EL25-49-000 · 2026-04-24 · Eolian, L.P.Antora Energy LLCCalibrant Energy and 3 others

Second Reply Brief of Eolian, L.P., et al

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)
Docket Nos. EL25-49-000
)

         EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)

         AD24-11-000
)
Constellation Energy Generation, LLC

)

         EL25-20-000
v.

)

         (Consolidated)
PJM Interconnection, L.L.C.

)

SECOND REPLY BRIEF OF JOINT CO-LOCATION DEVELOPERS

Pursuant to the Federal Energy Regulatory Commission’s (Commission) December 18, 2025 order (Co-Location Order),1 Eolian, L.P. (Eolian), Antora Energy, Inc., Calibrant Energy (Calibrant), Mainspring Energy, Inc. (Mainspring), U.S. Energy Storage Coalition, and Verrus, LLC (Verrus) (collectively, the Joint Co-Location Developers) submit this reply to the response briefs filed in the captioned dockets on March 25, 2026. The brief draws upon the affidavit of Andrew Levitt and Aniruddh Mohan of the Brattle Group on behalf of Eolian, at Attachment A.2 As highlighted in the Independent Market Monitor (IMM)’s response brief, PJM is proposing to restrict the availability of non-firm contract demand service on the basis of vague reliability concerns that are neither supported nor explained. But as the affidavit demonstrates, workable non-firm service offerings that are broadly available are fully consistent with reliable system operation, as demonstrated in other regions that are rapidly moving to implement non-firm transmission service offerings.

The Commission should not bow to the IMM’s and PJM’s thinly-supported attempts to undermine the Co-Location Order. PJM’s proposal, if adopted, would fall short of the

1 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order). 2 Attach. A, Supplemental Affidavit of Andrew Levitt & Aniruddh Mohan on Behalf of Eolian, L.P. (Levitt & Mohan Aff.).

PDF page 2

2
Commission’s goal of “ensuring that all Americans (and all American businesses) have access to affordable, reliable, and secure electricity.”3 As other regions are demonstrating, non-firm transmission service holds significant potential to address the speed-to-power challenge while maintaining a reliable electricity system. We therefore reiterate our request for the Commission to require PJM to establish workable Non-Firm Contract Demand Service (Non-Firm CDS) rules free from arbitrary and punitive terms that discourage their use, and Interim Network Integration Transmission Service (Interim NITS) rules that allow load to rely on co-located supply if it is not offering into the capacity market. By following through on the pathbreaking Co-Location Order, the Commission can achieve its goals of ensuring that all loads can connect to the transmission system in a timely, orderly, and non-discriminatory manner.

I. ARGUMENT
A. A broad range of stakeholders support full implementation of the Co-
Location Order.

A broad range of stakeholders, representing the parties aiming to engage in co-location arrangements as both load and generation, support robust implementation of the Co-Location Order. Their support demonstrates that a broad range of developers stand ready to achieve the Commission’s goals in the Co-Location Order of efficient and cost-effective load and generation development should the Commission require PJM to enable a workable, fair, and reliable service pathway. Specifically, these parties share our concerns that PJM and the PJM Transmission Owners’ proposals contravene the letter and spirit of the Co-Location Order and the Commission’s other requirements by:

3 Interconnection of Large Loads to the Interstate Transmission System, 195 FERC ¶ 61,045, Order Regarding Intent to Act at P 4 (2026).

PDF page 3

3
• limiting the availability of Non-Firm CDS to generator outages;4
• limiting the ability of Interim NITS customers to serve their load from co-located generators during curtailment conditions;5

• setting the Non-Firm CDS rate at the same level as the higher-quality Firm Contract Demand Service (Firm CDS) rate;6

• threatening inadvertent misoperation with draconian penalties;7 and
• delaying implementation, without justifying why such delay is necessary.8
The Commission should address these concerns in adopting a replacement rate, directing PJM to establish new transmission services that are commercially workable and therefore will result in their widespread use.

B. The Commission must adopt a Grid Reliance Charge that is cost justified.
In addition to these concerns, we also agree with Constellation, Vistra, and Geronimo Power that the proposed Grid Reliance Charge “is derived from an unsound methodology that violates cost causation principles”9—a point that we did not raise in our initial brief. The testimony of Zachary Ming on behalf of Constellation explains that the PJM “Transmission Owners attribute the full depreciation costs for a variety of transmission components (i.e. towers and fixtures, poles and fixtures, overhead conductors, etc.) that are sized to meet the actual peak

4 See Advanced Energy United & Solar Energy Industries Association March 25, 2026 Reply Brief at 5-10; Constellation March 25, 2026 Reply Brief at 10-12; Data Center Coalition March 25, 2026 Response Brief at 4-6; Vistra March 25, 2026 Response Brief at 25.
5 See Advanced Energy United & Solar Energy Industries Association March 25, 2026 Reply Brief at 19-21, Data Center Coalition March 25, 2026 Response Brief at 4-6; Enchanted Rock March 25, 2026 Reply Brief and Protest at 8-10. Note that such a limit is not proposed in the tariff language, but PJM stated to stakeholders that it plans to impose such a limit. See, e.g., Enchanted Rock March 25, 2026 Reply Brief and Protest at 2, 6-7.
6 Geronimo Power March 25, 2026 Response Brief at 4-9; Vistra March 25, 2026 Response Brief at 16-18.
7 Constellation March 25, 2026 Reply Brief at 18-21; Data Center Coalition March 25, 2026 Response Brief at 7-8; Vistra March 25, 2026 Response Brief at 29-30.
8 Constellation March 25, 2026 Reply Brief at 6-9; Data Center Coalition March 25, 2026 Response Brief at 9; Vistra March 25, 2026 Response Brief at 5-12. 9 Constellation March 25, 2026 Reply Brief at 25; see also Geronimo Power March 25, 2026 Response Brief at 9- 15; Vistra March 25, 2026 Response Brief at 18-23.

PDF page 4

4
demand requirements of the PJM system, even though customers paying the GRC, by definition, do not impose any demand or withdraw any energy from the PJM system.”10

The Joint Co-Location Developers stand ready and willing to pay our fair share of
transmission system costs. But part of the point of the new service framework is to reduce the need for new transmission infrastructure. Rates for the new services should not be premised on costs of infrastructure that is not needed to serve customers of these new services. Zachary Ming proposes an alternate cost calculation framework that follows the Commission’s cost causation principles.11 The Commission should direct the PJM Transmission Owners to adopt a Grid

Reliance Charge based on that methodology.
C. The Commission should not allow unsubstantiated reliability concerns to
defeat implementation of the Non-Firm CDS product required by the Co-Location
Order.

