Reply Comments of Earthjustice in response to the stakeholder's comments re PJM Interconnection, LLC's 02/23/2026 Initial Brief et al
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, LLC
)
)
)
Docket No. EL25-49-000
Docket No. ER26-1479-000
Reply Comments of Earthjustice
I. Introduction
On February 23, 2026, PJM Interconnection, LLC (“PJM”) submitted its initial brief1 and 60-day compliance filing2 in response to the Commission’s December 18, 2025, order on the show cause proceeding.3 Earthjustice appreciates the opportunity to respond to the wide range of comments that stakeholders submitted to the Commission in response to PJM’s filings.4 As PJM and other commenters remark, PJM is tasked with reimagining how it will provide transmission services, among other system changes. To date, PJM’s region has absorbed more load growth from large load customers than any other grid operator in the Commission’s jurisdiction. And projected load growth through 2030 is not slowing down.51 Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 (Feb. 23, 2026), Accession No. 20260223- 5189 (“PJM Initial Brief”).2 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et. al, Docket No. ER26-1479-000 (Feb. 23, 2026), Accession No. 20260223-5181 (“60-Day Compliance Filing”).3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Order on Show Cause Proceeding”).4 These comments are timely filed in Docket No. EL25-49-000. Though PJM chose to file its 60-Day Compliance Filing in a separate docket, ER26-1479-000, all of the issues discussed in these comments were initially raised in the Commission’s Order on the Show Cause Proceeding in Docket No. EL25-49-000. We respectfully request that the Commission consider these comments in both EL25-49-000 and ER26-1479-000.5 John Wilson, et. al., Power Demand Forecasts Revised Up for Third Year Running, Led by Data Centers, Grid Strategies 5 (2025), https://gridstrategiesllc.com/wp-content/uploads/Grid-Strategies-National-Load-Growth-Report- 2025.pdf.
PDF page 2
2
With this landscape, PJM has little margin for error in implementing the new and
modified services to avoid events that could devastate system reliability. As explained below, to avoid such risks, the Commission should (1) accept PJM’s proposed operational penalties;
(2) require PJM to clarify how and when curtailment directives will be enforced and how
violations will be communicated to the public; (3) decline to require that PJM rush the
implementation of protection mechanisms for its new non-firm transmission services; and
(4) require PJM to make its co-located generator interconnection studies and retail-BTMG rules consistent with the Commission’s Order on the Show Cause Proceeding and Order No. 2023.
Additionally, several comments in this docket express concern about PJM’s
interconnection queue, with commenters fearing delays.6 The Commission is aware of PJM’s
clogged interconnection queue and has raised concerns over PJM’s potential reliability and resource adequacy issues.7 Other regulators have expressed similar concerns.8 This docket reinforces that the Commission should require PJM to accelerate its interconnection process and ensure consistency with open access.
II. The Commission should accept PJM’s operational penalty proposal.
The Commission should accept PJM’s proposed operational penalties for data centers9
taking PJM’s new transmission services because financial penalties alone are insufficient to
6 See Limited Protest of Advanced Energy United and Solar Energy Industries Association, at 12, Docket No. ER26- 1479-000 (Mar. 16, 2026), Accession No. 20260316-5300 (“AEU & SEIA Protest”); Protest of Joint Parties, at 7 n. 32, Docket No. ER26-1479-000 (Mar. 16, 2026), Accession No. 20260316-5333 (“Joint Parties Protest”); Comments of the Digital Power Network, at 5, Docket No. ER26-1479-000 (Mar. 16, 2026), Accession No. 20260316-5220.7 Order on Show Cause Proceeding, supra note 3, at P 243.8 Statement of Principles Regarding PJM (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles- regarding-pjm.9 PJM’s proposal will apply to “Eligible Customers,” which PJM defines as “(1) any electric utility or any person generating electric energy for sale for resale, but with respect to transmission service that the Commission is prohibited from ordering by section 212(h) of the Federal Power Act, such entity is eligible only if the service is provided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled
PDF page 3
3
ensure compliance with curtailment directives. The Commission’s Order on the Show Cause Proceeding directs PJM to brief and establish an appropriate penalty charge and “any other remedial action” that PJM should take to address a customer’s unreserved use of the transmission system or excess energy withdrawals.10 Pursuant to the Commission’s order, PJM establishes three different penalties—pause in service, disqualification, and financial penalties— applicable where data centers fail to follow Load Shedding and Curtailment directives, rely on necessary control technologies that fail more than once, or make unreserved use of the transmission system. While PJM and Transmission Owners (“TOs”) propose to assess additional financial penalties for a customer’s unreserved use of the transmission system, PJM and TOs correctly acknowledge that financial penalties alone are not enough to incentivize data centers to follow curtailment procedures.11 Because financial penalties are insufficient to ensure that data centers will curtail energy use, the Commission should accept PJM’s more rigorous operational penalties.
A. Initial comments either support PJM proposed penalties or fail to adequately address PJM’s argument that financial penalties are insufficient to ensure
compliance.
Commenters generally support penalties for data centers that fail to follow curtailment procedures but disagree on whether PJM should impose its proposed operational penalties as opposed to solely financial penalties. Commenters who have a responsibility to ensure reliability,
transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner or (2) any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner.” PJM Open Access Transmission Tariff, Part VIII, Subpart A, Section 400, Definitions E. However, for simplicity, these comments refer to Eligible Customers as “data centers” because the majority of Eligible Customers will be taking service on behalf of data center customers.
