EL25-49-000 · 2026-04-24 · Maryland Office of People's Counsel

Reply Protest of Maryland Office of People's Counsel to PJM Interconnection, L.L.C. initial brief and responsive pleadings

Text extracted from the eLibrary original (SHA-256 633fb5fbd822c868…). Download the original from the official source.

Contents · 3 sections
  1. INTRODUCTION p. 2
  2. BACKGROUND p. 4
  3. CONCLUSION p. 12

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM INTERCONNECTION, L.L.C.
Read this passage

INTRODUCTION

printed heading · Topic match: Cost allocation

ER26-1479-000 proposes tariff revisions that would facilitate new large loads co-locating with existing generators, PJM’s filing in this docket suggests that only new generation is eligible for the new transmission services.4 These inconsistencies render it impossible to determine the effect of…
Read this passage Filed comments: Cost allocation

BACKGROUND

printed heading · Topic match: Connecting load and generation

ER26-1479-000 proposes tariff revisions requiring that “[a] Project Developer whose planned modifications include Co-Located Load configuration shall be required to enter into a Necessary Studies Agreement with Transmission Provider in the form set forth in Tariff, Part IX, Subpart G.”19 The…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Cost allocation

The Commission should clarify how its proposal meets the ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge and defer action on the proposed revisions until after PJM proposes tariff revisions to implement its planned RBP.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated this 24th day of April, 2026. /s/ electronic signature----_____ Mark S.