UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission
Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
-2-
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
RESPONSE BRIEF OF VISTRA CORP.
Vistra Corp. (“Vistra”) hereby submits this Response Brief pursuant to the Federal Energy Regulatory Commission’s (“Commission”) December 18, 2025 Order in Docket No. EL25-49 et al. (“Order on Show Cause Proceeding” or “Order”),1 and its Notice of Extension of Time,2 in the
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Order on Show Cause Proceeding”).2 PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49, et al. (Jan. 23, 2026) (extending deadlines for response briefs to March 25, 2026).
PDF page 3
-3-
above-captioned dockets. The Commission’s landmark Order articulated a vision for providing service to large loads that are co-located with generation resources in the PJM Interconnection, L.L.C. (“PJM”) region in order to fulfill customers’ “right to receive electric service on a timely basis” while ensuring that service is “reliable and affordable for all customers.”3 To do that, the Commission required a replacement rate that ensures that large loads are “able to take transmission services that reflect their actual impact on the transmission system.”4 Critically, the Commission directed PJM to create new transmission services to facilitate the expeditious development and interconnection of new loads co-located with generation resources in PJM.5 Such co-location will be critical to powering the next generation of digital infrastructure necessary to develop and maintain the artificial intelligence (“AI”) capability that is increasingly central to our national security.
But as is often the case, the devil is in the details. While the Commission set forth the
overarching framework for the new services, the actual rates, terms, and conditions will be
developed in this paper hearing. Those details will determine whether or not these new services accomplish the goals the Commission articulated. Unfortunately, the details proposed by PJM and
3 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 3).4 Id. P 162.5 See, e.g., FERC, Transcript: December 18, 2025 Open Meeting, at 16:11-16 (Dec. 18, 2025), https://ferc.gov/media/transcript-december-18-2025-open-meeting (Remarks of Comm’r Rosner) (“[C]reating options that only require PJM to plan for the firm service that the large load customers actually want . . . helps get the co-located load and generator online faster.”); id. at 18:17-21 (explaining that Interim NITS “leverages speed in the near term and unlocks the benefits of a full grid connection in the long term,” providing “increased speed to connect” in exchange for curtailment risk); id. at 24:21-25:16 (Remarks of Comm’r See) (“Co-located arrangements can be an important mechanism for faster interconnection to the system and have the potential for fewer network upgrade needs than a front-of-the-meter option. In short, when done right co-location can be both a consumer forward tool and a critical avenue in [meeting] our national imperative of speed to power and winning the AI race . . . . [O]ne of my key principles as I’ve worked through this order with my colleagues over the past months has been bringing to bear as much flexibility as responsibly possible to harness the speed and value adds that various co-located configurations can provide.”); id. at 26:4-7 (“FERC is meeting the urgent demand for speed to power by creating flexibility for a rapidly evolving industry without sacrificing reliability and affordability.”); id. 28:3-5 (“[T]oday is an important marker propelling us as we provide predictability, stability, and speed to meet this generational moment.”); id. at 33:20-21 (Remarks of Comm’r LaCerte) (“[T]he status quo has become untenable.”).
PDF page 4
-4-
the PJM Transmission Owners are directly counter to those goals. The proposal from PJM and the Transmission Owners consists of long delays, unreasonable rates, and undue discrimination. To adopt a replacement rate that is just, reasonable, and not unduly discriminatory, and to ensure that the new transmission services actually meet the needs they were created to fulfill, the Commission must direct PJM and the Transmission Owners to remedy various flaws in the proposal. As discussed further below, although there are numerous flaws in PJM and the Transmission Owners’ proposal, they can be grouped into three categories.
First, PJM proposes to delay the effectiveness of the new transmission services until June 1, 2029. Under that proposal, customers may have to wait until June 1, 2029 to even submit study requests associated with the new transmission services. In effect, that proposal creates a three- to five-year moratorium on the co-location of new large loads and generation in PJM—quite the opposite of “break[ing] the logjam.”6
Second, the proposed rates, terms, and conditions for Non-Firm Contract Demand Transmission Service are both unreasonable and unduly discriminatory. While the Commission compared Non-Firm Contract Demand Transmission Service to Non-Firm Point-to-Point Transmission Service,7 PJM and the Transmission Owners propose to make Non-Firm Contract Demand Transmission Service both more expensive and less available than its point-to-point counterpart.
Third, the proposal reserves unfettered discretion for PJM and the Transmission Owners in the study process. The proposal appears to allow PJM and the Transmission Owners to determine, for each transmission service request, whether studies are required, which studies to conduct, the
6 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 4).7 See id. P 215.
PDF page 5
-5-
timeline for doing so, and how to prioritize different requests. That level of discretion creates textbook opportunities for the type of undue discrimination that the Order was intended to prevent. The Commission must direct PJM and the Transmission Owners to address each of these items on further compliance to render the PJM Tariff just, reasonable, and not unduly discriminatory. The Commission can do so through the below targeted adjustments to PJM and the Transmission Owners’ proposal. In directing further compliance, Vistra urges the Commission to provide as specific and detailed guidance as possible, in addition to setting tight compliance deadlines, to achieve the Commission’s laudable goal of providing the clarity needed to promote the expeditious interconnection of large loads.
Facilitate speed to power by requiring PJM to implement the new transmission services sooner, with a transition process that reflects the services that can be provided most quickly and respects ongoing or completed necessary studies.
Ensure that the rate structure for Non-Firm Contract Demand Transmission Service is tailored to the benefits that the customer draws from the grid and does not create cost shifts. o
The rates for Non-Firm Contract Demand Transmission Service should recognize that customers may use the service differently, i.e., some customers may never reserve transmission service, some may reserve a de minimis amount, and some may reserve significant amounts. Those customers do not rely on the grid to the same extent and should not be subject to the same grid reliance charge.
Eliminate unfettered discretion in the proposed study process by ensuring that the Tariff clearly defines the studies that must occur and the timeline and order in which those studies will occur.
Remove unreasonable and unduly discriminatory restrictions on the use of special protective schemes and remedial action schemes. Any restrictions must comply with comparability principles and be governed by clear and objective standards to prevent undue discrimination.
I. The Proposed June 1, 2029 Effective Date is Unjust and Unreasonable and Fails to Provide Speed to Power
This entire proceeding exists because co-located loads need to access the transmission system quickly in order to satisfy the nation’s time-sensitive demand for the computing and
PDF page 6
-6-
manufacturing capability necessary to win the global race for AI dominance.8 As Commissioner Rosner put it, “a business-as-usual approach to load growth . . . will not suffice to timely meet growing demand while also keeping prices reasonable.”9 Indeed, the new transmission services created in this proceeding were created specifically “to facilitate more rapid interconnection and operation of Co-Located Loads[.]”10
PJM nevertheless proposes to delay the implementation of the new transmission services
until June 1, 2029—nearly four years after the Commission’s directive to take action.11 And customers may not even be able to submit study requests until the tariff provisions governing those applications are effective. A June 1, 2029 effective date means, then, that co-located loads will not begin to receive service in PJM until 2030 at the earliest—and potentially even later, depending on the length of PJM’s studies and the scope of required network upgrades.
8 See, e.g., FERC, Transcript: December 18, 2025 Open Meeting, at 6:13-22 (Dec. 18, 2025), https://ferc.gov/media/transcript-december-18-2025-open-meeting (Remarks by Chairman Swett) (“[T]oday FERC is pushing our country forward in the artificial intelligence and manufacturing revolution. While uncertainty is abounded across our country on how we will facilitate data centers, this morning, my colleagues and I are taking a critical step to give investors and consumers more certainty on how FERC believes we can solve the problem of meeting historical surging demand and realize our greatest potential as a country also while safeguarding the prices that we pay for electricity.”); id. at 24:16-25:2 (Remarks by Comm’r See) (“As a nation and an industry, we are grappling with unprecedented demand growth. Today the Commission votes to help assist co-located arrangements quickly and flexibly interconnect to meet some of that demand in PJM. Co-located arrangements can be an important mechanism for faster interconnection to the system and have the potential for fewer network upgrade needs than a front-of-the- meter option. In short, when done right, co-location can be both a consumer forward tool and a critical avenue in [meeting] our national imperative of speed to power and winning the AI race.”); Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 200 (“Co-Located Loads are concerned with the speed to interconnect to the PJM transmission system and begin operation.”); id. PP 145-146 (summarizing comments highlighting the importance of data centers and AI to national security and the urgent need for clarity and asking the Commission to act quickly); id. (Rosner, Comm’r, concurring at P 11) (discussing how the new interim transmission service provides speed to power).9 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 3). 10 Id. P 200; id. PP 200-201 (explaining that Interim NITS would address delays in obtaining service and allow Eligible Customers to obtain service more quickly in exchange for their willingness to curtail).11 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., at 79 (filed Feb. 23, 2026) (“PJM Initial Brief”).
PDF page 7
-7-
PJM has not shown that its four-year delay is just and reasonable.12 Nor can it. PJM
presents two arguments in support of its four-year delay: (1) the need to procure capacity to serve new load through the three-year forward schedule of the capacity market, and (2) the need for software updates to PJM’s market and operations systems to permit the curtailment of Non-Firm Contract Demand Transmission Service and Interim Network Integration Transmission Service (“NITS”) when needed.13 Neither bears scrutiny.
A. Capacity Market
PJM’s capacity market schedule does not justify delaying the provision of new
transmission services. As a threshold matter, resource adequacy considerations are simply outside the scope of a transmission provider’s obligation to serve: the Commission requires transmission providers to make transmission service decisions based on available transfer capacity.14 Moreover, two out of the three new transmission services are non-firm. PJM does not need to procure capacity
12 Commission regulations and policy must enable timely data center development, which is critical to our economy and our national security. As President Trump recently observed, the United States is competing with China and other nations in a “race to achieve global dominance in artificial intelligence,” which will bring with it the ability to “set global AI standards and reap broad economic and military benefits.” Executive Office of the President, Winning the Race: America’s AI Action Plan, at 1 (July 2025), https://www.whitehouse.gov/wp- content/uploads/2025/07/Americas-AI-Action-Plan.pdf. In that race, “every delay is a dollar lost . . . [w]e need to break ground faster . . . to build at the speed of national need.” President’s Budget Request for the U.S. Dep’t of Energy for Fiscal Year 2026: Hearing Before the S. Comm. on Energy & Nat. Res., 119th Cong. 5 (2025) (statement of Christopher Wright, Secretary, U.S. Dep’t of Energy), https://www.energy.senate.gov/services/files/35D195A3- 946E-46D0-A5E7-84C06F46B9A4. See also Sw. Power Pool, Inc., 192 FERC ¶ 61,131 (2025) (Rosner, Comm’r, concurring at P 3) (“It is critically important that grid operators continually look for ways to refine the efficiency and speed with which new generation can connect to the grid, especially as our country faces growing power needs to win the global AI race, re-shore manufacturing, and keep electricity affordable for everyday consumers.” (emphasis added)); Press Release, Dep’t of Energy, Energy Department Announces $1.9B Investment in Critical Grid Infrastructure to Reduce Electricity Costs (Mar. 12, 2026), https://www.energy.gov/articles/energy-department- announces-19b-investment-critical-grid-infrastructure-reduce-electricity (emphasizing the need to “accelerate urgently needed upgrades to the nation’s power grid”).13 PJM Initial Brief at 79.14 See Preventing Undue Discrimination & Preference in Transmission Serv., Order No. 890, 118 FERC ¶ 61,119, at P 2, order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh'g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009); Implementation of Dynamic Line Ratings, Advance Notice of Proposed Rulemaking, 187 FERC ¶ 61,201, at P 40 (2024); FERC, Pro Forma Open Access Transmission Tariff, §§ 14.2, 15.4, 18.4 (rev. Dec. 16, 2021).
