EL25-49-000 · 2026-04-24 · Northern Virginia Electric Cooperative, Inc.
Reply of Northern Virginia Electric Cooperative, Inc. to Responses to Initial Brief of PJM Interconnection, L.L.C. and to Initial Brief and Joint Responses…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
2
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
REPLY OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. TO
RESPONSES TO INITIAL BRIEF OF PJM INTERCONNECTION, L.L.C. AND TO
INITIAL BRIEF AND JOINT RESPONSES OF THE INDICATED PJM
TRANSMISSION OWNERS TO PAPER HEARING QUESTIONS
Pursuant to the Federal Energy Regulatory Commission’s (“Commission”) December 18,
2025 order (“Co-Location Order”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this reply to the responses to the initial briefs and joint responses to the paper hearing questions submitted by PJM Interconnection, L.L.C. (“PJM”)2 and the Indicated PJM Transmission Owners (“PJM Transmission Owners”).31 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, PP 219-20 (2025) (“Co-Location Order”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al. (Jan. 23, 2026) (Accession No. 20260123-3062) (Extending the due date for responses to initial briefs by seven days, from April 17, 2026, to April 24, 2026).2 PJM Interconnection, L.L.C., Initial Brief, Docket Nos. EL25-49-000, et al. (filed Feb. 23, 2026) (Accession No. 20260223-5189) (“PJM Initial Brief”).3 Indicated PJM Transmission Owners, Initial Brief and Joint Responses of the Indicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al. (filed Feb. 23, 2026) (Accession No. 20260223-5190) (“PJM TO Initial Brief”).
PDF page 3
3
I. INTRODUCTION
When the Commission issued the Co-Location Order4 ordering PJM to provide new transmission services to accommodate serving Co-Located Loads, the Commission left implementation details to be developed through this paper hearing. PJM and the PJM Transmission Owners have addressed many, but not all, of the necessary implementation details. NOVEC disagreed5 and continues to disagree that any new transmission service should be formulated for Co-Located Loads rather than requiring them to use Network Integration Transmission Service (“NITS”), largely because it is not just or reasonable for other transmission customers to subsidize Co-Located Load. But, respecting that the Commission has decided to require the development of these new variations of transmission service, NOVEC generally supported the proposals of PJM and the PJM Transmission Owners because they are designed to prevent existing transmission customers from subsidizing Co-Located Load.6
The responses to the initial briefs demonstrate that additional clarity is needed on certain threshold issues regarding which kinds of entities are or are not Eligible Customers (including whether a Load Serving Entity (“LSE”) like NOVEC can be required to serve as an Eligible Customer if a Co-Located Load or generator serving Co-Located Load were to interconnect to NOVEC’s distribution system in order to access the PJM transmission system), as well as Commission guidance on other aspects of the rates, terms, and conditions of the new transmission services. NOVEC’s comments focus on threshold issues relating to who is or must
4 See Co-Location Order.5 NOVEC, Protest, Docket No. EL25-20-000 (filed Dec. 18, 2024) (Accession No. 20241218-5285); see also NOVEC, Response to Initial Briefs, Docket Nos. EL25-49-000, et al. (filed Mar. 25, 2026) (Accession No. 20260325-5220”) (“NOVEC Brief”).6 See NOVEC Brief.
PDF page 4
4
be an Eligible Customer and on a number of issues relating to the rates, terms, and conditions of the new transmission services that require additional development.
As explained below, NOVEC respectfully requests that the Commission provide additional guidance on who may act as an Eligible Customer. NOVEC also requests that the Commission: (1) approve the use of the NITS rate for Non-Firm Contract Demand Transmission Service (“Non-Firm CDS”); (2) approve PJM’s proposal to restrict a Co-Located Load receiving Interim NITS from taking energy and capacity from the co-located generating facility when the Co-Located Load is curtailed; (3) confirm that there should be a Grid Reliance Charge; (4) consider the financial penalty proposal of the PJM Transmission Owners, subject to additional details; and (5) approve an effective date that allows all parties involved to prepare for providing services to Co-Located Load.
II. ANSWER
A. The Commission should make clear who may or must act as an Eligible
Customer and address related questions about the terms of service.
There are unanswered questions regarding the definition and role of Eligible Customer for purposes of the new transmission services for Co-Located Load. The Co-Location Order provides that it is the Eligible Customer that will take transmission service on behalf of the Co- Located Load.7 The PJM Open Access Transmission Tariff (“Tariff”), consistent with the pro forma tariff under Order No. 888, defines Eligible Customer as follows:
(i) Any electric utility … or any person generating electric energy for sale for resale … (ii) Any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a
Transmission Owner offer the transmission service, or pursuant to a
voluntary offer of such service by a Transmission Owner, is an Eligible
Customer under the Tariff . . . .87 Co-Location Order at PP 175-176; id. at n.379 (“…the replacement rate we establish in Part IV.B.4 applies to Eligible Customers taking transmission service on behalf of Co-Located Load….”).8 PJM Tariff, Part I, § 1, Definitions E-F.
PDF page 5
5
The Commission expanded on that definition in the Co-Location Order, stating that an Eligible Customer could be “for example, any person generating electric energy for resale or any retail customer taking unbundled transmission service under certain conditions…,”9 or that “subject to applicable state law, the Eligible Customer could create a corporate intermediary to serve the Co- Located Load, or the Co-Located Load, acting as an Eligible Customer, could request service from the relevant transmission owner directly”10 while referring back to the PJM Tariff definition for “the full definition of Eligible Customer….”11
Several parties raised a question about who can act as an Eligible Customer. Invenergy Renewables LLC and Invenergy Thermal LLC (collectively, “Invenergy”) asked the Commission to confirm that “where a state retail choice program results in unbundled retail access, customers may take transmission service as an Eligible Customer[,]” effectively asking when a Co-Located Load could qualify as an Eligible Customer.12 Old Dominion Electric Cooperative (“ODEC”) sought clarification as to whether it would have to provide authorization under circumstances where it is the Relevant Electric Retail Regulatory Authority (“RERRA”).13
The Commission should consider a more definitive delineation of who may be an Eligible Customer as well as the scope of the Eligible Customer’s obligations. NOVEC also seeks confirmation that it cannot be required to serve as an Eligible Customer serving Co- Located Load unless it agrees to do so. In the Co-Location Order, the Commission gives agency to the Eligible Customers who may “at their option, take a new interim, non-firm transmission
