Fourth, we seek clarification of PJM’s and the Indicated Transmission Owners’ filings to ensure clarity and compliance with the December 18th Order. We recommend that PJM add to the “Conditions Precedent for Receiving Service” the requirement that the Eligible Customer identify the Customer Facilities associated with the Co-Located Load, and, if the Customer Facilities include an existing generator, to certify that the existing generator supports the request. We also recommend that Indicated Transmission Owners confirm that the Firm Contract Demand Service rate is the actual NITS rate for the relevant Transmission Owner (the most common of which is a 5-coincident peak (“CP”) design). Last, we briefly reassert our arguments that (1) the Commission should clarify that it did not intend to require a capacity resource to delist even when it has no obligation to serve the Co-Located Load and remains fully capable of serving the grid during capacity emergencies;23 and (2) reject PJM’s proposal to override the Commission’s definition of Co-Located Load.2420 See infra at 25-28.21 See infra at 29.22 See infra at 29-30.23 See infra at 31; Motion for Leave and Second Answer of Constellation passim (March 24, 2026) (“Mar. 24 Answer to PJM”); Request for Clarification, or in the Alternative, Rehearing, at 1-3 (Jan. 20, 2026) (“Clarification Request”).24 See infra at 32; Protest and Comments of Constellation Energy Generation, LLC, Docket No. ER26-1479-000, at 2-8 (Mar. 16, 2026) (“Constellation 60-Day Compliance Filing Protest”); Comments and Conditional Protest of Constellation Energy Generation, LLC, Docket No. ER26-1088 (Feb. 20, 2026) (“Constellation 30-Day Compliance Filing Protest”).
PDF page 6
6
REPLY
I. The Commission Should Fast Track Interim NITS
The fastest approach to “release the bottleneck of large load investments across the PJM footprint”25 and obtain national and economic security is to quickly implement Interim NITS for new and pending large load applicants. Taking three and half years to implement this transmission service will not win the AI race, and such delay is inconsistent with the Commission’s December 18th Order.26 Immediately after the paper hearing briefing concludes, the Commission should establish a separate track to promptly approve the rates and terms for Interim NITS as modified below in Section III and make them effective no later than October 1, 2026. Five months is a reasonable amount of time to implement this service and advance the Commission’s goal of speedy interconnection. Indeed, PJM itself has been working on such a service since at least March 2025 when it suggested its “Option 7” in its Answer to the February 2025 Show Cause Order.27 Underscoring that there is no barrier to timely implementation, the Southwest Power Pool (“SPP”) recently committed to making its version of Interim NITS, Conditional High Impact Large Loads Service (“CHILLS”), available on July 1 of this year, less than five months after filing its revised tariff proposing the service and less than three months after SPP’s requested action date by the Commission.28 PJM should be expected to act with comparable urgency.
25 FERC, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator- create-new-rules-embrace-innovation-and?new= (quoting Chairman Swett).26 See supra note 5.27 PJM Answer to February 2025 Show Cause at 18-19 (March 24, 2025)28 Southwest Power Pool, Submission of Tariff Revisions to Add Conditional High Impact Large Load Service, Docket No. ER26-1323, at 2 (Feb. 10, 2026) (“CHILLS Filing”).
PDF page 7
7
PJM offers no legitimate reason for proposing a three and half year delay. PJM first claims that Interim NITS “will significantly affect the PJM Load Forecast and expected demand.”29 This is incorrect. The point of Interim NITS, as the Commission recognized, is that Co-Located Loads served by Interim NITS are “interruptible loads” and “capacity will not be procured on their behalf until such time as the Network Upgrades are in place to serve them.”30 PJM has not explained how Interim NITS will impact its load forecast.
PJM next claims that the service should be delayed by more than three years because “the addition of the three new transmission services will require significant changes to PJM’s core Markets and Operations systems”31 as they do not currently “automate Curtailment of Non-Firm Contract Demand Transmission Service (or Interim NITS) before Firm Contract Demand Transmission Service.”32 PJM implies implementing these changes could be delayed by “vendor availability, the speed with which the system changes can be designed, and the interaction of these requested changes with other competing priorities.”33 Possible logistical challenges will not risk delay if the Commission separates and implements Interim NITS on a fast track. Like SPP, PJM will only need to automate curtailment of Interim NITS before NITS just as it does for external Non-Firm Point to Point Transmission Service. Before entering Emergency Procedures, “PJM
29 PJM Initial Brief at 79.30 December 18th Order, 193 FERC ¶ 61,217 at P 200 (emphasis added); see also Answer of PJM Interconnection, at 18 (Mar. 24, 2025) (describing “Option 7” “Co-located load that takes Interruptible Service” as providing “as a non- capacity backed load where it avoids capacity costs if willing to curtail to support reliability in advance of emergency conditions” and will require capacity “only for portion that is not non-capacity backed.”).31 PJM Initial Brief at 81.32 Id. at 65 (emphasis added).33 Id. at 61.
PDF page 8
8
Dispatch recalls export transactions, as needed, in accordance with Part II of the PJM OATT.”34 PJM also interrupts non-firm service for economic reasons to accommodate “a request for Firm Transmission Service” among other circumstances.35 SPP has not raised any administrative challenges to implementing changes to its core systems. We should expect the same for PJM. Moreover, PJM could implement temporary operational and market workarounds until the changes to the core Markets and Operations systems are completed.
Last, PJM argues the more-than-three-year delay is necessary because it “does not expect that Eligible Customers and associated generation will be online and taking service under any of the proposed transmission services before June 1, 2029.”36 This rationale ignores—and effectively precludes—load co-locating with existing generation from selecting Interim NITS. Existing generators can serve Co-Located Loads after completing required Network Upgrades, and, consistent with the December 18th Order, PJM should be trying to promote speedy connection, including through co-location arrangements with existing generation, rather than to stymie such arrangements. Speed to service will not be achieved if discrimination is allowed against all the megawatts already available and ready to reliably serve.
Adopting Interim NITS as soon as possible should not be difficult. As PJM admits, “[g]enerally speaking, the non-rate terms and conditions for Interim NITS are the same as for NITS.”37 The Indicated Transmission Owners also propose to charge the same undiscounted NITS
34 PJM Manual 13, § 2.3.2; see also OATT, Part II, § 14.7 (“The Transmission Provider reserves the right to Curtail, in whole or in part, Non-Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons when an emergency or other unforeseen condition threatens to impair or degrade the reliability of its Transmission System or the systems directly and indirectly interconnected with Transmission Provider’s Transmission System.”).35 OATT, Part II, § 14.7 36 PJM Initial Brief at 82.37 Id. at 67.
PDF page 9
9
rate for Interim NITS.38 While we propose certain modifications that would apply to the proposed Interim NITS in Section III below, these modifications likely would decrease the time required for PJM and the Transmission Owners to implement Interim NITS. Allowing large loads with pending NITS applications to apply for Interim NITS may deliver immediate results.39 Clarification of what additional studies need to be performed, and the timeline for such studies, will streamline the process.40 Adopting PJM’s existing Tariff provisions on unreserved use for Non-Firm Point-to-Point Transmission Service for Interim NITS will simplify the development and implementation of penalty charges and other remedial actions.41 And removing the inapplicable and unnecessary requirements to obtain state authorization and to construct different feeders will prevent needless delays.42
Contract Demand Services can proceed on a separate track to allow the Commission to take more time, if needed, to establish the rates and terms of the new services, including a reasonable and cost-based Grid Reliance Charge. However, we urge the Commission not to delay these services until June 2029. “The risks of inaction or delayed action are simply too great.”4338 See Indicated TO Initial Brief, Exh. No. PTO-0001 at 16:10-12.39 See infra at 14.40 See infra at 14-18.41 See infra at 18-21.42 See infra at 29-30.43 See FERC, 1130th Commission Meeting Transcript, at 26:24-25 (Nov. 20, 2025), https://www.ferc.gov/media/transcript-november-20-2025-open-meeting (remarks of Commissioner LaCerte); see also id. at 7:1-3 (“[M]y priority as Chairman is to ensure that our country can connect and power data centers as quickly and as durably as possible.”) (remarks of Chairman Swett).
PDF page 10
10
II. PJM Proposes to Restrict Contract Demand Services in Conflict with the December 18th Order
PJM proposes to restrict Contract Demand Services in two ways: first, by restricting Non- Firm Contract Demand Service to a Co-Located Generating Facility’s outage,44 and second, by requiring Firm Contract Demand Service for any portion of the Co-Located Load not served by the Co-Located Generating Facility.45 These restrictions contradict or are otherwise inconsistent with the December 18th Order. They should be rejected.
First, the Commission did not limit Eligible Customers to taking Non-Firm Contract
Demand Service only at times when the Co-Located Generating Facility is on outage. The
December 18th Order made Non-Firm Contract Demand Service available for Eligible Customers to withdraw energy from the transmission system “when transmission capacity is available and not needed by firm customers,” period.46 The use of the Non-Firm Contract Demand Service to
44 PJM Initial Brief at 6; see also id. (“In short, for reliability reasons, the portion of the Co-Located Load for which the Co-Located Generating Facility will dedicate its output (in whole or in part) may be covered by Non-Firm Contract Demand Transmission Service, but any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility must be covered by Firm Contract Demand Transmission Service.”); id. at 16 (“An Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand Transmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load, and an Eligible Customer with an effective Service Agreement will be eligible to obtain Non- Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co- Located Generating Facility dedicated to serving the Co-Located Load is on outage.”).45 Id. at 6 (“any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility must be covered by Firm Contract Demand Transmission Service”); see also id. at 9 (“A Co-Located Generating Facility will not always be available (e.g., due to planned or unforced outage). To the extent that the gross demand of a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand Transmission Service, the Eligible Customer must cover the remaining gross demand by applying for Non-Firm Contract Demand Transmission Service. In that case, the Non-Firm Contract Demand Transmission Service, if PJM determines it is available for the requested period, will act as a backup to allow the Co-Located Load to meet its full demand, while the portion of the Co-Located Generating Facility dedicated to the Co-Located Load is on outage and unable to provide energy.”); id. at 16 (“Conversely, as discussed above in the overview section, an Eligible Customer taking service on behalf of a Co-Located Load must request Firm Contract Demand Transmission Service for no less than the MW level of the gross demand of the Co-Located Load that will not be served by the dedicated Co-Located Generating Facility.”)46 Id. P 214 (emphasis added); see also id. P 215 (“As noted above, Eligible Customers may use Non-Firm Contract Demand transmission service to make use of the transmission system above their Firm Contract Demand transmission service level, if transmission capacity is available.”).
