Reply Brief of Constellation Energy Generation, LLC
Text extracted from the eLibrary original (SHA-256 936022f422c5f4fc…). Download the original from the official source.
Contents · 13 sections
- I. The Commission Should Fast Track Interim NITS
- II. PJM Proposes to Restrict Contract Demand Services in Conflict with the December 18th
- III. The Commission Should Encourage Its New Transmission Services and Reject Attempts
- A. The Commission Should Direct PJM to Include a Transitional Mechanism
- B. PJM’s Proposed Study Procedures Lack Sufficient Detail to Prevent Needless
- C. PJM and Indicated Transmission Owners’ “To Be Determined” Penalty
- D. Clarification of Proposed System Protection Scheme Requirements is Needed
- E. The Grid Reliance Charge Must be Economically Grounded and Rational
- F. PJM’s Proposal to Require Retail Sale Authorization Will Delay
- G. Requiring Different Feeders is Potentially Unnecessary, Discriminatory and
- IV. Other Clarifications on Co-Located Loads and the Requirements of Existing Capacity
- Attachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology
- CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
PJM proposes to make this service available only when the Co-Located Generating Facility is on outage.Read this passage Filed comments: Connecting load and generation
I. The Commission Should Fast Track Interim NITS
printed heading · Topic match: Reliability and curtailment
Like SPP, PJM will only need to automate curtailment of Interim NITS before NITS just as it does for external Non-Firm Point to Point Transmission Service.Read this passage Filed comments: Reliability and curtailment
II. PJM Proposes to Restrict Contract Demand Services in Conflict with the December 18th
printed heading · Topic match: Connecting load and generation
The December 18th Order made Non-Firm Contract Demand Service available for Eligible Customers to withdraw energy from the transmission system “when transmission capacity is available and not needed by firm customers,” period.46 The use of the Non-Firm Contract Demand Service to 44 PJM Initial…Read this passage Filed comments: Connecting load and generation
III. The Commission Should Encourage Its New Transmission Services and Reject Attempts
printed heading
The Commission Should Encourage Its New Transmission Services and Reject Attempts that Frustrate Their Use PJM and Indicated Transmission Owners propose provisions that would restrict, delay or otherwise discourage the use of Interim NITS and Contract Demand Services.Read this passage
A. The Commission Should Direct PJM to Include a Transitional Mechanism
printed heading · Topic match: Connecting load and generation
PJM should clarify that Interim NITS is available for large loads meeting the Commission’s definition of Co-Located Load after PJM conducts a supplemental study, if necessary, to find the requested Interim NITS could be provided reliably.Read this passage Filed comments: Connecting load and generation
B. PJM’s Proposed Study Procedures Lack Sufficient Detail to Prevent Needless
printed heading · Topic match: Retail and wholesale authority
PJM must spell out in the Tariff the studies that it will perform in conjunction with the Co-Located Generating Facility and the timetable for completing these studies.Read this passage Filed comments: Retail and wholesale authority
C. PJM and Indicated Transmission Owners’ “To Be Determined” Penalty
printed heading · Topic match: Reliability and curtailment
PJM simply recalls export transactions and Transmission Customers are only subject to “Curtailment or Interruption under the terms of the Tariff.”86 Under PJM’s proposal, the failure by an Eligible Customer to follow one instance of Curtailment or Load Shed procedures, no matter who is at fault,…Read this passage Filed comments: Reliability and curtailment
D. Clarification of Proposed System Protection Scheme Requirements is Needed
printed heading · Topic match: Connecting load and generation
“[S]pecial protection schemes allow … Co-Located Load to effectively limit their withdrawals from the transmission system.”104 Constellation agrees with Indicated Transmission Owners’ second recommendation that the Co-Located Load customer should “pay for PJM and PJM Transmission Owner-administered…Read this passage Filed comments: Connecting load and generation
E. The Grid Reliance Charge Must be Economically Grounded and Rational
printed heading · Topic match: Cost allocation
The Grid Reliance Charge Must be Economically Grounded and Rational The Indicated Transmission Owners’ proposed Grid Reliance Charge for Contract Demand Service customers not drawing power from the PJM network is derived from an unsound methodology that violates cost causation principles.Read this passage Filed comments: Cost allocation
F. PJM’s Proposal to Require Retail Sale Authorization Will Delay
printed heading · Topic match: Connecting load and generation
PJM’s Proposal to Require Retail Sale Authorization Will Delay Interconnections Constellation conditionally opposes PJM’s new requirement for both Interim NITS and the Contract Demand Services that the Eligible Customer must “provide PJM with ‘an authorization or certification from its Relevant…Read this passage Filed comments: Connecting load and generation
G. Requiring Different Feeders is Potentially Unnecessary, Discriminatory and
printed heading · Topic match: Connecting load and generation
To the extent that PJM proposes to require different feeders to allow “selective curtailment” 139 for Co-Located Load receiving non-firm and firm services, the requirement should not apply to Interim NITS.Read this passage Filed comments: Connecting load and generation
IV. Other Clarifications on Co-Located Loads and the Requirements of Existing Capacity
printed heading · Topic match: Connecting load and generation
First, the Commission should clarify that it did not intend to require a capacity resource to delist even when it has no obligation to serve the Co-Located Load and remains fully capable of serving the grid during capacity emergencies.145 In explaining what Contract Demand Services an Eligible…Read this passage Filed comments: Connecting load and generation
Attachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology
printed heading · Topic match: Connecting load and generation
Attachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology include ComEd, PECO, BGE, and PSE&G.”). 145 Clarification Request at 1-3; Mar. 24 Answer to PJM passim. 146 PJM Initial Brief at 8. 32 Second, the Commission should make clear that the…Read this passage Filed comments: Connecting load and generation
CONCLUSION
printed heading
CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission promptly approve and make Interim NITS effective October 1, 2026, reject PJM’s and the Indicated Transmission Owners’ attempts to restrict, delay, or otherwise discourage new 147 December 18th Order,…Read this passage
CERTIFICATE OF SERVICE
printed heading
Large Loads Co-Located at Generating Facilities Constellation Energy Generation, LLC v.Read this passage
Table of Contents
printed heading · Topic match: Cost allocation
Even though the ancillary services 17 that a co-located load consumes do not impose any incremental wires cost on the 18 PJM system (because delivery of these services does not result in any withdrawal 19 of energy), they nevertheless must be delivered over the wires of the PJM 20 12 Initial Brief…Read this passage Filed comments: Cost allocation