ER26-1479-000 · 2026-04-24 · Indicated PJM Transmission Owners

Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners in response to certain parties’ protests and comments on PJM Interconnection,…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)

Docket No. ER26-1479-000

MOTION FOR LEAVE TO ANSWER AND ANSWER OF
THE INDICATED PJM TRANSMISSION OWNERS

Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”), 18 C.F.R. §§ 385.212 and 385.213, the Indicated PJM Transmission Owners1 submit this Answer in response to certain parties’ protests and comments on PJM Interconnection, L.L.C.’s (“PJM”) 60-Day Compliance Filing in the above-captioned proceeding.2

1 For purposes of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative (“PJM Transmission Owners”).
2 To the extent required, the PJM Transmission Owners respectfully move for leave to answer.  The Commission’s procedural rules generally prohibit answers to protests.  Specifically, Rule 213 states that “[a]n answer may not be made to a protest . . . unless otherwise ordered by the decisional authority.”  18 C.F.R. § 385.213(a)(2). The Commission has the discretion to waive its prohibition of answers to protests for good cause shown, i.e., to assist the Commission’s understanding and resolution of the issues raised or to ensure a complete record.  See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co., 140 FERC ¶ 61,057, at P 94 (2012); Midwest Indep. Transmission Sys. Operator, Inc., 120 FERC ¶ 61,083, at P 23 (2007); Morgan Stanley Cap. Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017, at 61,036 (2000); CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287 n.11 (1999).  This Answer is submitted to ensure a complete and accurate record.  Accordingly, good cause exists to permit this answer.

PDF page 2

2
I. ANSWER TO PROTESTS AND COMMENTS
A. Behind-the-Meter Generation
In its 60-Day Compliance Filing, PJM proposes revisions to the Behind the Meter
Generation (“BTMG”) provisions in its Open Access Transmission Tariff (“Tariff”) to comply with the Commission’s December 18, 2025 Order, which directed PJM to propose a new materiality threshold for Retail BTMG, establish a three-year transition period, and provide legacy treatment for certain existing contractual arrangements above the new threshold.3 PJM proposes to establish a materiality threshold of up to 50 MW for Retail BTMG eligibility based on the cumulative nameplate rating of generation used to serve retail load by a Network Customer4 at the at the same electrical location, excluding qualifying backup generation, while otherwise preserving existing substantive netting rules.5  Several commenters argue that a nameplate-based threshold is inappropriate and urge the Commission to adopt a materially higher threshold, such as 200 MW.6

The Commission should reject those arguments because the 50 MW threshold strikes the appropriate balance between allowing continued use of Retail BTMG and appropriate limitations to ensure reliability.  The Order expressly directed PJM to propose a new MW threshold for Retail BTMG and explained that such a threshold should reduce the reliability and resource adequacy

3
See PJM 60-Day Compliance Filing, Docket No. ER26-1479-000, at 4 (filed Feb. 23, 2026); see also PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 179, 221-224 (2025) (“Order”). 4

Terms not otherwise defined herein shall have the same meaning as set forth in the PJM Tariff. 5

PJM 60-Day Compliance Filing at 5-17.
6
See Protest of Calibrant Energy; Antora Energy, Inc.; Convergent Energy and Power; Eolian L.P.; and Mainspring Energy, Inc., Docket No. ER26-1479-000, at 6-8, 11-12 (filed Mar. 16, 2026) (collectively, the “BTMG Parties”); Comments of Crusoe Technologies LLC, Docket No. ER26-1479-000, at 2, 4-5 (filed Mar. 16, 2026) (“Crusoe”); Joint Protest and Comments of the PJM Industrial Customer Coalition, the Industrial Energy Consumers of America, and the National Railroad Passenger Corporation, Docket No. ER26-1479-000, at 5, 9, 23-33 (filed Mar. 16, 2026); Protest and Comments of Eastman Chemical Company, Docket No. ER26-1479-000, at 6 (filed Mar. 16, 2026).

PDF page 3

3
risks posed by large Retail BTMG, while allowing smaller customers to continue netting in a transparent and not unduly discriminatory manner.7  PJM reasonably selected 50 MW because that threshold aligns with the PJM Board’s definition of large load additions, preserves existing treatment for smaller and longstanding Retail BTMG arrangements, and avoids sweeping in retail customers whose grid impacts are comparatively limited.8  PJM reasonably based the threshold on generator size—measured by cumulative nameplate rating—because generator capacity is static and administrable, whereas load can fluctuate.9  The Commission should therefore reject commenters’ requests to materially increase the MW threshold or replace PJM’s brightline, nameplate-based standard with a more variable approach.