PDF page 11
11
support load during an expected outage was simply an “example.”47 Nothing in the December 18th Order limited the service to that one scenario.
PJM’s justifications for limiting Non-Firm Contract Demand Service are unpersuasive.
PJM claims that it must limit Non-Firm Contract Demand Service to times when the Co-Located
Generating Facility is on outage to ensure that Co-Located Loads do not “compromis[e] the level of reliability to firm loads.”48 This argument fails to recognize “the reality … that large loads can be flexible in the amount of transmission service they use.”49 The Commission repeatedly found that “the record demonstrates that Eligible Customers taking transmission service on behalf of Co- Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”50 If PJM disagreed, it should have timely sought rehearing.
PJM also claims that its limitation is necessary to ensure that Co-Located Loads do not
“over-utiliz[e] their non-firm contract arrangements at the cost of firm service ratepayers.”51 This
47 December 18th Order, 193 FERC ¶ 61,217 at P 214 (introducing its discussion of the scenario with the words “[f]or example”).48 PJM Initial Brief, Attachment B at ¶ 17 (“Abdulsalam Affidavit”).49 FERC, Transcript of 1131st Commission Meeting, at 7:5-7 (Dec. 18, 2025) https://www.ferc.gov/media/transcript- december-18-2025-open-meeting (remarks of Chairman Swett).50 December 18th Order, 193 FERC ¶ 61,217 at P 199; id. P 2 (“we find that PJM’s Tariff is unjust and unreasonable because it does not include types of transmission service that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their use of the transmission system under certain conditions”); id. P 159 (“We also find that PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the transmission system under certain conditions.”); id. P 177 (“we also find that PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions”); id. P 193 (“we find that PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”); see also FERC, Transcript of 1131st Commission Meeting, at 7:11-14 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-december-18-2025-open-meeting (“the order recognizes that PJM’s existing transmission services are insufficient in that they do not recognize the controllable nature of co-location arrangements.”) (remarks of Chairman Swett).51 Abdulsalam Affidavit at ¶ 17.
PDF page 12
12
argument similarly falls short. The Commission offered solutions for the precise issue of unreserved use: penalty charges, curtailment procedures, and technical and engineering requirements of special protection schemes.52 Moreover, as the Commission recognized, Non- Firm Contract Demand Service benefits ratepayers by “potentially avoid[ing] costly and inefficient transmission system buildout that may not be necessary.”53 In addition, as electricity market design expert Zachary Ming explained, “[c]ollection of as-available transmission charges would directly benefit existing ratepayers by reducing rates since as-available energy purchases by co-located loads would contribute to the recovery of transmission costs without requiring any additional costs to be incurred.”54 Others have stated similarly.55
Second, the Commission did not require Eligible Customers to take a Firm Contract Demand Service along with Non-Firm Contract Demand Service. While Eligible Customers have the option to take both services, they are not required to do so.56 They only must “choose at least one of the required transmission services.”57 Nor is there the requirement that the Eligible Customer must take Non-Firm Contract Demand up to the MW of the Co-Located Generating Facility. Crucially, the Commission specifically contemplated the arrangement where the Co-
52 December 18th Order, 193 FERC ¶ 61,217 at PP 217, 219.53 Id. P 160; see also id. P 199 (““Requiring this could necessitate inefficient and costly transmission buildout and costs paid by transmission customers that may not be necessary if Eligible Customers taking transmission service on behalf of Co-Located Loads are willing to limit their energy withdrawals and take a transmission service that requires fewer Network Upgrades to provide.”).54 Constellation Apr. 23 Reply Comments, Exhibit 2, Testimony of Zachary Ming 41:17-20.55 See, e.g., Norris, Tyler, et al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, at 11 (2025) https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf (“By strategically timing or curtailing demand, these flexible loads can minimize their impact on peak periods. In doing so, they help existing customers by improving the overall utilization rate—thereby lowering the per-unit cost of electricity—and reduce the likelihood that expensive new peaking plants or network expansions may be needed.”).56 December 18th Order, 193 FERC ¶ 61,217 at P 19457 Id. (emphasis added).
PDF page 13
13
Located Load “will not withdraw energy from the transmission system must take Non-Firm Contract Demand transmission service at 0 MW.”58 Likewise, there is no requirement that Eligible Customers must take Firm Contract Demand for the MWs of the Co-Located Load not served by the Co-Located Generating Facility. If an Eligible Customer selects Firm Contract Demand Service, the “Eligible Customer[] will have the right to request transmission service on behalf of a Co-Located Load up to a specified MW quantity, i.e., the contract demand.”59
The December 18th Order did not give PJM permission to dictate the transmission services that an Eligible Customer must take when taking service on behalf of Co-Located Load. The Commission explicitly gave Eligible Customers that choice, stating that Eligible Customers “should be allowed to choose the transmission service that aligns with their use of the transmission system”60 and Eligible Customers “may choose the transmission services that match their preferred use of the transmission system.”61
III. The Commission Should Encourage Its New Transmission Services and Reject Attempts that Frustrate Their Use
PJM and Indicated Transmission Owners propose provisions that would restrict, delay or otherwise discourage the use of Interim NITS and Contract Demand Services. The Commission should reject these attempts and allow co-location arrangements to move forward as the December 18th Order envisions and consistent with the national interest in winning the AI race.
58 Id. P 206.59 Id. P 208 (emphasis added).60 Id. P 199.61 Id. P 194 (emphasis added); see also Stockton Declaration at 1 (“Constellation Reply Comments”) (“The entities that own or operate the AI facilities should be given the choice to determine which configuration for interconnecting them is best for their needs, in close consultation with DOD and the other national security agencies that depend on their AI services. Neither FERC, PJM nor individual transmission owners should make that choice for them.”).
PDF page 14
14
These revisions should shrink the timeline required to implement both Interim NITS (and thus facilitate an earlier schedule) and the Contract Demand Services.
A. The Commission Should Direct PJM to Include a Transitional Mechanism
for Pending Large Load NITS Applications
PJM should revise its proposal to clarify that large loads with pending NITS applications may apply for Interim NITS. Limiting Interim NITS availability to new applicants would unnecessarily restrict the availability of the service and eliminate an opportunity to serve large loads faster. PJM should clarify that Interim NITS is available for large loads meeting the Commission’s definition of Co-Located Load after PJM conducts a supplemental study, if necessary, to find the requested Interim NITS could be provided reliably. The Interim NITS application and study processes would take place simultaneously with the pending NITS application. Clarifying that pending large load applications will be eligible to elect Interim NITS will prevent future disputes and delays. The election of Interim NITS eligibility, which itself is contingent upon a standard NITS application and meeting the definition of Co-Located Load, should not be an excuse to force applicants to re-start the NITS process.
B. PJM’s Proposed Study Procedures Lack Sufficient Detail to Prevent Needless
Delay and Discrimination by Transmission Owners
PJM’s proposed study procedures for both Interim NITS and the Contract Demand
Services fall short of “addressing with sufficient clarity or consistency” the terms that apply to Eligible Customers and that are necessary to ensure PJM’s Tariff is just and reasonable.62 Absent from the proposed procedures are descriptions of the studies to be performed. The studies that PJM will perform when evaluating Interim NITS are described vaguely as “additional studies beyond
62 Id. P 2.
PDF page 15
15
what is required to evaluate the Eligible Customer’s request for NITS.”63 The studies that PJM will perform when evaluating Firm Contract Demand Service are described as “necessary studies” “in accordance with PJM Manuals.”64 The studies PJM and the Transmission Owner will perform when evaluating Non-Firm Contract Demand are described as “additional studies”65 and “different evaluations to actually use such service on the Transmission System on any given day.”66 PJM provides no further explanation. PJM must spell out in the Tariff the studies that it will perform in conjunction with the Co-Located Generating Facility and the timetable for completing these studies. The scope of the “additional studies” and “necessary studies,” which will determine whether PJM can provide the requested service and any upgrades required, “significantly affect the rates, terms and conditions” of service and are “readily susceptible to specification.”67 They should not be placed in PJM’s business manuals where PJM has unilateral discretion and may not be enforced. They should be spelled out in the tariff, so that the Commission can review them and ensure that the study process does not frustrate the Commission’s goals, and so that parties have a standard they can enforce with the Commission if needed.68
Indeed, PJM’s proposed study procedures allow for the perpetuation of existing
discrimination, delays, tying, and encumbrances of large load configurations by Transmission
63 PJM Initial Brief at 70-71.64 Id. at 24.65 Id. at 33.66 Id.67 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018).68 See RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212, at P 38 (2026) (“The Commission does not review and approve PJM’s manuals, as they are not filed with the Commission. As a result, we have no statutory obligation to enforce the terms.”).
