EL25-49-000 · 2026-04-24 · Maryland Office of People's Counsel

Reply Protest of Maryland Office of People's Counsel to PJM Interconnection, L.L.C. initial brief and responsive pleadings

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM INTERCONNECTION, L.L.C.
DOCKET NOS. EL25-49-000
                          EL25-49-001

REPLY PROTEST OF THE MARYLAND OFFICE OF PEOPLE’S COUNSEL ON PJM’S PROPOSED TERMS AND CONDITIONS

April 24, 2026
DAVID S. LAPP
PEOPLE’S COUNSEL

William F. Fields
Deputy People’s Counsel

Philip L. Sussler
Senior Assistant People’s Counsel

Mark S. Byrd
Assistant People’s Counsel

PDF page 2

1
Pursuant to the Commission’s December 18, 2025 order setting an April 17, 2026 deadline for replies,1 which was extended one week by notice issued January 23, 2026, the Maryland Office of People’s Counsel (“MPC”) respectfully submits the following reply regarding PJM Interconnection, L.L.C.’s (“PJM”) initial brief (hereinafter, “PJM Initial Brief”) and responsive pleadings submitted in the above captioned proceeding. INTRODUCTION

PJM’s co-location proposals in this docket have major implications for Maryland’s residential ratepayers due to the potential impact on capacity market prices. The impact on existing customers depends on whether and how co-located arrangements between new large loads and existing generation effects supply in the Base Residual Auction (“BRA”) or effects procurement targets in PJM’s planned reliability backstop procurement (“RBP”). This distinction is substantial considering the BRA will allocate costs across the system, whereas the RBP, as currently under consideration in the PJM stakeholder process, may allocate costs to individual electric distribution companies (“EDCs”) and/or load serving entities (“LSEs”) on a pro rata or other basis.2 As described by PJM’s Independent Market Monitor, co-locating data center loads with existing

1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”).
2  See Reliability Backstop Procurement Design, PJM Staff (April 2026) at 9, https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260416/20260416-item-05---pjm-reliability- backstop-procurement-design---pjm-presentation.pdf.

PDF page 3

2
generation reduces the supply of capacity to the BRA, thereby increasing capacity prices.3

Additionally, PJM’s co-location proposals with respect to existing generation are inconsistent between this docket and the compliance filing in Docket No. ER26-1479- 000. Whereas PJM’s compliance filing in Docket No. ER26-1479-000 proposes tariff revisions that would facilitate new large loads co-locating with existing generators, PJM’s filing in this docket suggests that only new generation is eligible for the new transmission services.4 These inconsistencies render it impossible to determine the effect of these proposals on ratepayers. The Commission should therefore require PJM to clarify whether these co-location rules are intended to apply to co-location arrangements undertaken with existing baseload generation so the effect of these transmission services on ratepayers can be determined and, if so, how adverse impacts on existing (particularly residential) customers can be mitigated.

The Commission should not accept co-location rules that facilitate the
interconnection of large load data centers to the detriment of residential ratepayers. Such an outcome would be at direct odds with the statement of principles signed by the National Energy Dominance Council within the White House and thirteen governors of

3 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 (Sep. 24, 2024) at 1, https://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf.
4 Compare PJM, Proposed Tariff Revisions, Docket No. ER26-1479-000 (Feb. 23, 2026) (defining “Co- Located Generating Facility” as “an existing or planned Generating Facility that is physically connected to a Co-Located Load…”) with PJM Initial Brief at 79 (explaining that it is unlikely that generation intended to serve Co-Located Load will be constructed and operational before June 1, 2029).

PDF page 4

3
states within PJM5 stating that PJM’s tariff revisions should reflect how costs are allocated to data centers to protect residential customers. It would also contradict the White House’s ratepayer protection pledge that companies will build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from, new or otherwise additive power plants.6

BACKGROUND
1. Show Cause Order:
On December 18, 2025, the Commission determined that PJM’s tariff is unjust and unreasonable, explaining generally that the tariff:

does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load, including generators serving Co-

Located Load in a configuration with special protection schemes to prevent the Co-Located Load from taking energy from the transmission system.7

The Commission directed PJM to revise its tariff to provide clarity regarding the responsibilities of existing interconnection customers seeking to serve co-located load using their generating facilities.8 The Commission also directed PJM to file tariff changes specifying that an interconnection customer seeking to serve co-located load using an

5 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm. _

6 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, https://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ (Mar. 4, 2026).
7 Show Cause Order at P 249.
8 Id. P 225.