The IMM leans heavily on PJM’s testimony to argue that PJM cannot reliably offer the
transmission services required by the Co-Location Order.12 PJM asserts that Non-Firm CDS must be offered only “as a standby product” available “only ‘under limited circumstances.’”13 Its position appears to rest on the unexplained premise that offering non-firm transmission service under normal conditions involves widespread reliance on Remedial Action Schemes to control withdrawals. Reliance on Remedial Action Schemes, PJM contends, will create “complexity”14

10 Constellation March 25, 2026 Reply Brief, Attachment 1, Testimony of Zachary Ming (Ming Test.) at 12.
11 Id. at 14-15.
12 See IMM March 25, 2026 Reply Brief at 6 (arguing that, based on PJM’s statements, “there can be no such service as non-firm CDS that is fully consistent with maintaining a reliable PJM transmission system” and “the system would become unmanageable if all or a significant part of the data center users wanted to use non-firm CDS,” and further asserting that “[i]t is clear from PJM’s filing that Interim NITS . . . is not consistent with PJM’s normal transmission planning process and imposes potentially significant risks on the PJM system.”); see also id. at 2 (“some of the Commission’s defined transmission services cannot work”; “non-firm CDS and Interim NITS create significant reliability risks for the transmission system”; “the December 18th Order represents a set of dramatic changes in the nature of transmission service in PJM, not all of which are workable consistent with maintaining the reliable operation of the PJM system.”). 13 PJM Initial Brief at 10 (citing Attach. B, Affidavit of Dr. Sami Abdulsalam (Abdulsalam Aff.) ¶ 14).
14 Id. at 34-35 (“The control technologies and protection systems necessary to provide Non-Firm Contract Demand Transmission Service (and Interim NITS) is emblematic of the complexity associated with Non-Firm Contract

PDF page 5

5
that “introduces significant risks,”15 including that “unintended protection system misoperation . . . could lead to cascading events.”16

PJM’s and the IMM’s claims are based on the mistaken assumption that increasing the number of customers taking non-firm transmission service will proportionally increase system reliance on Remedial Action Schemes. Rather, in the attached testimony, Levitt and Mohan demonstrate that customers taking non-firm transmission service will not implicate widespread reliance on Remedial Action Schemes because customers can instead generally rely on simpler withdrawal-limiting protection systems internal to facilities to comply with curtailment requirements.17 Further, Levitt and Mohan explain that PJM’s proposal to limit Non-Firm CDS availability does not follow logically from its concerns with the reliability of Remedial Action Schemes because PJM’s limitations will increase the time during which loads must rely on facility-level protection systems and Remedial Action Schemes. Last, Levitt and Mohan show that experience from other regions confirms that non-firm transmission service can be provided without the limitations PJM seeks to impose. Specifically, Southwest Power Pool (SPP) and the Electric Reliability Council of Texas (ERCOT) are each developing non-firm services like those envisioned in the Co-Location Order—and on a much faster timeline than that proposed by PJM—without raising the purported reliability concerns that PJM and the IMM point to.18

1. PJM and the IMM’s claims about Remedial Action Schemes do not
justify limiting the availability of Non-Firm CDS.

Demand Transmission Service from an operations and planning perspective”); id. at 10 (“the complexities associated with the provision of Non-Firm Contract Demand Transmission Service call for relying on such service as a standby product only ‘under limited circumstances.’” (quoting Abdulsalam Aff. ¶ 14) (emphasis added)); id. at 60 (“the complexity introduced by the necessary control technology and protection systems (e.g., RAS) introduces significant risks, including possible failure to communicate material information about such protective technology or system” (citation omitted)).

15 Id. at 60.
16 Id. at 10 (citing Abdulsalam Aff. ¶ 12).
17 Levitt & Mohan Aff. at 9, 11-13.
18 Id. at 5-8.

PDF page 6

6

PJM contends that Non-Firm CDS should be offered only during a limited number of hours due to reliability risks from over-reliance on Remedial Action Schemes.19 This argument is flawed for several reasons.

First, the IMM and PJM elide a distinction between simple withdrawal-limiting protection systems that are required by PJM for sites taking non-firm transmission service, and standard Remedial Action Schemes. Levitt and Mohan emphasize that there is an important difference between the two.20 Unlike standard Remedial Action Schemes, which monitor and control components across the grid, simple withdrawal-limiting protection systems monitor and control only facility-internal components, monitoring flows, adjusting consumption or generation at the site level, and disconnecting from the grid if necessary. In this way, while both systems are designed to prevent unauthorized withdrawals from the grid, they operate at different levels of the electrical grid. A facility-level protection scheme operates on a level comparable to a home’s main circuit breaker. A standard Remedial Action Scheme is more like fast-acting air traffic control—it reacts to events in one area to manage the flow across a different part of the system to prevent overloads.

This means that simple withdrawal-limiting protection systems can be relied upon much more extensively than standard Remedial Action Schemes without creating the same complexities and interdependencies.21 And in fact, reliance on simple withdrawal-limiting protection systems under PJM’s proposal will extend beyond Non-Firm CDS customers: customers taking Firm CDS while self-supplying a portion of their load will also rely on simple

19 See PJM Initial Brief at 10 (citing Abdulsalam Aff. ¶ 14).
20 Levitt & Mohan Aff. at 11-13.
21 Id. at 13 (“Because of its simplicity and localized scope, it would appear on first principles that extensive installation of withdrawal-limiting protection systems would not introduce the complexity that is associated with standard RASs.”).

PDF page 7

7
withdrawal-limiting protection systems to prevent withdrawals above their contracted level.22 Nevertheless, PJM does not impose limits on when a Firm CDS customer may self-supply a portion of their load, nor does it voice concerns about the ability to serve Firm CDS customers reliably.

Second, PJM and the IMM ignore the redundancy built into the proposed service
construct. The co-location arrangements contemplated by the Co-Location Order entail redundancy in the required protection systems.23 This redundancy is designed to protect against failure and renders misoperation, already unlikely, even more improbable.

Third, limiting the scope of Non-Firm CDS scheduling to generator outages, as PJM
proposes, will increase reliance on simple withdrawal-limiting protection systems rather than decrease it. This is because withdrawal-limiting protection systems are only active when the customer cannot withdraw, i.e., because no transmission service has been scheduled. By limiting Non-Firm CDS to periods of generator outage, PJM’s proposal increases the frequency with which a customer will not be authorized to withdraw, thereby increasing the time for which such mechanisms must be relied upon. As Levitt and Mohan explain, “[i]t therefore follows that narrowing eligibility for N[on] F[irm] CDS scheduling does not decrease complexity.”24 Fourth, to the extent that PJM is concerned about managing the potential for interactions among standard Remedial Action Schemes that are monitoring and controlling elements on the bulk transmission system (as distinct from simple withdrawal-limiting protection systems), it

22 Id. at 13-14. There is also no need for protection systems of this nature, which exist simply to limit withdrawals consistent with transmission service limits, to be temporary as PJM claims. See id. at 13 (citing Abdulsalam Aff. ¶ 10 (“The temporary nature of such a protection system for this type of firm service is necessary to ensure the integrity and reliable operation of the transmission system as a whole since protection systems are designed based on system conditions anticipated at that time and will continue to change as system conditions evolve.”)). Levitt and Mohan note that “it is unclear why such a simple system would need to evolve with system conditions.” Id.
23 The PJM Transmission Owners recommend, and we agree, that “[a]ll [Special Protection Schemes] and [Remedial Action Schemes] should be fully redundant.” PJM Transmission Owners Initial Brief at 23.
24 Levitt & Mohan Aff. at 14.

