EL25-49-000 · 2026-04-24 · Old Dominion Electric Cooperative
Reply of Old Dominion Electric Cooperative to Responses to Initial Briefs of PJM Interconnection, L.L.C. and Indicated Transmission Owners
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
2
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities, Division
of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
AD24-11-000
EL25-20-000
(Consolidated)
REPLY OF OLD DOMINION ELECTRIC COOPERATIVE
TO RESPONSES TO INITIAL BRIEFS OF PJM INTERCONNECTION, L.L.C. AND
THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to the Order issued in the above-referenced proceeding on December 18, 2025, and the Notice of Extension of Time issued on January 23, 2026, Old Dominion Electric Cooperative (“ODEC”) submits this reply to certain of the responses to the Initial Brief and Joint Responses of the PJM Transmission Owners to Paper Hearing Questions and the Initial Brief of PJM Interconnection, L.L.C. (“PJM”).
In its Reply Brief, ODEC expressed its general agreement with the proposals submitted by PJM and the Indicated TOs. ODEC also expressed its willingness to adopt the Indicated TOs’ proposed rates for the new Firm Contract Demand and Non-Firm Contract Demand, subject to clarification. ODEC explained its support for the Commission’s acceptance of both filings, subject to further compliance filings as necessary to address the following issues described in its Reply Brief: (1) clarification of PJM’s proposed requirement that an Eligible Customer must be
PDF page 3
3
designated to take transmission service on behalf of a Co-Located Load and provide PJM with an authorization from its Relevant Electric Retail Regulatory Authority (“RERRA”); (2) with respect to the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the new Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the individual TOs will need to either confirm that their formula or stated rates and metrics reporting enable the direct crediting by PJM, or provide whatever revisions are necessary in order to do so;
(3) PJM and the PJM Transmission Owners will need to address how to charge regulation and black start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) the Commission consider whether any protections are needed for local utilities or TOs should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds contract demand or are called upon for Load Shedding and Curtailment. In such instances, the local utility or TO should not be liable for legal, financial or other damages that might be experienced by an Eligible Customer.
ODEC’s position on PJM and the Indicated TOs’ filings remains as stated in ODEC’s Reply Brief. ODEC reiterates its request that the Commission address these issues, particularly clarification regarding how a generation and transmission cooperative like ODEC will meet PJM’s proposed requirement that an Eligible Customer must be designated to take transmission service on behalf of a Co-Located Load and provide PJM with an authorization from its RERRA.1 ODEC submits this brief response to address two issues; the proposed measures to protect reliability, and the proposed Grid Reliance Charge.
1 ODEC Reply Brief at 6-7.
PDF page 4
4
A. PJM Must Ensure that Service to Co-Located Loads Does Not Adversely
Impact Reliability
ODEC continues to express its support for PJM’s proposal for escalating penalties in the form of disqualification and pauses in service for failures to shed load or curtail, as well as for failures in control technology, and/or protection system misoperation.2 However, as ODEC discussed in its Reply Brief, clarification is needed regarding how the Eligible Customer and RERRA for Co-Located Loads will be applied to generation and transmission cooperatives like ODEC.3 PJM’s implementation of its penalties must not subject ODEC or its member distribtion cooperatives to service interruptions or disqualification, or financial penalties, as a result of requiring ODEC to serve as the Eligible Customer. Instead, such penalties must be limited to and borne by the Co-Located Loads.
ODEC also continues to support development of financial penalties, while recognizing that financial penalties alone will not be sufficient to preserve reliability. The need to ensure reliability of the transmission system is paramount. To that end, ODEC disagrees with parties who have suggested that financial penalties alone will suffice, and that PJM’s proposed remedial measures are overly harsh.4 ODEC does not agree that PJM’s proposed suspension and disqualification measures are unfairly imposed regardless of fault and will make the services unduly risky for many loads.5 Reliability of the transmission system is critical and financial penalties imposed on the Eligible Customer, alone, will neither preserve reliability nor protect other users of the
2 Id. at 11.3 ODEC Reply Brief at 6-7.4 Constellation Reply Brief at 19-20; Vistra Reply Brief at 29-31; Joint Co-Location Developers Reply Brief at 23-27.5 Constellation Reply Brief at 19-20.
PDF page 5
5
transmission system from adverse impacts on reliability where an Eligible Customer exceeds reliable use of the transmission system.
ODEC also agrees with the Indicated PJM TOs that PJM should clarify that (1) each new transmission service, including Firm Contract Demand Transmission Service, will be conditioned on the implementation of control technologies and protection systems that will ensure Co-Located Loads do not exceed their specified level of transmission service; and (2) necessary control technologies and protection systems may be required on both the customer’s side and the Transmission Owner’s side of the point of interconnection.6
B. The Commission Should Accept the Indicated PJM TOs’ Grid Reliance
Charge
The Indicated PJM TOs proposed a Grid Reliance Charge to reflect the fact that Co- Location Arrangements are physically connected to and synchronized to the transmission system7 and use the transmission system.8 Although some have asserted there should be no charge at all for customers that reserve zero to a de minimis amount of transmission service,9 the disagreement among parties is not focused on whether there should be a Grid Reliance Charge, but instead on how such charges should be determined.10 ODEC continues to support the Indicated PJM TOs’ Grid Reliance Charge, in addition to charges for Black Start and Regulation Services. These services may not reflect the full use or reliance on the transmission system by Co-Location Arrangements, and Co-Located Loads must pay their fair share. While other proposals might be
6 Joint Response of the Indicated PJM Transmission Owners (“Indicated PJM TOs Response”) at 7-8.7 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Hearing Order”) at P 164.8 See id. at P 177.9 Vistra Initial Brief at 21.10 See Constellation Reply Brief at 25-28 (arguing for an alternative calculation methodology).
PDF page 6
6
just and reasonable, the Indicated PJM TOs have adequately supported their proposed Grid Reliance Charge and the Commission should accept it as filed.
WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider this response as well as the requests in ODEC’s Reply Brief and accept PJM’s and the Indicated PJM Transmission Owners’ proposals for transmission service to Co-Located Loads, subject compliance filings as necessary to address the following: (1) clarification of PJM’s proposed requirement that an Eligible Customer must be designated to take transmission service on behalf of a Co-Located Load and provide PJM with an authorization from its RERRA; (2) with respect to the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the new Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the individual TOs will need to either confirm that their formula or stated rates and metrics reporting enable the direct crediting by PJM, or provide whatever revisions are necessary in order to do so;
(3) PJM and the PJM Transmission Owners will need to address how to charge regulation and black start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) the Commission consider whether any protections are needed for local utilities or TOs should they need to take the extraordinary measure of disconnecting an Eligible Customer taking service on behalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds contract demand or are called upon for Load Shedding and Curtailment.
PDF page 7
7
Respectfully submitted,
/s/ Adrienne E. Clair
Adrienne E. Clair
Jenna Cliatt
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
(202) 585-6900
(202) 585-6969 (fax)
aclair@thompsoncoburn.com
jcliatt@thompsoncoburn.com
Attorneys for Old Dominion Electric
Cooperative
Dated: April 24, 2026
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that on this 24th day of April 2026, I have caused a copy of the foregoing to be served upon each party designated on the Commission’s Official Service List for this proceeding.
/s/Adrienne E. Clair