PDF page 5

4
existing generating facility must bear the costs of all network upgrades that PJM finds are necessary to preserve transmission system reliability for existing transmission customers.9

Furthermore, the Show Cause Order also required that PJM define “Co-Located Load” as a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.”10 The Commission clarified that an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its Capacity Interconnection Rights for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving network integration transmission service (“NITS”).11

The Commission’s Show Cause Order in this proceeding also directed PJM to revise its tariff to allow eligible customers seeking to take NITS on behalf of co-located load to take a new interim, non-firm transmission service until all Network Upgrades necessary to provide NITS are complete. The Commission also directed PJM to offer two other new transmission services—a firm contract demand transmission service and a non- firm contract demand transmission service—that an eligible customer can choose to take on behalf of a co-located load instead of taking NITS.”12

9 Id. P 176.
10 Id. P 164.
11 Id. P 230.
12 Id. P 160.

PDF page 6

5
2. White House and PJM Governors Statement of Principles and White House Pledge

On January 15, 2026, the National Energy Dominance Council within the White House and thirteen governors of states within PJM signed the Statement of Principles urging PJM to expeditiously file proposed tariff revisions with the Commission that reflect a set of principles for how generation capacity for data centers should be procured, and how costs should be allocated to data centers to protect residential customers.13 Specifically, under these principles, PJM should hold a procurement for capacity through the conduct of at least one reliability backstop auction (“RBA”) to procure new capacity resources, with the costs of such new capacity going primarily to load serving entities with new data centers that have not self-procured new capacity or agreed to be curtailable.14

On March 4, 2026, the White House issued the Ratepayer Protection Pledge that companies will build, bring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full cost of those resources whether by building, or buying from new or otherwise additive power plants.15 The pledge also provides that where possible, these companies will also add more capacity that serves the broader public by increasing supply.16

13 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.
14 Id. at 1.
15 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, https://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ (Mar. 4, 2026).
16 See id.

PDF page 7

6

3. PJM Board Letter

On January 16, 2026, the PJM Board of Managers (“Board”) issued a decisional letter expressing that PJM’s system is at higher risk than ever due to the PJM’s capacity market clearing short of its reliability requirement for the first time in history in the 2027/2028 BRA.17 The Board determined that this outcome is unacceptable and warrants corrective action through initiation of a reliability backstop procurement and a holistic review of investment incentives in PJM’s markets in 2026, among other initiatives.

4. PJM Compliance Filing in Docket No. ER26-1479-000
PJM’s February 23 Compliance Filing in Docket No. ER26-1479-000 generally sets forth the relative obligations of project developers seeking to serve co-located load, and PJM. The proposal defines “Co-Located Generating Facility” as “an existing or planned Generating Facility that is physically connected to a Co-Located Load,” and “Co-Located Load” as “a configuration that refers to end-use customer load that is physically connected to the facilities of an existing or planned Generating Facility on the Project Developer’s side of the Point of Change in Ownership to the Transmission Provider’s Transmission System.”18 Importantly, these definitions appear to accommodate not only new generators, but existing generators seeking to serve co- located load.

17 Board Letter at 1 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.
18 Proposed Tariff Revisions, Part I, Definition of Co-Located Load.

PDF page 8

7
Additionally, the February 23 Compliance Filing in Docket No. ER26-1479-000 proposes tariff revisions requiring that “[a] Project Developer whose planned modifications include Co-Located Load configuration shall be required to enter into a Necessary Studies Agreement with Transmission Provider in the form set forth in Tariff, Part IX, Subpart G.”19 The proposed tariff revisions would require a Project Developer to provide the Transmission Provider with “the amount of reduction to Capacity Interconnection Rights to facilitate the Co-Located Load configuration.”20 The proposed revisions also provide that:

Project Developer shall be responsible for the costs of any modifications or Network Upgrades identified by Transmission Provider, as applicable, as a result of the change to the Interconnection Service Agreement or

Generation Interconnection Agreement to serve Co-Located Load,
including to reflect any reduction in Capacity Interconnection Rights.21

“Capacity Interconnection Rights” (“CIRs”) are previously defined in PJM’s tariff as “the rights to input generation as a Generation Capacity Resource into the Transmission System at the Point of Interconnection where the generating facilities connect to the Transmission System.”22 Thus, the proposed revisions appear to accommodate new generators seeking to serve co-located load, as well as existing generators seeking to serve co-located load by reducing their CIRs, and, thus, their ability to input generation onto PJM’s transmission system.

19 Id. Part VIII, Subpart A, section 401.H.3.b.
20 Id. Section 401.H.3.b.i.c.
21 Id. Section 401.H.3.b.iii.
22 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - C - D (40.1.1).