PDF page 8
-8-
to meet demand from customers that take Non-Firm Contract Demand Transmission Service and Interim NITS (before it is converted to regular NITS).15 The capacity market schedule cannot be a reason to delay the implementation of services that are not capacity-backed.
The capacity market schedule is not a reason to delay the implementation of Firm Contract Demand Transmission Service either.16 PJM argues that it must ensure that it procures enough capacity to meet demand, and that the 2029/2030 Base Residual Auction (“BRA”) is the first auction in which it can do so because the 2027/2028 BRA has already occurred, and the parameters are already set for the 2028/2029 BRA.17 But that argument assumes that the loads that will take Firm Contract Demand Transmission Service were not already included in the load forecast for the 2027/2028 and 2028/2029 BRAs. That assumption is false.
To the contrary, the new large loads that could come online between now and June 2029
were already included in the load forecasts used for the 2027/2028 BRA and the 2028/2029 BRA.18 By definition, PJM’s load forecast is just that: a forecast of a future demand. That forecast
15 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 218 (“[U]nlike Network Load, Co-Located Loads on whose behalf Eligible Customers are taking Non-Firm Contract Demand transmission service would not be considered for resource adequacy planning purposes.”).16 Further undermining the justification for this delay is that fact that the PJM Board of Managers has committed to developing a connect-and-manage framework whereby, if a shortfall exists between forecasted load additions and new incremental generation, that load growth would be subject to curtailment until additional resources are deployed on the system. See PJM, Board Decisional Letter on Critical Issue Fast Path - Large Load Additions, at 4-5 (Jan. 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm- board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.17 PJM Initial Brief at 80.18 PJM has been closely monitoring and planning for large load growth for several years. See 2023 Long-Term Load Forecast Predicts Growth Fueled by Data Centers, PJM Inside Lines (Jan. 23, 2023), https://insidelines.pjm.com/2023-long-term-load-forecast-predicts-growth-fueled-by-data-centers/ (explaining that the 2023 load forecast showed increasing energy demand driven by data centers in Virginia and Maryland); Ethan Howland, Data centers were 40% of PJM capacity costs in last auction: market monitor, Utility Dive (Jan. 7, 2026), https://www.utilitydive.com/news/data-centers-pjm-capacity-auction/808951/ (explaining that in PJM’s last three capacity auctions, data center-driven costs constituted 45 percent of total cleared capacity); PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, at P 5 (2024) (describing that in PJM’s proposal to revise its Reliability Assurance Agreement to better allocate localized load adjustments, it noted that its proposal was “spurred by the recent proliferation of data centers that are contributing to large additions of forecasted load”).
PDF page 9
-9-
includes an adjustment that specifically accounts for new large loads like data centers.19 Indeed, the load forecast that was released in 2025 and used for the 2027/2028 auction included approximately 18 GW of new large loads in 2027 and 23 GW of new large loads in 2028.20 That forecast appeared to have been over-inclusive of new large loads such that PJM applied more conservative assumptions in the next load forecast.21 As a result, the forecast that was released in 2026 and will be used in the 2028/2029 BRA includes approximately 21 GW of new large loads in 2028 and 27 GW of new large loads in 2029.22 And given the new transmission services created in this proceeding, it is likely that some of the large loads included in the forecasts used in the 2027/2028 and 2028/2029 BRA may choose to take non-firm service, for which capacity is not required. Therefore, those forecasts necessarily must include the new loads that may come online before 2029 and take firm service.
PJM also argues that it does not expect any customers to take the new transmission services before June 1, 2029 because of the time it takes to de-list an existing generator from the capacity
19 PJM Manual 19: Load Forecasting & Analysis, Rev. 38 (eff. Dec. 17, 2025), attach. B. 20 More precisely, the load adjustments in the 2025 forecast totaled 17,721 MW for 2027 and 23,418 MW for 2028. PJM, Load Forecast Development Process, Forecast & Reports, Long-Term Load Forecast, Previous Reports (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/previous-load-forecast- reports.zip (zip file containing 2025 load report tables with 2025 load adjustment figures at tab B-9b).21 In the 2026 forecast, PJM revised the load adjustment figures for 2027 and 2028 down to 15,856 MW and 21,280 MW, respectively. PJM, Load Forecast Development Process, Forecast & Reports, Long-Term Load Forecast Tables, at B-9b (Feb. 6, 2026), https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/2026-load- report-tables.xlsx (“2026 Load Forecast Table”); see also PJM, 2026 PJM Load Forecast Report, at 4 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf (“2026 Load Forecast Report”) (explaining that the changes to large load adjustment request brought down the near-term forecast compared to the forecast published in 2025); PJM, Load Adjustment Request Implementation, at 3-5 (July 1, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/postings/load-adjustment- request-implementation.pdf (explaining PJM’s approach to implementing the large load adjustment). 22 The load adjustments in the 2026 forecast totaled 21,280 MW for 2028 and 27,361 MW for 2029. 2026 Load Forecast Table at B-9b; see also 2026 Load Forecast Report at 5 (explaining load adjustments for 2026 are primarily attributable to growth in data center load).
PDF page 10
-10-
market.23 There are multiple flaws with that rationale. First, there may be some generators that seek to serve co-located load that are not currently capacity resources. Second, there may be other generators that seek to serve co-located load that are already in the process of de-listing. Third, existing capacity resources that have not started the process to de-list still have the option to enter into a bilateral agreement with another generator to cover their capacity obligations.24 Finally, existing capacity resources can also buy out of their capacity positions in intervening Incremental Auctions if necessary.25
At bottom, the three-year forward capacity market schedule is no excuse to delay the
integration of co-located loads by several years when all of the load that could otherwise interconnect during that time is either not capacity-backed or already included in the capacity market forecast.
B. Software and System Changes
Separate from its capacity market argument, PJM asserts that delaying its reforms to mid-
2029 is necessary because it needs to implement software changes that depend on vendor
availability, speed of design, costs, managing competing priorities, and the resolution of rates, terms, and conditions for the new services.26 PJM also notes that “automation will be necessary” to avoid “non-optimal, untimely, and inefficient outcomes” in implementing the curtailable Interim
23 PJM Initial Brief at 82. PJM also points to the inability of new generation to come online within the next three years. Id. But at the same time, PJM just filed an Expedited Interconnection Track proposal that requires generators to interconnect within three years. See PJM, Open Access Transmission Tariff, pt. X, subpt. A, § 601(C)(3) (0.0.0) (proposed tariff provisions establishing Expedited Interconnection Track, pending in Docket No. ER26-1563) (“PJM Tariff”).24 PJM Tariff, attach. DD.4 (8.1.0), § 4.6(a) (Bilateral Capacity Transactions).25 PJM asserts that this pathway would be “inappropriate” because “Incremental Auctions are conducted to allow for replacement resource procurement . . . [.]” PJM Initial Brief at 80 (emphasis in original) (citing PJM Initial Brief, Attach. D, Affidavit of Timothy Horger, Senior Director, Forward Market Operations, at ¶ 15 (“Horger Affidavit”)). But PJM does not actually explain why customers could not use the Incremental Auction in this instance.26 See Horger Affidavit at ¶ 16.
PDF page 11
-11-
NITS and Non-Firm Contract Demand Transmission Service. 27 PJM does not plead with any degree of specificity why these factors, separately or together, require it to delay service until mid- 2029. Nor does PJM address the fact that its systems should already be capable of curtailing based on type of transmission service because its Tariff already provides Non-Firm Point-to-Point Transmission Service.28 Given PJM’s lack of evidence supporting its proposed delay, the Commission should give no probative value to PJM’s assertion that it needs over three years to implement software changes for the new transmission services.
Further, past precedent indicates that PJM should be able to implement software changes much more quickly than it has proposed here. For example, when PJM integrated energy storage resources into its markets pursuant to Order No. 841, PJM required only one year to develop software to accommodate an operationally distinct asset class.29 PJM has provided no explanation for why it needs three years to create new flavors of transmission service using the existing system, while it needed only one year to develop the software to implement a new participation model for an entire resource class. As it has in the past, the Commission should demand more support than a cursory gesture at complexity to justify delaying implementation of its directives.30 PJM does not offer the type of evidence the Commission has relied upon to support a finding that such a delay is necessary. For example, in its 2025 order approving the Midcontinent Independent System Operator’s (“MISO”) Order No. 2222 compliance timeline, the Commission 27 Id.
28 See PJM Tariff, pt. II, § 14.7 (0.0.0) (reserving the right to interrupt non-firm point-to-point transmission service for economic reasons and to curtail it for reliability reasons).29 See PJM Interconnection, L.L.C., Order No. 841 Compliance Filing ESR Markets and Operations Proposal, Docket No. ER19-469-000, at 61 (filed Dec. 3, 2018).30 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 185 FERC ¶ 61,011, at P 411 (2023) (“[W]e find that MISO’s proposed effective date of October 1, 2029 is not timely because, once MISO implements the [market system enhancement] project, MISO proposes to defer Order No. 2222 implementation for several years.”); Midcontinent Indep. Sys. Operator, Inc., 175 FERC ¶ 61,120, at PP 6, 27 (2021).
PDF page 12
-12-
relied on testimony from MISO staff detailing specific software and system changes that needed to occur and the timeline for each of those changes.31 PJM asks for a similarly lengthy timeline with nowhere near the same level of support.
Without further evidence, the Commission should not rely on PJM’s assertion about the complexity of implementation to delay implementation of its co-location reforms to mid-2029. Given the stakes of such a delay, the Commission should ensure that it is absolutely unavoidable.
C. The Commission Should Require a Transition Process that Accommodates Co-
Location Configurations that Commit to Not Take Electrons from the Grid
Even if the Commission accepts PJM’s unsupported assertion that it will take a third of a decade to update its software, the Commission should require PJM to immediately accommodate co-location arrangements for which those software changes are, as a practical matter, irrelevant. The Order explained that, under Non-Firm Contract Demand Transmission Service, “an Eligible Customer on behalf of a Co-Located Load may elect to not reserve any amount of transmission service to the extent that the Eligible Customer will not withdraw any electricity from the transmission system.”32 In that case, the customer will simply be charged for regulation and black start services.33
If a customer elects that option, the Non-Firm Contract Demand Transmission Service associated with that co-location arrangement consists of ex post invoicing of charges for regulation and black start services (and, if the Commission determines it is appropriate, a grid reliance charge—which we separately address below). That should not be difficult to implement,
31 See Midcontinent Indep. Sys. Operator, Inc., 190 FERC ¶ 61,031, at P 163 (2025) (citing Midcontinent Indep. Sys. Operator, Inc., Prepared Direct Testimony of Zakaria Joundi, Docket No. ER22-1640-003, at 13:13-19; Midcontinent Indep. Sys. Operator, Inc., Prepared Direct Testimony of Todd Ramey, Docket No. ER22-1640-003, at 11:5-13:18).32 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 178 n.380.33 Id.