9 Co-Location Order at n.404.
10 Id. at n.407. 11 Id. at n.404.12 Invenergy Renewables LLC and Invenergy Thermal LLC, Comments, Docket Nos. EL25-49-000, et al., at 6 (filed Mar. 16, 2026) (Accession No. 20260316-5254) (“Invenergy Brief”).13 Old Dominion Electric Cooperative, Reply Brief, Docket Nos. EL25-49-000, et al., at 7 (filed Mar. 25, 2026) (Accession No. 20260325-5233) (“ODEC Brief”).
PDF page 6
6
service until all Network Upgrades necessary to provide NITS are complete” if the Eligible Customer is seeking to provide NITS or the Eligible Customer “can choose to take [Firm or Non- Firm CDS] on behalf of a Co-Located Load instead of taking NITS.”14
NOVEC is an electric distribution cooperative and LSE that serves many of the data centers in “Data Center Alley” in Northern Virginia, sometimes referred to as the “Data Center Capital of the World.” NOVEC needs to understand what obligations, if any, the Commission is intending to impose on LSEs with respect to Co-Located Load that seeks to use the new transmission services required by the Co-Location Order. NOVEC is not a PJM Transmission Owner but does own and operate a significant distribution system which has numerous points of interconnection with the transmission system in PJM’s Dominion transmission pricing zone. NOVEC relies on PJM NITS to serve all of its load, including its very significant and constantly growing data center load.
NOVEC is an Eligible Customer under the PJM Tariff’s existing definition of that term, but seeks clarification of its obligations under the Co-Location Order to act as an Eligible Customer on behalf of a Co-Located Load in the event one were to interconnect to NOVEC’s distribution system and wish to use these new transmission services:
(1) Is a Co-Located Load eligible for these new transmission services if it interconnects to an LSE’s distribution infrastructure rather than directly to the transmission system?
(2) Even assuming that a Co-Located Load that is interconnected to distribution infrastructure that is not dedicated to or part of the PJM transmission system is eligible to use these new services under the PJM Tariff, NOVEC seeks confirmation
14 Co-Location Order at P 160.
PDF page 7
7
that the Commission is not requiring an LSE like NOVEC to serve as an Eligible Customer on behalf of the Co-Located Load unless it voluntarily elects to do so. Requiring an LSE like NOVEC to serve as an Eligible Customer on behalf of a Co- Located Load carries many complications. From a legal standpoint, because the states determine who may provide retail service, sales to the Co-Located Load as the end-user must be authorized under state law and the Co-Located Load cannot be an Eligible Customer unless state law allows it to take unbundled transmission service.15 The Commission of course must respect state jurisdiction over retail rates, which means, inter alia, that the Commission cannot require LSEs to modify their retail rates to accommodate these new service and undertake the administrative burden of being an Eligible Customer for a Co-Located Load unless the LSE chooses to do so. From a compliance and liability standpoint, LSEs like NOVEC should not be subject to potential liability for the transmission costs, much less penalties for non-compliance with the Tariff’s requirements, if a Co-Located Load for which NOVEC is serving as Eligible Customer fails to meet or comply with all applicable provisions of these services, including curtailing load when required to do so. Operationally, NOVEC is uncertain as to how the Co-Located Load might be curtailed without potentially creating operational constraints that are highly sensitive to the timing and frequency of curtailment notifications. In particular, frequent notices or ones that are insufficiently in advance of required implementation could hinder effective operational planning and resource allocation. Consideration of these dynamics is important to mitigate potential disruptions and maintain reliable system operations.
From a practical and PJM Tariff standpoint, if an LSE relies on NITS to serve its load, it is NOVEC’s understanding that the Co-Located Load would have to be electrically isolated from
15 Id. P 168.
PDF page 8
8
the remainder of the LSE’s network load if the Co-Located Load seeks to use Firm CDS, Non- Firm CDS, or Interim NITS, because typically an LSE cannot use NITS for only a portion of its load unless that portion is electrically isolated from the balance of the LSE’s load.16 Electrically isolating such Load would require physical and electrical configurations that would be unique to that of Co-Located Load and could require significant upgrades or additions.
NOVEC believes that utilities should be prepared to serve all customers within their authorized service areas, but NOVEC is concerned about the implications of being required to procure transmission service other than NITS to meet the load it serves. Absent a compelling benefit to its customers or arrangements that fully protect other customers from any adverse costs or operational impact arising out of service to Co-Located Load, NOVEC would rather not act as an Eligible Customer serving Co-Located Load for any service other than NITS. NOVEC respectfully requests that the Commission confirm that that NOVEC is not obligated to apply for Firm CDS, Non-Firm CDS, or Interim NITS on behalf of Co-Located Load that is interconnected to NOVEC’s distribution facilities or connected to Dominion but within NOVEC’s service area.
B. The Commission should address questions raised during the proceeding
regarding the rates, terms, and conditions of Firm CDS, Non-Firm CDS, and
Interim NITS.
1. The Commission should approve the use of the NITS rate for Non-Firm
CDS.