PDF page 8

8
should limit the arming of such Remedial Action Schemes, or avoid installing them in the first place, and instead maximize use of pre-contingency Non-Firm CDS curtailment through scheduling.25 Reliance on pre-contingency curtailment is similar to how SPP and ERCOT envision curtailment under the non-firm transmission services that they are developing, described in further detail below.

For these reasons, PJM’s and the IMM’s concerns do not “call for relying on” Non-Firm CDS “as a standby product” only.26 The Commission should instead require PJM to establish a Non-Firm CDS product consistent with the requirements of the Co-Location Order.

2. Non-firm transmission services proposed by SPP and ERCOT show
that non-firm transmission service can be offered reliably.

Other grid operators are developing non-firm transmission service options without the limitations that PJM and the IMM claim are needed.27 Specifically, SPP and ERCOT are developing non-firm services similar to those proposed in the Co-Location Order, showing that non-firm service can be offered reliably on an as-available basis and implemented quickly. Levitt and Mohan explain that SPP recently filed tariff revisions in Docket No. ER26- 1323 to offer a new non-firm Conditional High Impact Large Load Service (CHILLS) that would allow non-firm transmission service that is curtailable in the face of insufficient transmission capacity.28 Unlike PJM’s Non-Firm CDS product, however, SPP plans to make CHILLS broadly available during all non-constrained hours, rather than limit use to periods when an associated

25 Id. at 14-15.
26 See PJM Initial Brief at 10.
27 See IMM March 25, 2026 Reply Brief at 2 (“some of the Commission’s defined transmission services cannot work”); PJM Initial Brief at 10 (“the complexities associated with the provision of Non-Firm Contract Demand Transmission Service call for relying on such service as a standby product only ‘under limited circumstances.’”).
28 Levitt & Mohan Aff. at 5-6 (referencing SPP, Filing, Docket No. ER26-1323-000 (filed Feb. 10, 2026)).

PDF page 9

9
generation resource is on outage.29 In addition, unlike PJM’s proposal for Interim NITS,30 SPP does not restrict customers taking CHILLS from relying on co-located capacity or energy.31 Moreover, the SPP Transmission Owner Group supports CHILLS, explaining that “CHILLS has numerous guardrails, including curtailability, that would ensure SPP’s continued ability to maintain grid reliability.”32 The SPP Market Monitoring Unit also supports acceptance of SPP’s CHILLS proposal “as a just and reasonable way to effectuate SPP’s goals.”33

Levitt and Mohan also explain that ERCOT staff have developed a proposal by which a Provisional Controllable Load Resource (P-CLR) can withdraw power from the transmission network on a non-firm basis and subject to curtailment as part of ERCOT’s ongoing “Batch Zero” reforms to interconnect large loads.34 According to Levitt and Mohan, ERCOT’s existing Controllable Load Resource (CLR) construct enables curtailment of loads on a nodal basis in security-constrained economic dispatch (SCED) for resolving constraints.35 The P-CLR proposal builds on the CLR construct by allowing loads to accelerate interconnection if they choose to use the transmission system on an as-available basis and curtail to resolve constraints as necessary.36 Importantly, Levitt and Mohan note that PJM’s Non-Firm CDS would include more reliability

29 Id. at 6.
30 Enchanted Rock March 25, 2026 Reply Brief and Protest at 6-7 (“PJM has clearly indicated to its stakeholders that when it actually implements Interim NITS, it intends to ensure that ‘Co-located load taking Interim NITS service will not have rights to the capacity/energy from any specific co-located generation,’ and that ([sic]‘[i]f curtailed, [Eligible Customer] cannot take energy from co-located generator.’” (citations omitted)).
31 Levitt & Mohan Aff. at 6.
32 Southwest Power Pool Transmission Owner Group, Comments, Docket No. ER26-1323-000, at 2 (filed Mar. 3, 2026).
33 Southwest Power Pool Market Monitoring Unit, Comments, Docket No. ER26-1323-000, at 6 (filed Mar. 3, 2026).
34 Levitt & Mohan Aff. at 7-8 (citing ERCOT, Item 9.1: Batch Study Update, at 4 (April 20-21, 2026), https://www.ercot.com/files/docs/2026/04/13/9.1-Batch-Study-Update.pdf). The proposal is in final stages, and ERCOT is targeting a June 1, 2026 Board vote to finalize the design. Id. at 7.
35 Id. at 7.
36 Id. (citing ERCOT, Item 9.1: Batch Study Update, at 4 (April 20-21, 2026), https://www.ercot.com/files/docs/2026/04/13/9.1-Batch-Study-Update.pdf).

PDF page 10

10
screening than ERCOT’s proposed P-CLR program because PJM proposes to screen non-firm reservations in advance.37

SPP’s and ERCOT’s proposed non-firm transmission service offerings show that transmission service can be provided on a non-firm and as-available basis. PJM’s own proposed implementation of Interim NITS also demonstrates that non-firm transmission service need not be limited to periods of outage for the co-located generator as PJM has proposed for Non-Firm CDS. While PJM’s Interim NITS proposal suffers from other flaws, PJM has proposed to make it broadly available during normal operating conditions, and has not claimed that doing so will compromise reliability.

SPP and ERCOT have also shown that non-firm transmission service can be implemented quickly. Unlike PJM’s requested 2029 effective date, SPP requested a July 1, 2026 effective date for CHILLS,38 while ERCOT hopes to implement P-CLRs as soon as 2027.39 Neither PJM nor the IMM has described any PJM-specific conditions that would prevent PJM from promptly offering non-firm transmission service available during normal conditions in a similar manner to SPP or ERCOT.