10 Order on Show Cause Proceeding, supra note 3, at P 212, 217.11 PJM’s Initial Brief, supra note 1, at 50.
PDF page 4
4
including the Northern Virginia Electric Cooperative (“NOVEC”) and TOs, support PJM’s operational penalties and emphasize PJM’s obligation to protect the transmission system. NOVEC states that a pause in service and disqualification are appropriate and necessary to reliably manage co-location arrangements and protect the integrity of PJM’s transmission system.12 NOVEC also agrees that financial penalties alone are insufficient to ensure that data centers comply with their curtailment obligations, though both NOVEC and TOs support imposing complementary financial penalties alongside PJM’s proposed operational penalties.13 Unsurprisingly, developers of co-located resources argue for a weaker penalty structure based solely on financial penalties—but fail to show that financial penalties can actually affect their behavior. Joint Co-location Developers suggest PJM use a financial penalty similar to the Non-Performance Charge PJM assesses in the Capacity Resource context.14 They argue that PJM’s operational penalties are disproportionate to the harm caused by data centers that fail to curtail.15 They assert that “failure to respond to a Load Shedding or Curtailment procedure would have a similar impact to a capacity resource failing to perform during emergency events,” while the opportunity cost of shutting down a data center could purportedly be higher than the penalty charge ordinarily levied on capacity resources for failing to curtail.16
Joint Co-location Developers also argue that forcing a data center to take Network Integration Transmission Service (“NITS”) after a single unauthorized withdrawal is unfair and will threaten the commercial viability of PJM’s proposal.17 Other commenters argue that PJM’s
12 Response of the Northern Virginia Electric Cooperative, Inc., at 11-13, Docket No. EL25-49-000 (Mar. 25, 2026), Accession No. 20260325-5220 (“NOVEC Comments”).13 See NOVEC Comments at 13; Joint Response of the Indicated PJM Transmission Owners, at 11, Docket No. EL25-49-000 (Mar. 25, 2026), Accession No. 20260325-5203 (“TOs Response Brief”).14 Reply Brief of Joint Co-Location Developers, at 25, Docket No. EL25-49-000 (Mar. 25, 2026), Accession No. 20260325-5236 (“Co-Location Developers Reply Brief”).15 Id.16 Id.17 Id. at 23-24.
PDF page 5
5
strict liability rules unfairly assign penalties to load customers regardless of the cause or whether a third party is at fault.18
Commenters opposing operational penalties believe instead that financial penalties are sufficient to deter wrongful conduct, although they provide no explanation of why this is purportedly the case other than their references to other PJM penalties levied in different contexts. As detailed below, comments opposing PJM’s proposed operational penalties are unpersuasive because in addition to being self-serving, they ignore critical facts. Such comments fail to explain how financial penalties alone could be effective. They also disregard how data centers’ failure to curtail can pose extreme risks to reliability.
1. PJM’s operational penalties are proportionate to the prospective harm
associated with a customer’s failure to follow curtailment orders.
PJM explains that the consequences of a Remedial Action Scheme (“RAS”)
misoperation are more severe than failures of other fault protection schemes.19 A data center’s RAS misoperation or failure to comply with curtailment directives could have dire consequences for reliability, including the loss of all interim or non-firm load in one area—or even cascading outages across the Eastern Interconnection.20 These serious consequences warrant serious penalties. While opposing commenters note that PJM’s proposed penalties are stricter than the penalties it has levied in other circumstances, those comments fail to acknowledge that the stakes here are higher.
As the Commission points out in its December 18 order, NERC has stated that “co- location of large loads with generation facilities can have substantial reliability impacts due
18 Id. at 25-26, Response of the Data Center Coalition, at 8, Docket No. EL25-49-000 (Mar. 25, 2026), Accession No. 20260325-5208 (“DCC Comments”).19 PJM Initial Brief, supra note 1, at 43.20 PJM Initial Brief, Attach C., Affidavit of Matthew Wharton on behalf of PJM Interconnection, L.L.C. at P 21, 22 (“Wharton Affidavit”).
PDF page 6
6
to . . . loss of load incidents, while also presenting unique challenges and opportunities for grid transformation that require special consideration.”21 The unique challenges and opportunities of co-location arrangements require unique solutions. It is not enough to hope that financial penalties used in other circumstances—which, as explained below, did not actually work—will encourage data centers taking these new services to follow curtailment directives, especially when the reliability risks here are greater. The Commission must ensure that the penalties for failure to curtail are commensurate with the serious risks for PJM’s transmission system and ultimately customers such as residential ratepayers.
2. PJM’s obligation to offer non-firm service is not without limits.
PJM’s proposal to require data centers to take NITS after failure to follow curtailment orders is also reasonable. PJM’s new transmission services are explicitly designed for colocation arrangements to connect faster in exchange for promises to curtail when directed. It is reasonable to revoke a data center’s ability to use these new transmission services if a data center fails to uphold its end of the bargain. Otherwise, data centers would receive the benefits of these transmission services without providing a commensurate benefit to the grid. Simply put, large loads that fail to curtail when instructed cannot be trusted not to repeat that failure, especially in light of the severe reliability risks they present. While data centers that fail to curtail when instructed may have to wait for network upgrades before they can take NITS, that outcome is an entirely reasonable consequence for their failure to deliver promised flexibility.