PDF page 13
-13-
particularly given that the black start and regulation services will be based on gross load, which customers will be required to report (as opposed to Non-Firm Point-to-Point Transmission Service customers, which only pay for black start and regulation when actually using the system).34 Indeed, PJM has explained that the purpose of its software upgrade enabling Non-Firm Contract Demand Transmission Service is to ensure that it applies the appropriate curtailment priority to various customers.35 But curtailment priority is only relevant when customers are actually taking a service that can be curtailed. If a customer has reserved zero MW of transmission service, as the Order explained it has the right to do, there will be no transmission service scheduled and no transmission service to curtail. As a result, the software PJM develops to provide Non-Firm Contract Demand Transmission Service will have no material relevance to such a configuration. Even assuming that PJM will use its software upgrade to track customers reserving zero MW of Non-Firm Contract Demand Transmission Service to track which customers need to be invoiced for regulation and black start services based on gross load, PJM has provided no explanation for why it is lawful and consistent with the Order to prohibit service to such customers on that basis in the interim. Nor can it. Preventing service on the basis of a software upgrade that is, at best, only nominally relevant to that service is not just and reasonable.36 Further, customers that commit to taking no electricity from the grid and, therefore, take Non-Firm Contract Demand Transmission Service as an administrative formality to enable PJM to charge for regulation and black start services are not similarly situated to other co-located loads (and Eligible Customers)
34 See PJM Initial Brief, Attach, A, pt. XI, subpt. A, §§ 714.5, 715.4 (“Proposed Tariff”); PJM Manual 27: Open Access Transmission Tariff Accounting, Rev. 103 (eff. July 23, 2025), § 7.1; PJM Manual 28: Operating Agreement Accounting, Rev. 104 (eff. Mar. 1, 2026), §§ 4.1-3.35 PJM Initial Brief at 65-66.36 Cf. Midcontinent Indep. Sys. Operator, Inc., 175 FERC ¶ 61,120 at PP 6, 27 (denying MISO’s request to defer implementation of Order No. 841 in order to prioritize a broader overhaul of its market software platform).
PDF page 14
-14-
that will use Non-Firm Contract Demand Transmission Service to pull electricity from the grid. As a result, PJM’s attempt to impose a moratorium on the former while it upgrades its software to accommodate the latter is unduly discriminatory.37
Moreover, delaying service to co-located loads that commit to pulling no electricity from
the grid is fundamentally inconsistent with the Order’s goals of remedying PJM’s failure to provide transmission service that reflects a co-located load’s “willing[ness] and ab[ility] to limit its energy withdrawals from the transmission system under certain conditions.”38 The Commission was
fastidious in distinguishing between co-located loads that will not withdraw energy from the transmission system and those that will.39 PJM’s failure to recognize that distinction and propose rules—and an implementation timeline—that respect that critical consideration exacerbates, rather than remedies, the flaws that the Commission identified.
The net result is that PJM’s proposal will impede the nation’s ability to win the AI race.40 Further cementing that counterproductive outcome is the fact that, as Vistra previously explained, PJM’s proposed delay fails to acknowledge that some entities have already executed necessary study agreements or received study results for these types of co-location configurations.41 Requiring those entities to restart the necessary study process, and delaying service even for those
37 See Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236, at P 68 n.112 (2018) (“Typically, undue discrimination cases involve a seller charging a different rate to similarly-situated customers; but undue discrimination can also occur when a seller charges the same rate to differently-situated customers.”), order on reh’g & clarification, 171 FERC ¶ 61,034 (2020); Ala. Elec. Coop., Inc. v. FERC, 684 F.2d 20, 27-28 (D.C. Cir. 1982) (“[A] single rate design may also be unlawfully discriminatory. . . . It matters little that the affected customer groups may be in most respects similarly situated—that is, that they may require similar types of service . . . . If the costs of providing service to one group are different from the costs of serving the other, the two groups are in one important respect quite dissimilar.”).38 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 159.39 See id.40 See supra n.12.41 As Vistra explained further in its protest to PJM’s compliance filing in Docket No. ER26-1479-000, this aspect of PJM’s proposal is incompatible with the Commission’s Order, violates the filed rate doctrine, and represents an unexplained and unjustified departure from the Commission’s customary approach to interconnection reform. PJM Interconnection, L.L.C., Protest of Vistra Corp., Docket No. ER26-1479-000, at 4-6 (filed Mar. 16, 2026).
PDF page 15
-15-
that commit to not withdraw electricity from the grid, virtually ensures that PJM will fail to expedite co-location and meet the nation’s urgent need for expanded computing power. Accordingly, if the Commission accepts PJM’s twentieth century software upgrade timeline (which it should not, as discussed above), the Commission should direct PJM to implement rules under which (1) Eligible Customers procuring Non-Firm Contract Demand Transmission Service for co-located loads that commit to not withdraw energy from the grid can commence service to co-located load prior to the 2029 effective date, (2) generation owners and interconnection customers can pursue facility configurations to facilitate such service on the same timeline, and (3) those Eligible Customers that have already reached advanced stages of the necessary study process have a clear transition mechanism that respects executed necessary study agreements on file with the Commission.
II. The Structure of Non-Firm Contract Demand Transmission Service is Unjust and Unreasonable and Unduly Discriminatory
PJM and its Transmission Owners propose to implement Non-Firm Contract Demand Transmission Service in a manner that blatantly impedes co-location. Virtually every aspect of the proposed rates, terms, and conditions of the Non-Firm Contract Demand Transmission Service are unjust, unreasonable, and unduly discriminatory. While the Commission analogized Non-Firm Contract Demand Transmission Service to existing Non-Firm Point-to-Point Transmission Service both in terms of rates and the availability of reservations,42 PJM and the Transmission Owners have proposed to implement Non-Firm Contract Demand Transmission Service in a manner that is simultaneously more expensive and subject to more restrictions than its Non-Firm Point-to-Point
42 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at PP 215-216 (discussing how reservations for Non-Firm Contract Demand Transmission Service would be available in a similar manner to non-firm point to point service and suggesting that it may be just and reasonable to apply the zonal non-firm point-to-point rate to the new Non-Firm Contract Demand Transmission Service).
PDF page 16
-16-
counterpart. The Commission must direct PJM and the Transmission Owners to correct these errors.
A. The Proposed Rate for Non-Firm Contract Demand Transmission Service is Unjust and Unreasonable and Unduly Discriminatory
The proposed rates for Non-Firm Contract Demand Transmission Service—including both the zonal rate for service and the grid reliance charge—are unjust, unreasonable, and unduly discriminatory. This conclusion is all the more apparent when Non-Firm Contract Demand Transmission Service is compared to other, existing non-firm transmission service. Moreover, as discussed in the Affidavit of Rebecca Stadelmeyer (“Stadelmeyer Affidavit”), the proposal to use the revenues from the grid reliance charge to credit NITS customers will create large cost shifts.43 Each of these flaws, as discussed below, represents an independent, sufficient basis to reject PJM and the Transmission Owners’ proposed Non-Firm Contract Demand Transmission Service.
1. Use of Zonal NITS Rates
The PJM Transmission Owners’ proposal to charge the NITS zonal rate for Non-Firm Contract Demand Transmission Service does not respond to the Commission’s directive to explain “whether it would be just and reasonable to apply the current zonal non-firm PTPS rates to [Non- Firm Contract Demand Transmission Service].”44 Instead of grappling with the question, the Transmission Owners acknowledge in a footnote that “non-firm PTPS customers in PJM are currently subject to a discounted rate of $0.67/kWh,”45 but defer consideration of whether to offer such a discount for Non-Firm Contract Demand Transmission Service.46 Notably, they do not
43 Attach. A, Affidavit of Rebecca Stadelmeyer, at 6:3-8:11 (“Stadelmeyer Affidavit”). 44 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 216. 45 PJM Interconnection, L.L.C., Initial Brief of Indicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al., at 11 n.30 (filed Feb.23, 2026) (“PJM TOs Initial Brief”).46 Id.; id. at 12-13.
PDF page 17
-17-
explain the timeline on which they will consider a discounted rate or the conditions that would need to be met to offer it.47
Most critically, the Transmission Owners have not explained why it is just and reasonable and not unduly discriminatory to offer a discounted rate to Non-Firm Point-to-Point Transmission Service customers but not to Non-Firm Contract Demand Transmission Service customers.
Instead, the Transmission Owners suggest that Non-Firm Contract Demand Transmission Service will represent a “superior level of service” compared to Non-Firm Point-to-Point Transmission Service because PJM will re-dispatch generation prior to curtailing Non-Firm Contract Demand Transmission Service.48
Even if that were true, given that PJM proposed major (and unreasonable) limitations on
when Non-Firm Contract Demand Transmission Service can reserve service—i.e., only when the co-located generator is on outage —the benefit of re-dispatching generation prior to curtailment would be a fleeting benefit during rare occurrences. It is not clear why a rare, theoretical benefit justifies paying a substantially higher rate for a service that is otherwise inferior because it is subject to significantly more restrictions.49
Further, it is unclear whether Non-Firm Contract Demand Transmission Service is, in fact, superior in the manner the Transmission Owners suggest. PJM proposes to require Non-Firm
47 Id. at 12-13.48 Id. at 11-12.49 See Inquiry Concerning the Comm’n’s Pricing Pol’y for Transmission Servs. Provided by Pub. Utils. Under the Fed. Power Act, 59 Fed. Reg. 55,031, at 55,034 (Nov. 3, 1994) (“Transmission Pricing Policy Statement”) (“There is a relationship between price and quality of service (i.e., in general, higher quality service costs more).”); El Paso Nat. Gas Go., 112 FERC ¶ 61,150, at PP 56-57 (2005) (“The Commission has consistently held that [interruptible] service should be at a lower rate than [firm] service because it is of a lower quality . . . . It is not the Commission's policy that [interruptible] service should be priced in a manner that discourages its use.”); Bldg. for the Future Through Elec. Reg’l Transmission Planning & Cost Allocation & Generator Interconnection, Notice of Proposed Rulemaking, 179 FERC ¶ 61,028, at P 33 (2022) (finding reforms to the regional transmission planning process necessary where customers would otherwise “pay[] more for less”).
PDF page 18
-18-
Contract Demand Transmission Service customers to pay redispatch costs set forth in Attachment K of the PJM Tariff.50 The Tariff allows Non-Firm Point-to-Point Transmission Service customers to voluntarily agree to pay Attachment K redispatch costs in exchange for redispatch of generation prior to curtailment,51 indicating that Non-Firm Point-to-Point Transmission Service Customers may enjoy the same benefit as Non-Firm Contract Demand Transmission Service customers.
Either way, the re-dispatch of generation prior to curtailment Non-Firm Contract Demand
Transmission Service does not justify the substantially higher rate compared to Non-Firm Point- to-Point Transmission Service.
2. Grid Reliance Charge
The proposed grid reliance charge is likewise unresponsive to the Commission’s directives, unjust and unreasonable, and unduly discriminatory. The Order sought briefing on two related questions: (1) whether to impose a charge for Non-Firm Contract Demand Transmission Service customers that do not reserve service in a given period of time, and if so, how that charge should be determined,52 and (2) whether to impose a charge on Firm or Non-Firm Contract Demand
Transmission Service customers reserving only a de minimis amount of service,53 and if so, “how that additional charge, including a de minimis threshold, should be determined.”54 The PJM
50 See Proposed Tariff, pt. XI, subpt. B, § 715.2.51 See PJM Tariff, pt. II, § 27.2 (1.0.0) (“Whenever in the operation of the PJM Region the Transmission Provider identifies transmission constraints, the provisions of Tariff, Attachment K shall apply to all Transmission Customers (including Native Load Customers and a Transmission Owner making a Third-Party Sale); provided, however, that a Transmission Customer receiving Non-Firm Point-To-Point Transmission Service may elect not to pay the costs of redispatch determined pursuant to Tariff, Attachment K when those costs would be imposed consistent with Commission policy and Transmission Service to such Transmission Customer may be interrupted.”); see also PJM Tariff, attach. K App., § 5.1 (8.0.0), § 5.1.4 (calculation of transmission congestion charges for Network Customers, Firm Point-to-Point Transmission Service customers, and Non-Firm Point-to-Point Transmission Service customers that have elected to pay transmission congestion charges); see also Penn.-N.J.-Md. Interconnection, 94 FERC ¶ 61,072, at 61,339 (2001).52 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 219(3).53 Id. P 219(4).54 Id. P 207.
PDF page 19
-19-
Transmission Owners assume that the answer is “yes,” without addressing the nuances in the Commission’s questions or the actual ways that Non-Firm Contract Demand Transmission Service customers might rely—or not rely—on the grid.