3. The Commission must enforce the requirements of the Co-Location
Order.
The Co-Location Order proposed a commonsense solution to a critical and pressing problem. The Commission must not allow unsubstantiated reliability concerns to dilute or delay the Co-Location Order’s promise. Instead, the Commission must reject PJM’s attempt to limit

37 Id.
38 SPP, Filing, Docket No. ER26-1323-000, at 1-2 (filed Feb. 10, 2026). 39 Levitt & Mohan Aff. at 8 (citing ERCOT, Large Load Interconnection Batch Study Workshop #7, at 25 (April 9, 2026), https://protect.checkpoint.com/v2/r01/___https://www.ercot.com/files/docs/2026/04/09/ERCOT-Large-Load- Batch-Study-Workshop7-20260409_v03.pptx).

PDF page 11

11
the availability of Non-Firm CDS and require PJM to establish a Non-Firm CDS product available during normal system conditions as required in the Co-Location Order.

Respectfully submitted,
/s/ Eric Stoutenburg
Eric Stoutenburg

Chief Development Officer
Eolian L.P.

988 Howard Ave. Suite 200
Burlingame, CA 94010

eric.stoutenburg@eolianenergy.com
/s/ Noah Long
Noah Long
Director, State and Regulatory Affairs
Antora Energy, Inc.
200 West De Vargas St
Santa Fe, NM 87501
noah.long@antora.com

/s/ Matt Barnes
Matt Barnes
Chief Commercial Officer
Calibrant Energy
4830 W. Kennedy Blvd, Suite 600
Tampa, Florida 33609
matthew.barnes@calibrantenergy.com

/s/ Brian Kauffman
Brian Kauffman
Director, Wholesale Market Development
Mainspring Energy, Inc.
3601 Haven Ave.
Menlo Park, CA 94025
brian.kauffman@mainspringenergy.com

PDF page 12

12
/s/ Noah Roberts
Noah Roberts
Executive Director
U.S. Energy Storage Coalition
1299 Pennsylvania Ave NW
Washington, D.C. 20004
noah@energystorage.org

/s/ Jeff Bladen
Jeff Bladen
Head of Energy
Verrus, LLC
918 N Rengstorff Ave.

Mountain View, CA 94043

bladen@verrusdata.com

PDF page 13

13
CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.

Dated: April 24, 2026
/s/ Eric Stoutenburg
Eric Stoutenburg

Chief Development Officer
Eolian L.P.

988 Howard Ave. Suite 200
Burlingame, CA 94010

eric.stoutenburg@eolianenergy.com

PDF page 14

Attachment A

PDF page 15

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 1 of 16
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Large Loads Co-Located at Generating
Facilities
Docket No. EL25-49-000 et al.
SUPPLEMENTAL AFFIDAVIT OF
ANDREW LEVITT AND ANIRUDDH MOHAN
ON BEHALF OF
EOLIAN, L.P.
April 24, 2026

PDF page 16

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 2 of 16
I. QUALIFICATIONS
1
Our names are Andrew Levitt and Aniruddh Mohan. We have previously submitted the Affidavit 2

dated March 25, 2026, in this Docket EL25-49-000 et al.
3
II. ASSIGNMENT
4
We were asked by Eolian, L.P. to supplement our Affidavit dated March 25, 2026, to offer 5

additional perspectives on the reliability and timeline implications of the proposed new 6

transmission services in PJM’s Initial Brief in Docket No. EL25-49-000 et al. 7

III. BACKGROUND
8
As part of its compliance filing to FERC in Docket EL25-49-000, in February 2026, in an 9

accompanying Initial Brief, PJM set out illustrative tariff language and supporting positions for 10

three new service categories for generators serving co-located load: Non-Firm Contract Demand 11

Transmission Service (“Non-Firm CDS” or “NFCDS”), Interim Network Integration 12

Transmission Service (“Interim NITS”), and Firm Contract Demand Service (“Firm CDS”).1 13

PJM also submitted supporting affidavits addressing planning, operations, market design, and 14

implementation timing.
15
Since then, a number of stakeholders have submitted responses to PJM’s Initial Brief. We submit 16

this Supplemental Affidavit in response to the timing and transmission reliability issues PJM and 17

other stakeholders have raised before the Commission regarding the impact of non-firm services. 18

IV. SUMMARY
19
Since PJM has taken steps in its Initial Brief and compliance filing to create new transmission 20

services for co-located loads, a minority of stakeholders have raised concerns that provision of 21

these new transmission services would be inconsistent with the safe and reliable operation of the 22

1 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order).

PDF page 17

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 3 of 16
transmission system.2 In this Supplemental Affidavit, we find that the concerns raised do not 1

provide evidence that provision of NFCDS or Interim NITS would be inconsistent with reliable 2

system operations. To the contrary, we point to similar non-firm services developed in other 3

regional transmission organizations (“RTOs”) as evidence that such services can be offered and 4

implemented reliably. We also note that non-firm services being developed in other RTOs have 5

many of the enhancements we previously proposed to PJM in our prior Affidavit dated March 6

25, 2026. We then note that these services in other RTOs are being implemented on a faster 7

timeline than that proposed by PJM. Moreover, PJM has long provided non-firm point-to-point 8

transmission service without causing the reliability concerns voiced by these stakeholders. 9

We also find that PJM’s Initial Brief and its Supporting Affidavits have made unclear and often 10

conceptually inconsistent arguments regarding the reliability implications of Interim NITS and 11

NFCDS that have led to comments citing potential risks from provision of non-firm service.3 12

PJM suggests that its requirement to use protection systems to limit withdrawals at facilities 13

taking CDS implies complexity that warrants narrow limitations on scheduling of NFCDS. The 14

PJM Independent Market Monitor has asserted that, due to complexity, extensive deployment of 15

NFCDS could become “unmanageable.”4 However, we show that PJM’s argumentation is 16

flawed, that NFCDS scheduling therefore could be allowed at any time without increasing 17

complexity from protection systems (and potentially reducing it), and that the use of the required 18

protection systems does not imply any reliability issues due to widescale adoption of CDS. 19

In particular, PJM’s Initial Brief does not sufficiently distinguish between types of protection 20

systems. For facilities taking CDS, the protection system required by PJM monitors and controls 21

conditions internal to those facilities in order to limit withdrawals at all times. By contrast, a 22

standard Remedial Action Scheme (RAS) monitors and controls disparate parts of the bulk 23

transmission system to avoid overloads there. Even though standard RAS is not required for a 24

2 PJM Independent Market Monitor (“IMM”) Reply Brief at p.2 claims the December 18th Order represents a set of dramatic changes in the nature of transmission service in PJM, not all of which are workable consistent with maintaining the reliable operation of the PJM system.”
3 PJM IMM Reply Brief at p.6 claims “Interim NITS is not a preferred path forward because it is not consistent with PJM’s normal transmission planning process and imposes potentially significant risks on the PJM system.” As evidence, it cites PJM’s Initial Brief at p. 60, stating that “the complexity introduced by the necessary control technology and protection systems (e.g. RAS) introduces significant risks.”
4 PJM IMM, Reply Brief at p.6.