3. PJM’s penalty proposal is appropriately designed to protect system reliability, rather than assign fault.
PJM’s proposal also reasonably addresses the concern that it may assign penalties to large load customers no matter who is at fault. Where failure to curtail results from a mishap
21 Order on Show Cause Proceeding, supra note 3, at P 136.
PDF page 7
7
with control technologies—for which a large load may not be at fault—PJM proposes a pause in service to provide a chance to correct the problems. Throughout the subsequent evaluation period, PJM and TOs will be able to investigate the issue and implement fixes, while also allowing the data center to resume the service once the fixes are in place.22 This evaluation period reasonably allows PJM to get to the root of the issue without disqualifying the load customer.
Some commenters speculate that other factors outside their control could cause a failure to curtail, such as problems with TOs’ facilities or communication systems. Setting aside the speculative nature of these concerns, PJM reasonably addresses this prospect by proposing an implementation timeline that will allow PJM and TOs to develop sufficiently sophisticated curtailment procedures. As PJM requires data centers to demonstrate their ability to fully comply with Load Shedding and Curtailment Procedures before the Service Commencement Date to begin service, PJM similarly must ensure that the systems that PJM and TOs will use to issue load shedding and curtailment directives will be robust.
The Commission should not allow hypothetical mishaps to prevent PJM from
implementing meaningful operational penalties. PJM has correctly described the seriousness of misoperation and failures to curtail and has given itself a three-year timeline to implement its curtailment scheme to ensure that the necessary modifications can be made for curtailment procedures.23 PJM’s decision to approach this issue with adequate caution and care is reasonable and will decrease the likelihood that the commenters’ hypothetical concerns will arise.
22 PJM Initial Brief, supra note 1, at 44-45.23 PJM Initial Brief, Attach. D, Affidavit of Timothy Horger on behalf of PJM Interconnection, L.L.C. at P 16. (“Horger Affidavit”).
PDF page 8
8
B. The Commission should accept PJM’s proposed penalties because financial
penalties alone are insufficient to ensure that data centers will comply with curtailment directives.
PJM is correct that financial penalties alone are not enough to incentivize data centers to follow curtailment or load shed procedures. Some commenters have suggested that financial penalties could in theory be sufficient to deter data centers from failing to curtail when instructed,24 but no comments actually describe what financial penalty could be sufficient in practice. That notable silence is likely because none of the commenters know what financial penalty could convince large load customers—with virtually unlimited capital and very high contractual uptime requirements—to curtail when directed. Though commenters argue that operational penalties are too strict, they are far more effective than financial penalties. To be effective, financial penalties must be more than merely the cost of doing business for well- financed large loads. However, because data centers are wealthy and have diverse business practices, calculating an effective financial penalty is extremely difficult. Moreover, payments made after the fact will not prevent the harm from non-performance.
Data center spending is growing exponentially, making it increasingly difficult to determine a uniform financial rate that could convince this multi-billion dollar—soon trillion dollar—industry to follow curtailment procedures instead of just paying the penalties. As of December 2025, data center deals hit a new record of $61 billion globally.25 According to McKinsey, global spending on data centers could reach $7 trillion by 2030.26 With data center
24 Co-Location Developers Reply Brief, supra note 14, at 25.25 April Roach, Data Center Deals Hit Record $61 Billion in 2025 Amid Construction Frenzy, CNBC (Dec. 19, 2025), https://www.cnbc.com/2025/12/19/data-center-deals-hit-record-amid-ai-funding-concerns-grip- investors.html. 26 Maria Goodpaster, et. al., The $7 Trillion Data Center Build-Our: How Industrials Can Capture Their Share, McKinsey & Company (Mar. 27, 2026), https://www.mckinsey.com/industries/technology-media-and- telecommunications/our-insights/the-7-trillion-dollar-data-center-build-out-how-industrials-can-capture-their-share.
PDF page 9
9
spending increasing by billions year over year, it is impossible to gauge what level of financial penalty could incentivize data centers to curtail their operations rather than just taking the penalty charge as an operating cost. Indeed, new research suggests that there is no price level currently observed in wholesale markets where certain data center loads will curtail.27
Data centers’ low participation in demand response programs also indicates that financial penalties are unlikely to be effective. In a study examining the potential for data center flexibility, the Nicholas Institute for Energy, Environment & Sustainability found that data centers have historically had low participation rates in demand response programs, likely as a result of their operational priorities and low financial incentives.28 Data centers are designed to provide uninterrupted service, often with mandated benchmarks, including uptime, latency, and quality of service.29 Responses to financial incentives, whether demand response payments or financial penalties, could vary based on a data center’s particular operational capabilities. Data centers are organized by tiers, ranging from tier I to tier IV.30 At the most basic capacity, tier I offers 99.671% of uptime per year, leaving less than 28.8 hours of downtime per year, and tier IV offers 99.995% of uptime per year, leaving less than 26.3 minutes of downtime per
year.31 For large loads with “high utilization rates and controlling costs, the economic
27 In February 2026, Hans Royal, Senior Director of Renewable Energy and Carbon Advisory at Schneider Electric, introduced the Compute Heat Rate, which is the first measurement to quantify the maximum electricity price at which AI computation remains economically viable, i.e. the demand-side price tolerance for data centers relative to curtailment thresholds. Royal’s preliminary analysis found that for four data center workload tiers, AI demand will not curtail at any price level currently observed in U.S. wholesale markets. Hans Royal, The Compute Heat Rate: Quantifying AI-Driven Electricity Price Tolerance and its Implications for Wholesale Market Repricing 8 (Feb. 28, 2026), https://ssrn.com/abstract=6322318.28 Tyler Norris, et. al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, Nicholos Institute for Energy, Environment & Sustainability 9 (2025), https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load- growth.pdf. (“Rethinking Load Growth”).29 Id.30 Breaking Down Data Center Tier Level Classifications, CoreSite, https://www.coresite.com/blog/breaking-down- data-center-tiers-classifications.31 Id.