The Commission’s questions illustrate that customers could use Non-Firm Contract Demand Transmission Service in different ways. A customer might (a) never reserve service (in fact, it might actually commit to never reserving service),55 or (b) occasionally reserve a de minimis amount of service, or (c) frequently reserve significant amounts of service. The first customer in that example clearly does not rely on the grid to the same extent as the second or third, and the second customer clearly does not rely on the grid to the same extent as the third. A customer that never reserves transmission service relies on the PJM grid only to transport black start and regulation services, while other customers may rely on the PJM grid for energy withdrawals, either for primary or back-up service, in significantly varying amounts. Yet the PJM Transmission Owners’ proposal would impose the same grid reliance charge on these very different customers.56 Instead of grappling with the differences in how those customers rely on the grid, the PJM Transmission Owners simply assert that they are all “synchronized” to the grid.57 But “synchronization” is “simply an operational reality of the system and a prerequisite to taking any transmission or ancillary service.”58 Synchronization is not, itself, a service.59 Indeed, when the Commission required transmission providers to unbundle ancillary services from transmission service in Order No. 888, it explained that customers that take similar amounts of transmission
55 See id. P 178 n.380.56 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1263 (D.C. Cir. 2018) (“FERC must make some reasonable effort to match costs to benefits.”); BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014) (the cost causation principle is a “matter of making sure that burden is matched with benefit”).57 PJM TOs Brief at 4, 14-15.58 Stadelmeyer Affidavit at 9:8-9.59 Id. at 9:8-16.
PDF page 20
-20-
service may require different amounts of ancillary services, so “bundling these services with basic transmission service would result in some customers having to take and pay for more or less of an ancillary service than they use.”60 The Commission therefore required transmission providers to “offer and price the individual ancillary services separately,” and it stated that transmission providers “may not tie the purchase of one to the purchase of another.”61 The Transmission Owners’ proposal stands in stark contrast to this long-standing policy by creating a new service charge for what appears to be an undefined ancillary service (i.e., grid reliance), which they assert covers a “suite of synchronization support services.”62 Not only do the Transmission Owners not explain how customers benefit from that “suite” of purported services, they propose to “tie the purchase” of that suite together instead of “pric[ing] the individual [services] separately.” Even more concerningly, the Transmission Owners then propose to impose that cost on customers without regard to the extent to which customers actually rely on the grid.
The Transmission Owners do not justify how it is consistent with cost causation principles to impose the same grid reliance charge for those very different types of grid reliance.63 While the three permutations of Non-Firm Contract Demand Transmission Service customers discussed above exist on a spectrum—and the PJM Transmission Owners failed to respond to the Commission’s directive to identify a “de minimis threshold”64—there is at the very least a clear distinction between Non-Firm Contract Demand Transmission Service customers that never
60 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Serv. by Pub. Util.; Recovery of Stranded Costs by Pub. Util. and Transmitting Util., Order No. 888, 61 Fed. Reg. 21,540, at 21,588 (May 10, 1996), FERC Stats. & Regs. ¶ 31,036 (1996), order on reh'g, Order No. 888-A, 62 Fed. Reg. 12,274 (Mar. 14, 1997), FERC Stats. & Regs., ¶ 31,048, order on reh'g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh'g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff'd in relevant part sub nom. Transmission Access Pol’y Stud. Group, et al. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002);61 Id. at 21,589.62 See PJM TOs Brief at 15.63 See supra n.37. 64 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 207.
PDF page 21
-21-
reserve transmission service and those that do. It is not clear why a Non-Firm Contract Demand Transmission Service customer who never reserves transmission service to pull energy from the grid and only relies on the grid for black start and regulation service should pay for something other than black start and regulation service.
Contrary to PJM’s and the Transmission Owners’ assumption, the Commission did not prejudge, as a legal or policy matter, whether or under what circumstances a grid reliance charge is necessary. The Commission merely called for briefing on the issue. As discussed herein, a customer that is relying on the grid solely for regulation and black start service is demonstrably relying very little on the grid. Accordingly, Vistra contends that the Commission could reasonably conclude that no grid reliance charge is necessary for a customer that commits to making zero transmission service reservations or that only reserves a de minimis amount of transmission service.
Even if it were just and reasonable and not unduly discriminatory to impose some form of a grid reliance charge on Non-Firm Contract Demand Transmission Service customers that will never pull energy from the grid, the Transmission Owners have not adequately justified the particular rate they propose. It defies belief that a customer that never takes transmission service receives benefits approximating 25.8% of the Transmission Owner’s transmission revenue requirement. The adjustment to account for the ratio between firm load and gross load does not solve the fundamental problem that the proposed charge is not tied to the share of transmission and operations and maintenance (“O&M”) costs that are associated with the ways in which these Non-Firm Contract Demand Transmission Service Customers actually rely on the grid.
PDF page 22
-22-
The Transmission Owners’ proposal is therefore inconsistent with cost causation
principles.65 To the extent that a Non-Firm Contract Demand Transmission Service customer that never reserves transmission services relies on the grid, its reliance is for the sole purpose of receiving black start and regulation service. And as the Stadelmeyer Affidavit illustrates, black start and regulation services represent a miniscule amount of the use of the PJM system.66 Indeed, only 0.5% of PJM’s monthly total billings are related to black start and regulation charges.67 Yet the Transmission Owners suggest that services that represent only 0.5% of PJM’s monthly billings use the transmission system to such an extent that the cost of the transportation of those services should be predicated on 25.8% of the total revenue requirement.
The proposal also stands in direct conflict with the Commission’s transmission pricing policy, which indicates that “[t]he major purpose of transmission pricing reform should be to provide more efficient price signals, particularly for new transmission uses, and not simply to reallocate sunk costs.”68 A Non-Firm Contract Demand Transmission Service customer that does not actually reserve transmission service promotes the most efficient use of the transmission system,69 yet the Transmission Owners’ proposal disincentivizes that efficiency and instead focuses on re-allocating a large share of sunk costs.
If the Commission finds it necessary to impose a grid reliance charge on customers that never reserve transmission service, it should do so in a manner that is appropriately tailored to the specific benefits those customers receive, in accordance with the cost causation principle. As the
65 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (“[A]ll approved rates [must] reflect to some degree the costs actually caused by the customer who must pay them.”).66 Stadelmeyer Affidavit at 11:12-13.67 Id. at 11:12-14.68 Transmission Pricing Policy Statement, 59 Fed. Reg. at 55,035.69 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 160 (explaining that Non-Firm Contract Demand Transmission Service “reflect[s] a Co-Located Load’s ability to limit withdrawals from the transmission system and potentially avoid costly and inefficient transmission system buildout that may not be necessary”).
PDF page 23
-23-
Stadelmeyer Affidavit explains, the percentage of PJM’s total monthly billings that relates to black start and regulation charges is a reasonable proxy for the amount of transmission system costs that are associated with use of the grid to deliver black start and regulation service.70 That is because the vast majority of the costs of PJM’s total monthly billing are based on the provision of actual transmission service, not the transportation of black start and regulation service over the grid. This type of connection to the share of the transmission system associated with the transportation of black start and regulation service would be necessary to justify a grid reliance charge for customers that never reserve transmission service.
3. Distribution of Revenues
In addition to imposing costs that are not roughly commensurate with the benefits that Non- Firm Contract Demand Transmission Service customers that do not reserve service would receive, the PJM Transmission Owners’ proposal is also unjust and unreasonable and unduly discriminatory because it would create significant and unjustified cost shifts between classes of customers. Figure 1 from the Stadelmeyer Affidavit provides a simple example of a zone with the following three customers to demonstrate the extent of these cost shifts:71
Customer A takes 250 MW of NITS
Customer B takes a combination of Contract Demand Transmission Services:
o
150 MW of Firm Contract Demand Transmission Service
o
100 MW of Non-Firm Contract Demand Transmission Service (which it
uses during two months of the year when the co-located generator is on
outage)
Customer C contracts for—but does not actually use—250 MW of Non-Firm
Contract Demand Service.
Customer A will pay significantly less for transmission service than it otherwise would based on the existence and contributions of the Contract Demand Transmission Service
70 Stadelmeyer Affidavit at 11:4-12:4.71 Id. at 7, fig. 1.
PDF page 24
-24-
customers.72 Specifically, Customer A will only pay 84% of the transmission charges it incurred and otherwise would have been required to pay.73 The magnitude of that cost shift cannot possibly be considered just and reasonable and not unduly discriminatory. And while Customer B will only take 40% of the amount of firm transmission service that Customer A takes, it will pay 73% of the costs. The charge Customer B will pay cannot be said to be “roughly commensurate” with the level of service that Customer B receives.
While PJM and the Transmission Owners focus on preventing NITS customers from cross-
subsidizing Non-Firm Contract Demand Transmission Service customers,74 they do not
acknowledge that under their proposal, it is structurally certain that Non-Firm Contract Demand Transmission Service customers will cross-subsidize NITS customers or propose safeguards to prevent such cross-subsidization.75
Moreover, while the Transmission Owners assert that the distribution of revenues will
“ensure against double recovery,”76 it is not clear that is the case. The revenues from the grid reliance charge will be credited to NITS and Firm Contract Demand Transmission Service
72 The only way these cost shifts would not occur under this proposal is if the existence of Non-Firm Contract Demand Transmission Service Customers increased the Transmission Owner’s transmission revenue requirement. But that circumstance should not occur because the Transmission Owners will not plan the transmission system to serve non-firm customers, and to the extent any upgrades are necessary to accommodate the change in power flows from an existing generator, those upgrades will be directly assigned to the generator. The costs of any special protection schemes or remedial action schemes should likewise be borne directly by the parties instead of increasing the Transmission Owner’s rate base.73 Stadelmeyer Affidavit at 7:3.74 PJM TOs Initial Brief at 8-9.75 Transmission Pricing Policy Statement, 59 Fed. Reg. at 55,035 (“[W]e do not believe that third-party transmission customers should subsidize existing customers.”); see Order No. 888, 61 Fed. Reg. at 21,635 (explaining that shifting costs to customers that did not cause costs to be incurred violates the cost causation principle); Transmission Plan. & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000-A, 139 FERC ¶ 61,132, at P 578 (“The principle of cost causation is intended to prevent subsidization.”), order on reh’g, Order No. 1000-B, 141 FERC ¶ 61,044 (2012), aff’d sub nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014). 76 PJM TOs Initial Brief at 11.
PDF page 25
-25-
customers. But the PJM Transmission Owners are major NITS customers in PJM.77 It is not clear what the Transmission Owners will do with those bill credits. Whether the Transmission Owners pass the savings onto retail customers is a question for state regulators and is not a foregone conclusion based on their current proposal.
B. The Proposed Restrictions on Non-Firm Contract Demand Transmission Service are
Unreasonable and Unduly Discriminatory
The proposed rates are all the more unreasonable in light of the restrictions that PJM and the Transmission Owners propose to impose on customers that take Non-Firm Contract Demand Transmission Service. Specifically, PJM and the Transmission Owners propose significant limitations on when Non-Firm Contract Demand Transmission Service customers can make
transmission reservations—i.e., only when the co-located generator is on outage. They also propose overly strict and unduly discriminatory rules governing the use of special protection systems and remedial action schemes for Contract Demand Transmission Service customers. Both sets of restrictions are unreasonable and unduly discriminatory.
