EL25-49-000 · 2026-04-24 · Earthjustice

Reply Comments of Earthjustice in response to the stakeholder's comments re PJM Interconnection, LLC's 02/23/2026 Initial Brief et al

Text extracted from the eLibrary original (SHA-256 02a81344144d46d3…). Download the original from the official source.

Contents · 12 sections
  1. I. Introduction p. 1
  2. II. The Commission should accept PJM’s operational penalty proposal. p. 2
  3. A. Initial comments either support PJM proposed penalties or fail to adequately p. 3
  4. B. The Commission should accept PJM’s proposed penalties because financial p. 8
  5. III. The Commission should require PJM to clarify how and when PJM will enforce p. 14
  6. A. Initial comments urge the Commission to require PJM to clarify its proposed p. 15
  7. B. The Commission should require PJM to clarify its curtailment procedures to ensure p. 16
  8. IV. The Commission should decline to require that PJM rush the implementation of p. 19
  9. V. The Commission should require PJM to ensure that rules governing generator p. 21
  10. A. Initial Comments correctly urge the Commission to require PJM to clarify that p. 22
  11. B. Initial comments correctly support revising PJM’s Retail-BTMG rules to be p. 24
  12. VI. Conclusion p. 24

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, LLC ) ) ) Docket No.
Read this passage

I. Introduction

printed heading · Topic match: Connecting load and generation

Additionally, several comments in this docket express concern about PJM’s interconnection queue, with commenters fearing delays.6 The Commission is aware of PJM’s clogged interconnection queue and has raised concerns over PJM’s potential reliability and resource adequacy issues.7 Other regulators…
Read this passage Filed comments: Connecting load and generation

II. The Commission should accept PJM’s operational penalty proposal.

printed heading · Topic match: Reliability and curtailment

The Commission’s Order on the Show Cause Proceeding directs PJM to brief and establish an appropriate penalty charge and “any other remedial action” that PJM should take to address a customer’s unreserved use of the transmission system or excess energy withdrawals.10 Pursuant to the Commission’s…
Read this passage Filed comments: Reliability and curtailment

A. Initial comments either support PJM proposed penalties or fail to adequately

printed heading · Topic match: Reliability and curtailment

As PJM requires data centers to demonstrate their ability to fully comply with Load Shedding and Curtailment Procedures before the Service Commencement Date to begin service, PJM similarly must ensure that the systems that PJM and TOs will use to issue load shedding and curtailment directives will…
Read this passage Filed comments: Reliability and curtailment

B. The Commission should accept PJM’s proposed penalties because financial

printed heading · Topic match: Reliability and curtailment

To be effective, financial penalties must be more than merely the cost of doing business for well- financed large loads.
Read this passage Filed comments: Reliability and curtailment

III. The Commission should require PJM to clarify how and when PJM will enforce

printed heading · Topic match: Reliability and curtailment

As failures to curtail can cause dire ramifications for the transmission system, the Commission must have clarity on several important points: (1) how PJM will communicate its curtailment directives to Transmission Providers and Data centers; (2) how and when Transmission Providers will determine…
Read this passage Filed comments: Reliability and curtailment

A. Initial comments urge the Commission to require PJM to clarify its proposed

printed heading · Topic match: Reliability and curtailment

Several commenters argue that PJM did not provide adequate clarity about key points, including (1) what specific conditions will trigger curtailments, (2) what the earliest point is at which a Non-Firm customer can be curtailed and how far in advance curtailment information will be provided, and…
Read this passage Filed comments: Reliability and curtailment

B. The Commission should require PJM to clarify its curtailment procedures to ensure

printed heading · Topic match: Reliability and curtailment

PJM’s initial brief states that PJM will issue a directive to curtail, and data centers must implement that directive and respond to any real-time instruction to curtail within five minutes.55 PJM’s proposed tariff further establishes that “the Transmission Provider will notify the data center of…
Read this passage Filed comments: Reliability and curtailment

IV. The Commission should decline to require that PJM rush the implementation of

printed heading · Topic match: Reliability and curtailment

Though there is a strong push from some commenters to rush this process, the Commission must ensure that PJM does not sacrifice the reliability of the transmission system to fulfill data centers’ near- term power demands.
Read this passage Filed comments: Reliability and curtailment

V. The Commission should require PJM to ensure that rules governing generator

printed heading · Topic match: Cost allocation

However, PJM proposes a Retail BTMG rule that is fundamentally different from what the Commission ordered, limiting the size of generator that can participate in BTMG netting instead of the amount of load that a generator may net.
Read this passage Filed comments: Cost allocation

A. Initial Comments correctly urge the Commission to require PJM to clarify that

printed heading

PJM must clarify that hybrid resources can nominate net withdrawal limitations to comply with both the Commission’s Order on the Show Causing Proceeding and Order No. 2023. 70 Joint Parties Protest, supra note 6, at 7. 71 Id. 72 Order No. 2023, 184 FERC ¶ 61,054 at P 1509 (2023). 73 Id. at P 1510.…
Read this passage

B. Initial comments correctly support revising PJM’s Retail-BTMG rules to be

printed heading

Initial comments correctly support revising PJM’s Retail-BTMG rules to be consistent with the Commission’s Order on the Show Cause Proceeding.
Read this passage

VI. Conclusion

printed heading · Topic match: Reliability and curtailment

The Commission must ensure that PJM protects the reliability of its transmission system for all of its customers, rather than protecting the financial interests of a well-resourced few.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that the foregoing has been served in accordance with 18 C.F.R. § 385.2010 upon each party designated in the official service list compiled by the Secretary in this proceeding, by email. /s/ Aaliyah Adkins Aaliyah Adkins Associate Attorney Earthjustice 1400 L…