PDF page 16
16
Owners.69 In fact, PJM repeatedly makes clear that Transmission Owners will play a lead role in determining whether an Eligible Customer can take Interim NITS and Contract Demand Services:
• “The Transmission Provider, in consultation with the affected Transmission
Owner(s), will determine the amount of Interim Network Integration Transmission
Service that can be provided to an Eligible Customer, including through the use of
temporary solutions, while maintaining the reliability of the Transmission
System.”70
• “PJM would ‘coordinate with the affected Transmission Owner(s) to complete
studies, including load integration studies, [to obtain] data relevant to the
69 See, e.g., Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000 at 7 (Nov. 22, 2024) (“Exelon is refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled interconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, and forcing additional services to be procured.”) (“Constellation Complaint”); id at 7-8. (“Exelon fulfilled its responsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear station, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center (‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); Constellation Complaint at 8 (“projects are being held hostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); id. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”) (citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully Isolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ refusal to cooperate … with reliability studies related to interconnection modifications.”); see also Supporting Comments of Constellation Energy Generation, LLC, Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, at 3-4 (Nov. 21, 2025) (“Some Transmission Owners have simply refused to participate in PJM’s studies to analyze reliability impacts; and some, acting under unfiled interconnection study procedures, have changed their entire construct and timetable for processing load studies.”) (“Constellation ANOPR Comments”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., Docket Nos. EL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff to require this one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different configuration.”); id. at 14 (“What is more, regardless of what the Tariff actually says and does not say, some of the Indicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load agrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) (citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on LaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to complete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to Constellation by $15.3-$19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (“there are allegations in the record that Exelon has delayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s concerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail distribution service.”).
70 PJM Initial Brief, Illustrative Tariff, Part XI, § 702.3.
PDF page 17
17
determination of whether (and to what level)’ Firm or Non-Firm Contract Demand Transmission Service ‘can be reliably provided’ and ‘identify any necessary enhancements to the Transmission System to accommodate the requested level of service.’”71
• “PJM, in consultation with the affected PJM Transmission Owner(s), will determine the level of Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service that can be reliably provided and inform the Eligible Customer.”72
• PJM states that “upon receiving a request for Non-Firm Contract Demand Transmission Service, [it] will coordinate with the affected Transmission Owner(s) to complete necessary studies to determine whether—and at what level—Non-Firm Contract Demand Transmission Service can be reliably provided.”73
• “PJM will not study transmission service requests alone, but rather will coordinate and consult with any affected Transmission Owners to determine whether and how the requested transmission service may be provided.”74
• “PJM and the affected Transmission Owner(s) will determine whether additional studies are required ‘to assess whether the Transmission System has sufficient available capacity to provide Non-Firm Contract Demand Transmission Service, and if so, which studies are appropriate.’”75
There is reason to believe that Transmission Owners may use their role and their natural monopoly market power to delay and deny co-location arrangements they do not favor. Delays associated with the Transmission Owners’ refusal to process necessary studies are well documented in the record.76 To achieve speed to market, Transmission Owners should not be given the opportunity to deny transmission service or, what amounts to the same, to delay transmission service unreasonably. Deadlines and other mechanisms must be set forth in the Tariff to prevent
71 PJM Initial Brief at 17-18.
72 Id. at 18.73 Id. at 32-33.74 Id. at 33. 75 Id.76 See supra note 69.
PDF page 18
18
Transmission Owners from needlessly delaying studies and unreasonably denying new transmission services.
C. PJM and Indicated Transmission Owners’ “To Be Determined” Penalty
Charges and Remedial Actions are Not Just and Reasonable
PJM and Indicated PJM Transmission Owners have failed to follow the Commission’s directive to propose an “appropriate penalty charge or other remedial action that PJM should take to address any unreserved use”77 by an Eligible Customer taking Interim NITS and Contract Demand Services.
First, they offer no proposal on a penalty charge. Penalty charges are “[t]o be determined”78 subject to PJM’s and the Indicated Transmission Owners’ “inten[tion] to work” with each other “in continuing to explore the penalty options and will, if appropriate, offer a proposal at a subsequent stage of this paper hearing process.”79 Whether and when to respond to a Commission’s directive is not optional. PJM and the Indicated Transmission Owners were to respond to the Commission’s questions with “specificity”80 by the extended deadline.81 The Commission did not grant 30-day extension the Indicated Transmission Owners requested. The Commission shortened the extension to seven days after having recognized Constellation’s comment that “the original 60-day deadline is consistent with the administration’s goals to
77 December 18th Order, 193 FERC ¶ 61,217 at P 219 (Question Numbers 5 and 6).78 PJM Initial Brief at 41.79 Indicated TO Initial Brief at 20 (emphasis added); see also PJM Initial Brief at 50 (“With regard to the financial penalty, PJM intends to work with the PJM Transmission Owners to explore such a financial penalty.”).80 December 18th Order, 193 FERC ¶ 61,217 at P 219.81 See FERC, Notice of Extension of Time (Jan. 23, 2026).
PDF page 19
19
promptly resolve large load issues and that transmission owners have an interest in delaying implementation of the new transmission services.”82
As discussed in further detail below, using SPP’s proposed CHILLS as a model, the
Commission can promptly direct PJM to align its treatment of unreserved use by Eligible
Customers taking Interim NITS and Non-Firm Contract Demand Services with its treatment of Non-Firm Point-To-Point Transmission Service.
Second, the “remedial actions” that PJM does propose—suspensions or disqualification of
Eligible Customers from taking Interim NITS and Contract Demand Services83—are not “remedial actions,” that is, actions “to correct, remove, or lessen a wrong, fault, or defect.”84 They are extreme punishments that were not contemplated by the December 18th Order85 and are placed only upon Co-Located Load arrangements. Transmission Customers taking Non-Firm Point-To- Point Transmission Service are not subject to suspension or disqualification for unreserved use of the transmission system. PJM simply recalls export transactions and Transmission Customers are only subject to “Curtailment or Interruption under the terms of the Tariff.”86
Under PJM’s proposal, the failure by an Eligible Customer to follow one instance of
Curtailment or Load Shed procedures, no matter who is at fault, disqualifies an Eligible Customer
82 Id. at 3. 83 PJM Initial Brief at 41-50.84 See Remedial, BLACK’S LAW DICTIONARY (12th ed. 2024)85 December 18th Order, 193 FERC ¶ 61,217 at P 212 (“We direct parties to brief the appropriate penalty charge for a Firm Contract Demand transmission service customer’s unreserved use of the PJM transmission system. We also direct parties to brief the appropriate procedures for PJM to curtail Eligible Customers taking the new Firm Contract Demand transmission service on behalf of Co-Located Loads that withdraw energy in excess of the contract demand and any other remedial action that PJM should take to address withdrawals in excess of the contract demand. We also note that, as discussed in the briefing questions below, PJM will determine the technical and engineering requirements of special protection schemes to help address reliability risks associated with unreserved use of the transmission system.”).86 OATT, Part II, § 14.5.
PDF page 20
20
indefinitely from taking Interim NITS or Contract Demand Services.87 If necessary control technology or protection scheme misoperates, the Eligible Customer is suspended 120 days from taking Interim NITS and Contract Demand Services the first time and disqualified indefinitely the second time.88 For disqualified Eligible Customers, PJM emphasizes, not once but four times, that “[i]mportantly … such an Eligible Customer may take NITS, which would begin after all necessary upgrades are placed into service.”89 These Draconian punishments are not reasonable, as they are imposed regardless of fault and will make these services unduly risky for many loads. “Remedial actions” cannot be so extreme that they effectively make the alternatives to NITS dead letters. Like SPP’s proposed tariff provisions for CHILLS,90 the Commission should direct PJM to align the treatment of unreserved use by Interim NITS and Contract Demand Services with its treatment of Non-Firm Point-To-Point Transmission Service. SPP has proposed that if a Transmission Customer exceed its CHILLS reserved capacity, similar to Non-Firm Point-To-Point Transmission Service, “the Transmission Customer may pay, in addition to the charges for all of the CHILLS capacity used, one-hundred percent (100%) of the Non-Firm Point-To-Point Transmission Service charges under Schedules 8 and 11 for the period when the additional service was used ….”91 SPP proposes no suspension or disqualification of interruptible loads. The Commission should adopt SPP’s approach and direct PJM to align unreserved use by Eligible
87 PJM Initial Brief at 41-42.88 Id. at 44-46.89 Id. at 46.90 CHILLS Filing at 31. 91 Id. at 30.
PDF page 21
21
Customers taking Interim NITS and Contract Demand Services with its treatment of Non-Firm Point-To-Point Transmission Service in section 14.5 of Part II of its Tariff.92
D. Clarification of Proposed System Protection Scheme Requirements is Needed
to Prevent Discrimination and Delays
We make two discrete comments on PJM’s proposal for system protection schemes, including special protection systems (“SPS”) and remedial action schemes (“RAS”). First, PJM should make clear that its statement “[t]he interconnection requirements and operational practices necessary for necessary control technologies and protection systems to maintain system reliability … will be set forth in the PJM Manuals”93 means that PJM will apply the requirements set forth in PJM Manual 3 to co-located arrangements. As “[t]here is no technical reason … to expect that protective relaying in the context of co-location would perform any less reliably,”94 new requirements should not be established solely for Co-Located Loads. Second, PJM should clarify that it did not intend for its statement “[t]heir implementation is generally limited to temporary conditions involving the outage of critical equipment”95 to restrict the use of permanent system protection schemes. The Commission intended special protection schemes to be a permanent fixtures for Co-Located Loads.96 Moreover, NERC does not recognize this temporal limitation.9792 OATT, Part II, § 14.593 PJM Initial Brief at 57. 94 Constellation Reply Comments, Exhibit 4, at ¶ 23 (Affidavit of Steven Herling) (“Herling Aff.”).95 PJM Initial Brief at 58.96 December 18th Order, 193 FERC ¶ 61,217 at P 205.97 See NERC, Special Protection Systems (SPS) and Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards, at 8 (2013), https://www.nerc.com/globalassets/standards/projects/2010- 05.2/system_protection_and_control_subcommittee_spcs_20_sams-spcs_sps_technic_02182014.pdf (explaining the cases where permanent special protection schemes have been implanted).
