Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners in response to certain parties’ protests and comments on PJM Interconnection,…
Text extracted from the eLibrary original (SHA-256 8d9f348c95899746…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Reliability and curtailment · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
I. ANSWER TO PROTESTS AND COMMENTS
printed heading
I.Read this passage
A. Behind-the-Meter Generation
printed heading · Topic match: Reliability and curtailment
ER26-1479-000, at 4 (filed Feb. 23, 2026); see also PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 179, 221-224 (2025) (“Order”). 4 Terms not otherwise defined herein shall have the same meaning as set forth in the PJM Tariff. 5 PJM 60-Day Compliance Filing at 5-17. 6 See Protest of…Read this passage Filed comments: Reliability and curtailment
B. Transmission Services for Co-Located Load
printed heading · Topic match: Connecting load and generation
Transmission Services for Co-Located Load Consistent with the Order, PJM proposes Tariff revisions establishing the transmission- service framework applicable to Eligible Customers taking transmission service on behalf of Co- Located Load, including three new transmission service options in…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION The PJM Transmission Owners respectfully request that the Commission accept this answer and that any subsequent Commission orders addressing these issues be consistent with the discussion herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC this 24th day of April, 2026. /s/ Deiman Flores Deiman Flores Davis Wright Tremaine LLP 1301 K Street, NW Suite 500 East Washington, DC 20005 (202) 402-4037 deimanflores@dwt.comRead this passage