EL25-49-000 · 2026-03-25 · Vistra Corp.

Response Brief of Vistra Corp

Text extracted from the eLibrary original (SHA-256 f6b6acdefdb13854…). Download the original from the official source.

Contents · 20 sections
  1. I. The Proposed June 1, 2029 Effective Date is Unjust and Unreasonable and Fails to p. 5
  2. A. Capacity Market p. 7
  3. B. Software and System Changes p. 10
  4. C. The Commission Should Require a Transition Process that Accommodates Co- p. 12
  5. II. The Structure of Non-Firm Contract Demand Transmission Service is Unjust and p. 15
  6. A. The Proposed Rate for Non-Firm Contract Demand Transmission Service is Unjust p. 16
  7. B. The Proposed Restrictions on Non-Firm Contract Demand Transmission Service are p. 25
  8. A. PJM Has Granted Itself Unfettered Discretion to Determine Whether to Conduct p. 32
  9. B. PJM Has Not Explained the Standard for Assessing Whether PJM can “Reliably” p. 38
  10. V. Conclusion p. 40
  11. Attachment A p. 43
  12. A. My name is Rebecca Stadelmeyer. My business address is 2001 Market Street, Suite 2500, p. 44
  13. A. PJM will require Eligible Customers taking one of the Contract Demand services on behalf p. 46
  14. A. PJM Transmission Owners propose to create a new charge, called the Grid Reliance p. 46
  15. A. Yes. The new Grid Reliance Charge will result in Contract Demand Transmission Service p. 48
  16. A. No. The Commission’s December 18, 2025 Order requested briefing on whether a grid p. 50
  17. A. No. Synchronization is simply an operational reality of the system, and a prerequisite to p. 51
  18. A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service p. 52
  19. A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service p. 54
  20. A. Yes. This concludes my affidavit. p. 56

Read topic-matched comments in EL25-49

Topics in the text: Cost allocation · Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

To adopt a replacement rate that is just, reasonable, and not unduly discriminatory, and to ensure that the new transmission services actually meet the needs they were created to fulfill, the Commission must direct PJM and the Transmission Owners to remedy various flaws in the proposal.
Read this passage Filed comments: Filing procedure

I. The Proposed June 1, 2029 Effective Date is Unjust and Unreasonable and Fails to

printed heading · Topic match: Reliability and curtailment

PJM presents two arguments in support of its four-year delay: (1) the need to procure capacity to serve new load through the three-year forward schedule of the capacity market, and (2) the need for software updates to PJM’s market and operations systems to permit the curtailment of Non-Firm…
Read this passage Filed comments: Reliability and curtailment

A. Capacity Market

printed heading · Topic match: Reliability and curtailment

PJM does not need to procure capacity 12 Commission regulations and policy must enable timely data center development, which is critical to our economy and our national security.
Read this passage Filed comments: Reliability and curtailment

B. Software and System Changes

printed heading

Operator, Inc., 185 FERC ¶ 61,011, at P 411 (2023) (“[W]e find that MISO’s proposed effective date of October 1, 2029 is not timely because, once MISO implements the [market system enhancement] project, MISO proposes to defer Order No. 2222 implementation for several years.”); Midcontinent Indep.
Read this passage

C. The Commission Should Require a Transition Process that Accommodates Co-

printed heading · Topic match: Connecting load and generation

The Order explained that, under Non-Firm Contract Demand Transmission Service, “an Eligible Customer on behalf of a Co-Located Load may elect to not reserve any amount of transmission service to the extent that the Eligible Customer will not withdraw any electricity from the transmission system.”32…
Read this passage Filed comments: Connecting load and generation

II. The Structure of Non-Firm Contract Demand Transmission Service is Unjust and

printed heading

The Commission must direct PJM and the Transmission Owners to correct these errors.
Read this passage

A. The Proposed Rate for Non-Firm Contract Demand Transmission Service is Unjust

printed heading · Topic match: Cost allocation

PJM proposes to require Non-Firm 47 Id. at 12-13. 48 Id. at 11-12. 49 See Inquiry Concerning the Comm’n’s Pricing Pol’y for Transmission Servs.
Read this passage Filed comments: Cost allocation

B. The Proposed Restrictions on Non-Firm Contract Demand Transmission Service are

printed heading · Topic match: Connecting load and generation

Rather, PJM states that requests and the need for control technologies and protection systems (including remedial action schemes) will be evaluated on a request-specific basis,84 and that PJM will be the “ultimate decider for any necessary control technology or protective system.”85 As an initial…
Read this passage Filed comments: Connecting load and generation