PDF page 18

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 4 of 16
facility taking non-firm transmission, PJM repeatedly cites limitations on the feasible scale of 1

RAS installations as a rationale to limit the scope of NFCDS and to justify the interim nature of 2

Interim NITS.5 We address these conceptual issues as they relate to reliability risk to provide 3

clarity to the Commission in the implementation of its order in Dockets EL25-49-000 et al. 4

V. ASSESSMENT OF RELIABILITY IMPLICATIONS AND
5
IMPLEMENTATION TIMELINE OF PJM’S PROPOSED NEW
6
TRANSMISSION SERVICES
7
PJM’s Independent Market Monitor (“IMM”) claims that the “Commission’s defined 8

transmission services cannot work given the potentially very large load additions that could 9

request service, given the critical importance of maintaining a reliable transmission grid….”6 10

They also claim that the Commission’s “December 18th Order represents a set of dramatic 11

changes in the nature of transmission service in PJM, not all of which are workable consistent 12

with maintaining the reliable operation of the PJM system. In particular, non-firm CDS and 13

Interim NITS create significant reliability risks for the transmission system.”7 14

We assess these claims and find no evidence that new transmission services ordered by the 15

Commission and proposed by PJM, especially non-firm transmission services, are unworkable 16

and create significant reliability concerns. We also find further evidence to support the assertion 17

in our prior affidavit that NFCDS scheduling eligibility can be extended to all hours. 18

5 For example, PJM’s Initial Brief, pp. 10–11 says that NFCDS should be a standby product only used “under limited circumstances.” As evidence for this it cites the complexity associated with provisions of NFCDS due to permanent protection systems such as a RAS on the PJM transmission system. PJM’s Initial Brief, pp. 34–35 says: “The control technologies and protection systems necessary to provide Non-Firm Contract Demand Transmission Service (and Interim NITS) is emblematic of the complexity associated with Non-Firm Contract Demand Transmission Service from an operations and planning perspective.” 6 PJM IMM Reply Brief, p.2.
7 PJM IMM Reply Brief, p.2.

PDF page 19

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 5 of 16
V.A.
SPP CHILLS shows non-firm service is workable and does not
1
create significant reliability concerns
2
Southwest Power Pool (“SPP”) recently filed with FERC, in Docket No. ER26-1323-000, tariff 3

revisions to offer a new non-firm transmission service called Conditional High Impact Large 4

Load Service (“CHILLS”).8 Similar to PJM’s proposed NFCDS and Interim NITS, load that is 5

served under CHILLS does not have firm access to the transmission system, and SPP has no 6

obligation to serve the load if insufficient transmission capacity exists. In SPP’s filing to FERC, 7

Part VII § 44.4 states that: “The Transmission Provider and Transmission Owners undertake no 8

obligation under the Tariff to plan the Transmission System in order to have sufficient capacity 9

for CHILLS”;9 CHILLS “is subject to availability and to Curtailment or Interruption”; “[t]he 10

Transmission Customer or the Network Customer must not withdraw energy from the 11

Transmission System at the CHILL delivery point that exceeds its CHILLS Reserved Capacity”; 12

and “The Transmission Customer or the Network Customer must fully respond to a load shed or 13

curtailment for the CHILL delivery point directive by the Transmission Provider.”10 In both grid 14

planning and operations this is broadly similar to PJM’s proposed design of NFCDS and Interim 15

NITS: for example PJM states in its illustrative tariff that both NFCDS and Interim NITS are 16

“non-firm” and “interruptible.”11 In a supporting affidavit, Dr. Abdulsalam notes that the 17

transmission system is not planned for NFCDS: “this load is neither planned for (i.e., PJM’s 18

transmission planning does not consider this load and so the system is not designed to 19

accommodate it)” showing consistency with SPP’s CHILLS.12
20

8 SPP, Submission of Tariff Revisions to Add Conditional High Impact Large Load Service, Docket No. ER26- 1323-000, Part VII § 44.4 (filed Feb. 10, 2026). (“SPP CHILLS Filing”). 9 Note that, to be eligible for CHILLS, the customer must request a firm transmission service, and a CHILLS customer must transition to firm transmission service within seven years.
10  SPP CHILLS Filing, Part VII § 44.4.
11  PJM Attachment A, Illustrative Language for New Tariff, Part XI § 709.2(b). PJM says “Non-Firm Contract Demand Transmission Service is a transmission service that allows an Eligible Customer taking service on behalf of Co-Located Loads to obtain non-firm, interruptible transmission service...” On Interim NITS, Part XI, § 701.1 says Interim NITS lets an Eligible Customer “receive transmission service on behalf of a Co-Located Load on a non-firm, interruptible basis.”
12  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 12.

PDF page 20

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 6 of 16
The SPP market monitor has assessed CHILLS as just and reasonable.13 The Transmission 1

Owners Group has asserted that “CHILLS has numerous guardrails, including curtailability, that 2

would ensure SPP’s continued ability to maintain grid reliability.”14 The imminent implementation 3

of CHILLS in SPP directly contradicts the PJM IMM’s claim that implementation of non-firm 4

service would be unworkable and create significant reliability risks. The PJM IMM does not 5

point to specific planning or operational reasons why PJM offering NFCDS and Interim NITS, as 6

directed by the Commission’s Co-Location Order, would create reliability concerns, even though 7

SPP can reliably implement such a service.15
8
We also note that SPP does not limit the reservation of CHILLS to periods in which an 9

associated generation resource is on outage, unlike PJM’s proposed implementation of NFCDS. 10

Rather, SPP plans to make CHILLS broadly available during all hours. In addition, in contrast to 11

PJM’s description of its Interim NITS offering to stakeholders,16 SPP does not restrict customers 12

taking CHILLS from relying on co-located capacity or energy during periods of system tightness 13

and supply adequacy shortfalls.17 All of this suggests that PJM’s Interim NITS and NFCDS 14

service is not only workable and able to be reliably implemented, but can in fact be further 15

enhanced for broader uptake and commercial viability. We detail these enhancements in our 16

previous Affidavit in this docket, dated March 25, 2026.18
17

13  Southwest Power Pool Market Monitoring Unit, Comments of the Southwest Power Pool Market Monitoring Unit, Docket No. ER26-1323-000, at p.1 (filed Mar. 3, 2026).
14  Southwest Power Pool Transmission Owner Group (“SPP TO Group”), Comments of the Southwest Power Pool Transmission Owner Group, Docket No. ER26-1323-000, at p.2 (filed Mar. 3, 2026)
15  PJM IMM, Reply Brief
16  See, e.g. Reply Brief and Protest of Enchanted Rock, at p. 2 (March 25, 2026) (“[A]s described by PJM to stakeholders—but not set forth in its Initial Brief, Illustrative Tariff or the February 23 Compliance Filing— PJM intends to prohibit Co-Located Load from receiving any capacity or energy from a Co-Located Generating Facility while the Co-Located Load is taking Interim NITS”.)
17  SPP CHILLS Filing, p.26 (“In general, the co-located generation may be used by the customer to displace its CHILL amount, including compliance with any Curtailment directives.”). 18  Affidavit of Andrew Levitt & Aniruddh Mohan (filed March 25, 2026).

