EL25-49-000 · 2026-04-24 · Eolian, L.P.Antora Energy LLCCalibrant Energy and 3 others

Second Reply Brief of Eolian, L.P., et al

Text extracted from the eLibrary original (SHA-256 3a7f5980cf41ddde…). Download the original from the official source.

Contents · 9 sections
  1. I. ARGUMENT p. 2
  2. B. The Commission must adopt a Grid Reliance Charge that is cost justified. p. 3
  3. C. The Commission should not allow unsubstantiated reliability concerns to p. 4
  4. Attachment A p. 14
  5. I. QUALIFICATIONS p. 16
  6. II. ASSIGNMENT p. 16
  7. III. BACKGROUND p. 16
  8. IV. SUMMARY p. 16
  9. V. ASSESSMENT OF RELIABILITY IMPLICATIONS AND p. 18

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket Nos.
Read this passage

I. ARGUMENT

printed heading · Topic match: Reliability and curtailment

A broad range of stakeholders support full implementation of the Co- Location Order.
Read this passage Filed comments: Reliability and curtailment

B. The Commission must adopt a Grid Reliance Charge that is cost justified.

printed heading · Topic match: Cost allocation

Zachary Ming proposes an alternate cost calculation framework that follows the Commission’s cost causation principles.11 The Commission should direct the PJM Transmission Owners to adopt a Grid Reliance Charge based on that methodology.
Read this passage Filed comments: Cost allocation

C. The Commission should not allow unsubstantiated reliability concerns to

printed heading · Topic match: Reliability and curtailment

Rather, in the attached testimony, Levitt and Mohan demonstrate that customers taking non-firm transmission service will not implicate widespread reliance on Remedial Action Schemes because customers can instead generally rely on simpler withdrawal-limiting protection systems internal to facilities…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated: April 24, 2026 /s/ Eric Stoutenburg Eric Stoutenburg Chief Development Officer Eolian L.P. 988 Howard Ave.
Read this passage

Attachment A

printed heading

Attachment A Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan Docket No.
Read this passage

I. QUALIFICATIONS

printed heading

QUALIFICATIONS 1 Our names are Andrew Levitt and Aniruddh Mohan.
Read this passage

II. ASSIGNMENT

printed heading

ASSIGNMENT 4 We were asked by Eolian, L.P. to supplement our Affidavit dated March 25, 2026, to offer 5 additional perspectives on the reliability and timeline implications of the proposed new 6 transmission services in PJM’s Initial Brief in Docket No.
Read this passage

III. BACKGROUND

printed heading · Topic match: Connecting load and generation

BACKGROUND 8 As part of its compliance filing to FERC in Docket EL25-49-000, in February 2026, in an 9 accompanying Initial Brief, PJM set out illustrative tariff language and supporting positions for 10 three new service categories for generators serving co-located load: Non-Firm Contract Demand…
Read this passage Filed comments: Connecting load and generation

IV. SUMMARY

printed heading

EL25-49-000 et al. | Page 3 of 16 transmission system.2 In this Supplemental Affidavit, we find that the concerns raised do not 1 provide evidence that provision of NFCDS or Interim NITS would be inconsistent with reliable 2 system operations.
Read this passage

V. ASSESSMENT OF RELIABILITY IMPLICATIONS AND

printed heading · Topic match: Reliability and curtailment

In SPP’s filing to FERC, 7 Part VII § 44.4 states that: “The Transmission Provider and Transmission Owners undertake no 8 obligation under the Tariff to plan the Transmission System in order to have sufficient capacity 9 for CHILLS”;9 CHILLS “is subject to availability and to Curtailment or…
Read this passage Filed comments: Reliability and curtailment