The PJM Transmission Owners proposed charging the NITS rate for Non-Firm CDS.17 In responsive briefs, several participants indicated opposition to the use of the NITS rate for Non- Firm CDS.18 NOVEC supported the proposal and continues to support this proposal. Non-Firm
16 See, e.g., FERC Pro Forma Open Access Transmission Tariff, Part I, § 1.23 Network Load (stating that a customer may not designate only part of the load at a discrete Point of Delivery as Network Load).17 See PJM TO Initial Brief at 10.18 Geronimo Power, LLC, Response Brief, Docket Nos. EL25-49-000, et al., at 4-9 (filed Mar. 25, 2026) (Accession No. 20260325-5235) (“Geronimo Power Brief”); Vistra Corp., Response Brief, Docket Nos. EL25-49-000, et al., at 16-18 (filed Mar. 25, 2026) (Accession No. 20260325-5239) (“Vistra Brief”); Joint Co-Location Developers, Reply
PDF page 9
9
CDS “is a transmission service that allows an Eligible Customer taking service on behalf of Co- Located Loads to obtain non-firm, interruptible transmission service on behalf of a Co-Located Load in the event the Co-Located Generating Facility is on outage and unable to provide any of the dedicated level of energy….”19 Under PJM’s proposal, it is only available when the generator is on outage. Reservations are available “for terms ranging from one hour to one month, consistent with the terms available for non-firm [Point-to-Point Service (“PTPS”)] currently in the PJM Tariff.”20 As proposed by the PJM Transmission Owners, “the maximum rate for Non- Firm Contract Demand Service on behalf of Co-Located Load will be calculated by multiplying
(i) their reserved, non-firm contract demand amount (in MWs) by (ii) the applicable zonal NITS rate.”21 The Non-Firm CDS customer will also receive an adjustment to reflect the impact of the Grid Reliance Charge in order to prevent double-recovery.22
Based on the design proposed by the PJM Transmission Owners, the intention behind the proposal is to charge Non-Firm CDS customers only when they make a reservation to use transmission capacity on an as-available basis. This is reflected in the PJM Transmission Owners’ request for clarification that “an Eligible Customer’s initial application for a certain amount of Non-Firm Contract Demand Transmission Service would essentially serve as a ‘holding’ request, and the actual reservation and use of Non-Firm Contract Demand Transmission Service would require the Eligible Customer to submit individual requests for service in advance of the interval during which it wishes to obtain such service.”23 The PJM
Brief and Motion to Intervene Out-of-Time, Docket Nos. EL25-49-000, et al., at 20-23 (filed Mar. 25, 2026) (Accession No. 20260325-5236) (“Joint Co-Location Developers Brief”).
19 PJM Initial Brief, Illustrative Tariff at § 709.2(b).
20 PJM TO Initial Brief, Blazunas, Shafer, & Hammer Testimony, PTO-0001 at 11:12-13.21 Id. at 11:20-12:2.22 PJM TO Initial Brief at 7.23 Indicated PJM Transmission Owners, Joint Response, Docket Nos. EL25-49-000, et al., at 4 (filed Mar. 25, 2026) (Accession No. 20260325-5203) (“PJM TO Reply Brief”).
PDF page 10
10
Transmission Owners added that “the amount that PJM determines is available for a particular requested interval or intervals would presumably serve as the basis for determining the relevant charge to the Eligible Customer for Non-Firm Contract Demand Transmission Service.”24 The PJM Transmission Owners concluded by asking PJM to “confirm [that] these understandings are correct and add appropriate language to its proposed Tariff provisions.”25 Some of the opposition appears to come from a misapprehension of the proposal, which illustrates why the request for clarification by the PJM Transmission Owners should be granted. Geronimo Power, LLC (“Geronimo Power”) suggests by way of example that a “100 MW load co-located with a 100 MW generator located within a zone with a NITS and Firm Contract Demand transmission service rate of $10,000/MW/year and a Grid Reliance Charge of $2,580/MW/Year” would “pay the same amount if it reserved 100 MW of Firm Contract Demand transmission service or 100 MW of Non-Firm Contract Demand transmission service.”26 But, under PJM’s proposal, Geronimo Power’s hypothetical customer would only take and pay for Non-Firm CDS when the generator was experiencing an outage. Even under an alternative scenario where Eligible Customers had greater flexibility to mix and match Firm and Non-Firm CDS, the Eligible Customer would only pay for the actual Non-Firm CDS it receives to cover whatever it chooses not to generate or procure through Firm CDS. In contrast, the customer would pay for Firm Contract Demand Service throughout the term of its reservation regardless of its usage. The same rate thus does not equate to the same cost to the customer, as Geronimo Power seems to argue.
24 Id.25 Id.26 Geronimo Power Brief at 5.
PDF page 11
11
Other opposition to the proposal is rooted in a flawed analysis of Commission precedent and the cost-causation principle or an appeal to policy reasons. The cost-causation principle requires that all approved rates reflect to some degree the costs actually caused by the customer who must pay them, and the courts “evaluate compliance with this unremarkable principle by comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party.”27 While adhesion to the cost causation principle does not require “exacting precision,” the Commission must have an “articulable and plausible reason” to believe that the benefits are roughly commensurate with costs.28
Various parties argue that Non-Firm CDS service imposes lesser costs on the grid that should warrant a discount.29 This premise remains unproven. When the Co-Located Load is using Non-Firm CDS and is not curtailed, its use of the transmission system is comparable to the way NITS customers use it. Unlike a point-to-point transmission service product, Non-Firm CDS is not restricted to designated sources and sinks. And although under PJM’s construct Non-Firm CDS is only available when the generator is experiencing an outage, that may occur more frequently than expected. In its reply brief, the Independent Market Monitor for PJM (“IMM”) pointed out that “[g]enerators providing co-located service will not be available for 8,760 hours per year.”30 Rather, the availability factor for other PJM generators “was 83.2 percent…in 2025” and “the system would become unmanageable if all or a significant part of the data center users wanted to use non-firm CDS….”31 Unlike NITS, which “ensures the system overall is ‘proactively’ planned to a forecasted level of service and the needed resource capacity to
27 Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004); see also Old Dominion Electric Cooperative v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018).28 Illinois Commerce Commission v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).29 Geronimo Power Brief at 8-9; Joint Co-Location Developers Brief at 20-22; Vistra Brief at 16-17.30 Independent Market Monitor for PJM, Reply Brief, Docket Nos. EL25-49-000, et al., at 6 (filed Mar. 26, 2026) (Accession No. 20260326-5062) (“IMM Brief”). 31 Id.
