EL25-49-000 · 2026-04-24 · Northern Virginia Electric Cooperative, Inc.

Reply of Northern Virginia Electric Cooperative, Inc. to Responses to Initial Brief of PJM Interconnection, L.L.C. and to Initial Brief and Joint Responses…

Text extracted from the eLibrary original (SHA-256 a4f90194904c303f…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 3
  2. II. ANSWER p. 4
  3. A. The Commission should make clear who may or must act as an Eligible p. 4
  4. B. The Commission should address questions raised during the proceeding p. 8
  5. C. The Commission should approve an effective date that accounts for the time p. 27
  6. III. CONCLUSION p. 28

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

AND TO INITIAL BRIEF AND JOINT RESPONSES OF THE INDICATED PJM TRANSMISSION OWNERS TO PAPER HEARING QUESTIONS Pursuant to the Federal Energy Regulatory Commission’s (“Commission”) December 18, 2025 order (“Co-Location Order”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully…
Read this passage Filed comments: Filing procedure

I. INTRODUCTION

printed heading · Topic match: Connecting load and generation

NOVEC also requests that the Commission: (1) approve the use of the NITS rate for Non-Firm Contract Demand Transmission Service (“Non-Firm CDS”); (2) approve PJM’s proposal to restrict a Co-Located Load receiving Interim NITS from taking energy and capacity from the co-located generating facility…
Read this passage Filed comments: Connecting load and generation

II. ANSWER

printed heading

II.
Read this passage

A. The Commission should make clear who may or must act as an Eligible

printed heading · Topic match: Connecting load and generation

From a legal standpoint, because the states determine who may provide retail service, sales to the Co-Located Load as the end-user must be authorized under state law and the Co-Located Load cannot be an Eligible Customer unless state law allows it to take unbundled transmission service.15 The…
Read this passage Filed comments: Connecting load and generation

B. The Commission should address questions raised during the proceeding

printed heading · Topic match: Connecting load and generation

Vistra Brief at 5, 19 (discussing Co-Located Load configurations that will allegedly not use transmission service or make de minimis transmission service requests). 35 IMM Brief at 6. 13 the required level of Non-Firm CDS, the Co-Located Load could simply switch to Firm CDS or NITS at that point.
Read this passage Filed comments: Connecting load and generation

C. The Commission should approve an effective date that accounts for the time

printed heading

The Commission should approve an effective date that accounts for the time necessary for utilities and other relevant regulators to install policies, procedures, and equipment required to align with and implement the order.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission accept this reply to the responses to the initial briefs of PJM and the PJM Transmission Owners and adopt a replacement rate consistent with the PJM and PJM Transmission Owners’ proposals and NOVEC’s…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 24th day of April, 2026. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.com