PDF page 10
10
proposition of demand response participation may be unattractive.”32 Just as demand response payments are insufficient to entice flexibility, financial penalties will be insufficient to compel flexibility.
Although some data centers may be more likely to respond to financial incentives, the diversity among data centers makes a uniform financial penalty impossible to calculate. Some data centers have different operational priorities that could allow for more flexibility in their energy usage33 Data centers used for artificial intelligence (“AI”) training purposes may be better suited for flexible operations because they are able to defer their training operations, whereas conventional data centers have less flexible real-time processing demands.34 For data centers training AI, financial penalties could theoretically be more meaningful. But without knowing a data center’s operating structure, service agreements, and priorities, there is no clear way to figure out what level of financial penalty would be enough to incentivize a data center to curtail. Additionally, many predict that in the longer term, AI training data centers will become less important as AI models improve, and most data centers will ultimately be used for inference and other, less flexible real-time processing applications. According to research by McKinsey, “by 2030 inference will surpass training to become the dominant workload in AI Data centers.”35 This trend further calls into question the long-term viability of data center load flexibility. Additionally, some large-scale co-located data centers, like some at issue in this docket, house multiple tenants, each with different operational requirements.36 A uniform financial penalty
32 Rethinking Load Growth, supra note 28, at 9.33 Id.34 Id. at 11.35 Chhavi Arora, The Next Big Shifts in AI Workloads and Hyperscaler Strategies, Mckinsey & Company (Dec. 17, 2025), https://www.mckinsey.com/industries/technology-media-and-telecommunications/our-insights/the-next-big- shifts-in-ai-workloads-and-hyperscaler-strategies. https://www.mckinsey.com/industries/technology-media-and- telecommunications/our-insights/the-next-big-shifts-in-ai-workloads-and-hyperscaler-strategies36 Rethinking Load Growth, supra note 28, at 9.
PDF page 11
11
alone would not be effective applied across all these different types of service arrangements, which all have different operational and financial priorities.
Indeed, PJM has used financial penalties in other contexts, and PJM is learning from its mistakes. Joint Co-Location Developers attempt to compare underperforming capacity resources to the data centers here, arguing that a rate similar to PJM’s Non-Performance Charge for a capacity resource that fails to perform during an emergency would be appropriate and sufficient in this context.37 However, PJM’s penalty charges for poorly performing capacity resources are not a model for a penalty for large loads that abuse new transmission services for three key reasons: (1) PJM’s Capacity Performance structure is ineffective; (2) PJM’s Capacity Performance structure is designed to transfer penalties from underperforming resources to bonus payments for overperforming resources, and there is no comparable structure for the new transmission services; and (3) the risks of nonperformance for PJM’s curtailment procedures are much graver than underperformance of a capacity resource during an emergency event. First, PJM’s Capacity Performance structure is ineffective. PJM implemented its Capacity Performance system in response to capacity resource failures during the 2014 Polar Vortex. The Polar Vortex hit the PJM region in January 2014, setting a record wintertime peak demand.38 Twenty-two percent of PJM’s generation capacity failed to perform during the storm.39 PJM attempted to address these nonperformance issues by creating a new Capacity Performance system to incentivize capacity resources to perform during emergencies. PJM’s Capacity Performance system assesses penalties, or Non-Performance Charges, to resources that
37 Co-Location Developers Reply Brief, supra note 14, at 25.38 PJM, Analysis of Operational Events and Market Impacts During the January 2014 Cold Weather Events, at 4 (May 8, 2014) (“Polar Vortex Report”), https://www.hydro.org/wp-content/uploads/2017/08/PJM-January-2014- report.pdf.39 Id.
PDF page 12
12
underperform during emergencies.40 PJM then uses those penalties to fund bonuses to resources that overperformed during the emergency.41
Unfortunately, PJM’s financial penalty system has not been an effective mechanism to ensure that capacity resources perform when called. PJM created the Capacity Performance system because it anticipated that emergency events like the Polar Vortex would occur again. And PJM was right. But when an event like the Polar Vortex happened again, the Capacity Performance system failed to incentivize resources to perform. Winter Storm Elliot hit the PJM region in 2022 and despite PJM’s new penalty structure, PJM saw even more capacity resources fail to perform in Winter Storm Elliott than in the Polar Vortex.42 These capacity resource failures resulted in the largest Capacity Performance penalties that PJM has ever assessed, with PJM charging underperforming resources $1.80 billion in Non-Performance Charges.43 However, in response to calls from generators to reduce the penalties, PJM has limited the definition of an “Emergency Action” that would trigger penalties, which reduces instances where PJM would assess penalties to nonperforming generators.44 PJM also entered into settlements to reduce the penalties that PJM assessed to generators that failed to perform during Winter Storm Elliott.45 Additionally, in 2022, the Commission confirmed that generators can include the risk of increased Capacity Performance penalties in their market bids.46 This history—in which
40 See generally PJM Interconnection, LLC, 151 FERC ¶ 61,208 (2015).41 Id.42 PJM, Winter Storm Elliott: Event Analysis and Recommendation Report, at 49 (July 17, 2023) (“Winter Storm Elliott Report”), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/20230717- winter-storm-elliott-event-analysis-and-recommendation-report.pdf.43 Id. at 2.44 Proposed Revisions to Prospectively Refine the Definition of Emergency Action, Request for Shortened Comment Period and Expedited Commission Action, at 4, Docket No. ER23-1996 (Aug. 28, 2023), Accession No. 20230828- 5201.45 PJM, Offer of Settlement, at 4, 7 (Sept. 29, 2023), https://www.pjm.com/- /media/DotCom/documents/ferc/filings/2023/20230929-er23-2975-000.ashx.46 Indep. Mkt. Monitor for PJM v. PJM Interconnection, L.L.C., 178 FERC ¶ 61,121 at P 49 (2022).