However, it is important that this threshold be paired with grandfathering provisions that appropriately recognize that industrial and commercial customers have relied on Retail BTMG rules and that eliminating the ability to continue relying on those provisions could cause them substantial financial harm.  To that end, the PJM Transmission Owners support certain proposed additions and clarifications to PJM’s grandfathering proposal, namely:

 Grandfathering treatment should extend to projects that are not yet in service and would have been eligible for Retail BTMG treatment, but have made substantial progress towards completion.

 The “existing contract” exception to the application of the new Retail BTMG rules should be construed broadly to cover a wide range of contracts and recognition of renewal rights in those contracts.

7 Order at PP 186, 221.
8 PJM 60-Day Compliance Filing at 11-13.
9 Id. at 14.

PDF page 4

4
 Grandfathering treatment should be extended to existing Retail BTMG arrangements that have been physically in service and operating for a significant period of time to avoid disrupting these long-standing arrangements.

B. Transmission Services for Co-Located Load
Consistent with the Order, PJM proposes Tariff revisions establishing the transmission- service framework applicable to Eligible Customers taking transmission service on behalf of Co- Located Load, including three new transmission service options in addition to Network Integration Transmission Service (“NITS”).10

1. The Commission Should not Mandate a Combined Interconnection
and Transmission Study Process for Co-Located Loads and Generation
In its comments, Invenergy Renewables LLC and Invenergy Thermal LLC argue that the Commission and PJM should clarify how the transmission and generator interconnection study processes can work in tandem.11  In Invenergy’s view, developers and lenders will be reluctant to commit to projects without both sets of study results showing that the project is viable and identifying expected upgrade costs, and coordinated studies would better align generation and load, improve efficiency, reduce system costs, and provide the certainty needed for co-location projects to be financed and developed at scale.12

Invenergy’s comments primarily address PJM’s initial brief in the paper hearing process imposed by the Commission in Docket Nos. EL25-49, et al.,13 and the PJM Transmission Owners will respond fully to those comments in that proceeding.  However, because Invenergy also

10 PJM 60-Day Compliance Filing at 18.
11 Comments of Invenergy Renewables LLC and Invenergy Thermal LLC, Docket Nos. EL25-49, et al., at 5 (filed Mar. 16, 2026) (“Invenergy”).
12 Id. at 4. 13 Order at PP 2, 219-220.

PDF page 5

5
included the PJM 60-Day Compliance Filing docket in the caption of its comments, the PJM Transmission Owners summarize their response here as well.

It is unclear what Invenergy is asking for here, but to the extent it is requesting that the Commission impose a combined transmission and interconnection study process for Co-Located Load and generation, the Commission should decline.  In its initial brief in the paper hearing process, PJM has already proposed a coordinated load and generation study process, with the PJM Transmission Owners conducting load integration studies and PJM performing generator interconnection and transmission service studies, as necessary.  Requiring PJM to administer a single study process goes beyond the issues set for hearing by the Commission in the Order, as well as the scope of compliance directed by the Commission in the instant proceeding. Finally, end-use load is still retail load and existing load interconnection rules set forth in state jurisdictional tariffs and agreements cannot be ignored or sidestepped.  However, there is no need for the Commission to entangle itself in questions regarding the division between its jurisdiction over interstate transmission matters and state jurisdiction over retail service in this proceeding.  The coordinated study approach proposed by PJM will provide a just and reasonable opportunity for Co-Located Load to interconnect and assess the appropriate type and level of transmission service that it wishes to obtain.

2. Use of New Transmission Services by Behind-the-Meter Generation
and Load-Only Customers
The Joint Parties14  ask the Commission to reject, or at least defer action on, PJM’s proposal to limit PJM’s new transmission service options to Co-Located Load, while excluding Retail BTMG customers and other load-only customers that can limit withdrawals from the grid unless

14 Protest of Eolian L.P.; Antora Energy, Inc.; Calibrant Energy; Convergent Energy and Power; Mainspring Energy, Inc.; and Verrus, LLC, Docket No. ER26-1479-000, at 10-15 (filed Mar. 16, 2026) (collectively, the “Joint Parties”).