PDF page 22
22
In addition, we comment on eight of the nine recommendations proposed by Indicated Transmission Owners relating to special protection schemes for Co-Located Loads taking Interim NITS and Contract Demand Services.98 As Indicated Transmission Owners state they are “not offering a specific proposal at this time,” we also reserve our ability to comment on any proposal that the Indicated Transmission Owners offer at a later date.99
1. Indicated Transmission Owner Recommendations 1 to 4 are Reasonable
Subject to Clarification to Avoid Delay and Discrimination
Constellation agrees with Indicated Transmission Owners’ first recommendation that “[a]ll SPS and RAS should be fully redundant.”100 However, clarification on what “full redundancy” means is necessary. As explained by Steven Herling, protective schemes can be designed so that they are “completely redundant.”101 Mr. Herling provided the example of where “[t]here are two circuit breakers placed in series supplying the co-located load, so that if one fails, the second will still open the circuit. Each circuit breaker has two trip coils such that either the primary or backup protective relay can successfully trip the load. All elements of the protective scheme, including the electric current transformers, the fiber channels, and the trip relays, are redundant resulting in a single-failure-proof design.”102 To the extent Indicated Transmission Owners argue that more is required, we object. We reiterate, “[t]here is no technical reason … to expect that protective
98 See Indicated TO Initial Brief at 22-26. We do not comment on Indicated Transmission Owner’s ninth recommendation suggesting that “The Commission should direct NERC to establish requirements that Co-Located Load customers register with NERC so that those customers may be responsible for meeting NERC’s reliability standards, including NERC Reliability Standard PRC-012-2.” Id. at 24. We also note that Indicated Transmission Owners’ recommendations differ from PJM’s proposal in that PJM only applies its system protection schemes requirements to Interim NITS and Non-Firm Contract Demand Service, not Firm Contract Demand Service. See PJM Initial Brief at 56.99 Indicated TO Initial Brief at 22.100 Id. at 23.101 Herling Aff. at ¶ 21; id. ¶ 23 (providing example of fully redundant design).102 Id. at ¶ 22.
PDF page 23
23
relaying in the context of co-location would perform any less reliably.”103 The Commission has agreed. “[S]pecial protection schemes allow … Co-Located Load to effectively limit their withdrawals from the transmission system.”104
Constellation agrees with Indicated Transmission Owners’ second recommendation that the Co-Located Load customer should “pay for PJM and PJM Transmission Owner-administered studies to ensure any SPS or RAS can effectively mitigate the risks of potential failure modes.”105 However, a detailed description of the studies to be performed and the timelines they are to be completed must be on file as they are a key element of the service to be provided and will directly implicate the time to provide such service. To do otherwise risks delays and discriminatory conduct by Transmission Owners.106
We do not oppose the third recommendation that “PJM Transmission Owners should have the option to review and agree to any customer load curtailment procedures or operational control mechanisms.”107 However, there must be additional terms establishing deadlines for review and preventing Transmission Owners from unreasonably withholding approval over customer load.108 Last, Constellation agrees in principle with the fourth recommendation that “[a]ll SPS and RAS must fully meet PJM and PJM Transmission Owner technical criteria.”109 PJM Manual 3 sets forth PJM’s procedures for reviewing RAS based on the reliability-related considerations in
103 Id. at ¶ 23.104 December 18th Order, 193 FERC ¶ 61,217 at P 205; see also id. (“We note that, in general, special protection schemes allow Eligible Customers on behalf of Co-Located Load to effectively limit their withdrawals from the transmission system.”).105 Indicated TO Initial Brief at 23.106 See supra note 69.107 Indicated TO Initial Brief at 23.108 See supra note 69.109 Indicated TO Initial Brief at 23.
PDF page 24
24
Attachment 2 of NERC Reliability Standard PRC-012-2 that the Reliability Coordinator must review and verify for new and modified each RAS.110 New technical criteria should not be established solely for Co-Located Loads.
2. Indicated Transmission Owner Recommendations 5 through 8 Should be
Rejected as Unsupported and Discriminatory
The Commission should reject Transmission Owners’ fifth, sixth, seventh, and eighth recommendations. These recommendations are unsupported and unduly discriminatory towards Co-Located Load arrangements. As “[t]here is no technical reason … to expect that protective relaying in the context of co-location would perform any less reliably,” there is no justification for Indicated Transmission Owner to require that only Co-Located Loads be subject to:
• “PJM Transmission Owners … requir[ing] the implementation of SPS or RAS on the Transmission Owner’s side of the point of interconnection and to require that the costs associated with such SPS or RAS be fully recoverable,”111 (Seventh Recommendation);
• allowing PJM Transmission Owners to “own, maintain, and operate any SPS or RAS installed on the customer’s side of the point of interconnection”112 (Eighth Recommendation);
• “limits on the total amount of load that can be covered by SPS or RAS”113 (Sixth Recommendation); and
• “more frequent testing of SPS and RAS than is currently required by NERC Reliability Standards”114 (Fifth Recommendation).
110 PJM Manual 3, § 1.7. 111 Indicated TO Initial Brief at 24.112 Id.113 Id. at 24.114 Id. at 23.
PDF page 25
25
Protection schemes “regularly employed on the PJM transmission system” are not subject to these new requirements. There is no legitimate basis for treating Co-Located Load arrangements differently.115
Moreover, the Indicated Transmission Owners’ proposal to take ownership over special
protection schemes is the exact scenario of discrimination that Constellation identified in its comments opposing PJM’s proposal to revise the Commission-mandated definition of Co-Located Load.116 If the Transmission Owners takes ownership of all or part of the ring bus, as they propose, the ring bus would be a Transmission Owner Interconnection Facility and fall on the Transmission Owner’s side of the Point of Change in Ownership. Under PJM’s proposed definition of “Co- Located Load,” the new load would not qualify. Thus, the Commission should not be fooled by the Indicated Transmission Owners’ insistence on owning special protection schemes: if they prevail, then they can stymie all non-NITS services by claiming that the load falls outside the definition of “Co-Located Load,” at least as PJM would define it.
E. The Grid Reliance Charge Must be Economically Grounded and Rational
The Indicated Transmission Owners’ proposed Grid Reliance Charge for Contract Demand
Service customers not drawing power from the PJM network is derived from an unsound
methodology that violates cost causation principles. Put simply, the rate is not just and reasonable and does not represent the “fair share” of such Contract Demand Service customers.117 The
115 See supra note 104 (citing December 18th Order, 193 FERC ¶ 61,217 at P 205).116 See Constellation 60-Day Compliance Filing Protest at 2-8; Constellation 30-Day Compliance Filing Protest passim.117 See December 18th Order, 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at P 10) (“given that all Co-Located Loads rely on the existence of the PJM grid and are synchronized to it, such loads should pay for at least their fair share of the system’s operations and maintenance costs”); id. (Chang, Comm’r concurring at P 9) (“This minimum charge would provide a floor to the Co-Located Load’s cost responsibilities to pay for a portion of system costs, commensurate with the benefits that the Co-Located Load receives from the system, even where it plans to draw little or no energy from that system.”).
PDF page 26
26
Commission should reject the proposed Grid Reliance Charge, and instead direct the Transmission Owners to adopt the well-established methodology, the “minimum system” method, proposed by electric market design expert Zachary Ming in the attached analysis118 and recalculate the Grid Reliance Charge using that method. This should be done on a track separate from Interim NITS as the Grid Reliance Charge does not apply to Interim NITS.119 A separate track will provide the Commission with sufficient time to evaluate and establish this new minimum charge while ensuring Interim NITS is implemented immediately to facilitate the timely provision of transmission service.
1. The Proposed Grid Reliance Charge is Not a Just and Reasonable Rate
The proposed Grid Reliance Charge equal to 25.8% of NITS is not just and reasonable because, as Mr. Ming states, the methodology used to calculate the charge is “not grounded in sound ratemaking principles, cost causation principles or … any relevant precedent.”120 The Indicated Transmission Owners assert the proposed Grid Reliance Charge is calculated “using a standardized, percentage-based methodology that relies on publicly available FERC Form No. 1 data for PJM Transmission Owners to determine the portion of transmission depreciation and operation and maintenance (‘O&M’) expense associated with grid reliance capability.”121 However, as Mr. Ming explains, the Indicated Transmission Owners “are both excluding reasonable costs and including unreasonable costs”122 in the grid reliance capability O&M and
118 See Attachment 1 at 13:1-22:9 (“Mar. 25, 2026 Ming Testimony”).119 Indicated TO Initial Brief at 14 (proposing the Grid Reliance Charge for “Eligible Customers taking the new Contract Demand services.”). See also December 18th Order, 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at P 5) (limiting “the need to establish a minimum charge for the Firm and Non-Firm Contract Demand transmission services.”) (emphasis added).120 Mar. 25, 2026 Ming Testimony at 11:19-20.121 Indicated TO Initial Brief, Exh. No. PTO-0001 at 19:10-13.122 Mar. 25, 2026 Ming Testimony at 11:20 to 12:1.