PDF page 21

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 7 of 16
V.B.
ERCOT’s Provisional Controllable Load Resource proposal shows
1
non-firm service is workable, does not create significant reliability
2
concerns, and can be implemented quickly
3
Similar to SPP, developments at the Electric Reliability Council of Texas (“ERCOT”) evince the 4

workability of non-firm transmission services. As part of their ongoing “Batch Zero” reforms to 5

interconnect large loads, ERCOT staff have developed a proposal by which a Provisional 6

Controllable Load Resource (“P-CLR”) can withdraw power from the transmission network on a 7

non-firm basis by being subject to curtailment.19 The proposal is in final stages, and ERCOT is 8

targeting a June 1, 2026, Board vote to finalize the design.
9
ERCOT’s existing CLR construct enables curtailment of loads on a nodal basis via security 10

constrained economic dispatch (“SCED”) for resolving constraints. The P-CLR proposal builds 11

on this construct with new offer rules, and by using CLR curtailment capability as a tool to 12

accelerate connection to the transmission grid for new large loads. That is, a load signing up as 13

P-CLR can use the transmission system on an as-available basis and curtail to resolve constraints 14

as necessary.20
15
V.B.1. ERCOT’s proposed P-CLR shows non-firm service is
16
workable and does not create significant reliability
17
concerns, even without the additional reliability
18
screening of NFCDS
19
As with SPP’s CHILLS and PJM’s proposed non-firm services, ERCOT under its proposed 20

construct has no obligation to serve a P-CLR load, which is obligated to comply with dispatch 21

instructions and is prohibited from withdrawing more than its authorized amount, with the non- 22

firm amount managed through SCED.21
23
Operationally, curtailing P-CLR load in ERCOT’s SCED is similar to what PJM has envisaged 24

for NFCDS and Interim NITS, except that PJM’s NFCDS would have an added step of screening 25

19  ERCOT, Batch Study Update, Board of Directors Meeting (April 20–21, 2026) at p.4.
20  ERCOT, Batch Study Update, p.4.
21  ERCOT, Batch Study Update, p.4.

PDF page 22

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 8 of 16
non-firm reservations ahead of time (unlike both ERCOT’s CLRs and PJM’s Interim NITS). As 1

PJM notes, NFCDS reservation requests would be evaluated and “requests for non-firm service 2

shall only be granted when PJM has determined there is available transmission capacity.”22 3

Compared with ERCOT’s P-CLR construct, the need to reserve PJM’s NFCDS on a forward 4

basis provides yet another opportunity to ensure that NFCDS can be provided reliably. Similar to 5

SPP’s CHILLS detailed above, ERCOT’s P-CLR product once again runs contrary to the claim 6

from PJM’s IMM that non-firm service is unworkable and inconsistent with reliable operations. 7

We also note again that unlike PJM’s proposed NFCDS product which restricts NFCDS 8

reservations to hours where the co-located resource is on outage, ERCOT’s P-CLR allows loads 9

to take service during all hours, subject to SCED curtailment.23
10
V.B.2. SCED curtailment of ERCOT P-CLRs will be
11
developed by 2027 showing that faster
12
implementation than PJM’s 2029 proposal is feasible
13
PJM has proposed implementation of its new transmission services by 2029. The affidavit of 14

PJM’s Timothy Horger says that changes to SCED for dispatching load in market operations will 15

require significant updates that necessitate delaying implementation until 2029.24 However, it is 16

unclear why this must be delayed until 2029 given that ERCOT has committed to 17

implementation of P-CLRs in its Batch Zero process, proposed for implementation as soon as 18

2027.25 While building out such tools warrants careful design and rigorous testing, PJM has 19

provided no reasons why PJM’s system uniquely requires a longer implementation process 20

compared to other RTOs. Further, as pointed out in our previous affidavit, PJM is well placed to 21

implement changes to SCED given the existing capability of its nodal Price Responsive Demand 22

(“PRD”) implementation in SCED. The PRD construct, similar to CLR, allows nodal, real-time 23

curtailment of loads via SCED. PJM can directly use or build on its PRD tools in SCED to 24

execute needed reliability-related curtailments of non-firm transmission services in order to 25

maintain transmission security in real-time in response to changing system conditions. 26

22  PJM Initial Brief, pp. 32–33.
23  ERCOT, Batch Study Update, p.4 24  PJM Initial Brief, Attachment D (Affidavit of Timothy Horger), pp. 4–5. 25  ERCOT, Large Load Interconnection Batch Study Workshop #7 (April 9, 2026) at p.25.

PDF page 23

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 9 of 16
V.C.
Non-firm transmission service is workable at scale even when
1
enhanced with simple protection systems
2
Citing complexity associated with over-reliance on RAS, the IMM suggests that NFCDS cannot 3

scale, while PJM proposes that NFCDS may only be scheduled during a very limited number of 4

hours. Below, we describe what a RAS is and why offering NFCDS during all normal operating 5

conditions would not cause an over-reliance on RAS. In summary, our position rests on the 6

following points:
7
1. There is an important distinction between standard RAS and the simple withdrawal-limiting 8

protection systems PJM proposes to require. Unlike standard RASs, which monitor and 9

control components across the broader transmission grid, withdrawal-limiting protection 10

systems monitor and control only facility-internal components. Because these systems are far 11

narrower in scope and operationally simpler, they can be relied upon more extensively 12

without creating the same system complexities and interdependencies associated with 13

standard RAS.
14
2. That simplicity is reinforced by the PJM Transmission Owners’(“TOs'”) proposal to 15

implement protection systems in a redundant manner that guards against the possibility of 16

protection system failure.26
17
3. Allowing NFCDS to be scheduled more frequently rather than limiting it to periods of 18

generator outage reduces reliance on withdrawal-limiting protection systems, because when 19

NFCDS is scheduled, that protection system is disabled to allow those scheduled withdrawals 20

that are not curtailed by SCED. PJM’s proposal to reduce the extent to which NFCDS can be 21

used will therefore tend to increase the extent to which withdrawal-limiting protection 22

systems are relied upon.
23
4. Standard RASs can provide important system benefits but also have recognized limits. Even 24

so, a customer need not install a standard RAS in order to take non-firm transmission service, 25

even if PJM requires a withdrawal-limiting protection system for that customer’s facility. 26

26  The PJM TOs recommend, and we agree, that “All SPS and RAS should be fully redundant.” PJM TOs Initial Brief at p.23.