PDF page 13
13
Capacity Performance penalties failed to compel strong performance from generators during Winter Storm Elliott and were then watered down—makes clear that financial penalties are insufficient to ensure performance in the Capacity Resource context. These financial penalties would likely be even more inadequate to ensure that extremely wealthy data centers will curtail as directed, where PJM has already acknowledged that data centers would likely “absorb financial penalties” rather than follow curtailment procedures.47
Second, even if financial penalties were effective in the Capacity Performance context, PJM’s Capacity Performance structure is not comparable to a penalty system for new transmission services. To start, the Capacity Performance system is designed to provide a resettlement of the capacity market by charging penalties to underperforming resources that fund bonus payments to overperforming resources. No similar resettlement approach is possible in the context of these new transmission services, because there is no set of “overperforming” loads that could ameliorate the harms from large loads that violate the terms of the new transmission products. In this context, the only way to reduce the harm caused by failures to curtail is to stop service to the large loads that violate the terms.
Finally, large loads that violate the terms of new transmission products are not comparable to underperforming generators because they pose far graver risks to reliability. PJM explains that there could be dire loss of load events if all interim or non-firm loads in an electrically close area have curtailment violations.48 If multiple customers in a close area have similar RAS violations, the loss of one facility could require reducing or dropping all interim or non-firm load in the area.49 Even worse, the failure or misoperation of one RAS in PJM could
47 PJM Initial Brief, supra note 1, at 50.48 Wharton Affidavit, supra note 20, at P 22.49 Id.
PDF page 14
14
lead to cascading outages, which could affect the entire Eastern Interconnection.50 In contrast, generator underperformance has not historically caused such severe harm. While the Polar Vortex and Winter Storm Elliott featured generator failures and subsequent penalty charges, the storms never caused widespread system outages.51 In contrast, the stakes are much higher for PJM if customers taking its new transmission services fail to follow curtailment directives, and PJM cannot risk its entire system to appease one category of customers. The Commission must ensure that PJM is prioritizing reliability over the commercial interests of large loads. The Commission should accept PJM’s operational penalty structure because financial incentives are insufficient to incentivize performance or ensure reliability.
III. The Commission should require PJM to clarify how and when PJM will enforce its curtailment procedures.
While PJM’s proposed curtailment procedures and penalty structure are generally reasonable, PJM has not provided sufficient detail about implementation. As failures to curtail can cause dire ramifications for the transmission system, the Commission must have clarity on several important points: (1) how PJM will communicate its curtailment directives to Transmission Providers and Data centers; (2) how and when Transmission Providers will determine that load shed is necessary, which loads will be curtailed first, and at what stage curtailments will occur; and (3) how a data center will be disqualified and the timeline for that disqualification.
Additionally, the Commission should require PJM to explain how the public can obtain records of violations of curtailment procedures and records of enforcement of penalties for those violations. PJM has emphasized that misoperation of control technology and failures to respond
50 Id.51 Winter Storm Elliott Report, supra note 42, at 1; Polar Vortex Report, supra note 38, at 1.
PDF page 15
15
to curtailment instructions can be detrimental to the transmission system, endanger reliability across multiple regions, and even threaten the entire Eastern Interconnection. These reliability risks mean that curtailment violations could significantly affect all of PJM’s ratepayers. With stakes this high, the public must have access to information about how these risks and violations play out.
A. Initial comments urge the Commission to require PJM to clarify its proposed curtailment procedures.
Initial comments explain that PJM’s initial brief did not provide sufficient detail about its curtailment procedures. Several commenters argue that PJM did not provide adequate clarity about key points, including (1) what specific conditions will trigger curtailments, (2) what the earliest point is at which a Non-Firm customer can be curtailed and how far in advance curtailment information will be provided, and (3) what the expected duration or frequency of curtailment events is.52 Joint Co-Location Developers also seek clarification as to how PJM will determine curtailment priority among its different classes of Non-Firm Service.53 Additionally, Advanced Energy United (“AEU”) and the Solar Energy Industries Association (“SEIA”) provide PJM with specific action items, requesting that PJM publish historical analysis and forward-looking modeling of curtailment frequency and duration for the new Non-Firm transmission services and hold a presentation to walk stakeholders through the curtailment process.54 To address confusion around PJM’s curtailment procedures, the Commission should require PJM to provide more information about specific curtailment triggers, curtailment duration and frequency, and how the curtailment process will actually work.
52 See DCC Comments, supra note 18, at 7; Reply Brief of Advanced Energy United and the Solar Energy Industries Association, Docket No. EL25-49-000, at 11-12, Accession No. 20260325-5237 (Mar. 25, 2026) (“AEU & SEIA Comments”).53 Co-Location Developers Reply Brief, supra note 14, at 17.54 AEU & SEIA Comments, supra note 52, at 13-14.