PDF page 27
27
provide “very little justification” for doing so.123 For example, the Indicated Transmission Owners’ propose to exclude return on rate base and associated income taxes despite “well-established cost- of-service-regulation principles recogniz[ing] that the rate of return and taxes are just as much a cost of providing service as depreciation.”124
In addition, the Indicated Transmission Owners propose to inappropriately include the “full depreciation costs for a variety of transmission components … that are sized to meet the actual peak demand requirements of the PJM system, even though customers paying the [Grid Reliance Charge], by definition, do not impose any demand or withdraw any energy from the PJM
system.”125 Not only is this inclusion not based on precedent, but it violates cost causation principles.126 A Grid Reliance Charge equal to 25.8% of NITS “fails the fundamental requirement of cost causation, which is that a customer should pay rates that ‘match, as closely as practicable, the costs to serve’ the customer.”127
2. The “Minimum System” Method Produces a Just and Reasonable Grid
Reliance Charge
The simplest way to ensure that Co-Located Load pays its “fair share” is to calculate the Grid Reliance Charge using the “minimum system” method. As Mr. Ming states, the “minimum
123 Id. at 11:7.124 Id. at 12:1-3.125 Id. at 12:5-10 (emphasis added).126 Id. at 12:16-21 (explaining “the Transmission Owners’ GRC proposal violates cost causation principles by charging for demand-driven transmission costs that co-located customers with zero demand that their service does not cause”).127 Antero Res. Corp. v. FERC, 156 F.4th 654, 662 (D.C. Cir. 2025) (quoting Gulf South Pipeline Co., LP v. FERC, 955 F.3d 1001, 1009 (D.C. Cir. 2020). See also Consol. Edison Co. of N.Y. v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,179, at P 63 (2026) (rejecting settlement that “cannot be approved as just and reasonable because it leaves in place the de minimis threshold exemption that violates the cost causation principle”); Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 480 (7th Cir. 2009) (“Cost causation requires that “approved rates reflect to some degree the costs actually caused by the customer who must pay them.”) (quoting Midwest ISO Transmission Owners
v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004)).
PDF page 28
28
system” method is “well-established,”128 is designed to calculate “precisely the set of costs that a co-located load that benefits from the existence of wires but imposes no demand on the grid should share,”129 and “has substantial precedent in electricity-sector ratemaking, particularly in distribution cost allocation and rate design”130—including by utility affiliates of Indicated Transmission Owners.131
Under the “minimum system” method, Mr. Ming explains a “transmission minimum
system study could estimate the customer-driven share of transmission costs as a fraction of the total PJM transmission revenue requirement.”132 The “customer-driven share of transmission costs” would be calculated by “determining the minimum size of all electricity system components (e.g., poles, conductors, transformers, etc.) that could be used by the utility to recreate its system and connect each customer to the grid.”133 This fraction then would “be applied to each PJM Transmission Owner’s [NITS] rate to estimate the [Grid Reliance Charge] in dollars per kW- year.”134 Using relatively high-level publicly available data, Mr. Ming illustrates how this method could be implemented.135
128 Mar. 25, 2026 Ming Testimony at 14:15.
129 Id. at 13:15-16.
130 Id. at 17:5-6.
131 Id. at 16:4-6 (“Many utilities within PJM use minimum system studies in distribution cost allocation, including at least two Indicated PJM Transmission Owners: PPL Electric Utilities Corporation and FirstEnergy Service Company.”) (citations omitted).132 Id. at 17:10-11.133 Id. at 14:21 to 15:1-2.134 Id. at 17:12-14.135 Id. at 19:1-20:3.
PDF page 29
29
F. PJM’s Proposal to Require Retail Sale Authorization Will Delay
Interconnections
Constellation conditionally opposes PJM’s new requirement for both Interim NITS and the Contract Demand Services that the Eligible Customer must “provide PJM with ‘an authorization or certification from its Relevant Electric Retail Regulatory Authority which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load.’”136 As we stated in our Clarification Request,137 often a generator will not serve Co-Located Load directly. Rather the generator will first sell electricity at wholesale to an entity, such as a retail supplier, that will then engage in the ultimate retail sale to the Co-Located Load. If the generator is the Eligible Customer, it would be unreasonable and cause needless delay to require the generator to have to go to the state commission for a special approval if the load is located in a retail competition state. PJM should require Eligible Customers to provide no more than a showing that the load will ultimately be served by the Transmission Owner or a licensed competitive retail supplier. PJM should not be establishing additional state regulatory hoops (or roadblocks) for Eligible Customers to navigate.
G. Requiring Different Feeders is Potentially Unnecessary, Discriminatory and
Serves to Delay the Interconnection of Co-Located Load
Without explanation, PJM states, “Eligible Customers taking transmission service on behalf of Co-Located Load, would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.”138 On its face, the multiple feeders requirement appears discriminatory and serves only to further prolong or discourage Co-Located Load arrangements and require additional, unnecessary construction of
136 PJM Initial Brief at 19.
137 Clarification Request at 6-7.138 PJM Initial Brief at 66 (emphasis added).
PDF page 30
30
transmission lines, which is likely to delay service. The Commission should direct PJM and Indicated Transmission Owners to provide sufficient justification and explanation for any requirement to require multiple feeders. To the extent that PJM proposes to require different feeders to allow “selective curtailment” 139 for Co-Located Load receiving non-firm and firm services, the requirement should not apply to Interim NITS. Eligible Customers taking Interim NITS take only non-firm service until they are transitioned to full NITS when they only take firm service.
IV. Other Clarifications on Co-Located Loads and the Requirements of Existing Capacity Resources are Recommended
Last, we seek clarification of PJM’s and the Indicated Transmission Owners’ filings to ensure clarity and compliance with the December 18th Order.
We recommend that PJM add to the “Conditions Precedent for Receiving Service” in Part XI, Subparts A and B of its Illustrative Tariff140 the requirement that the Eligible Customer identify the Co-located Arrangement, including the Customer Facilities that will be associated with the Co-Located Load for which the Eligible Customer is taking the service. If the Customer Facilities include an existing generator, certification that the existing generator supports the request should also be required. This clarification will ensure the Co-Located Load “is physically connected to the facilities of the existing or planned Customer Facility,” consistent with the Commission’s mandated definition of Co-Located Load.141
139 Indicated TO Initial Brief, Ex. No. PTO-0001, at 39:6-10.
140 See PJM Initial Brief, Illustrative Tariff, Part XI, Subpart A, § 702.1 (Conditions Precedent for Receiving Service); Illustrative Tariff, Part XI, Subpart B, § 710.1 (Conditions Precedent for Receiving Service).141 December 18th Order, 193 FERC ¶ 61,217 at P 164 (defining Co-Located Load as “a ‘configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.’”).
PDF page 31
31
In addition, we recommend that the Indicated Transmission Owners clarify the rate they propose to charge for Firm Contract Demand Service. The Indicated Transmission Owners propose that “the transmission rate for Firm Contract Demand Service will be the same rate as the rate for NITS.”142 The Indicated Transmission Owners also propose “the calculation of the transmission rate for … Firm Contract Demand Service … will necessarily need to include … the measure of the single coincident peak (‘CP’) for NITS.”143 However, the majority of PJM Transmission Owners do not use a single coincident peak (“1-CP”) methodology to calculate the NITS rate. The most common methodology is “5-CP.”144 We request that Indicated Transmission Owners confirm the Firm Contract Demand Service Rate will be equal the applicable Transmission Owner’s NITS rate calculated using that Transmission Owner’s CP methodology.
We also briefly reassert two of our arguments made on rehearing and in response to PJM’s compliance filings and need not further elaborate here. First, the Commission should clarify that it did not intend to require a capacity resource to delist even when it has no obligation to serve the Co-Located Load and remains fully capable of serving the grid during capacity emergencies.145 In explaining what Contract Demand Services an Eligible Customer must take under PJM’s proposal, PJM states “the portion of Co-Located Generating Facility dedicated to the Co-Located Load would be ineligible to participate in PJM’s capacity market.”146142 Indicated TO Initial Brief, Exh. No. PTO-0001 at 26:7-8.143 Id. at 26:9-12.144 See OATT, Attachment M-2 (ComEd) (using a 5-CP methodology); id. at Attachment M-2 (PECO) (same); Attachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology include ComEd, PECO, BGE, and PSE&G.”).145 Clarification Request at 1-3; Mar. 24 Answer to PJM passim.146 PJM Initial Brief at 8.
PDF page 32
32
Second, the Commission should make clear that the definition of Co-Located Load means a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.”147 Alternatively, the Commission should adopt the modifications that Constellation proposed if the Commission revises the definition to replace “Point of Interconnection” with “Point of Change in Ownership.”148
CONCLUSION
For the reasons stated above, Constellation respectfully requests that the Commission promptly approve and make Interim NITS effective October 1, 2026, reject PJM’s and the Indicated Transmission Owners’ attempts to restrict, delay, or otherwise discourage new
147 December 18th Order, 193 FERC ¶ 61,217 at P 1 n.3. See also Constellation 60-Day Compliance Filing Protest at 2-8; Constellation 30-Day Compliance Filing Protest passim.148 See Constellation 60-Day Compliance Filing Protest at 7-8; Constellation 30-Day Compliance Filing Protest at 5- 6.
PDF page 33
33
transmission services in contradiction with the December 18th Order, and grant the requested clarifications.
Respectfully submitted,
/s/ Paul F. Wight
March 25, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 34
CERTIFICATE OF SERVICE
I hereby certify that I have on this 25th day of March, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025).