PDF page 24

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 10 of 16
V.C.1. IMM and PJM are concerned with the complexity of
1
non-firm service due to protection systems and RASs
2
The IMM in its comments asserts that “[g]iven the scale of potential data center users of non-firm 3

CDS, the system would become unmanageable if all or a significant part of the data center users 4

wanted to use non-firm CDS…,”27 and, commenting on its reliability concerns with non-firm 5

services generally, cites to PJM’s statement that “the complexity introduced by the necessary 6

control technology and protection systems (e.g., RAS) introduces significant risks.”28 We expand and 7

comment on the nature of that complexity to help clarify where scale may or may not introduce 8

issues.
9
In the following statements, PJM explains the complexity associated with protection systems, and 10

that it warrants limiting scheduling eligibility for NFCDS to a very narrow window: 11

…PJM will offer and manage pre-scheduled Non-Firm Contract Demand
12
Transmission Service “‘operationally’ and ensure that permanent monitoring and 13

aggressive, fast-acting protections are in place if conditions arise that may 14

compromise reliable system operations.” This approach, as Dr. Abdulsalam explains, 15

“allows for more reliable system operation, reduces the number of permanent 16

protection systems on the system,” such as a RAS, on the PJM Transmission System, 17

and thus “reduc[es] the likelihood of unintended protection system misoperation that 18

could lead to cascading events.”
19
In addition, as explained further below, and by Dr. Abdulsalam, from an operations 20

and planning perspective, the complexities associated with the provision of Non-Firm 21

Contract Demand Transmission Service call for relying on such service as a standby 22

product only “under limited circumstances.”29 [emphasis added]
23
In the relevant section “further below,” PJM goes on to state that:
24
The control technologies and protection systems necessary to provide Non- 25

Firm Contract Demand Transmission Service (and Interim NITS) is
26
emblematic of the complexity associated with Non-Firm Contract Demand
27
Transmission Service from an operations and planning perspective.30
28

27  PJM IMM Reply Brief, p.6.
28  PJM Initial Brief, p.60.
29  PJM Initial Brief, p.10
30  PJM Initial Brief, pp. 34-35.

PDF page 25

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 11 of 16
The IMM reasons that NFCDS cannot be installed at scale and cites these complexity concerns 1

raised by PJM. According to PJM, those concerns arise because complex control technologies 2

and protection systems are necessary for providing NFCDS, the protection systems may 3

misoperate and lead to cascading events, and therefore NFCDS can only be relied on as a 4

standby product (i.e., when a co-located generator at a CDS facility is on outage). In the 5

following sections, we show that this reasoning is flawed.
6
V.C.2. Simple withdrawal-limiting protection systems are
7
distinct from standard RAS
8
PJM describes a protection system at a co-located facility that disconnects a co-located load 9

when there is a sudden failure of one of its co-located generation units, and states that all co- 10

located facilities will have such a protection system.31 PJM describes this type of protection 11

system as “overwhelmingly beneficial.”32 PJM states that the protection system will be “set to 12

ensure such load does not withdraw energy in excess of the megawatt level permitted under its 13

effective service agreement.”33 In order to prevent withdrawals from exceeding the permissible 14

level, such a protection system: monitors flows into the co-located facility; monitors the status of 15

components internal to the facility; and takes action to either adjust consumption or generation of 16

components in the facility, or to disconnect the facility from the grid. Therefore, all of the 17

monitoring and control of this type of protection system is internal to the co-located facility. We 18

call this a “withdrawal-limiting protection system.”34
19

31   PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 25, and Abdulsalam Affidavit, ¶ 9. Following Dr. Abdulsalam’s naming convention, we refer to this device broadly as a protection system, noting that Mr. Wharton has classified it as a RAS. We further note that, in the ERCOT Batch Zero process, a device with the equivalent functionality that is required for a Self-Limited Facility is not referred to as a RAS but rather as a “reverse power relay or equivalent protection.” See ERCOT, Large Load Batch Study Update, presented to PUCT Open Meeting, April 2, 2026, p.7.
32  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 25.
33  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 9.
34  It does not appear to be necessary to have a withdrawal-limiting protection system in order to enable non-firm transmission service, and indeed such systems are not required for conventional point-to-point non-firm service, nor are they proposed for use in SPP CHILLS nor ERCOT P-CLR (both of which are suitable for load-only sites that would not make sense with a withdrawal limiter). However, we concur with PJM that a withdrawal- limiting protection system is beneficial and therefore expect efficiencies in PJM’s proposal to install them widely, noting that some customers may prefer not to use them and instead curtail as necessary to ensure reliable operations in case of a contingency internal to their facility.

PDF page 26

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 12 of 16
Unlike a withdrawal-limiting protection system (which monitors and controls only facility- 1

internal components), a standard RAS monitors and controls components across the grid. When 2

it detects a triggering condition on one element on the transmission system, it takes action to 3

control or disconnect a distinct, often remote element on the transmission system.35 4

Both a withdrawal-limiting protection system and a standard RAS are beneficial because they 5

allow a non-firm large load to withdraw power from a constrained transmission network with 6

less (or no) curtailment relative to the constraint, as follows. With the higher consumption, a 7

contingency would ordinarily overload the constrained element. However, the protection system 8

monitors for the contingency and, if it occurs, reacts immediately (e.g., by curtailing load) to 9

protect the constrained element.36 This allows curtailment after a contingency happens, rather 10

than proactively curtailing before the contingency (which is the ordinary practice in absence of a 11

withdrawal-limiting protection system or RAS).
12
However, a standard RAS is not necessary to accommodate a non-firm load, precisely because 13

the alternative (pre-contingency curtailment) is always an option due to the non-firm nature of 14

the load. As we have pointed out, the extent of standard RAS installation must be carefully 15

considered, and a standard RAS is not suitable in all applications due to complexity. As Dr. 16

Abdulsalam notes, with increasing adoption, RAS may interact under abnormal operating 17

conditions, leading to unintended consequences and potential cascading failures.37 This 18

interaction is indeed a hallmark of standard RAS, since the facilities they monitor and control are 19

“apparently unrelated” and can span across a wide area that overlaps with other standard RASs.38 20

35  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 15.
36  A withdrawal-limiting protection system directly or indirectly monitors loss of a generation unit internal to the co-located facility, while a standard RAS would monitor one or more transmission elements or generation units elsewhere on the bulk electric system.
37  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 10. 38  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 15; CAISO, Planning Guide, p. 11 (“With the increased transmission system utilization that comes with application of RAS, there can be increased exposure to not meeting system performance criteria if the RAS fails or inadvertently operates…If there are a large number of RAS, it may become difficult to assess the interdependency of these various schemes on system reliability. In addition, as RAS has become progressively increasing in complexity, it is necessary to consider the level of logic complexity through combining multiple features that were acceptable individually but that could compound to a level that cannot be integrated into market operation.”)