1. Restrictions on Making Transmission Service Reservations
PJM’s proposed restrictions on Non-Firm Contract Demand Transmission Service directly contradict the Commission’s directives. The Commission established Non-Firm Contract Demand Transmission Service as an option for “Eligible Customers taking service on behalf of Co-Located
77 For example, Dominion, AEP, and FirstEnergy and their affiliates together appear to take approximately 70,121 MW of NITS service in PJM. See, e.g., PJM Service Agreement No. 6425, Network Integration Transmission Service Agreement among PJM and Virginia Elec. & Power Co. (Apr. 12, 2022) (providing for approximately 17,373 MW of NITS); PJM Service Agreement No. 4956, Network Integration Service Agreement among PJM and AEP Service Corp. (Jan. 10, 2018) (providing for approximately 20,219.6 MW of NITS); PJM, Electric Quarterly Reports (Q4 2025) (listing contracts for 3,442 MW of network service with The Potomac Edison Co.; 5,024 MW with Ohio Edison Co.; 10,211 MW with FirstEnergy Pennsylvania Electric Co.; 5,731 MW with Jersey Central Power & Light Co.; 1,914 MW with The Toledo Edison Co.; 2,140 MW with Monongahela Power Co.; and 4,067 MW with The Cleveland Electric Illuminating Co.). As a point of comparison, PJM’s peak demand in 2024 was approximately 162,400 MW. See 2025 in Review: Operations Improvements See PJM Through Record Peaks, Growing Demand, PJM Inside Lines (Dec. 30, 2025), https://insidelines.pjm.com/209696-2/.
PDF page 26
-26-
Loads,” in recognition of the fact that “not all Co-Located Loads will necessarily plan to withdraw energy from the transmission system on a regular basis,” but may seek to do so “from time to time when transmission capacity is available.”78 The Commission specifically noted that “the new Non- Firm Contract Demand transmission service must be available during normal operations and curtailed during emergency operations[.]”79 The Commission used the possibility of a co-located generator being on outage as an example of when the non-firm transmission service would be particularly helpful, but nothing in the Order suggested that a transmission reservation should only be available during the generator’s outages.
Yet that is exactly what PJM proposed.80 They reframe Non-Firm Contract Demand Transmission Service as “a limited supplemental service that may be needed for the benefit of Firm Contract Demand Service customers,”81 that can be used only when the co-located generator is on outage.82 Nothing in the Commission’s Order suggested that Non-Firm Contract Demand Transmission Service should be so limited. And PJM and the Transmission Owners have provided no justification for this limitation.
2. Restrictions on Remedial Action Schemes
Several of PJM and the PJM Transmission Owners’ proposals regarding special protection schemes and remedial action schemes are excessively punitive, violate Order No. 888’s comparability principle, and create opportunities for undue discrimination. The Commission
78 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 214. 79 Id. P 215.80 See PJM Initial Brief at 16 (“[A]n Eligible Customer . . . will be [able] to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage.”); Proposed Tariff, pt XI, subpt. B, § 709.2(b) (same). 81 PJM TOs Initial Brief at 12.82 PJM Initial Brief at 16.
PDF page 27
-27-
should direct PJM and the Transmission Owners to take a fundamentally different approach to special protection schemes and remedial action schemes in the replacement rate. First, the Commission should reject PJM Transmission Owners’ request that the Commission permit PJM and the PJM Transmission Owners to “implement and enforce reasonable limits on the total amount of load that can be covered by [special protection schemes] or [remedial action schemes], particularly for customers in relatively close proximity to one another or in a transmission-constrained area.”83 PJM’s proposal does not clarify how it and/or the PJM Transmission Owners would develop and implement these limits, including how they would designate relevant areas and decide which customers in each area may use special protection schemes/remedial action schemes (i.e., may access transmission service) and which may not. Rather, PJM states that requests and the need for control technologies and protection systems (including remedial action schemes) will be evaluated on a request-specific basis,84 and that PJM will be the “ultimate decider for any necessary control technology or protective system.”85 As an initial matter, it is not clear where decision-making authority over access to service would lie: while PJM states that it will have ultimate authority over the necessity of control technologies and systems, the PJM Transmission Owners ask for their own right to implement these limits. But regardless of where that authority lies, it creates textbook conditions for the exercise of undue discrimination: the ability to pick and choose, with no apparent parameters or constraints, customers that may receive transmission service and customers that may not. If the Commission permits PJM or the PJM Transmission Owners to limit the special protection
83 PJM TOs Initial Brief at 24.84 PJM Initial Brief at 35 (citing id., Attach. B, Affidavit of Dr. Sami Abdulsalam, Director of Transmission Planning, at ¶ 9).85 Id. at 44 (citing Proposed Tariff, pt. XI, subpt. A, § 705.5; id. subpt. B, § 713.6).
PDF page 28
-28-
schemes/remedial action schemes in a particular area, the Commission must ensure that standardized and transparent guidelines are in place to cabin PJM and/or Transmission Owners’ discretion to define affected areas and to determine which customers in those areas may access transmission service and which may not.
Further, the PJM Transmission Owners’ proposal subjects Eligible Customers serving co- located load to different requirements than the Transmission Owners subject themselves, violating the comparability requirement. The Federal Power Act’s (“FPA”) prohibition on undue discrimination requires that transmission owners and providers “offer third parties access on the same or comparable basis, and under the same or comparable terms and conditions, as the transmission provider’s uses of its system.”86 PJM’s existing procedures for approval of remedial action schemes include no location-based restrictions. Rather, PJM evaluates whether a proposed remedial action scheme meets the North American Electric Reliability Corporation (“NERC”) definition and whether the remedial action scheme is needed for reliability purposes, including operational performance. The remedial action scheme is then subjected to technical feedback by a sequence of PJM Committees before it is implemented.87 There is no evidence that PJM applies a categorical, area-based limitation on use of remedial action schemes for existing customers. Nor is there a basis for applying such a categorical limitation only to Eligible Customers taking service on behalf of co-located load but not to other entities with remedial action schemes (and neither PJM nor PJM Transmission Owners proffer one). Applying such a limitation only to Eligible Customers taking service on behalf of a co-located load would therefore violate the comparability requirement.
86 See Order No. 888, 61 Fed. Reg. at 21,548.87 See PJM Manual 03: Transmission Operations, Rev. 70 (eff. Mar. 4, 2026), § 1.7.
PDF page 29
-29-
Second, PJM proposes a two-strikes policy for special protection scheme/remedial action
scheme misoperation that diverges from the Commission’s directives and violates the
comparability principle. PJM proposes that, after one misoperation, PJM will prohibit an Eligible Customer from taking transmission service from the PJM transmission system for up to 120 days pending analysis of the special protection scheme/remedial action scheme operational
performance, a requirement PJM alleges is consistent with NERC Standards PRC-012-02 and
PRC-004-6.88 After two misoperations, PJM proposes that an Eligible Customer taking either form of Contract Demand Transmission Service will be disqualified from taking any Contract
Demand Transmission Service, and an Eligible Customer taking Interim NITS will be disqualified from taking any service other than regular NITS.89
PJM’s proposal goes far beyond the penalties the Commission envisioned in the Order,
which did not contemplate a two-strikes policy disqualifying co-located facilities from accessing the new services the Commission mandated.90 In fact, PJM’s proposal goes far beyond the
penalties the Commission has permitted for unreserved use of the transmission system in general— the Commission has addressed this issue in many contexts and has repeatedly held that tailored financial penalties are appropriate for penalizing unreserved use.91 Against that backdrop, PJM’s 88 See PJM Initial Brief at 44-45; Proposed Tariff, pt. XI, subpt. A, § 705.6(b) (Interim NITS); id. subpt. B, § 713.7(b) (Firm and Non-Firm Contract Demand Transmission Service).
89 See PJM Initial Brief at 45; Proposed Tariff, pt. XI, subpt. A, § 705.6(b) (Interim NITS); id. subpt. B, § 713.7(b) (Firm and Non-Firm Contract Demand Transmission Service).90 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 212.91 See Integration of Variable Energy Res., Order No. 764, 139 FERC ¶ 61,246, at P 108 (holding that “the ability to avoid penalties in the first two tiers of generator imbalance charges will provide a sufficient incentive for [variable energy resources] to adjust transmission schedules” and noting that a transmission provider could propose additional penalties if it could “demonstrate that [variable energy resources] are not adjusting their transmission schedules despite their reasonable ability to foresee that output will deviate significantly from existing transmission schedules”), order on reh’g, Order No. 764-A, 141 FERC ¶ 61,232, at PP 89, 95 (2012) (denying commenter’s request to clarify that customers that intentionally overstate firm schedules may be subject to substantial fines or penalties, explaining that “rather than impose a novel and generic restriction on transmission customers' discretion to schedule transmission
PDF page 30
-30-
proposal is “excessively punitive.”92 PJM’s proposal may also be unduly discriminatory insofar as it treats unreserved use of the transmission system by point-to-point customers differently from unreserved use by customers taking these new transmission services.
Moreover, this policy is significantly more stringent than penalties imposed on market
participants under existing rules, yet again violating the comparability requirement. PJM’s proposal treats co-location arrangements utilizing special protection schemes/remedial action schemes differently from any other entities using special protection schemes/remedial action schemes, including the PJM Transmission Owners. Neither the relevant NERC standards nor
PJM’s own rules require special protection scheme/remedial action scheme owners to pause all service for 120 days after a single misoperation.93 Nor do relevant NERC standards or PJM rules subject special protection scheme/remedial action scheme owners to a two-strikes standard. PJM does not explain why Eligible Customers serving co-located load with a special protection
scheme/remedial action scheme are dissimilarly situated from other special protection
scheme/remedial action scheme owners such that this discrimination is due.
service here . . . we will allow the mechanisms discussed in Order No. 764 to work and revisit them when and if necessary”); Order No. 890, 118 FERC ¶ 61,119 at PP 834-835 (adopting unreserved use penalties for use of the transmission system without a reservation, including lesser penalties for instances of inadvertent unreserved use); id. P 849 (requiring transmission providers proposing penalty rates greater than twice the applicable transmission rate to address why that rate is required to combat pervasive unreserved use of transmission and why the standard rate is inadequate to discourage repeated violations), order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 at P 447 (explaining that the unreserved use penalty would “more closely approximate[] the penalty charge with the impact on the transmission system while maintaining the correct incentive for transmission customers to take the necessary steps to ensure that they reserve appropriate service”).
92 See Order No. 890, 118 FERC ¶ 61,119 at P 849.93 See NERC Standard PRC-012-2, R5 (providing that a remedial action scheme owner shall participate in analysis of a remedial action scheme’s operational performance within 120 days of its operation or its failure and provide results of that analysis to its reliability coordinator(s)); id. R6 (requiring development of a corrective action plan within six months of notification of a remedial action scheme deficiency); NERC Standard PRC-004-6, R1-R3 (providing that the owner of a bulk electric system interrupting device shall identify whether its protection system component caused a misoperation within the later of 120 days of an event involving the device or 60 days of notification by other owners); id. R5 (requiring development of a corrective action plan within 60 days of identification of a cause of the misoperation).
PDF page 31
-31-
Finally, PJM’s two-strikes proposal conflicts with the PJM Transmission Owners’ proposal to own special protection schemes/remedial action schemes. The Transmission Owners ask the Commission to allow them to unilaterally exercise an option to own and operate special protection schemes/remedial action schemes on the transmission owner side of the point of interconnection and the customer side of the point of interconnection.94 The Commission should reject this proposal, which would needlessly raise the cost of transmission service simply to generate extra revenue for the PJM Transmission Owners. Nevertheless, if the Transmission Owners are to own and operate the special protection schemes/remedial action schemes for an Eligible Customer’s facility, the consequences of that special protection scheme/remedial action scheme’s misoperation must attach to the PJM Transmission Owner, not the Eligible Customer.95
In sum, PJM’s two-strikes proposal is excessively punitive, unduly discriminatory, and erodes Eligible Customers’ ability to reliably utilize the transmission services the Commission mandated that PJM develop in the Order.96
III.Study Process
The study process in PJM’s proposal is flawed because it reserves for PJM and the Transmission Owners too much discretion to determine whether studies are required for a particular customer, which studies to conduct, the timeline for doing so, and how to prioritize different requests. Further, the Commission should require PJM to clarify how it will assess whether non-firm service can occur “reliably” and ensure that PJM does not intend to study non-
94 See PJM TOs Initial Brief at 24.95 See NERC Standard PRC-012-2 (applying requirements to the “RAS-entity,” defined as the transmission owner, generator owner, or distribution provider that owns all or part of a remedial action scheme).96 See PJM Initial Brief at 47-50 (noting that Eligible Customers disqualified from the Commission-mandated new services can still take NITS, then discussing at length PJM’s views of the merits of NITS and its long history as the only transmission service offered internal to PJM’s borders).