/s/ Sophia Browning
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
PDF page 35
ATTACHMENT 1
TESTIMONY OF ZACHARY MING
PDF page 36
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
Testimony of Zachary Ming
Partner
Energy and Environmental Economics, Inc. (“E3”)
On behalf of
Constellation Energy Generation, LLC (“Constellation”)
March 25, 2026
3
Constellation
1
2
Transmission Tariffs for Co-Located Load – Grid Reliance Charge 3
4
5
Testimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. 6
(“E3”)
7
1 Introduction 8 Q1. PLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS 9 ADDRESS. 10 A1. My name is Zachary Ming. My current position is Partner at Energy and 11 Environmental Economics (“E3”). My business address is 44 Montgomery Street 12 Suite 1250, San Francisco, California 94104. 13 Q2. PLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY. 14 A2. I am filing this testimony as an independent expert, and it represents my own 15 positions and perspectives. Constellation compensated for my testimony, but my 16 compensation did not depend on my conclusions. 17 Q3. ARE YOU THE SAME ZACHARY MING THAT PREVIOUSLY 18 SUBMITTED TESTIMONY IN THIS DOCKET? 19 A3. Yes. I am the same Zachary Ming who previously submitted testimony in this 20 docket regarding the appropriate rate designs that should be applied to different 21 configurations of co-located load.1 22
1 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49- 000, AD24-11-000, and EL25-20-000 (filed Apr. 23, 2025).
PDF page 39
4
Q4.
ARE YOUR QUALIFICATIONS THE SAME AS THOSE SET FORTH IN
1
YOUR PRIOR TESTIMONY IN THESE DOCKETS?
2
A4.
My qualifications are the same as those set forth in my prior testimony in this docket 3
and include testimony before FERC and multiple state and provincial utility
4
commissions. Since then, I have additionally testified before the Puerto Rico 5
Energy Board on the topic of rate design.2
6
Q5.
PLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY.
7
A5.
My testimony outlines that the concept of a Grid Reliance Charge (“GRC”) for co- 8
located load is just and reasonable. However, I show that the Indicated PJM
9
Transmission Owners’3 (the “Transmission Owners”) proposal for calculating the 10
GRC is not grounded in sound ratemaking principles, violates cost causation
11
principles, and is unreasonably high. Finally, I propose an alternative methodology 12
to calculate the GRC that is based on both sound theory and precedent, and I provide 13
a reasonable range for the value of this charge.
14
2 NEPR-AP-2023-0003.3 The Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company (“PECO”), and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company (“PSE&G”); Rockland Electric Company; and the Southern Maryland Electric Cooperative (“SMECO”).
PDF page 40
5
Q6.
PLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY.
1
A6.
My testimony is organized as follows:
2
• In Section 2, I provide the background on the Grid Reliance Charge (“GRC”), 3
including its intended purpose, my assessment of the charge, and how it relates 4
to customers’ reliance on the grid;
5
• In Section 3, I demonstrate why the Transmission Owners’ proposal for the 6
calculation and value of the GRC is unjust and unreasonable;
7
• In Section 4, I outline a theoretically sound and fundamentals-based proposal 8
to calculate the GRC and provide a reasonable range for the value of this charge; 9
and
10
• In Section 5, I summarize my arguments and recommendations.
11
PDF page 41
6
2 Background
1
Q7.
ON WHAT BASIS DO REGULATORS TYPICALLY ALLOCATE
2
ELECTRICITY SYSTEM COSTS?
3
A7.
In electric system ratemaking, regulators primarily allocate costs based on “cost 4
causation” principles. In other words, regulators allocate costs based on how 5
customers cause the utility to incur costs. As the National Association of Regulatory 6
Utility Commissioners (“NARUC”) explains, cost allocation should “attempt to 7
determine what, or who, is causing costs to be incurred by the utility.”4 Broadly 8
speaking, cost drivers are classified into three categories: energy, demand, and 9
customer. Energy-classified costs are driven by total energy consumption of 10
customers. Demand-classified costs are driven by peak demand of all customers. 11
Customer-classified costs are driven by the existence of the system and usually 12
scale with the number of customers. In other words, customer-classified costs are 13
costs that the utility incurs regardless of the energy or demand imposed by its 14
customers.
15
Q8.
HOW ARE TRANSMISSION COSTS TYPICALLY ALLOCATED TO
16
CUSTOMERS?
17
A8.
Because transmission facilities are built to serve peak demand conditions, 18
customers are typically allocated transmission costs on the basis of their 19
4 NARUC, Electric Utility Cost Allocation Manual (Jan. 1992), page 38.
8
Q10. WHAT LEVEL OF DEMAND DO CUSTOMERS THAT PAY THE GRC
1
IMPOSE ON THE TRANSMISSION SYSTEM?
2
A10. Zero, by definition. The GRC, as proposed by the Transmission Owners, applies 3
only to load that is not withdrawn from the transmission system via Firm or Non- 4
Firm Contract Demand Service. Therefore, load that pays the GRC definitionally 5
imposes zero demand on the PJM transmission system.
6
Q11. DESCRIBE THE RATIONALE OF THE GRC.
7
A11. The Transmission Owners propose a GRC as a new charge “designed to reflect the 8
costs of using the transmission system to deliver black start and regulation 9
services.”12 The GRC is intended to capture some contribution toward the cost of 10
the physical wires that are used to deliver black start, regulation, and other 11
synchronization support to co-located loads. The GRC is, in essence, the type of 12
“minimum transmission service charge” Commissioner Chang suggested PJM 13
should include in its new transmission tariff to protect against cost shifts when co- 14
located customers with minimal, or even zero, demand remain reliant on the grid.13 15
Q12. DO YOU AGREE THAT SOME FORM OF GRC IS APPROPRIATE?
16
A12. Yes, the basic concept of the GRC is reasonable. Even though the ancillary services 17
that a co-located load consumes do not impose any incremental wires cost on the 18
PJM system (because delivery of these services does not result in any withdrawal 19
of energy), they nevertheless must be delivered over the wires of the PJM 20
12 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026), page 14.13https://www.ferc.gov/news-events/news/e-1-commissioner-changs-concurrence-pjm-co-location.
PDF page 44
9
transmission system. As a result, it is reasonable for co-located load customers to 1
make some contribution to the cost of wires of the PJM system in the form of a 2
GRC.
3
PDF page 45
10
3 Evaluation of PJM Transmission Owners’ GRC Proposal
1
Q13. PLEASE DESCRIBE THE GRID RELIANCE CHARGE (“GRC”)
2
PROPOSED BY THE PJM TRANSMISSION OWNERS.
3
A13. At a high level, the Transmission Owners propose to calculate a GRC that they say 4
is “designed to recover the costs of delivering ancillary services, including the 5
delivery of black start and regulation, and providing synchronization and grid 6
reliance support … regardless of whether they withdraw energy from the grid.”14 7
The Transmission Owners propose to calculate the GRC based on a fraction of the 8
total transmission revenue requirement, functionally yielding a charge that is 9
applied to co-located load that is a fraction of the NITS rate. They propose that this 10
rate be applied to the gross peak demand of co-located load that is not served 11
through Firm Contract Demand.
12
Q14. WHAT CALCULATION METHODOLOGY DO THE TRANSMISSION
13
OWNERS PROPOSE FOR THE GRC?
14
A14. The Transmission Owners identify a portion of costs that they assert are “associated 15
with grid reliance capability” and use public FERC Form 1 data to calculate these 16
costs as a fraction of the total PJM transmission revenue requirement. Specifically, 17
the Transmission Owners include a portion of transmission depreciation and 18
operation and maintenance expenses, while excluding costs related to amortization 19
14 Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer (Concentric), Exhibit No. PTO-0001 at Page 17, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026).
PDF page 46
11
and general-plant depreciation and Administrative and General expenses. Dividing 1
the sum of these costs by the total PJM transmission revenue yields a GRC charge 2
equal to 25.8% of the NITS rate.
3
Q15. WHAT BASIS DO THE TRANSMISSION OWNERS PROVIDE FOR
4
INCLUDING AND EXCLUDING PARTICULAR COSTS IN THEIR
5
PROPOSED GRC METHODOLOGY?
6
A15. The Transmission Owners provide very little justification for which costs are 7
included or excluded from the GRC and why. For example, the entirety of their 8
justification for including depreciation and operations and maintenance (“O&M”) 9
costs appears to be their statement that “depreciation reflects the annualized 10
consumption of the transmission infrastructure that enables customers to rely on the 11
grid, while O&M reflects the ongoing expense required to keep that infrastructure 12
functional.”15 They then further state that they exclude return on rate base and 13
associated income taxes to produce a “conservative result focused on cost recovery 14
rather than investment return.”16
15
Q16. WHAT IS YOUR ASSESSMENT OF THE TRANSMISSION OWNERS’
16
GRC PROPOSAL?
17
A16. The Transmission Owners’ proposal to include certain costs and exclude others is 18
not grounded in sound ratemaking principles, cost causation principles or, to my 19
knowledge, any relevant precedent. In important regards, they are both excluding 20
15 Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer (Concentric), Exhibit No. PTO-0001 at Page 24, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026).16 Id.
PDF page 47
12
reasonable costs and including unreasonable costs. First, well-established cost-of- 1
service-regulation principles recognize that the rate of return and taxes are just as 2
much a cost of providing service as depreciation.17 The Transmission Owners do 3
not substantiate why these costs are excluded other than to produce a 4
“conservative” outcome. Second, the Transmission Owners attribute the full 5
depreciation costs for a variety of transmission components (i.e., towers and 6
fixtures, poles and fixtures, overhead conductors, etc.) that are sized to meet the 7
actual peak demand requirements of the PJM system, even though customers 8
paying the GRC, by definition, do not impose any demand or withdraw any energy 9
from the PJM system (if they did they would be paying either Firm Contract 10
Demand Service or Non-Firm Contract Demand Service). Put differently, the PJM 11
system could be sized to a much smaller level and still deliver the ancillary services 12
that co-located customers consume.
13
Q17. DOES THE TRANSMISSION OWNERS’ GRC PROPOSAL ADHERE TO
14
COST CAUSATION PRINCIPLES?