PDF page 16
16
B. The Commission should require PJM to clarify its curtailment procedures to ensure that PJM will adequately protect the reliability and safety of the transmission system.
In addition to the concerns raised in initial comments, PJM’s initial brief, tariff, and proposed service agreements fail to adequately state (1) how PJM and its Transmission Providers will direct customers to curtail, (2) how and when Transmission Providers will decide that load shed is necessary and how they will choose which specific loads are curtailed first, (3) exactly how and when disqualification will occur, and (4) how PJM will communicate curtailment violations and disqualifications to the public. Without clarity on the issues, the Commission and the public cannot be sure that PJM’s proposal can adequately protect the transmission system. PJM fails to state how it will actually communicate its orders to the Transmission Providers and how the Transmission Providers will actually direct their customers to curtail. PJM’s initial brief states that PJM will issue a directive to curtail, and data centers must implement that directive and respond to any real-time instruction to curtail within five minutes.55 PJM’s proposed tariff further establishes that “the Transmission Provider will notify the data center of any Curtailment in a timely manner” and that any requests to curtail will be consistent with Good Utility Practice.56 Beyond that, PJM’s filings are silent as to how these directives will be made known to data centers and what those directives will say. The Commission should require PJM to clarify what the content of these directives will be and how these directives will be communicated to data centers.
PJM also fails to clarify how and when Transmission Providers will determine that load shed is necessary, how Transmission Providers will select specific loads to curtail, and at what
55 PJM Initial Brief, supra note 1, at 25.56 PJM Initial Brief, Attach. A, Part XI, Subpart A, §§705.1, 713.1 (“Proposed Tariff”).
PDF page 17
17
stage curtailment will occur. Under PJM’s proposal, data centers that apply for Interim NITS, Non-Firm Contract Demand Service, or Firm Contract Demand Service must agree to follow PJM’s real-time curtailment instructions within 5 minutes or risk disqualification.57 PJM states that Interim NITS will be curtailed prior to Firm Contract Demand Transmission Service and NITS and that PJM may curtail Interim NITS and Non-Firm Contract Demand Transmission Service prior to the Pre-Emergency Load Response Program.58 However, PJM fails to clarify with any more detail when and how it will actually implement these procedures. The tariff states that data centers will curtail when Transmission Providers deem it necessary, but PJM provides no other information to explain how Transmission Providers will determine when load shedding is necessary.59 While there may be existing procedures that could apply to this circumstance, PJM and Transmission Providers should at least document what those procedures are and explain how they are adequate to this circumstance.
Additionally, although PJM states that data centers taking Interim NITS or Contract Demand Services may be curtailed prior to initiating a pre-emergency event, it is unclear when exactly curtailment would occur before a pre-emergency event or whether there is some set threshold that would need to be crossed for curtailment to begin.60 While PJM has detailed in its operating agreement when a pre-emergency event will be called, PJM has not provided a detailed explanation for how it will determine that resources need to be curtailed before pre-emergency or emergency conditions have been triggered.61 Additionally, it is unclear how Transmission Providers will decide which specific loads will be curtailed. While the tariff states that Interim
57 Id.58 PJM Initial Brief, supra note 1, at 7.59 Proposed Tariff, supra note 56, at §705.3.60 Id. at § § 705.2, 713.4.61 PJM Operating Agreement, Schedule 1, Section 8.5.
PDF page 18
18
NITS and Non-Firm Contract Demand Service will be curtailed before Firm Contract Demand Service, NITS, and the Pre-Emergency Load Response Program, PJM provides no further information about how Transmission Providers will determine the order in which specific loads will be curtailed.41 The Commission should require PJM and TOs to clarify their curtailment process to ensure that Transmission Providers and customers can adequately understand curtailment protocols.
PJM similarly fails to adequately explain its disqualification procedures for customers that fail to curtail when called. While PJM’s tariff states that data centers will be disqualified after the first instance where they fail to respond to curtailment procedures or after the second instance of a misoperation, the tariff fails to explain any further how that disqualification will actually happen.62 PJM fails to address important operational questions, like whether PJM will physically disconnect the facility from the point of interconnection or will allow the connection to remain intact if the Customer applies for NITS. Though PJM states that disqualification automatically applies after one instance of a data center failing to follow a curtailment directive or after control technology fails a second time, PJM never states how that disqualification will occur in practice or what the timeline is for disqualification. Important considerations like when the data centers will stop receiving service or how PJM and Transmission Providers will disable transmission service remain unanswered. Without more clarity on these points, PJM’s disqualification scheme may not have real teeth to ensure customers comply with curtailment directives and, more importantly, may not sufficiently protect the transmission system. The Commission should require PJM to clarify its disqualification procedures to ensure that PJM has created a reliable and effective enforcement mechanism.
62 Proposed Tariff, supra note 56, at § 713.7.
PDF page 19
19
Finally, the Commission should require PJM to explain how it will provide the public with records of curtailment violations and subsequent disqualification. PJM is on the right track to ensure that data centers comply with curtailment procedures. However, without proper enforcement mechanisms and public transparency, regulators and the public will not be able to evaluate the scope of risks to reliability and the efficacy of PJM’s penalty scheme. PJM has described in detail how misoperations and failures to curtail can threaten the reliability of its entire transmission system. The Commission should require PJM to post violations publicly, ensuring that non-data center customers are aware of reliability threats and that violations are handled appropriately.
IV. The Commission should decline to require that PJM rush the implementation of protection mechanisms for its new non-firm transmission services.