PDF page 32
-32-
firm customers as though they will take transmission service during system conditions in which they will, in fact, be curtailed.
A. PJM Has Granted Itself Unfettered Discretion to Determine Whether to Conduct Studies, What Studies to Conduct, and the Timeline for Doing So.
PJM’s proposed procedures for evaluating transmission service requests are “too broad and not sufficiently detailed to direct as a replacement rate.”97 Indeed, PJM’s proposal perpetuates the very problem the Commission sought to address in the Order: it reserves to PJM and the Transmission Owners unfettered discretion with respect to “the necessary steps that apply to Interconnection Customers seeking to serve Co-Located Load through a Co-Location Arrangement.”98 This discretion creates the risk of undue discrimination in the transmission service request process and violates the rule of reason.
There are at least five ways in which PJM’s proposal affords it and the Transmission Owners too much discretion with respect to the process for studying transmission service requests for co-located arrangements. The degree of that discretion is particularly clear when comparing the proposed procedures to PJM’s existing procedures for generator interconnection requests. First, the proposed tariff does not contain a mechanism for assigning customers a queue position in chronological order based on submission of a complete application. By contrast, generator interconnection requests are assigned to a study cycle if they submit a completed application prior to the cycle’s application deadline, then are allocated costs of network upgrades identified in the cycle’s system impact study based on their contribution to the reliability violation necessitating the upgrade.9997 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 202.98 Id. P 175.99 See PJM Tariff, pt. VIII, subpt. B, § 403(A) (0.1.0); id. subpt. C, § 404(A)(5)(c) (1.0.0).
PDF page 33
-33-
Second, PJM has reserved to itself full discretion to determine whether studies must be conducted and what analyses those studies will involve. PJM has no discretion to determine whether or not to conduct a study of a generator interconnection request100—and the procedures for that study, including analyses within the scope of the study, are set out in the Tariff.101 By contrast, for Interim NITS, PJM proposes that it shall determine “whether additional studies are needed beyond what was required to evaluate the Eligible Customer’s request for [NITS],” without specifying in any detail how PJM will make that determination or what those additional studies may be.102 For Firm Contract Demand Transmission Service, the proposed tariff provides only that PJM and the Transmission Owner “shall coordinate to study the effects” of providing service “pursuant to the applicable affected Transmission Owner requirements” and that PJM “shall determine, in accordance with the PJM Manuals, any necessary studies for reliably providing the requested Firm Contract Demand Transmission Service.”103 It is not clear what the “applicable affected Transmission Owner requirements” are or where they are housed. It is likewise unclear how PJM will determine if there are other necessary studies, and if so, what those additional studies may be. The tariff also contemplates that PJM will “consider the results of any studies conducted by the affected Transmission Owner,” alluding to studies conducted at the Transmission Owner’s discretion mentioned nowhere else in the Tariff.104 And for Non-Firm Contract Demand Transmission Service, PJM again determines whether and “which studies” are appropriate.105 100 See id. subpt. C, § 405(A)(1) (0.1.0) (“After the Application Phase of a Cycle is completed and a group of valid New Service Requests is established therein, Phase I of a Cycle will commence. During Phase I of a Cycle, the Transmission Provider shall conduct a Phase I System Impact Study.”).
101 See id. pt. III, § 32.3 (3.0.0); id. pt. VIII, subpt. C, § 404(A)(2)-(4) (1.0.0); id. pt. VII, subpt. D, § 307(A)(2)-
(4) (1.0.0).
102 Proposed Tariff, pt. XI, subpt. A, § 704.1.103 Id. subpt. B, § 712.1.104 See id.105 Id. § 712.2.
PDF page 34
-34-
Third, it is not clear that the proposed tariff limits the results of PJM’s analysis of transmission service requests to the results of duly conducted studies. With respect to Interim NITS, PJM proposes that it, in consultation with the affected transmission owner, will determine the amount of Interim NITS that can reliably be provided, a determination that “will consider the results of the study procedures set forth in Tariff, Part XI, Subpart A, section 704.”106 It is not clear what else PJM may consider in making that determination. Similarly, with respect to Firm and Non-Firm Contract Demand Transmission Service, the proposed tariff provides that PJM and the transmission owners’ studies “will provide data relevant to the determination of whether (and to what level as applicable)” service can be “reliably provided.”107 As discussed further below, it is also unclear what it means to provide Interim NITS or Non-Firm Contract Demand Transmission Service “reliably.”
Fourth, PJM’s proposal contains no timeline or deadlines for processing Interim NITS, Firm Contract Demand Transmission Service, or Non-Firm Contract Demand Transmission Service requests. For generator interconnection requests, by contrast, PJM must complete the Phase I System Impact Study within deadlines set out in the Tariff: 120 days for the Phase I study,108 180 days for the Phase II study,109 and 180 days for the Phase III study.110 106 Id. subpt. A, § 702.3 (emphasis added).
107 Id. subpt. B, § 710.3.108 PJM Tariff, pt. VIII, subpt. C, § 405(A)(1)(b)(i) (0.1.0).109 Id. § 407(A)(1)(e)(ii) (0.1.0).110 See id. § 409(A)(1)(e)(ii) (0.1.0).
PDF page 35
-35-
Fifth, the proposed tariff provides PJM total discretion to set study fees for Interim NITS111 and for Contract Demand Transmission Service requests,112 with zero parameters or guardrails in place for setting those fees. For generator interconnection requests, by contrast, the study fee is determined based upon the amount of service requested (in MW), and is up to 90% refundable, or subject to increase, based on actual study costs.113
This unfettered discretion creates profound risk of undue discrimination. The FPA
prohibits public utilities from exercising undue discrimination or preference both between
similarly situated customers and against potential competitors.114 “[W]ide discretion” in the study of transmission service requests, “when coupled with a transmission provider’s incentive to
discriminate, creates opportunities for discrimination” cognizable under the FPA.115 For example, in Order No. 890, the Commission found that wide discretion in calculating Available Transfer Capability—the gatekeeper for transmission service—coupled with Transmission Owners’
incentives to discriminate against competitors led to undue discrimination, which the Commission was required to remedy under section 206.116 As illustrated above, the discretion in the proposed 111 See Proposed Tariff, pt. XI, subpt. A, §§ 702.2, 704.1 (providing that, to apply for Interim NITS, the Eligible Customer must pay a study fee set out in section 704.2); id. § 704.2 (“Eligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for Interim Network Integration Transmission Service.”).
112 See id. subpt. B, § 712.3 (providing that, to apply for Contract Demand Transmission Service, the Eligible Customer must pay a study fee set out in section 712.4); id. § 712.4 (“Eligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service.”).113 See PJM Tariff, pt. VIII, subpt. A, § 401(D)(1) (2.0.0); id. subpt. B, § 403(A)(5)(a)(iv) (0.1.0).114 16 U.S.C. § 824d(b).115 Order No. 890, 118 FERC ¶ 61,119 at P 41. Indeed, across contexts, the Commission has acknowledged that excess discretion in the provision of transmission service is impermissible. See, e.g., Sw. Power Pool, Inc., 175 FERC ¶ 61,198, at PP 38-39 (2021) (cost allocation context). 116 Order No. 890, 118 FERC ¶ 61,119 at P 68 (“[T]he lack of a consistent and transparent methodology for calculating ATC gives transmission providers the ability and opportunity to unduly discriminate in the provision of open access transmission service. There are few clear rules respecting ATC calculation, and transmission providers retain unnecessarily broad discretion in this area. This resulting discretion is a significant problem because calculation of ATC, which varies greatly depending on the criteria and assumptions used, may allow the transmission provider to
PDF page 36
-36-
study process for the new transmission services creates the opportunity for PJM and Transmission Owners to treat customers disparately with respect to queue position, the timeline for processing requests, the studies conducted,117 whether and how the results of those studies inform the quantity of service is granted and upgrades identified, and the fees assessed for those studies. And transmission owners have the incentive to exercise that opportunity and discriminate among
similarly situated transmission service customers, particularly against those taking a type of transmission service that may be less profitable to the transmission owner than other types of service. To mitigate these conditions for undue discrimination, the Commission should direct PJM to cabin the discretion it has reserved for itself and the Transmission Owners by filling in the missing details described above.
PJM’s proposal also violates the Commission’s rule of reason. The FPA requires that all
rates and charges for services within the Commission’s jurisdiction, as well as practices affecting such rates and charges, be on file with the Commission.118 As part of its implementation of this discriminate in subtle ways against its competitors. On systems where transmission capacity is congested, this lack of consistency, coupled with a lack of transparency, is of heightened importance and has led to recurring disputes over whether the transmission provider is exercising its discretion to discriminate against its competitors. This discretion also hampers the detection of undue discrimination and, thereby, undermines the Commission's ability to enforce the general requirement in Order No. 888 that transmission service be provided on a not unduly discriminatory basis.”).
117 See Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103, at P 785 (2003) (explaining that article 4.1.2.2 of the pro forma LGIA, describing interconnection study procedures for Network Resource Interconnection Service, “establishes the standards for conducting necessary studies to provide the requested service while ensuring that the reliability of the system is maintained” and “deters a Transmission Provider from delaying an interconnection by imposing on competing Interconnection Customers, in the name of reliability, more stringent Interconnection Study requirements than it would require of its own interconnections or those of its Affiliates”), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61, 287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007); Reform of Generator Interconnection Procs. & Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 237 (2018) (explaining that requiring transmission providers to make available network models and underlying assumptions for interconnection studies would “reduce the possibility that some interconnection customers will have unduly discriminatory access to relevant information,” “generally increase transparency,” “allow interconnection customers to make more informed interconnection decisions,” and “hold[] transmission providers accountable as to which network models and assumptions they use to assess interconnection requests”), order on reh’g & clarification, Order No. 845-A, 166 FERC ¶ 61,137, order on reh’g, Order No. 845-B, 168 FERC ¶ 61,092 (2019).118 16 U.S.C. § 824d(c).
PDF page 37
-37-
requirement, the Commission applies a “rule of reason” pursuant to which a utility must file with the Commission those practices that (1) significantly affect rates, terms, and conditions of service,
(2) are realistically susceptible of specification, and (3) are not so generally understood in a contractual arrangement as to render recitation superfluous.119 The missing information from PJM’s proposal satisfy each criterion.
First, the missing information significantly affects rates, terms, and conditions of service. A customer’s queue position, the analyses that PJM and the Transmission Owners conduct, and the timeline for conducting those analyses all directly and significantly affect how much service a customer can receive and the cost of the upgrades required to receive that service. Similarly, study fees and discretion as to the evaluation timeline can be used to interfere with a customer’s ability to receive service at all. These are no “mere implementation details”;120 they go to the heart of access to transmission service.
Second, the missing information is readily susceptible of specification: as shown above, each missing item has a counterpart that is specified for generator interconnection requests in the PJM Tariff.
Third, the missing information is not so readily understood as to render recitation superfluous. Each practice can diverge widely: customers can be queued and studies can be performed serially or in clusters;121 transmission providers conduct various types of analyses in the course of their studies, and the proposed tariff contemplates that PJM will conduct studies
119 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985); Hecate Energy Greene Cty. 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023) (citing id.); see also Cal. Indep. Sys. Operator, Inc., 116 FERC ¶ 61,274, at PP 54, 64, 618 (2006) (requiring CAISO to provide details in tariff on its parameters for treatment of ancillary service bids in the forward market because such parameters could significantly affect rates), order on reh’g, 119 FERC ¶ 61,076, order on reh’g, 120 FERC ¶ 61,271 (2007). 120 Hecate Energy Greene Cty. 3, 72 F.4th at 1312.121 Compare, e.g., PJM Tariff, pt. VIII, subpt. J, § 437 (1.1.0) (serial study for replacement generating facilities), with id. subpt. A, § 401(A) (2.0.0) (cluster study for new generating facilities).