15
A17. No. The Transmission Owners’ GRC proposal assigns GRC customers a share of 16
the costs of a transmission system sized to serve PJM’s peak demand, even though 17
these customers, by definition, impose zero demand on that system. Therefore, the 18
Transmission Owners’ GRC proposal violates cost causation principles by charging 19
for demand-driven transmission costs that co-located customers with zero demand 20
that their service does not cause.
21
17https://www.ferc.gov/formula-rates-electric-transmission-proceedings-key-concepts-and-how-participate
PDF page 48
13
Q18. ARE ALL OTHER ASPECTS OF THE TRANSMISSION OWNERS’ RATE
1
DESIGN PROPOSAL CLEAR?
2
A18. No. On one hand, the Transmission Owners’ rate design proposal states that “the 3
transmission rate for Firm Contract Demand Service will be the same rate as the 4
rate for NITS.”18 On the other hand, the Transmission Owners’ proposal states that 5
“the calculation of the [Firm Contract Demand Service] rate will necessarily need 6
to include … the measure of the single coincident peak (“CP”) for NITS.” 19 7
However, the majority of PJM Transmission Owners do not use a single coincident 8
peak (“1-CP”) methodology to calculate the NITS rate. The most common 9
methodology is “5-CP.”20 Thus it is not clear if Transmission Owners are proposing 10
that the Firm Contract Demand Service Rate be calculated on the basis of its 1-CP 11
share or whether the Firm Contract Demand Service Rate would simply be equal to 12
the NITS rate. If the latter, the Transmission Owners should clarify why they 13
repeatedly mention 1 CP throughout their filing in both explanations and example 14
calculations.
15
18 Concentric Testimony, page 26. 19 Id.20 Utilities that use a 5-CP methodology include ComEd, PECO, BGE, and PSE&G.
PDF page 49
14
4 E3 GRC Proposal
1
Q19. WHAT IS THE APPROPRIATE BASIS FOR DETERMINING A GRID
2
RELIANCE CHARGE (“GRC”)?
3
A19. Customers subject to the GRC are, by definition, not drawing power from the PJM 4
network in order to serve their load. If they were drawing power from the system 5
to serve their load, they would be required to purchase Firm or Non-Firm Contract 6
Demand Service. In this sense, co-located load customers receive ancillary services 7
from the existence of the wires that synchronize them to the rest of the PJM system. 8
However, PJM’s wires are sized and built to serve PJM’s actual peak 9
demand. That creates a cost causation distinction. The incremental costs of sizing 10
the PJM system to serve actual peak demand should reasonably be borne by 11
customers who cause this demand, while customers benefitting from the existence 12
of the wires should be responsible for their share of costs that would be necessary 13
to construct the wires without sizing them to meet peak demand. Within the context 14
of electricity system ratemaking, there is a well-established methodology designed 15
to calculate precisely the costs of constructing wires to connect all customers, i.e., 16
customer-driven costs. It is called the “minimum system” method.
17
Q20. WHAT IS A “MINIMUM SYSTEM”?
18
A20. A “minimum system” is a theoretical electricity system designed only to connect 19
each customer and deliver a de minimis amount of power. An analyst can calculate 20
the cost of such a system by determining the minimum size of all electricity system 21
PDF page 50
15
components (e.g., poles, conductors, transformers, etc.) that could be used by the 1
utility to recreate its system and connect each customer to the grid. 2
Q21. IS THE MINIMUM SYSTEM METHOD RELATED TO COST
3
CAUSATION PRINCIPLES?
4
A21. Yes. The minimum system method is specifically designed to identify the portion 5
of system costs that are customer-driven rather than demand- or energy-driven. It 6
answers the question of what it would cost to construct a system to connect all 7
customers before the system is upsized to serve actual peak demand or energy 8
usage. That is precisely relevant to the question at hand. Co-located load subject to 9
the GRC benefits from the existence of wires but, by definition, does not impose 10
any demand on the PJM system. The minimum system framework therefore 11
provides the appropriate cost causation-aligned methodology for calculating the 12
GRC.
13
Q22. DOES THE MINIMUM SYSTEM FRAMEWORK HAVE PRECEDENT IN
14
ELECTRICITY SECTOR RATEMAKING?
15
A22. Yes. The minimum system framework has substantial precedent in electricity- 16
sector ratemaking, particularly in distribution cost allocation and rate design. It is 17
widely used to identify the portion of system costs that are customer-driven; that is, 18
costs incurred because the customer is connected to the system. NARUC recognizes 19
this framework, referring to it as the “minimum-size method,” as one of the “[t]wo 20
methods … used to determine the … customer components of distribution 21
PDF page 51
16
facilities.” 21 These costs are distinct from the additional costs of facilities needed 1
to serve higher levels of demand that should be appropriately allocated based on 2
how much demand each customer is drawing from the network.
3
Many utilities within PJM use minimum system studies in distribution cost 4
allocation, including at least two Indicated PJM Transmission Owners: PPL 5
Electric Utilities Corporation22 and FirstEnergy Service Company.23 6
Q23. IS THE MINIMUM SYSTEM METHOD TYPICALLY USED IN THE
7
CONTEXT OF THE TRANSMISSION SYSTEM AND WHY?
8
A23. The minimum system method is generally not used in the context of transmission 9
system cost allocation and rate design. Transmission system components are 10
generally much larger and more costly relative to a minimum system. This 11
inherently shrinks the quantity of costs that could be customer-classified and makes 12
the need to perform this step less important. Additionally, transmission 13
customers—whether large individual loads or aggregations of smaller loads—have 14
traditionally imposed a meaningful level of demand on the system, meaning there 15
has not been a significant need to allocate a portion of transmission system costs to 16
customers that are not actually drawing power from the grid. Against this backdrop, 17
utilities typically allocate transmission costs largely on the basis of demand. In 18
effect, this classifies 0% of transmission costs to the “customer” cost driver. 19
21 NARUC, Electric Utility Cost Allocation Manual (Jan. 1992), page 90.
22https://www.pplelectric.com/site/-/media/ppl-jss-app/assets/Home/Landing-Pages/Public-Utility- Commission/PDFs/PPL--2025-Rate-Case--Volume-XI-PPL-Electric-Exhibit-BR2.pdf.23https://www.puc.pa.gov/pcdocs/1822988.pdf.
PDF page 52
17
Q24. IS THE MINIMUM SYSTEM METHOD APPROPRIATE IN THE
1
CONTEXT OF THE GRC AND WHY?
2
A24. Yes. While the minimum system method is typically not used in the context of 3
transmission cost allocation or ratemaking, the cost of the minimum system is 4
precisely the set of costs that a co-located load that benefits from the existence of 5
wires but imposes no demand on the grid should share. The costs of the minimum 6
system therefore provide a theoretically-sound basis to calculate the GRC. 7
Q25. HOW CAN THE RESULTS OF A MINIMUM SYSTEM STUDY BE USED
8
TO ESTIMATE THE GRC?
9
A25. A transmission minimum system study could estimate the customer-driven share of 10
transmission costs as a fraction of the total PJM transmission revenue requirement. 11
This fraction could then be applied to each PJM Transmission Owner’s Network 12
Integration Transmission Service (“NITS”) rate to estimate the GRC in dollars per 13
kW-year. For example, if the minimum system study indicates that 5% of 14
transmission costs are customer-driven, the GRC would be 5% of the applicable 15
NITS rate.
16
Q26. WHAT RANGES DO MINIMUM SYSTEM STUDIES GENERALLY
17
YIELD FOR THE FRACTION OF COSTS THAT ARE CUSTOMER-
18
DRIVEN?
19
A26. As stated previously, utilities typically only use the minimum system method to 20
classify distribution costs, not transmission costs, to the “customer” cost driver. 21
While these results vary by utility, a typical range of results may show that between 22
PDF page 53
18
30% – 50% of distribution costs are driven by the number of customers on the
1
system. For example, a recent filing from PPL shows that 43% of distribution costs 2
were categorized to the customer category using the minimum system method.24
3
Q27. HOW WOULD THESE RESULTS CHANGE IF APPLIED TO THE
4
TRANSMISSION SYSTEM INSTEAD OF THE DISTRIBUTION SYSTEM?
5
A27. Applying the minimum system method to the transmission system would
6
definitionally yield a smaller fraction than the distribution-level values discussed 7
above. This is because transmission system components are much larger than
8
distribution system components, so the minimum system is a smaller fraction of 9
total transmission system costs.
10
As discussed above, no utilities that I am aware of classify any transmission
11
costs to the customer cost driver, meaning they are implicitly assuming a minimum 12
system value of 0% for the transmission system. Thus, it is reasonable to assume 13
that a proper minimum system study when applied to the transmission system
14
would yield a value significantly lower than 25.8%.
15
24https://www.pplelectric.com/site/-/media/ppl-jss-app/assets/Home/Landing-Pages/Public-Utility- Commission/PDFs/PPL--2025-Rate-Case--Volume-XI-PPL-Electric-Exhibit-BR2.pdf, pages 10-12. The 43% distribution-system-wide value is a cost-weighted average across the asset categories included in PPL’s minimum-size study. Customer-categorized minimum-system costs total $2,220,555,755, consisting of primary and secondary poles ($521,359,795 + $249,684,941), overhead conductors ($306,415,614 + $56,927,365), underground conductors and conduit ($276,309,292 + $10,958,340), and line transformers ($798,900,408). Total plant costs for those same asset categories equal $5,164,745,630 ($1,167,387,366 + $948,692,824 + $897,426,932 + $2,151,238,508). The resulting ratio is 43.0%.
PDF page 54
19
Q28. CAN YOU ESTIMATE MINIMUM SYSTEM COSTS AS A FRACTION OF
1
THE PJM TRANSMISSION SYSTEM?