The Commission should approve PJM’s requested timeline to implement new
transmission services and accompanying RAS and Special Protection Schemes (SPS). Though there is a strong push from some commenters to rush this process, the Commission must ensure that PJM does not sacrifice the reliability of the transmission system to fulfill data centers’ near- term power demands. The Commission has already expressed concern about the reliability and resource adequacy implications of Co-Location Arrangements, stating in its December order that “the speed at which co-located load can be added to the grid may pose particular resource adequacy challenges, especially if co-location arrangements are not adequately and transparently reflected in existing RA planning mechanisms.”63 Similarly, PJM has acknowledged that its new transmission services and protection schemes could threaten the reliability of the transmission system. Considering the serious threats to reliability, PJM must ensure that its systems are safe
63 Order on Show Cause Proceeding, supra note 3, at P 243.
PDF page 20
20
and reliable for all customers. The Commission and PJM must not rush the process to serve certain customers at the expense of overall reliability.
Commenters who have a responsibility to ensure reliability support PJM’s proposed implementation date. PJM’s Independent Market Monitor (“IMM”) and NOVEC both agree with Mr. Horger’s explanation that the three-year timeline is necessary to give PJM enough time to implement the modifications needed to support PJM’s new transmission services and curtailment procedures.64 Similarly, NOVEC finds Mr. Horger’s explanation that it is no longer possible to implement necessary changes to the 2028/2029 RPM to be well-founded and persuasive.65 Predictably, comments criticizing PJM’s deadline overwhelmingly come from entities with a direct financial interest in developing co-located resources. These commenters push for urgency and speed, calling for the Commission to require PJM to push up its deadline. The Commission should find that PJM’s deadline is appropriate for the planning and training needed to implement PJM’s transmission services and curtailment protocols. PJM must take appropriate time to implement new services and RAS. Getting it right is more important than moving fast. Mr. Wharton’s affidavit acknowledges that the new transmission services and its RAS and SPS schemes pose significant reliability risks.66 To limit reliability risks, PJM will need to develop telemetry requirements for Co-Located Loads and ensure that necessary control technologies and protective systems are properly designed.67 Typically, a RAS monitors one specific, pre-determined condition, but those typical RASs would not be suitable here as PJM will need an RAS or multiple RASs to monitor and activate for multiple conditions.68 As PJM
64 Reply Brief of the Independent Market Monitor, Docket No. EL25-49-000, at 8, Accession No. 20260326-5062 (Mar. 26, 2025); NOVEC Comments, supra note 12, at 17.65 NOVEC Comments, supra note 12, at 17.66 Wharton Affidavit, supra note 20, at P 16, P 22.67 PJM Initial Brief, supra note 1, at 60.68 Wharton Affidavit, supra note 20, at P 22.
PDF page 21
21
will be implementing RASs outside of their normal functions, PJM will need to take time to adapt these technologies to these new circumstances. Mr. Horger’s affidavit also notes that PJM needs time to implement updates to software and automation to avoid “non-optimal, untimely, and inefficient outcomes.”69 PJM must ensure that its systems are sufficient to protect the safety and reliability of the transmission system. The Commission should not rush to expedite PJM’s implementation process in favor of large load customers’ convenience and at the expense of the rest of PJM’s customers. The Commission should approve PJM’s proposed June 2029 effective date to ensure that PJM has enough time to implement its new transmission services and curtailment procedures safely and reliably.
V. The Commission should require PJM to ensure that rules governing generator interconnection studies and behind-the-meter generation are consistent with the Commission’s Order on the Show Cause Proceeding and Order No. 2023.
PJM’s proposed rules are unjust and unreasonable because PJM’s proposed generator interconnection study and behind-the-meter generation (“BTMG”) rules fail to comply with the Commission’s Order on the Show Cause Proceeding and Order No. 2023. To ensure that PJM’s rules are consistent with the Commission’s Orders, the Commission should: (1) require PJM to clarify that hybrid resources can nominate their net withdrawal limitations for purposes of the interconnection study process and (2) require PJM to set a materiality threshold for the amount of load a generator can net using BTMG.
The Commission ordered PJM to amend its tariff because it did not include conditions of service for co-location arrangements that are willing and able to limit their withdrawals from the transmission system. Despite the Commission’s orders, PJM’s proposed tariff is silent as to whether a hybrid co-located facility can nominate net withdrawals for the purposes of PJM’s
69 Horger Affidavit, supra note 23, at P 16.
PDF page 22
22
Necessary Study Process. Without incorporating the net withdrawal limitations of hybrid generators in the operating assumptions for the Necessary Study Process, PJM’s proposed rules will likely force hybrid generators to pay for unnecessary upgrades because the Necessary Study Process will not accurately reflect hybrid generators’ use of the transmission system. The Commission should require PJM to clarify that hybrid co-located facilities can nominate their net withdrawal limitations for purposes of the Necessary Study Process to avoid excessive and unnecessary network upgrade costs for hybrid generators.
In addition to the Commission’s order to clarify the terms of service for co-location arrangements, the Commission also ordered PJM to amend its retail-BTMG rules. The Commission determined that PJM’s existing BTMG rules may lead to reliability and resource adequacy risk and ordered PJM to create a MW materiality threshold for the amount of load a Network Customer may net using BTMG. However, PJM proposes a Retail BTMG rule that is fundamentally different from what the Commission ordered, limiting the size of generator that can participate in BTMG netting instead of the amount of load that a generator may net. The Commission should reject PJM’s materiality threshold and require PJM to make its retail-BTMG rules consistent with the Commission’s Order on the Show Cause Proceeding.