PDF page 12
12
maintain the reliability of service is secured ahead of time[,]” Non-Firm CDS is not accounted for in models and will appear on the system frequently, but irregularly.32 PJM faces significant challenges in planning to ensure that this can be done reliably.33
Rather than contend that Non-Firm CDS imposes lesser costs on the transmission system than NITS, it would be fairer to say that it imposes costs differently. It is true that PJM will not be building upgrades to accommodate requests for Non-Firm CDS, but PJM will now be faced with the prospect of receiving and managing these requests (for as much as 20 percent of the time) for short-term transmission service. And the anticipated frequency of these requests based on generators’ likely downtime points to a greater use and reliance on the transmission system than the other parties represent.34 The Commission needs to be cautious to avoid providing “co- located generators a subsidized low cost option to use the system whenever they need backup.”35 Part of what NITS customers pay for is the ability to use the transmission system when needed. The Commission should disfavor the argument that because Non-Firm CDS is a lower priority than NITS it should necessarily have a lower cost. The practical reality is that Co- Located Load can game the system if the Commission accepts that premise. As part of the application for Non-Firm CDS, PJM studies how much it can reliably provide. If the Co-Located Load is unhappy with that result, it always has the option to request Interim NITS, NITS, or Firm CDS. Co-Located Load in areas where PJM can accommodate a large amount of Non-Firm CDS could end up with the best of both worlds, where they are very rarely curtailed but pay a subsidized rate for transmission service. If PJM later determines it can no longer accommodate
32 PJM Initial Brief, Attachment B, Abdulsalam Affidavit at P 7.33 Id. PP 9-12.34 See, e.g. Vistra Brief at 5, 19 (discussing Co-Located Load configurations that will allegedly not use transmission service or make de minimis transmission service requests).35 IMM Brief at 6.
PDF page 13
13
the required level of Non-Firm CDS, the Co-Located Load could simply switch to Firm CDS or NITS at that point. Choosing to accept the risk of curtailment could simply reflect the de minimis nature of that risk. Accordingly, the Commission should not sanction a discount from NITS simply because the risk of curtailment exists.
Vistra argues that Non-Firm CDS should receive the same rate as non-firm PTPS
customers because both services are non-firm.36 The Commission should reject this argument. In addition to a differing level of firmness,37 Non-Firm CDS differs from non-firm PTPS because it is not a point-to-point service, which Vistra does not acknowledge. It would not be appropriate to allow Non-Firm CDS the same discount as non-firm PTPS because the two products
fundamentally differ.
The Commission has said that non-firm transmission services may be charged at the same rate as NITS.38 The PJM Transmission Owners have adequately supported their proposal. The PJM Transmission Owners explained that Non-Firm CDS will “represent a superior level of service compared to non-firm PTPS.”39 In addition to that superior level of service, Non-Firm CDS have greater flexibility and do not have to pay for generation capacity.40 Those benefits, coupled with the potential reliability concerns and gaming issues, demonstrate that the NITS rate satisfies the cost-causation principle for use as the Non-Firm CDS rate.
The PJM Transmission Owners further explained that “[b]efore determining whether a discount is appropriate for Non-Firm Contract Demand Service, and if so what level it should be
36 Vistra Reply Brief at 16-18.37 PJM TO Initial Brief at 11-12.38 See Co-Location Order at P 200 (“Eligible Customers taking this interim, non-firm transmission service on behalf of Co-Located Loads would pay the NITS rate for the new service, as well as ancillary services charges and charges for black start service, but they would not be charged for generation capacity because, as interruptible loads, capacity will not be procured on their behalf until such time as the Network Upgrades are in place to serve them.”); see also PJM TO Initial Brief at 11-12.39 PJM TO Initial Brief at 12.40 Id.
PDF page 14
14
set at, it is necessary for the PJM Transmission Owners to gather data on how Non-Firm Contract Demand Service customers are utilizing the service, taking into account the intended purpose of the service, and the effect of that utilization on the system.”41 NOVEC agrees that before a discount is set, it is appropriate to consider how Non-Firm CDS customers are using the service and the effect of their utilization on the system. Without that practical experience, no one can reasonably determine whether a discount is appropriate. If the Commission were to pre- emptively order a discounted rate, the Commission would effectively be forcing existing transmission customers—which includes ordinary people struggling with affordability concerns—to bear the risk that they will subsidize large loads. In addition to the impact of transmission upgrades to accommodate large loads that are socialized to all transmission customers, large loads may also have an impact on aspects of PJM markets. NOVEC respectfully submits that as between the two types of customers that could bear that risk, the customer that should bear the risk of any mistake should be the ones receiving a special privilege to facilitate their service. The Federal Power Act is a consumer-protection statute; therefore, the Commission should protect the consumer, institute the NITS rate for Non-Firm CDS, and reserve the question for a future filing by the PJM Transmission Owners.
Finally, the Joint Co-Location Developers argue that the proposed rate would “discourage productive industrial development, if adopted.”42 It is the Commission’s obligation to ensure that rates are just and reasonable, not to provide subsidies to select, power-intensive industries at the expense of ordinary consumers. If some industries are not viable without subsidization by other customers, it is not the Commission’s role to provide them subsidies at the expense of transmission customers at-large.
41 Id. at 13.42 Joint Co-Location Developers Brief at 22.
PDF page 15
15
2. When a Co-Located Load using Interim NITS is curtailed, it should not
be able to take energy from the co-located generating facility.
After filing its initial brief, PJM explained in a March 16, 2026, stakeholder presentation that Co-Located Load taking Interim NITS will not have the rights to the capacity and energy from any specific co-located generation in its proposed Interim NITS construct when curtailed.43 Many commenters objected to this aspect of PJM’s proposal.44 The arguments boil down to an assertion that the lack of those rights defeats the purpose of co-location or makes Interim NITS unworkable or unfair in some way. These arguments are without merit and should be disregarded.