2
A28. Using publicly available data, I estimate that a minimum transmission system in 3
PJM would constitute approximately 6% of the costs of the actual PJM transmission 4
system. This estimate is based on an approximate count of assets in the PJM 5
transmission system for four major categories: overhead conductors, transmission 6
poles, transmission towers, and transmission substations.
7
To approximate cost of PJM’s existing (not minimum) system, I
8
disaggregated the component counts by voltage level and multiplied by their unit 9
costs. The result is an approximate cost to build a “new” PJM system using the 10
existing mix of components, allowing for an apples-to-apples comparison to a 11
“new” minimum system. It is not intended to replicate total transmission plant-in- 12
service across all PJM transmission owners.
13
To approximate the cost of the minimum system, I identified the relevant 14
minimum system components and associated unit costs and applied them to the 15
component count estimate. In effect, the analysis assumes the same categories and 16
count of components. The assumptions, calculations, and results from my high- 17
level minimum system study for PJM’s transmission system are shown in Table 1. 18
PDF page 55
20
Table 1: PJM Minimum System Study Assumptions, Calculations, and Results
1
Overhead
Conductors
Poles
Towers
Substations
Total
(1) Component
Count Estimate25
~265,000
conductor miles
~365,000
poles
~210,000
towers
~8,000
substations
Minimum System
(2) Minimum System
Component
267 kcmil ACSR
Distribution
wood pole
Distribution
wood pole
15 kVA
transformer
(3) Minimum System
Unit Cost26
$7,500/mile
$7,000/pole
$7,000/pole
$15,000/transf.
(1) x (3) = (4) Minimum System
Cost
$2.0 billion
$2.6 billion
$1.5 billion
$0.1 billion
$6.2 billion
Existing System
(5) Existing System
Component
336-2,156 kcmil
ACSR
Transmission
steel pole
Transmission
steel tower
<69/69 kV-
500/765 kV
transformer
(6) Existing System
Unit Cost (wtd.
average)27
$70,000/mile
$80,000/pole
$125,000/tower
$3,000,000
/transformer
(1) x (6) = (7) Existing System
Cost
$18.6 billion
$29.2 billion
$26.3 billion
$24.0 billion
$98.1 billion
Minimum Study Result
(4) / (7) = (8) Minimum System
Fraction (%)
11%
9%
6%
1%
6%
As shown in the table above, this calculation yields a minimum system that
2
is approximately 6% of the cost of the actual PJM system.
3
25 Component counts are high-level estimates. PJM reports 88,333 miles of transmission lines in its system (https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/pjm-at-a-glance.pdf). Assuming three phase conductors per line-mile yields about 265,000 conductor-miles. Based on the system’s voltage profile and my experience, I assumed a 50/50 split of line-miles between pole-supported and tower- supported lines and spacing of about eight poles per mile and five towers per mile, respectively. The substation count was estimated using geographic information system (“GIS”) data for PJM substations.26 Minimum-system unit costs are simplifying assumptions intended to reflect the least-cost configuration needed to maintain a de minimis level of service. For conductors, I selected the smallest ACSR conductor listed in MISO’s public cost guide since PJM does not publish their own transmission cost guide (https://cdn.misoenergy.org/20240501%20PSC%20Item%2004%20MISO%20Transmission%20Cost%20E stimation%20Guide%20for%20MTEP24632680.pdf). For poles and towers, I assumed a distribution pole structure; the $6,500 unit cost reflects my experience, informed by public benchmark pricing for distribution wood-pole installations. The substation unit cost similarly reflects my judgment regarding a minimal 15 kVA configuration sufficient to keep the load connected and synchronized with the grid.27 Existing system unit costs are weighted averages. I first allocated the estimated PJM system components across voltage classes and selected a representative standard asset type for each class. For these unit cost estimates, I also used MISO’s public cost guide. The table values reflect the weighted average of those voltage-specific unit costs across the estimated component mix by asset type.
PDF page 56
21
Q29. HOW SHOULD AN ACTUAL MINIMUM TRANSMISSION SYSTEM
1
VALUE BE CALCULATED FOR APPLICATION TO THE GRC?
2
A29. While the results of my calculation above are reasonable, they are based on 3
relatively high-level publicly available data. For specific application to the GRC, 4
the Transmission Owners should perform a minimum system study for the PJM 5
transmission system using more detailed information about their system. 6
Q30. HOW WOULD YOU ASSESS WHETHER THE RESULTS OF ANY PJM-
7
SPECIFIC MINIMUM SYSTEM STUDY ARE REASONABLE?
8
A30. As discussed above, there is little to no precedent for applying the minimum system 9
method to the transmission system, so there is relatively little available data upon 10
which to benchmark results. Nonetheless, it is the case that most utilities implicitly 11
classify transmission costs 100% to demand and 0% to customer. This implicitly 12
means that something significantly lower than the 25.8% charge proposed by the 13
Transmission Owners. It is also definitionally true that applying the minimum 14
system to the transmission system should yield a smaller fraction than if applying 15
it to the distribution system.
16
Based on this information and my calculation estimate above, a minimum 17
system that yields between 2% to 10% of actual system costs is reasonable based 18
on the sheer differences of minimum components relative to the large towers and 19
conductors that constitute the PJM system. Any result higher than 10% would be 20
unreasonable and should call into question the methodological approach or 21
assumptions used in the study, with demand-driven transmission costs likely being 22
improperly assigned to customers that do not cause them.
23
PDF page 57
22
Q31. HOW SHOULD THE OUTPUT OF A MINIMUM SYSTEM STUDY BE
1
USED TO CALCULATE THE GRC?
2
A31. The minimum system study will yield a percentage value that is substitutable for 3
(but lower than) the 25.8% value that the Transmission Owners have proposed as 4
their Grid Reliance Percentage Allocator to calculate the GRC. The only difference 5
is that a value calculated using the minimum system that is below 10% will be both 6
theoretically sound, fair, just, and reasonable. With a new and lower Grid Reliance 7
Percentage Allocator, the Transmission Owners should re-calculate the GRC using 8
the same methodology that they have already proposed.
9
Q32. WHAT ARE THE IMPACTS OF A GRC THAT IS TOO HIGH?
10
A32. Customers that pay the GRC by definition do not impose any incremental cost on 11
the transmission system. Thus, all GRC charges that the Transmission Owners 12
collect are used to directly reduce the NITS rate for all other customers.28 In this 13
regard, it may seem that a higher GRC rate would yield higher GRC revenues and 14
thus higher reductions to the NITS rate for all other customers. However, basic 15
economics tells us that this is not necessarily the case. As Art Laffer artfully 16
demonstrated, higher tax rates can actually yield lower tax revenues to the extent 17
that they discourage work and investment.29
18
In the case of the GRC, inappropriately increasing the rate to too high of a 19
level could have the effect of reducing absolute GRC revenues for two reasons. 20
First, it could discourage the development of co-located load in the PJM region. 21
28 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026), page 17.29https://en.wikipedia.org/wiki/Laffer_curve.
PDF page 58
23
Second, it could disincentivize the configuration of load in a lower cost co-located 1
configuration and instead incentivize configuration of load in a higher cost NITS 2
configuration that would require inefficient buildout of the transmission system. An 3
explicit objective of this proceeding is to “avoid costly and inefficient transmission 4
system buildout that may not be necessary.”30 Thus, a GRC that is too high risks 5
inefficiently increasing system costs and reducing GRC collections that can be used 6
to reduce the NITS rate for other customers. It is therefore not in the best interest 7
of PJM’s consumers for Transmission Owners to seek a high GRC that would 8
ultimately reduce GRC revenue collections.
9
30 FERC Order EL25-49-000, page 70.
PDF page 59
24
5 Recommendations & Summary
1
Q33. IN LIGHT OF THE ARGUMENTS YOU MAKE, DO YOU HAVE A
2
RECOMMENDATION?
3
A33. Yes. I recommend that FERC not approve either the methodology or value for the 4
Grid Reliance Charge (“GRC”) that the Transmission Owners have put forward. It 5
is not theoretically sound, has no precedent, and is unreasonably high. Instead, I 6
recommend that FERC order PJM to conduct a minimum system study to determine 7
a percentage that can be applied to the NITS rate to calculate the GRC. I estimate 8
that 6% of NITS is a reasonable basis for the GRC, but any value between 2% to 9
10% may be reasonable. FERC should ensure that PJM does not produce a GRC 10
rate higher than 10% of the NITS rate which would be unreasonable, not aligned 11
with cost causation principles, and would call into question the methodological 12
approach or assumptions.
13
Q34. PLEASE SUMMARIZE YOUR TESTIMONY.
14
A34. Yes. The key takeaways of my testimony are:
15
• The concept of a GRC is reasonable so that co-located loads make some 16
contribution to the cost of the wires that deliver the ancillary services they 17
consume;
18
• The Transmission Owners’ proposal for the GRC is unjust and unreasonable 19
because it is not based on sound ratemaking principles, has no precedent, is 20
inconsistent with cost causation principles, and is unreasonably high; 21
PDF page 60
25
• The minimum system method provides a theoretically sound basis for 1
developing a GRC;
2
• Using the minimum system method, I estimate an appropriate GRC should be 3
6% of the NITS rate, although a value between 2% to 10% may be reasonable; 4
and
5
• A GRC rate that is too high could have the unintended negative consequences 6
of both reducing GRC revenues and causing inefficient transmission buildout, 7
contrary to the objective of the FERC Order.
8
Q35. DOES THIS CONCLUDE YOUR TESTIMONY?
9
A35. Yes
10
PDF page 61
VERIFICATION
I declare under penalty of perjury that the foregoing Testimony is true and correct to the best of my knowledge, information, and belief.
Executed this 25th day of March, 2026.
________________________
Zachary Ming