A. Initial Comments correctly urge the Commission to require PJM to clarify that hybrid resources can nominate net withdrawal limitations in PJM’s necessary study process.
As initial comments explain, the Commission should require PJM to clarify that hybrid resources may nominate net withdrawal limitations in PJM’s Necessary Study Process to avoid triggering costly and unnecessary network upgrades. Joint Parties argue that without clear provisions to allow hybrid generators to nominate net withdrawal limitations, PJM may include
PDF page 23
23
inaccurate operating assumptions for hybrid generators in its Necessary Study Process.70 These assumptions could inaccurately identify overlapping grid impacts where storage resources and co-located loads could instead manage withdrawals, triggering unnecessary network upgrades.71 If PJM fails to clarify that hybrid customers can nominate their net withdrawal limits, hybrid generators may be forced to pay for and wait for network upgrades that they will not use. The Commission should require PJM to clarify that hybrid co-located facilities can nominate their net withdrawal limitations for the necessary study process. This clarification would be consistent not only with the Commission’s Order on its Show Cause Proceeding, but also consistent with the Commission’s Order No. 2023. In Order No. 2023, the Commission required transmission providers to use operating assumptions that reflect the proposed charging behavior of storage resources, including hybrid facilities, in their interconnection studies.72 The Commission issued these reforms to ensure that transmission providers do not overestimate the impact of storage resources on the transmission system and to ensure that transmission providers avoid assigning excessive and unnecessary network upgrades.73 PJM’s current proposal would be inconsistent with Order No. 2023 by including inaccurate, overestimated assumptions in its necessary study process for hybrid co-located resources. PJM’s proposal will likely trigger the same excessive, unnecessary network upgrades that the Commission sought to prevent with Order No. 2023. PJM must clarify that hybrid resources can nominate net withdrawal limitations to comply with both the Commission’s Order on the Show Causing Proceeding and Order No. 2023.
70 Joint Parties Protest, supra note 6, at 7.71 Id.72 Order No. 2023, 184 FERC ¶ 61,054 at P 1509 (2023).73 Id. at P 1510.
PDF page 24
24
B. Initial comments correctly support revising PJM’s Retail-BTMG rules to be consistent with the Commission’s Order on the Show Cause Proceeding.
Initial comments also urge the Commission to require PJM to change its proposed BTMG rules because PJM’s proposal is unjust and unreasonable. PJM’s BTMG rules allow loads to reduce their costs by netting their output from BTMG to determine their transmission charges.74 PJM’s proposed threshold limits retail-BTMG to generation that has a cumulative nameplate rating of no greater than 50 MW.75 PJM’s proposed threshold is materially different from the threshold that FERC ordered because PJM set a MW threshold for the size of generator that can participate in netting rather than a threshold for the amount of load a generator can net. Generators argue that PJM’s nameplate capacity cap unnecessarily limits the types of generators that can participate in BTMG netting.76 Resources that would be excluded under PJM‘s current proposal are technically capable of providing retail-BTMG and should be able to do so.77 Unlike PJM’s proposed nameplate capacity threshold, the Commission’s load netting threshold would apply fairly across all resource types. The Commission should reject PJM’s proposed BTMG rules and require PJM to set a materiality threshold that is consistent with the Commission’s Order on the Show Cause Proceeding.
VI. Conclusion
For the reasons discussed above, the Commission should (1) accept PJM’s proposed operational penalties; (2) require PJM to clarify its curtailment procedures and clarify how
74 Order on Show Cause Proceeding, supra note 3, at 7-8.75 60-Day Compliance Filing, supra note 2, at 7.76 AEU & SEIA Protest, supra note 6, at 4.77 See e.g., PJM Interconnection, LLC, 162 FERC ¶ 61,127, at P 4 (2018) (ordering RTOs/ISOs to revise their tariff provisions to ensure that electric storage resources are eligible to provide all services that they are technically capable of providing in the RTO/ISO markets); PJM Interconnection, LLC, 172 FERC ¶ 61,247, at P 141 (2020) (requiring that each RTO’s/ISO’s rules cannot exclude particular types of technologies from being eligible to provide all of the services that they are technically capable of providing).
PDF page 25
25
violations will be communicated to the public; (3) decline to require PJM to rush its implementation deadline for its new transmission services; and (4) require PJM to make its proposed rules consistent with the Commission’s Order on the Show Cause Proceeding and Order No. 2023. The consequences of faulty rules for co-located loads could be dire. The Commission must ensure that PJM protects the reliability of its transmission system for all of its customers, rather than protecting the financial interests of a well-resourced few. DATED: April 24, 2026
PDF page 26
26
Respectfully submitted,
EARTHJUSTICE
/s/ Aaliyah Adkins
Aaliyah Adkins
Associate Attorney
Earthjustice
1400 L St NW
Lobby 2, Unit 34117
Washington DC 20005
(202) 797-5253
aadkins@earthjustice.org
/s/ Nick Lawton
Nick Lawton
Senior Attorney
Earthjustice
1400 L St NW
Lobby 2, Unit 34117
Washington DC 20005
(202) 780-4835
nlawton@earthjustice.org
PDF page 27
27
CERTIFICATE OF SERVICE
I hereby certify that the foregoing has been served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email.
/s/ Aaliyah Adkins
Aaliyah Adkins
Associate Attorney
Earthjustice
1400 L St NW
Lobby 2, Unit 34117
Washington DC 20005
(202) 797-5253
aadkins@earthjustice.org