A. PJM Has Granted Itself Unfettered Discretion to Determine Whether to Conduct

printed heading · Topic match: Connecting load and generation

PJM’s proposed procedures for evaluating transmission service requests are “too broad and not sufficiently detailed to direct as a replacement rate.”97 Indeed, PJM’s proposal perpetuates the very problem the Commission sought to address in the Order: it reserves to PJM and the Transmission Owners…
Read this passage Filed comments: Connecting load and generation

B. PJM Has Not Explained the Standard for Assessing Whether PJM can “Reliably”

printed heading · Topic match: Cost allocation

IV.Payment Guarantees The Transmission Owners expressed concerns about potential cost shifting if a customer taking Firm Contract Demand Transmission Service exits the transmission system before the costs of needed network upgrades to accommodate its load are fully paid.130 The Transmission Owners…
Read this passage Filed comments: Cost allocation

V. Conclusion

printed heading · Topic match: Cost allocation

Conclusion To establish a lawful replacement rate, the Commission must require PJM and the Transmission Owners to modify the proposed rates, terms, and conditions of the new transmission services to ensure that they are implemented expeditiously and in a manner that is both consistent with the FPA…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated: March 25, 2026 Washington, D.C. /s/ Rachel Neuburger Rachel Neuburger Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006
Read this passage

Attachment A

printed heading

Attachment A Affidavit of Rebecca Stadelmeyer Page 2 Q.
Read this passage

A. My name is Rebecca Stadelmeyer. My business address is 2001 Market Street, Suite 2500,

printed heading

At PJM, I held 1 leadership and technical roles, including Manager of Market Settlement Development, 2 Manager of Client Management, and Senior Consultant, overseeing billing system 3 operations and streamlining complex client requests.
Read this passage

A. PJM will require Eligible Customers taking one of the Contract Demand services on behalf

printed heading · Topic match: Connecting load and generation

PJM will allow customers to obtain a combination of Firm Contract Demand 3 Transmission Service and Non-Firm Contract Demand Transmission Service, as long as 4 that combination equals the full gross load.1 If the customer does not take any Firm 5 Contract Demand Transmission Service, then it “must…
Read this passage Filed comments: Connecting load and generation

A. PJM Transmission Owners propose to create a new charge, called the Grid Reliance

printed heading · Topic match: Connecting load and generation

EL25-49-000, et al., at 9 (filed Feb. 23, 2026) (“PJM Initial Brief”); id. at 11 (“ . . . so long as the combination of the two services covers the entire gross demand of the Co-Located Load”). 2 Id. at 31.
Read this passage Filed comments: Connecting load and generation

A. Yes. The new Grid Reliance Charge will result in Contract Demand Transmission Service

printed heading · Topic match: Cost allocation

Page 7 Figure 1: Illustration of Cost Shifts Caused by the Grid Reliance Charge The key focus is reference line numbers 33, 37, and 41, which represent the “Percentage 1 of Charges paid” by each customer.
Read this passage Filed comments: Cost allocation

A. No. The Commission’s December 18, 2025 Order requested briefing on whether a grid

printed heading

The Commission’s December 18, 2025 Order requested briefing on whether a grid 15 reliance charge was appropriate.10 The Order did not make any findings on that question. 16 In fact, the Commission’s questions recognized that customers can use Non-Firm Contract 17 Demand Transmission Service in…
Read this passage

A. No. Synchronization is simply an operational reality of the system, and a prerequisite to

printed heading · Topic match: Cost allocation

The PJM Transmission Owners assert that customers taking transmission service 16 on behalf of a co-located load will benefit from “various ancillary services and a suite of” 17 additional “synchronization support services,”14 but do not list the full set of services such 18 11 Id.
Read this passage Filed comments: Cost allocation

A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service

printed heading · Topic match: Cost allocation

HOW WILL APPLYING A BENEFIT PERCENTAGE TO THE GRID RELIANCE 5 CHARGE RATE PREVENT COST SHIFTS AND MORE APPRORIATELY 6 BALANCE COST CAUSATION WHEN NO SERVICE IS USED? 7
Read this passage Filed comments: Cost allocation

A. If there is a Grid Reliance Charge for Non-Firm Contract Demand Transmission Service

printed heading · Topic match: Cost allocation

Scenario A applies 16 the proposed methodology described in the PJM Transmission Owner’s Initial Brief. 17 Scenario B applies the alternative rate I describe above. 18 Page 13 Figure 3: Illustrative Comparison of Alternative Rate Structure to Minimize Cost Shifts The PJM Transmission Owner’s…
Read this passage Filed comments: Cost allocation

A. Yes. This concludes my affidavit.

printed heading

A.