PDF page 38
-38-
above and beyond those ordinarily performed in the system impact study process, raising the question of what those will be;122 and timelines for studies vary across transmission providers and processes,123 as do study fees.124
The missing information therefore cannot be left to PJM and the Transmission Owners’
discretion. The FPA and the rule of reason require that it be articulated and filed with the Commission.
B. PJM Has Not Explained the Standard for Assessing Whether PJM can “Reliably”
Serve Curtailable Customers
PJM proposes that it will consult with Transmission Owners to determine “the amount of
Interim [NITS] that can be provided to an Eligible Customer . . . while maintaining the reliability of the Transmission System.”125 Similarly, PJM proposes to consult with Transmission Owners to determine “whether (and to what level as applicable) Firm Contract Demand Transmission
Service or Non-Firm Contract Demand Transmission Services can be reliably provided for an
Application, and if so, what level of service may be provided.”126 The proposal contemplates the possibility that PJM will determine that “only a portion of the Non-Firm Contract Demand
Transmission Service requested by Eligible Customer can be provided reliably” and the possibility that PJM will determine that “no level of Non-Firm Contract Demand Transmission Service
requested by Eligible Customer can be provided reliably.”127122 Compare, e.g., id. subpt. C, § 404(2)(a) (1.0.0) (procedures for studying New Service Requests in PJM), with SPP, Open Access Transmission Tariff, attach. Z1, § III(C) (4.0.0) (procedures for studying long-term NITS requests in SPP) (“SPP Tariff”).123 Compare, e.g., PJM Tariff, pt. VIII, subpt. C §§ 409(A)(1)(d), (e)(ii) (0.1.0) (180-day Phase III study, including Facilities Study), with MISO, FERC Electric Tariff, attach. X (184.0.0), § 3.3.1.2(2) (90-day Facilities Study).124 Compare, e.g., PJM Tariff, pt. VIII, subpt. B, § 403(A)(5)(a)(iv) (0.1.0) (new service request study deposit schedule starting at $75,000 for requests up to 20 MW), with SPP Tariff, attach. V, § 8.2(b) (27.0.0) (generator interconnection study deposit schedule starting at $35,000 plus $1,000 per MW for requests up to 80 MW).125 Proposed Tariff, pt. XI, subpt. A, § 702.3.126 Id. subpt. B, § 710.3.127 Id.
PDF page 39
-39-
Customers electing to take Interim NITS and Non-Firm Contract Demand Transmission
Service have agreed to be curtailable.128 Indeed, the purpose of non-firm transmission service is to use the capacity of the transmission system as it exists at any given point in time, subject to use by transmission customers of higher priority. It is therefore unclear what it means to ensure that non-firm transmission service can be provided “reliably.” And it is critical that the PJM and Transmission Owners’ determination of whether non-firm service can be provided “reliably” not hold the non-firm request to some higher standard. Study standards must be appropriate for the level of service and must be transparent to avoid undue discrimination. Studying non-firm customers as if they are firm customers, or as if they will take transmission service during system conditions in which they will in fact be curtailed, will needlessly inhibit access to, and efficient utilization of, available transmission system capacity.129
The Commission should require PJM to articulate the standard of “reliability” for
customers that have expressly agreed to be curtailable, and the Commission should ensure that this standard does not unnecessarily restrict access to non-firm transmission system capacity. IV.Payment Guarantees
The Transmission Owners expressed concerns about potential cost shifting if a customer
taking Firm Contract Demand Transmission Service exits the transmission system before the costs of needed network upgrades to accommodate its load are fully paid.130 The Transmission Owners
128 See Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 200 (“This new interim, non-firm transmission service must allow an Eligible Customer that has requested NITS on behalf of a Co-Located Load to take non-firm transmission service that can be interrupted until the Network Upgrades necessary to provide NITS are complete and the Co-Located Load can be designated as Network Load.”); id. P 215 (“Reservations under this service would be available only when there is available transmission capacity, similar to existing non-firm transmission service options in the Tariff.”).129 See Order No. 890, 118 FERC ¶ 61,119 at P 925 (finding that it was unjust and unreasonable for transmission providers to deny firm long-term transmission service request on the basis that firm service is unavailable in a very few hours of the year, and requiring transmission providers to offer conditional firm service as remedy).130 PJM TOs Initial Brief at 21.
PDF page 40
-40-
suggested in a footnote that they may “require separate payment guarantees” to collateralize network upgrades to mitigate that risk.131 Some of the Transmission Owners, such as ComEd, have filed Transmission Security Agreements to establish firm financial commitments to mitigate that risk.132
The risk of network upgrade cost shifts simply does not apply to co-location arrangements where the generator bears the cost of any necessary network upgrades. Vistra has previously explained that it is willing and able to bear those costs,133 and the Commission’s Order confirmed that the necessary study process requires generators to bear any network upgrade costs.134 The Transmission Security Agreements that the Commission has accepted are therefore not necessary in this context.
V. Conclusion
To establish a lawful replacement rate, the Commission must require PJM and the
Transmission Owners to modify the proposed rates, terms, and conditions of the new transmission services to ensure that they are implemented expeditiously and in a manner that is both consistent with the FPA and fulfills the purpose they were designed to serve. Specifically, the Commission should:
Require PJM to implement the new transmission services quickly, and provide a pathway for customers who commit to pulling zero energy from the grid to take service as soon as possible;
131 Id. n.50132 See, e.g., PECO Energy Co., Transmission Security Agreement between PECO Energy Co. & Amazon Data Services, Inc., Docket No. ER25-3492-000 (filed Sep. 23, 2025); Commonwealth Edison Co., Transmission Security Agreement between Commonwealth Edison Co. & Aligned Data Centers (Acquisition) PropCo, LLC, Docket No. ER26-838-000 (filed Dec. 19, 2025); Commonwealth Edison Co., Transmission Security Agreement between Commonwealth Edison Co. & Equinix, Inc., Docket No. ER26-989-000 (filed Jan. 9, 2026).133 See, e.g., Interconnection of Large Loads to the Transmission Sys., Comments of Vistra Corp., Docket No. RM26-4-000, at 4 (filed Nov. 21, 2025); Interconnection of Large Loads to the Transmission Sys., Reply Comments of Vistra Corp., Docket No. RM26-4-000, at 2-3 (filed Dec. 5, 2025); PJM Interconnection, L.L.C., Comments of Vistra Corp., Docket Nos. EL25-49-000, et al., at 24-25 (filed Apr. 23, 2025).134 Order on Show Cause Proceeding, 193 FERC ¶ 61,217 at P 176.
PDF page 41
-41-
Adopt a common-sense transition process for co-location arrangements that have already taken steps under the existing tariff;
Ensure that the rate structure for Non-Firm Contract Demand Transmission Service is tailored to the benefits that the customers draw from the grid and does not create cost shifts;
Eliminate unfettered discretion in the study process; and
Remove unreasonable and unduly discriminatory restrictions on the use of the new services. Those adjustments are necessary to render the PJM Tariff just, reasonable, and not unduly discriminatory—and it will ensure that this proceeding lives up to its transformative potential. Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
__________________
Nicholas M. Gladd
Sarah Greenberg
Rachel Neuburger
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
rneuburger@wsgr.com
Counsel for Vistra Corp.
Dated: March 25, 2026
PDF page 42
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: March 25, 2026
Washington, D.C.
/s/ Rachel Neuburger
Rachel Neuburger
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
PDF page 43
Attachment A
Affidavit of Rebecca Stadelmeyer
PDF page 44
Page 2
Q.
PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
1
A. My name is Rebecca Stadelmeyer. My business address is 2001 Market Street, Suite 2500, 2
Philadelphia, Pennsylvania 19103.
3
Q.
BY WHOM ARE YOU EMPLOYED AND IN WHAT CAPACITY?
4
A. I am employed by Gabel Associates, Inc., where I serve as the Vice President of RTO 5
Wholesale Power and Market Services. I first joined Gabel Associates in 2022 as a 6
Director and was promoted to Vice President in 2025. In this role, I manage our firm’s 7
engagements on wholesale power market matters throughout the United States, including 8
issues in the PJM Interconnection (“PJM”). I advise clients on state and federal electric 9
market design matters, support mergers and acquisitions, perform diligence on wholesale 10
power market transactions, monitor ongoing policy issues in PJM and abroad, and evaluate 11
PJM’s capacity, energy, and ancillary service markets.
12
I frequently engage with PJM staff and industry stakeholders on all matters impacting our 13
clients directly or indirectly, including but not limited to capacity market design issues, 14
capacity accreditation, reserve market reforms, regulation Phase 1 and Phase 2 changes, 15
market offering rules, operational regulations, and ultimately how money changes hand in 16
settlements.
17
Q.
PLEASE
DESCRIBE
YOUR
EDUCATIONAL
AND
PROFESSIONAL
18
EXPERIENCE.
19
A. I graduated from Moravian College, renamed to Moravian University in 2021, with a 20
bachelor’s degree in management. I have over 20 years of experience in wholesale power 21
PDF page 45
Page 3
markets in various positions at Mirant, Exelon Power Team, and PJM. At PJM, I held 1
leadership and technical roles, including Manager of Market Settlement Development, 2
Manager of Client Management, and Senior Consultant, overseeing billing system 3
operations and streamlining complex client requests. I contributed to major market rule 4
changes, including Capacity Performance, 5-minute Settlement, and facilitated Market 5
Settlement Subcommittee and member interactions. My roles prior to PJM, from trade 6
floor portfolio analyst to regulatory affairs manager, honed my analytical skills and applied 7
them to the regulatory arena. My roles supporting capacity performance, 5-minute 8
settlements, and various NOPRs at PJM contributed to my overall understanding of the 9
technical underpinnings of market rules, and how those rules are properly implemented in 10
PJM.
11
Q.
WHAT IS THE PURPOSE OF YOUR AFFIDAVIT?
12
A. I was retained by Vistra Corp. to evaluate the PJM Transmission Owners’ proposed rates 13
for Firm and Non-Firm Contract Demand Transmission Services and determine if cost 14
shifts occur between the different transmission service classes, especially when Non-Firm 15
Contract Demand Transmission Service customers take no transmission service (or a de 16
minimis amount of service) from the grid.
17
Q.
CAN YOU BRIEFLY SUMMARIZE HOW PJM PROPOSES TO IMPLEMENT
18
THE NEW FIRM AND NON-FIRM CONTRACT DEMAND TRANSMISSION
19
SERVICES?
20
PDF page 46
Page 4
A. PJM will require Eligible Customers taking one of the Contract Demand services on behalf 1
of a co-located load to sign a Transmission Service Agreement that covers the entire gross 2
load. PJM will allow customers to obtain a combination of Firm Contract Demand 3
Transmission Service and Non-Firm Contract Demand Transmission Service, as long as 4
that combination equals the full gross load.1 If the customer does not take any Firm 5
Contract Demand Transmission Service, then it “must request Non-Firm Contract Demand 6
Transmission Service equivalent to the MW level of the Co-Located Load’s gross 7
demand.”2
8
For example, an Eligible Customer procuring service on behalf of a 200 MW gross load 9
may sign a Transmission Service Agreement for either (a) 200 MW of Firm Contract 10
Demand Transmission Service, (b) 200 MW of Non-Firm Contract Demand Transmission 11
Service, or (c) a combination of both Firm and Non-Firm Contract Demand Transmission 12
Service that, together, equals 200 MW.
13
Q.