PDF page 27

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 13 of 16
However, PJM has not explained how a simple withdrawal-limiting protection system, which is 1

restricted to monitoring and controlling elements internal to a single facility, would exhibit the 2

interdependencies and complexities that characterize typical RAS. Because of its simplicity and 3

localized scope, it would appear on first principles that extensive installation of withdrawal- 4

limiting protection systems would not introduce the complexity that is associated with standard 5

RASs.
6
Further, PJM has asserted that a protection system must be temporary because it will need to 7

adapt to changing system conditions.39 However, if the nature of the protection system is simply 8

to limit withdrawals consistent with transmission service limits, it is unclear why such a simple 9

system would need to evolve with system conditions.
10
Finally, the robustness associated with the simplicity of withdrawal-limiting protection systems 11

is reinforced by the PJM TOs’ proposal to implement protection systems in a redundant manner 12

that guards against the possibility of protection system failure.40
13
V.C.3. Narrow eligibility for scheduling NFCDS does not
14
reduce any complexity from withdrawal-limiting
15
protection systems
16
According to PJM, any facility taking Contract Demand Service must have a withdrawal-limiting 17

protection system.41 When there is zero or partial NFCDS scheduled, this protection system 18

serves to ensure there are no withdrawals above the authorized Firm CDS level. When NFCDS 19

may be reliably scheduled, the protection system obviously must be adjusted or disabled in order 20

to allow the corresponding higher withdrawals. That is: under PJM’s proposal, all co-located 21

facilities will have a withdrawal-limiting protection system active at all times they are taking 22

39  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 10 (“The temporary nature of such a protection system for this type of firm service is necessary to ensure the integrity and reliable operation of the transmission system as a whole since protection systems are designed based on system conditions anticipated at that time and will continue to change as system conditions evolve.”)
40  PJM TOs Initial Brief at p.23.
41  PJM Initial Brief at p.34 (“PJM is requiring Eligible Customers taking Non-Firm Contract Demand Transmission Service to work with PJM and affected Transmission Owners to ‘establish necessary control technologies and protection systems, . . . which may include a [RAS], for each Service Agreement for Non-Firm Contract Demand Transmission Service.”)

PDF page 28

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 14 of 16
Firm + Non-Firm CDS for less than their load level. It therefore follows that narrowing 1

eligibility for NFCDS scheduling does not decrease complexity associated with such protection 2

systems. And, to the extent that the withdrawal-limiting protection system is disabled due to the 3

scheduling of Firm + Non-Firm CDS to cover the full load, any corresponding complexity is 4

removed. Thus, PJM has not effectively demonstrated that its proposal to limit NFCDS 5

scheduling eligibility to generator outage periods is reasonable for maintaining reliability, since 6

NFCDS scheduling does not exacerbate complexity due to protection systems, and in many cases 7

mitigates it.
8
V.C.4. NFCDS can be scaled reliably, notwithstanding limits
9
to installation of standard RAS
10
In addition to a withdrawal-limiting protection system, a standard RAS that monitors 11

transmission system elements and controls the co-located facility in response can be beneficial 12

for further accelerating load interconnections ahead of or instead of transmission upgrades. A 13

standard RAS allows non-firm large loads to be curtailed instantaneously after a grid 14

contingency (such as loss of a nearby transmission line) to prevent overload of a constrained 15

element, rather than pre-curtailing it before the contingency (which would be the typical 16

operating practice in absence of a RAS). The result is that, with a standard RAS, such a load 17

would face curtailment due to that constraint with far lower frequency—possibly never— 18

compared to the alternative of pre-contingency curtailment. Standard RAS can and should 19

therefore be installed at as many facilities as practical within the limits that PJM has identified. 20

That said, notwithstanding its benefits, the complexity of standard RAS means there will likely 21

be a limit on the number of load facilities at which it can be installed, even if that limit is beyond 22

the current usage of standard RAS in PJM.
23
The IMM has asserted that, due to complexity, extensive deployment of NFCDS could become 24

“unmanageable.”42 However, it would be incorrect to conclude that scale constraints due to 25

complexity of standard RAS mean widescale installation of NFCDS is “unmanageable.” This is 26

because standard RAS is not required for NFCDS, even if PJM requires a withdrawal-limiting 27

42  PJM IMM Reply Brief at p.6.

PDF page 29

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 15 of 16
protection system at each site. Instead of standard RAS, NFCDS can be curtailed pre- 1

contingency. PJM can and should only install standard RAS for NFCDS facilities to the extent it 2

is manageable. Beyond that threshold, PJM can instead rely on pre-contingency curtailment of 3

NFCDS without installing standard RAS, similar to how ERCOT and SPP envisage curtailment 4

of non-firm load under the proposed P-CLR and CHILLS constructs. In this way, PJM avoids 5

suffering a reliability degradation from too much standard RAS while granting NFCDS service 6

at scale. The non-firm nature of NFCDS provides this operational flexibility—precisely because 7

pre-contingency curtailment is always an option for non-firm load.
8
V.D.
NFCDS is consistent with a reliable and efficient PJM transmission
9
system
10
The IMM asserts that “there can be no such service as non-firm CDS that is fully consistent with 11

maintaining a reliable PJM transmission system.”43 As we point out in our prior affidavit, the CDS 12

construct (including NFCDS scheduled whenever it is available and desired) provides the unique 13

benefit of a reliable system that can permanently avoid the need for high-cost and unnecessary 14

transmission upgrades and allow for efficient exchanges with the grid when the transmission network 15

is available to support them. By taking advantage of flexibility in grid withdrawals inherent in a site 16

and PJM’s direct control of how much a facility withdraws via SCED, depending on system 17

conditions, a large load customer can be connected reliably more quickly and at lower cost. As we 18

point out above, neither IMM nor PJM have shown any cause for reliability concern associated with 19

the CDS construct.
20

21

43  PJM IMM Reply Brief at p.6.

PDF page 30

Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan
Docket No. EL25-49-000 et al. | Page 16 of 16
Affidavit of Andrew Levitt

I, Andrew Levitt, do hereby swear that I have co-authored this Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true and accurate to the best of my knowledge and belief.

Andrew Levitt

Date: April 24, 2026
Affidavit of Aniruddh Mohan

I, Aniruddh Mohan, do hereby swear that I have co-authored this Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true and accurate to the best of my knowledge and belief.

Aniruddh Mohan

Date: April 24, 2026