Interim NITS is a temporary service provided while the transmission system is prepared to provide full NITS to the Co-Located Load. What is important to remember is that the end goal is NITS—the Co-Located Load is in that sense no different than any other large load. Proximity of a generator to the load is irrelevant when the Co-Located Load is being served under network service. PJM has represented that it will “endeavor to dispatch the co-located generation to the maximum extent to reduce, but not eliminate, the risk of curtailment to this interim NITS load” but if load is curtailed, it is curtailed.45 Unlike Co-Located Load served by Firm or Non-Firm CDS, all of Interim NITS Co-Located Load is served by the transmission system, which means it does not have a dedicated generator that has given up its Capacity Interconnection Rights (“CIR”) and is no longer a Capacity Resource. In the case of an existing resource with a must- offer requirement, to do what PJM’s opponents ask seems to be incompatible with the
43 PJM, Co-Located Load Use Cases, Presentation at 12 (Mar. 16, 2026), available at: 20260316-item-02--- colocated-load-use-cases---presentation.pdf (“Co-Location Presentation”).44 See, e.g., Data Center Coalition, Response, Docket Nos. EL25-49-000, et al., at 3 (filed Mar. 25, 2026) (Accession No. 20260325-5208) (“Data Center Coalition Response”); Enchanted Rock, LLC, Reply Brief and Protest, Docket Nos. EL25-49-000, et al., at 7-10 (filed Mar. 25, 2026) (Accession No. 20260325-5191); Joint Co- Location Developers Brief at 18-19; Advanced Energy United and Solar Energy Industries Association, Reply Brief, Docket Nos. EL25-49-000, et al., at 19-21 (filed Mar. 25, 2026) (Accession No. 20260325-5237).45 Co-Location Presentation at 15.
PDF page 16
16
obligations of a Capacity Resource, if it makes itself exclusively available to one customer on demand. Even for new generation, setting aside the fact that it too would become a Capacity Resource, the request does not make sense. If the Co-Located Load is taking NITS, it is using the transmission system for service and if PJM has determined that power is insufficient or not deliverable (i.e., the load is curtailed), generation is unavailable to serve the Co-Located Load. Accordingly, NOVEC respectfully requests that the Commission approve PJM’s
proposal. NOVEC is concerned that to do otherwise would devalue the concept of NITS. Worse, it invites the same argument when the Co-Located Load is being served by full NITS, which would end with some NITS customers being more equal than others, in the interest of validating the decision to co-locate with a generator. Let NITS remain NITS and Interim NITS be just a temporary, non-firm version of NITS. There is no need to blend Interim NITS with Firm and Non-Firm CDS. The Commission specifically created several co-location options. If prospective customers find that Interim NITS is not desirable, they have the flexibility to pursue a combination of Firm and Non-Firm CDS. As a Firm CDS customer, the Co-Located Load even has the option to transition to NITS. When the Co-Located Load is a full NITS customer, it would not be able to call upon the co-located generator to avoid curtailment. It makes little sense to create a right exclusive to a temporary service just as it makes little sense to blur the distinctions between co-location options.
3. The Commission must require a Grid Reliance Charge.
In the Co-Location Order, the Commission found that “Co-Located Loads benefit from black start service even if they have zero net energy withdrawals and Eligible Customers taking one of the new transmission services on behalf of Co-Located Load must be assessed for this
PDF page 17
17
service based on gross demand basis at the existing Tariff rate.”46 The Commission made an identical finding for regulation service.47 In Questions 3 and 4 of the Co-Location Order, the Commission asked whether there should be a charge to reflect that reliance and how it should be determined.48 In response, the PJM Transmission Owners proposed the Grid Reliance Charge. Thus, the Commission has two questions before it, whether there should be a charge and what should that charge be? There should be a charge, and the Commission should set the charge high enough to reflect the true reliance of the grid, rejecting the “minimum system” method as proposed by Constellation and Vistra’s ratio methodology.49
a. A charge to reflect Co-Located Load’s reliance on the
transmission system is necessary.
Any suggestion that there should not be any charge at all should be rejected outright. The propriety of some charge, whether the Grid Reliance Charge or not, is rooted in the services that even Co-Located Load with zero net energy withdrawals requires from the transmission system. These critical services rely on the existence and operation of the transmission system to be delivered and used. Black Start Service “is the ability of generators to start without an outside electric supply or remain operating when disconnected from the transmission system.”50 The PJM Tariff requires all transmission customers to take Black Start Service.51 Black Start Service is critically important, as it “encompasses the well-planned, coordinated, and deliberate actions
46 Co-Location Order at P 185.47 Id. P 184.48 Id. P 219(3),(4).49 Constellation Energy Generation, LLC, Reply Brief, Docket Nos. EL25-49-000, et al., at 25-28 (filed Mar. 25, 2026) (Accession No. 20260325-5238) (“Constellation Brief”); see Vistra Brief, Attachment A, Stadelmeyer Affidavit.50 Co-Location Order at P 185; PJM Tariff, Part I, § 1, Definitions A-B (Black Start Service: “‘Black Start Service’ shall mean the capability of generating units to start without an outside electrical supply or the demonstrated ability of a generating unit with a high operating factor (subject to Transmission Provider concurrence) to automatically remain operating at reduced levels when disconnected from the grid.”).51 PJM Interconnection, L.L.C., 176 FERC ¶ 61,080, P 3 (2021).