PDF page 9

8
5. PJM’s Initial Brief
PJM’s Initial Brief proposes non-rate terms and conditions for the new
transmission services required by the Show Cause Order (Interim NITS and the two Contract Demand Transmission Services). PJM states that Interim NITS “will significantly affect the PJM Load Forecast and expected demand.”23 PJM seeks an effective date of June 1, 2029, for tariff revisions implementing the three new transmission services. In support of this effective date, PJM explains that it is unlikely that generation intended to serve Co-Located Load will be constructed and operational before June 1, 2029, which suggests that PJM does not intend for existing load to be eligible for these Co-Located Load transmission services.24

PROTEST
As explained by the Commission in the Show Cause Order, PJM’s tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co- Located Load.25 However, in light of the recent issuance of Statement of Principles issued jointly by the White House and thirteen governors of states within PJM, the Ratepayer Protection Pledge, and PJM’s proposed Reliability Backstop Procurement applicable to

23 PJM Initial Brief at 79.
24 PJM Initial Brief at 79.
25 See Show Cause Order at P 2.

PDF page 10

9
new capacity resources, PJM’s proposed terms and conditions remain without sufficient clarity and consistency.

The Statement of Principles directed PJM to hold a reliability backstop auction to procure new capacity resources, which PJM has proposed to implement in two phases— the first in September 2026 and the second in March 2027.26 The Statement of Principles further urges that costs of such new capacity should go primarily to load serving entities with new data centers that have not self-procured new capacity or agreed to be curtailable.27 The Ratepayer Protection Pledge also commits the major data center developers to procure new capacity resources to serve their needs. Thus, the thrust of the Statement of Principles and the Ratepayer Protection Pledge is that generally new data centers should pay for new capacity.

Under this framework, new data centers that are not served by self-procured new co-located generation could be subject to higher costs from the load serving entity as result of the reliability backstop auction. But PJM’s proposed terms and conditions do not explain how existing capacity resources that shift to co-located arrangements with new data centers would be treated relative to the PJM’s proposed RBP. For example, it is unclear whether capacity from existing generators that remove themselves from the capacity market and enter co-location arrangements with new data center load would need to be replaced with new capacity through the RBP or in the regular BRA to serve

26 See Statement of Principles at 1; See Reliability Backstop Procurement Design, PJM Staff (April 2026) at 2, https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260416/20260416-item- 05---pjm-reliability-backstop-procurement-design---pjm-presentation.pdf.

27 See Statement of Principles at 1.

PDF page 11

10
existing load. Additionally, it is unclear whether new data center load that co-locates with an existing generator will be included in the cost allocation of the reliability backstop procurement.

If the capacity of existing generation that shifts to serve new co-located data center load is added to the BRA, ratepayers would be saddled with enormous costs that should be assigned to the co-located load, in contravention of the Statement of Principles and the Ratepayer Protection Pledge. For example, analysis by PJM’s Independent Market Monitor concluded that if 1,000 UCAP MW of nuclear capacity in Maryland was removed—due to shifting to serving a co-located load for example—total market revenues for the 2025/2026 BRA would increase by more than $3.6 billion.28 Yet PJM’s compliance filing provides no explanation as to how such costs would be paid by new co- located data center load rather than being shifted to existing ratepayers. PJM’s proposed terms and conditions thus leave significant and fundamental questions unanswered with respect to how existing generation can serve new co-located data center load. Without providing more details regarding how the proposal will align with PJM’s plans for the RBA, PJM’s proposal remains unclear and inconsistent with the Statement of Principles underpinning the RBA. This lack of clarity and consistency causes PJM’s proposed terms and conditions to remain unjust and unreasonable. At a minimum, the Commission should require PJM’s proposal to be consistent across the co-

28 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 (Sep. 24, 2024) at 3, https://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf.

PDF page 12

11
location compliance dockets so the effect on ratepayers may be understood and demonstrate how its proposal meets the ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge.

CONCLUSION
The issuance of the Statement of Principles by the White House and thirteen governors of states within PJM calling for an RBA to serve new data center load and the Ratepayer Protection Pledge are salient intervening events that have occurred since the Show Cause Order issued. However, despite the significance of PJM’s work toward implementing an RBP, fundamental issues surrounding how existing generators that shift to serve Co-Located Load under PJM’s proposed tariff revisions will be treated relative to the RBP remain unaddressed. As a result, PJM’s proposed revisions do not provide the clarity and consistency required by the Show Cause Order. PJM’s proposed terms and conditions thus are unjust and unreasonable without a complete picture of how they will interact with PJM’s planned RBP. The Commission should clarify how its proposal meets the ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge and defer action on the proposed revisions until after PJM proposes tariff revisions to implement its planned RBP.

Respectfully submitted,

DAVID S. LAPP
PEOPLE’S COUNSEL

PDF page 13

12
William F. Fields
Deputy People’s Counsel

Philip L. Sussler
Senior Assistant People’s Counsel

/electronic signature/
Mark S. Byrd
Assistant People’s Counsel

Office of People’s Counsel
6 St. Paul Street, Suite 2102
Baltimore, Maryland 21202
(410) 767-3908

PDF page 14

13
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing pleading to be served upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated this 24th day of April, 2026.

/s/ electronic signature----_____
Mark S. Byrd