PDF page 6

6
PJM revises the tariff to make the new transmission services available to BTMG and similarly situated load-only customers.15  According to the Joint Parties, BTMG-served loads and similarly flexible load-only customers are sufficiently comparable to Co-Located Load that they should have access to the same transmission service options, rather than being required to take full NITS simply because they are not connected to a generating facility with PJM interconnection rights.16 The Commission should reject the Joint Parties’ request that it reject or defer action on PJM’s proposal to limit the new transmission service options to Co-Located Load.  In the Order, the Commission made clear that the new transmission services are limited to Eligible Customers taking transmission service on behalf of Co-Located Load, and repeatedly described NITS, Firm Contract Demand Transmission Service, and Non-Firm Contract Demand Transmission Service as options available only within that Co-Located Load framework.17

While a number of PJM Transmission Owners disagree that the new transmission services are necessary at all, there is absolutely no evidence in the record to suggest that load-only customers should be entitled to utilize these transmission services.  Those customers must continue to take NITS.  Moreover, the Joint Parties’ assertion that Co-Located Load and ordinary BTMG or other load-only customers are “similarly situated” should be rejected because it ignores the line the Commission expressly drew in the Order.  The Commission did not establish a generally available transmission-service option for any customer that claims it can limit withdrawals from the grid.  Rather, it directed PJM to create those new services only for an Eligible Customer taking transmission service on behalf of Co-Located Load, which the Commission defined as load

15 Joint Parties at 10-12, 14-15.
16 Id. at 10-14.
17 Order at PP 2, 186, Ord. Para. (C).

PDF page 7

7
physically connected to an Interconnection Customer’s existing or planned generator.18  The new services are tied to generator-specific attributes that ordinary load-only customers do not share, including an associated generator, separate metering from that generator, and the ability and willingness to prevent or limit withdrawals through the co-location configuration itself.19  The Commission also declined to comprehensively address retail load interconnection more generally, confirming that the replacement rate was directed to Co-Located Load, not load-only customers as a class.20

3. Permitting Interim NITS Customers to Serve On-Site Load with On-
Site Generation During a Curtailment
The Data Center Coalition and Crusoe argue that PJM’s proposed Interim NITS framework is unworkable unless a curtailed customer may continue to serve on-site load with co-located generation.21  They contend that curtailment should limit withdrawals from the transmission system, not prevent a customer from using its own co-located generation or Retail BTMG, because otherwise Interim NITS would provide little or no practical value and significantly undermine the viability of co-location arrangements.22  They therefore urge the Commission to clarify that an Interim NITS customer may continue to use co-located generator during curtailment, including while the generator remains in the interconnection study process.23

The PJM Transmission Owners do not oppose the requested clarification that Interim NITS customers be permitted to continue serving on-site load with co-located generation during a

18 Id. at P 164.
19 Id. at PP 204-205.
20 Id. at P 170.
21 Comments of Data Center Coalition, Docket No. ER26-1479-000 at 6-7 (filed Mar. 16, 2026); Crusoe at 6-
7. 22 Data Center Coalition at 6-7; Crusoe at 6-7.
23 Data Center Coalition at 6-7; Crusoe at 6-7.

PDF page 8

8
curtailment event, provided that PJM implements appropriate safeguards to ensure that any such operation does not result in unreserved use of the transmission system or otherwise compromise reliability.  This position is consistent with the Commission’s recognition in the Order that, when curtailed, an Eligible Customer taking Interim NITS on behalf of Co-Located Load “may be able to continue to take energy from the Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”24

II. CONCLUSION
The PJM Transmission Owners respectfully request that the Commission accept this answer and that any subsequent Commission orders addressing these issues be consistent with the discussion herein.

Respectfully submitted,

/s/ Michael Kunselman

Michael Kunselman

Richard P. Sparling

Nicholas J. Cicale

Jonathan A. Namazi

Davis Wright Tremaine LLP

1301 K Street NW

Suite 500 East

Washington, DC 20005

Counsel for the FirstEnergy

  Companies

On behalf of the PJM

  Transmission Owners

Dated:  April 24, 2026

24 Order at P 201 (emphasis added).

PDF page 9

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list for the above-captioned docket, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure (18 C.F.R. § 385.2010).

Dated at Washington, DC this 24th day of April, 2026.

/s/ Deiman Flores

Deiman Flores

Davis Wright Tremaine LLP

1301 K Street, NW

Suite 500 East

Washington, DC 20005

(202) 402-4037

deimanflores@dwt.com