PDF page 18
18
facility operators must take after such a harmful system collapse (of whatever geographic scope) has actually occurred, to bring the grid back into operation in a safe, prudent, and incremental manner.”52 Because of the nature of the service, units capable of providing Black Start Service must be located throughout PJM.53 PJM stated that there were 154 of these units in 2021.54 The units work together to re-energize the transmission system:
Once started, Black Start Service resources can energize select transmission
facilities connecting to the next most critical generators or other critical
loads that need to be brought online. This cycle establishes and extends
service areas to ensure the balance between load and generation, and then
brings together (i.e., synchronizes) those separate “islands” until the grid is
fully restored.55
Without the transmission system to stitch such units together, they could not bring the transmission system (or the load and non-black start generation using it) back online following a blackout.56 Because transmission customers in PJM already pay for the right to use the
transmission system, the current formula for Black Start Service does not include a delivery component.57
Regulation service is also necessary for Co-Located Loads, which are “unlikely to have a perfect load factor, and it will therefore be necessary for PJM to use regulation service to maintain the power balance between the five-minute intervals of the real-time energy market.”5852 PJM Interconnection, L.L.C., Transmittal Letter, Docket No. ER21-1635-000, at 4 (filed Apr. 7, 2021) (Accession No. 20210407-5217) (emphasis in original) (“Black Start Filing”).53 Black Start Filing, Attachment A, Bryson Affidavit at PP 7-8. 54 Black Start Filing, Attachment B, Hauske Affidavit at P 8.55 PJM Interconnection, L.L.C., 192 FERC ¶ 61,190, P 2 (2025).56 Co-Location Order at P 183 (Noting that ancillary services pass through transmission lines).57 PJM Tariff, Schedule 6A; see also Co-Location Order, Commissioner Chang, concurring, at P 6 (“Because the charges for those services only account for the provision of those discrete ancillary services, they do not contribute to the actual cost of building, operating, or maintaining the grid, or the Co-Located Load’s explicit reliance on the PJM system. Black start and regulation service charges are nearly inconsequential. Thus, just paying black start and regulation service charges does not constitute the Co-Located Loads paying for their ‘fair share’ of the cost of maintaining and operating the transmission system. Furthermore, under such a scenario, a Co-Located Load would not pay for a portion of PJM’s administrative costs, which are typically included in transmission service rates, even though the Co-Located Load benefits from services provided by PJM.”).58 Co-Location Order at P 184.
PDF page 19
19
“This variability will exist even if the Co-Located Load takes no energy from the transmission system.”59 Schedule 3 of the PJM Tariff states that:
Regulation and Frequency Response Service is accomplished by
committing resources whose output is raised or lowered (predominantly
through the use of automatic generating control equipment) and by other
non-generation resources capable of providing this service as necessary to
follow the moment-by-moment changes in load. The obligation to maintain
this balance between resources and load lies with the Transmission
Provider.60
This service too, requires the transmission system. Nor does it have a delivery component.
In its reply brief, Geronimo Power argues that the delivery of Black Start Service and regulation service does not require the transmission system.61 Geronimo Power contends that because Black Start generators are called upon to restart the grid and are located in various locations, Black Start generators “are not, as the PJM Transmission Owners seem to imply, delivering Black Start Service to discrete points on the grid.”62 Vistra’s witness Ms. Stadelmeyer similarly ignores the necessity of the transmission system to deliver ancillary services.63 Black Start units are effectively delivering Black Start Service to every part of the grid. The fact that there is no delivery component simply reflects the fact that all load besides Co-Located Load in PJM would otherwise cover the cost of transmission service required for Black Start Service. Geronimo Power also implies that regulation service is not delivered to a discrete part of the grid because it is provided on a zonal basis.64 Geronimo Power’s and Vistra’s assertions are belied by the Commission’s recognition that these ancillary services “pass through transmission
59 Id.60 PJM Tariff, Schedule 3.61 Geronimo Power Brief at 12. Geronimo Power alternates between arguing that there should be no Grid Reliance Charge and arguing that the Grid Reliance Charge proposed by the Indicated PJM TOs is not just and reasonable.62 Id. at 13.63 Vistra Brief, Attachment A, Stadelmeyer Affidavit at 8:15-10:2.64 Geronimo Power Brief at 13.
PDF page 20
20
lines.”65 Geronimo Power’s misapprehension leads it to correctly observe that the PJM Transmission Owners have not “demonstrate[d] that there [is] a separate delivery component to black start and regulation services.”66 That is precisely correct—the services do not have a delivery component, which is why the Commission asked whether there should be a charge, as they nonetheless rely on the transmission system, and the Commission was concerned that Co- Located Loads would not be paying their “fair share” of the cost of maintaining and operating the transmission system.
There is a benefit simply to being connected to the transmission system. The Commission’s question anticipates that possibility, as it asks whether there should be an additional charge “reflecting that the Co-Location Arrangement is physically connected and synchronized to the PJM transmission system?”67 Constellation and Vistra both limit their inquiry to the role of the transmission system as the provider of ancillary services. Ms. Stadelmeyer asserts that the Grid Reliance Charge should be “based on the benefits those customers receive from the grid in supporting black start and regulation services only,” referring to customers who reserve no transmission service or a de minimis amount of service.68 That narrow view ignores the benefit of the transmission system as a “Plan B” to Co-Located Load. Even if the Co-Located Load draws only from the generator it is sited with, its connection to the transmission system allows it to draw on the transmission system if needed. For example, if the co-located generating facility trips offline, the transmission system is available to provide the necessary power to bring it back online. The Co-Located Load could reserve Non-Firm CDS if
65 Co-Location Order at P 183.66 Geronimo Power Brief at 13. 67 Co-Location Order at P 219(4).68 Vistra Brief, Attachment A, Stadelmeyer Affidavit at 10:6-9.
PDF page 21
21
needed and it could apply for Firm CDS. The option to do so is a benefit, and unless the Grid Reliance Charge reflects the value of that option, Co-Located Load is being undercharged. The optionality associated with interconnection is possibly more valuable than the
provision of ancillary services. If the only obstacles to islanding generation were regulation and Black Start Service, then islanding data centers would be commonplace. The IMM’s comments regarding generator outage time illustrate that no generator can operate indefinitely without maintenance and no generator can be guaranteed to operate without a forced outage.69 One way to consider the value of a grid interconnection would be to consider the difference between the cost of a proposed co-located configuration and the cost to island the co-located configuration with the same level of service reliability as being interconnected to the transmission system. That would presumably involve redundant generation, additional emergency equipment, and the investment to make the co-located generating facility able to start without external power. The difference between the two costs is the cost that the Co-Located Load avoids, and thus benefits from the interconnection. While that may not be reducible to rates, it is one measure of the magnitude of the benefit that Co-Located Load actually accrues from the existence of the transmission system.