CAN YOU BRIEFLY SUMMARIZE THE PJM TRANSMISSION OWNERS’ GRID
14
RELIANCE CHARGE METHODOLOGY?
15
A. PJM Transmission Owners propose to create a new charge, called the Grid Reliance 16
Charge, which will apply to Contract Demand customers based on “the difference between 17
1 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., at 9 (filed Feb. 23, 2026) (“PJM Initial Brief”); id. at 11 (“ . . . so long as the combination of the two services covers the entire gross demand of the Co-Located Load”).2 Id. at 31.
PDF page 47
Page 5
their gross load and their Firm Contract Demand.”3 Customers that “only [take] Non-Firm 1
Contract Demand Service would pay the Grid Reliance Charge on their entire load.”4 The 2
PJM Transmission Owners propose to use a calculated uniform percentage rate across all 3
zones, which they assert represents an “average fixed percentage of the portion of 4
transmission depreciation and operations and maintenance (“O&M”) expense associated 5
with providing grid reliance services.”5 The average fixed percentage, 25.8%, will be 6
multiplied by the applicable zonal NITS rate to produce an “unadjusted” Grid Reliance 7
Charge.6 That unadjusted Grid Reliance Charge will then be “multiplied by a ratio that 8
accounts for the difference between the demand used to account for the NITS and Firm 9
Contract Demand Service rate (NITS customer load plus Firm Contract Demand Service 10
load) and Co-Located Load customers’ gross load, to arrive at the final Grid Reliance 11
Charge for each Zone.”7 The Transmission Owners will allocate the monies collected from 12
the Grid Reliance Charge “as a dollar-for-dollar credit to NITS and Firm Contract Demand 13
Service customers located in the relevant Zone based on their share of the coincident peak 14
load.”8 The Transmission Owners will similarly credit revenues from any transmission 15
3 PJM Interconnection, L.L.C., Initial Brief of Indicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al., (filed Feb. 23, 2026) (“PJM TOs Initial Brief”), Attach. A, Affidavit of Peter Blazunas, Lance Schafer and Hanhan Hammer, at 18:18-19 (“Blazunas, Schafer, and Hammer Affidavit”).4 PJM TOs Initial Brief at 14.5 Id. at 15.6 Id.7 Id. at 17.8 Id. at 17-18.
PDF page 48
Page 6
service that Non-Firm Contract Demand Transmission Service customers take back to 1
NITS and Firm Contract Demand Transmission Service customers.9
2
Q.
WILL THE GRID RELIANCE CHARGE SHIFT COSTS INAPPROPRIATELY
3
BETWEEN CUSTOMER CLASSES?
4
A. Yes. The new Grid Reliance Charge will result in Contract Demand Transmission Service 5
customers subsidizing NITS customers. The proposal would allow NITS customers to pay 6
less than they currently do, for a superior product compared to either the Firm or Non-Firm 7
Contract Demand Transmission Service.
8
Figure 1 below illustrates this result, using a simple example based on the Transmission 9
Owners’ proposal. This example includes three customers, each with 250 MW of gross 10
load, in a zone with a $1,000,000 transmission revenue requirement. Customer A takes 11
250 MW of NITS. Customer B takes 150 MW of Firm Contract Demand Transmission 12
Service and 100 MW of Non-Firm Contract Demand Transmission Service, but only uses 13
its Non-Firm service during two months of the year when the co-located generator is on 14
outage. Customer C takes 250 MW of Non-Firm Contract Demand Transmission Service, 15
but does not use the Non-Firm service. The chart below provides a step-by-step calculation 16
of the transmission service charges and Grid Reliance Charges that each customer would 17
incur under the Transmission Owners’ proposal, as well as the allocation of bill credits 18
from revenues received from Non-Firm Contract Demand Transmission Service 19
customers.
20
9 Id. at 7.
PDF page 49
Page 7
Figure 1: Illustration of Cost Shifts Caused by the Grid Reliance Charge The key focus is reference line numbers 33, 37, and 41, which represent the “Percentage 1
of Charges paid” by each customer. Customer A, taking 250 MW of NITS, will pay only 2
84% of its transmission charges because the rest will be offset by bill credits. Customer B 3
will pay 87% of its transmission charges, and Customer C will pay 100% of its transmission 4
PDF page 50
Page 8
charges. Customer A therefore receives a substantial discount from the transmission 1
charges it incurs and would have otherwise been required to pay.
2
Additionally, even though Customer B only takes 40% of the firm service that Customer 3
A takes (i.e., 100 MW compared to 250 MW), Customer B is required to pay over 73% of 4
the transmission charges that Customer A pays (i.e., $386,708 compared to $527,292). 5
And Customer C, who did not actually take any transmission service from the grid, pays 6
16% of what Customer A pays for the highest level of around-the-clock, firm service. 7
The proposed Grid Reliance Charge calculation and credit allocation therefore causes 8
significant cost shifts, resulting in the Non-Firm Contract Demand Transmission Service 9
customers subsidizing the NITS customer. It also results in charges that are not 10
commensurate with the benefits that the different customers receive.
11
Q.
IS A GRID RELIANCE CHARGE NECESSARY AND SHOULD NON-FIRM
12
CONTRACT DEMAND SERICE CUSTOMERS PAY THIS CHARGE WHEN NO
13
SERVICE IS TAKEN OR WHEN ONLY DE MINIMIS SERVICE IS TAKEN?
14
A. No. The Commission’s December 18, 2025 Order requested briefing on whether a grid 15
reliance charge was appropriate.10 The Order did not make any findings on that question. 16
In fact, the Commission’s questions recognized that customers can use Non-Firm Contract 17
Demand Transmission Service in different ways and to varying degrees, including by 18
explaining that a customer may elect to reserve no transmission service ‘to the extent that 19
10 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 219 (2025) (“Order on Show Cause Proceeding”).
PDF page 51
Page 9
the [customer] will not withdraw any electricity from the transmission system.’”11 1
Applying the Grid Reliance Charge to Non-Firm Contract Demand Transmission Service 2
when no service or when only de minimis service is taken is unnecessary, undermines the 3
purpose of the service, and creates a charge that is not commensurate with the benefits the 4
customer receives.
5
Q.
IS SYNCHRONIZATION WITH THE GRID A STANDALONE BASIS FOR
6
IMPOSING A GRID RELIANCE CHARGE?
7
A. No. Synchronization is simply an operational reality of the system, and a prerequisite to 8
taking transmission and ancillary services. There is no standalone benefit from 9
synchronization when a customer is not taking service from the grid. While the 10
Commission recognized that certain specific services enabled by synchronization to the 11
grid—namely, black start and regulation—benefit co-located loads,12 and asked whether 12
an additional charge might be appropriate to reflect that regulation and black start could 13
not be provided without the transmission system,13 the Commission did not make a finding 14
that synchronization is itself a service or otherwise provides a standalone compensable 15
benefit. The PJM Transmission Owners assert that customers taking transmission service 16
on behalf of a co-located load will benefit from “various ancillary services and a suite of” 17
additional “synchronization support services,”14 but do not list the full set of services such 18
11 Id. P 178 n.380.
12 Id. PP 177, 183-185.13 Id. P 219. 14 PJM TOs Initial Brief at 15.
PDF page 52
Page 10
loads allegedly benefit from nor explain how such customers taking no transmission 1
service or de minimis transmission service benefit from them.
2
Q.
IF THE COMMISSION DETERMINES THAT A GRID RELIANCE CHARGE IS
3
NECESSARY, IS THERE A METHODOLOGY THAT WOULD RESOLVE
4
THOSE COST SHIFTS?
5
A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service 6
customers that reserve no transmission service (or a de minimis amount of service), that 7
charge should be based on the benefits those customers receive from the grid in supporting 8
black start and regulation services only. Since no electricity (or a de minimis amount of 9
electricity) is taken from the grid, the customer is not relying on the grid, i.e., taking 10
transmission service, for electricity. Only a sub-part of the costs of transmission 11
depreciation and O&M are associated with the use of the grid to support black start and 12
regulation, so only that sub-part of the costs should be assessed. To identify that portion 13
of costs, PJM could calculate an annual ratio share that represents the value of these 14
services in relation to PJM’s monthly total billings. Figure 2 below provides a monthly 15
breakdown of PJM’s monthly total billings, monthly total black start billings, and monthly 16
total regulation billings in 2025,15 along with black start and regulation revenue as a 17
percentage of PJM’s monthly total billings.
18
15 Monitoring Analytics, Components of the Total Cost of PJM Wholesale Power, https://www.monitoringanalytics.com/data/pjm_cost.shtml (last visited Mar. 24, 2026).
PDF page 53
Page 11
Figure 2: Black Start and Regulation Billing as Percentage of PJM Monthly Total Billings in 2025 To produce a Grid Reliance Charge that represents the benefits associated with black start 1
and regulation services only, PJM could apply the sum of the percentage of total billings 2
associated with black start and the percentage of total billings associated with regulation to 3
the proposed PJM Transmission Owner Grid Reliance Charge rate. Since the proposed 4
PJM Transmission Owner Grid Reliance Charge rate captures all of the costs of the FERC 5
Accounts that they assert are relevant to grid reliance, a ratio share of that proposed rate to 6
represent the portion of those costs that are attributable to supporting black start and 7
regulation (rather than supporting transmission service itself) appropriately captures the 8
benefits obtained and removes the cost shift between customer classes.
9
There are minimal monthly variations in the monthly total billings, so PJM could use an 10
annual percentage, updated annually to reflect market conditions, to reduce the 11
administrative burden. In 2025, the percentage of total billings related to black start is 12
0.08%, and the percentage of total billings related to regulation is 0.46%. Together, those 13
values produce a total annual grid reliance benefit percentage of 0.54%. That percentage, 14
PDF page 54
Page 12
applied to the proposed PJM Transmission Owner’s Grid Reliance Charge rate, creates an 1
alternative rate that can be applied to Non-Firm Contract Demand Transmission Service 2
customers in a billing month when no service or when a de minimis amount of service is 3
taken.
4
Q.
HOW WILL APPLYING A BENEFIT PERCENTAGE TO THE GRID RELIANCE
5
CHARGE RATE PREVENT COST SHIFTS AND MORE APPRORIATELY
6
BALANCE COST CAUSATION WHEN NO SERVICE IS USED?
7
A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service 8
customers that reserve no transmission service (or a de minimis amount of service), then 9
the charge should reflect only the benefits provided from the grid, black start and 10
regulation, and should not subsidize NITS customers. The alternative rate captures these 11
benefits.
12
Figure 3 below shows a comparison of rates, charges and credits applied to two customers 13
in one zone, both with the same gross load of 250 MWs. Customer A is a NITS customer 14
and Customer B is a Non-Firm Contract Demand Transmission Service customer that does 15
not reserve service from the grid in either Scenario A or Scenario B. Scenario A applies 16
the proposed methodology described in the PJM Transmission Owner’s Initial Brief. 17
Scenario B applies the alternative rate I describe above.
18
PDF page 55
Page 13
Figure 3: Illustrative Comparison of Alternative Rate Structure to Minimize Cost Shifts The PJM Transmission Owner’s proposal, represented in Scenario A, results in an 1
inappropriate cost shift and a 12.9% reduction of cost for the NITS customers based on the 2
contributions of Customer B, who never takes service from the grid. Scenario B more 3
appropriately allocates to Customer B the costs of receiving black start and regulation from 4
the grid and allocates costs appropriately among customer classes.
5
Scenario B continues to allocate credits from the Grid Reliance Charge to the NITS and 6
Firm Contract Demand Transmission Service customers based on ratio share of the 7
coincident peak, without creating significant cost shifts. This alternative compensates the 8
transmission owner for the provision of ancillary services while avoiding cost shifting. 9
PDF page 56
Page 14
Q.
DOES THIS CONCLUDE YOUR AFFIDAVIT?
1
A. Yes. This concludes my affidavit.
2