Vistra’s suggestion that the Commission may not find any version of the Grid Reliance Charge necessary is incongruent with the benefits that Co-Located Load will draw from the
69 IMM Brief at 5 (“The equivalent availability data (EAF is the equivalent availability factor) for all types of generators in PJM demonstrate that the non-firm service would have to be used on a regular basis. Generators providing co-located service will not be available for 8,760 hours per year. The available factor (EAF) for PJM resources was 83.2 percent (1 – EAF is 16.8 percent) in 2025. Given the scale of potential data center users of non- firm CDS, the system would become unmanageable if all or a significant part of the data center users wanted to use non-firm CDS, and the service would not be available on a consistent basis and would therefore be meaningless.”); Monitoring Analytics, LLC, 2025 Annual State of the Market Report for PJM, Volume 2: Section 5 Capacity Market, at 366 (Table 5-39) (Mar. 12, 2026) (available at https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025.shtml) (“2025 State of the Market Report”).
PDF page 22
22
transmission system.70 “Such [a] scenario[] would fail to recognize the benefits Co-Located Loads receive from the grid and risk shifting system costs to other customers.”71 Consistent with the cost-causation principle, NOVEC urges the Commission to find that a charge is necessary. b. The Commission should consider the PJM Transmission Owners’
proposed Grid Reliance Charge, but under no circumstances
should it adopt Constellation’s or Vistra’s proposals, either of
which would result in an unreasonably low rate that does not
reflect the extent of the Co-Located Load’s reliance on the
transmission system.
The next question is what the charge should be. Aside from the Commission’s inherent section 206 authority to set its own replacement rate, the PJM Transmission Owners, Constellation, and Vistra have all suggested possible frameworks. NOVEC previously indicated that it believed the Commission should accept the Grid Reliance Charge as filed by the PJM Transmission Owners, and further suggested that the Commission may want to consider a PJM stakeholder process to determine whether the rate should be changed in the future.72 NOVEC generally maintains that position, although NOVEC reserves the right to update its position in response to new developments, testimony, and pleadings in this proceeding. NOVEC’s principal concern remains ensuring that existing transmission customers do not subsidize Co-Located Load, which requires a complete understanding of the costs imposed on the grid and the benefits drawn from the grid by Co-Located Load. That understanding may evolve as aspects of the co- location regime becomes more concrete.
1. Constellation’s proposal should be rejected.
Constellation’s witness Mr. Ming proposes a “minimum system” method for determining “the costs of constructing wires to connect all customers, i.e., customer-driven costs” which he
70 Vistra Brief at 22.71 Co-Location Order, Commissioner Chang, concurring, at P 7.72 NOVEC Brief at 10.
PDF page 23
23
submits should be the basis for the Grid Reliance Charge.73 Mr. Ming explains that a minimum system is “a theoretical electricity system designed only to connect each customer and deliver a de minimis amount of power.”74 It is the “the minimum size of all electricity system components (e.g., poles, conductors, transformers, etc.) that could be used by the utility to recreate its system and connect each customer to the grid.”75
Mr. Ming makes several arguments for why a “minimum system” method is appropriate, none of which pass muster. Constellation argues that the minimum system method is cost- aligned because Co-Located Load benefits from the existence of the wires but, “by definition, does not impose any demand on the PJM system.”76 This necessitates the development of a “customer-driven” rather than “demand-driven” basis to allocate costs. But Mr. Ming’s proposal is not cost-aligned with the use of Black Start Service or Regulation Service. Black Start Service implicates a significant portion of the grid, and it is not clear from the testimony whether Mr. Ming’s “minimum transmission system in PJM” corresponds to the transmission equipment needed to provide Black Start Service, which spans the PJM region.77 In particular, units are geographically dispersed and, in the event of a blackout, would have to work in concert across the PJM transmission system to restore power. Black Start Service is a high cost service that provides an invaluable guarantee that service can be restored safely in the event of a blackout. It relies on the existence and durability of the transmission system in a way that Constellation’s “minimum system” methodology does not capture. Mr. Ming’s analysis also does not consider the inherent benefit associated with being interconnected to the transmission system.78 The
73 Constellation Brief, Attachment 1, Ming Testimony at 14:16-17.74 Id. at 14:19-20.75 Id. at 14:21-15:2.76 Id. at 15:10-11.77 Id. at 19:3-4.78 Supra at 20-21.
PDF page 24
24
option to use the entire transmission system by reserving transmission service when needed is its own benefit and must be accounted for.
Mr. Ming argues that his proposal has been used for distribution purposes in alignment with the cost-causation principle, even as he admits that the method is “generally not used in the context of transmission system cost allocation and rate design.”79 Mr. Ming references several uses in distribution cost allocation, but does not provide any examples of the method being used in the transmission context. This suggests that there may not be any and that the methodology is not appropriate for transmission cost allocation.80 The methodology is also out of step with the Commission’s directives in its December 18, 2025, Co-Location Order. Both Commissioner Rosner and Commissioner Chang stated in their concurrences that the goal was to make Co- Located Load pay its fair share of the grid. A fair share of transmission costs must recognize Co- Located Load’s reliance on the entire transmission system, not a hypothetical, curated subset of transmission facilities.
Finally, Mr. Ming’s reasoning for his six percent estimate of the PJM transmission system for the minimum transmission system does not seem to reflect the usual results of his own methodology.81 He explained that in the distribution context, “a typical range of results may show that between 30% – 50% of distribution costs are driven by the number of customers on the system.”82 He tries to explain away the disparity by claiming that “[a]pplying the minimum system method to the transmission system would definitionally yield a smaller fraction than the distribution-level values” because “transmission system components are much larger than
79 Constellation Brief, Attachment 1, Ming Testimony at 16:9-10.80 Which belies Constellation’s own assertion in its brief that the “minimum system” method is a “well-established methodology.” Constellation Brief at 26.81 Constellation Brief, Attachment 1, Ming Testimony at 19:3-4.82 Id. at 17:22-18:2.
PDF page 25
25
distribution system components, so the minimum system is a smaller fraction of total transmission system costs.”83 If components of the transmission system are much larger than distribution system components, then the corresponding minimum transmission system should also be larger. Further, the argument that “no utilities…classify any transmission costs to the customer cost driver, meaning they are implicitly assuming a minimum system value of 0% for the transmission system” and so a “minimum system” study applied to a transmission system should be much less than the 25.8 percent proposed by the PJM Transmission Owners does not make sense.84 Mr. Ming had just contended that transmission customers traditionally use the transmission system, which meant that there has never been a reason to try to divide costs between those caused by demand and customers.85 No entity made the attempt to allocate costs in the way that Mr. Ming describes, but it does not follow that the lack of an attempt means it is zero. The Commission typically uses rolled-in pricing to allocate costs because all those who rely on the transmission system are deemed to benefit from the integrated network.86 The minimum system method is inconsistent with Commission precedent on cost allocation, so an argument about how it should be applied because it was not applied has no persuasive power.
2. Vistra’s proposal would violate the cost-causation principle
and should be rejected.
Vistra proposes to use the percentage of PJM’s total monthly billings that relate to Black Start and Regulation charges as a proxy for the amount of transmission system costs associated
83 Id. at 18:6-10.84 Id. at 18:11-15.85 Id. at 16:9-19.86 Kansas City Power and Light Co., 3 FERC ¶ 61,254, at 61,685 (1978) (“We reaffirm the view that the rolled- in method of cost allocation is favored except in exceptional circumstances.”); Municipal Energy Agency of Nebraska v. Public Service Company of Colorado, 190 FERC ¶ 61,158, P 9 (2025) (“The Commission's longstanding policy ‘favors a roll-in of rates on integrated transmission systems, absent special circumstances.’ Network facilities such as the Power Pathway provide benefits to all network users by their nature, and so network transmission customers pay for these network facilities through rolled-in pricing.”) (internal citations omitted).
PDF page 26
26
with the transmission system’s role in delivering those ancillary services.87 Vistra reasons that this principle is sound because the “vast majority of the costs of PJM’s total monthly billing are based on the provision of actual transmission service, not the transportation of black start and regulation service over the grid.”88 Ms. Stadelmeyer estimated that to be 0.54% of the total PJM Annual Transmission Revenue Requirement.89
The problem with using this ratio is that it has no relation to the benefit being received. Although it is an ancillary transmission service, Black Start Service is a cost-based rate based on the aggregate costs of various generators providing the service. It does not have a delivery component, nor does regulation service. A Grid Reliance Charge, to address the use of the transmission system in ensuring that a Co-Located Load could receive those ancillary services, should be roughly commensurate to the use of the transmission system for that purpose. The ratio method advanced by Vistra arbitrarily confuses the cost of Black Start and Regulation services with the cost of the transmission infrastructure necessary for customers to receive them. The revenue requirements of units to be able to provide Black Start Service has no direct relation to the cost of the transmission system. The same is true for regulation service. The Commission should reject Vistra’s proposal.
4. The Commission should consider the financial-penalty structure
proposed by the PJM Transmission Owners in their response to PJM’s
Initial Brief.
NOVEC supports a financial penalty to complement the proposed disqualification penalties proposed by PJM.90 The PJM Transmission Owners did not initially propose a financial
87 Vistra Brief at 22-23.88 Vistra Brief at 23; see also Vistra Brief, Attachment A, Stadelmeyer Affidavit at 10:6-12:4.89 Vistra Brief, Attachment A, Stadelmeyer Affidavit at 11:13-14.90 NOVEC Brief at 13.
PDF page 27
27
penalty.91 In their response, the PJM Transmission Owners “propose a financial penalty charge structure with two components: (1) a base penalty charge, which applies to each individual hour in which the reserved transmission service limit is exceeded, and (2) a penalty ratchet, which applies when such exceedances occur repeatedly.”92 When the Co-Located Load exceeds the amount of its transmission reservation, the base penalty charge will be assessed for any hour during which at least one five-minute interval occurs where the customer exceeds that limit. A penalty using a ratchet design escalates those charges as the frequency of that unreserved uses increases. The PJM Transmission Owners do not provide any further details. NOVEC believes it could generally support this framework, subject to the PJM Transmission Owners providing further information about the proposal. NOVEC reserves the right to update its position as new information becomes available and other proposals for a financial penalty are made available for consideration.
C. The Commission should approve an effective date that accounts for the time necessary for utilities and other relevant regulators to install policies,
procedures, and equipment required to align with and implement the order.
NOVEC supports an effective date that supports the timing necessary to align all necessary processes, policies, and operations with implementing the order. As to the proposals by the Data Center Coalition and Constellation to phase-in Interim NITS if the other services cannot be expedited,93 NOVEC does not oppose the phased-in implementation of Interim NITS since that service will ultimately result in the provision of NITS under the existing PJM Tariff, provided that appropriate safeguards, including any necessary control technologies, are in place to ensure that the reliability of the transmission system is not impaired.
91 PJM TO Initial Brief at 20.92 PJM TO Reply Brief at 12.93 Constellation Brief at 6-9; Data Center Coalition Response at 9.
PDF page 28
28
III. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission accept this reply to the responses to the initial briefs of PJM and the PJM Transmission Owners and adopt a replacement rate consistent with the PJM and PJM Transmission Owners’ proposals and NOVEC’s comments on those proposals. Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to Northern Virginia Electric Cooperative, Inc.
Dated: April 24, 2026.
PDF page 29
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated at Washington, D.C. this 24th day of April, 2026.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com