EL25-49-000 · 2026-04-24 · Constellation Energy Generation, LLC
Response Brief of Constellation Energy Generation, LLC
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
RESPONSE BRIEF OF CONSTELLATION ENERGY GENERATION, LLC
Constellation1 submits this response brief to discuss three points with broad support in the reply briefs regarding how PJM and the Transmission Owners2 must modify their proposals to ensure compliance with the Commission’s December 18th Order.
First, a proposed effective date of June 2029 runs counter to the spirit of the Commission’s December 18th Order.3 PJM and Transmission Owners must act expeditiously. Winning the AI race requires a sprint, not a stroll. The Commission could help accelerate the interconnection of large loads by setting the new transmission services on separate tracks. Interim Network
1 Constellation Energy Generation, LLC (“Constellation”) submits this response in accordance with the hearing procedures established by the Commission in its December 18, 2025 Order. See PJM Interconnection, LLC, 193 FERC ¶ 61,217, at P 220 (2025) (“December 18th Order”).2 The Transmission Owners that filed the February 23, 2026 Initial Brief are a subset of Transmission Owners in PJM, excluding Old Dominion Electric Cooperative, for example. The same subset filed the March 25, 2026 Reply (“Indicated TO Mar. 25 Reply”).3 In the same spirit of expedition, Constellation largely acceded to the rate proposals submitted by the PJM Transmission Owners – avoiding a potentially protracted litigation over the precise rates avoids delay in implementing these needed new services.
PDF page 2
2
Integration Transmission Service (“Interim NITS”)4 should go first and should be implemented by October 1, 2026.
Second, Interim NITS and Contract Demand Services should be fully supported, not made “meaningless.”5 The Commission’s December 18th Order was a “landmark” order intended to address the “urgent need ... that large loads are ‘able to connect to the transmission system in a timely, orderly, and non-discriminatory manner.’”6 PJM and the Transmission Owners cannot impose rates, terms and conditions that risk discrimination and render the new services so unattractive that Network Integration Transmission Service (“NITS”) remains the only viable option. New service terms and conditions must be just and reasonable.
Without delay, the Commission should reject and direct further compliance on PJM’s and the Transmission Owners’ proposals that restrict, discriminate, eliminate, or otherwise discourage the new transmission services. PJM and the Transmission Owners’ initial briefs included several provisions that would enable undue discrimination by Transmission Owners and continue to delay large load interconnections. On reply, the Transmission Owners introduce several more. Two simple solutions can prevent discrimination and delay: first, deadlines for deliverables from the Transmission Owners, such as studies, and second, requiring standards, practices, and technical requirements to be clear and on file at the Commission.
Third, several critical terms of service need to be refined to make Interim NITS and Contract Demand Services commercially workable. Before investing hundreds of millions of
4 Unless otherwise defined, all capitalized terms have the same meaning as in the December 18th Order.5 Independent Market Monitor for PJM Interconnection, LLC March 25, 2026 Reply at 6 (stating Non-Firm Contract Demand Service “would not be available on a consistent basis and would therefore be meaningless.”) (“Market Monitor Mar. 25 Reply”). 6 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC ¶ 61,045, at P 2 (2026).
PDF page 3
3
dollars, Eligible Customers and Co-Located Loads must have clarity on how PJM will determine whether the transmission services can be reliably provided and how loads will be curtailed. A lack of clarity was the exact basis for the Commission finding PJM’s Tariff unjust and unreasonable.7 Consistent with the December 18th Order, the Commission should require these critical terms of service to be stated clearly. We cannot afford continued setbacks from incremental or incomplete proposals.
REPLY
I. Winning the AI Race Requires a Sprint, Not a Stroll
A June 2029 effective date imposes a “three- to five- year moratorium” on the co-location
of large loads.8 This goes against the speedy interconnection that the Commission envisioned and that is needed to win the AI race.9 Moreover, it allows rates found to be unjust and unreasonable— that is, unlawful—to remain in place for three and a half more years, fundamentally undermining the December 18th Order, not to mention the purpose of the Federal Power Act.107 December 18th Order, 193 FERC ¶ 61,217 at P 2 (“[W]e find that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”).8 Vistra Corp. March 25, 2026 Reply at 4 (“Vistra Mar. 25 Reply”).9 Id. at 5-6 (“This entire proceeding exists because co-located loads need to access the transmission system quickly in order to satisfy the nation’s time-sensitive demand for the computing and manufacturing capability necessary to win the global race for AI dominance.”); Joint Co-Location Developers March 25, 2026 Reply at 2 (“The Commission issued the Co-Location Order within the context of a broader national effort to confront the affordability, reliability, and speed-to-power challenges that rapid large load growth poses for the electricity system.”) (“Joint Developer Mar. 25 Reply”): Constellation Energy Generation, LLC March 25, 2026 Reply at 1-2 (“Constellation Mar. 25 Reply”).10 See 16 U.S.C. § 824d(a) (“[A]ll rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable, and any such rate or charge that is not just and reasonable is hereby declared to be unlawful.”); see also Joint Developers Mar. 25 Reply at 27 (“the Commission should not leave the rates that it found unjust and unreasonable in the Co-Location Order in place for more than three more years”).
PDF page 4
4
The Commission should direct PJM to act expeditiously.11 PJM has devoted significant
resources to such changes for well over a year.12 PJM also has the tools to implement new rules quickly but seems determined to slow roll the transmission services that PJM disfavors. “[W]hen PJM integrated energy storage resources into its markets pursuant to Order No. 841, PJM required only one year to develop software to accommodate an operationally distinct asset class.”13 PJM should be capable of following at least the same course when there is national urgency. The Commission should also clarify this is not the time for providing “basic outline[s]” with “more
11 See Written Testimony of Laura V. Swett, Chairman, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1-2 (Feb. 3, 2026) https://www.ferc.gov/news-events/news/testimony-laura-v-swett-chairman-federal-energy-regulatory-commission- us-house (“We’re in a global energy arms race created by the rise of technology, its tremendous load growth, and our push to onshore manufacturing and jobs. I want the United States to lead that race; This is the moment to cement America’s energy leadership.”); Written Testimony of Lindsay S. See, Commissioner, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 3 (Feb. 3, 2026), https://www.ferc.gov/news-events/news/testimony-lindsay-s-see-commissioner- federal-energy-regulatory-commission (“our national imperative of speed to power and winning the AI race”); Written Testimony of David LaCerte, Commissioner, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1 (Feb. 3, 2026), https://www.ferc.gov/news-events/news/testimony-david-lacerte-commissioner-federal-energy-regulatory- commission-house (“[T]he AI race, and even more importantly, who ultimately wins, will also fundamentally transform how Americans engage, transact, and compete on the global stage. The AI race is here and America’s power grid is a major battlefield.”); Data Center Coalition March 25, 2026 Reply at 10 (urging “the Commission to require targeted modifications to ensure that the final framework … can be implemented in a timeframe that supports current and near-term development”) (“DCC Mar. 25 Reply”); Joint Developer Mar. 25 Reply at 3 (“Given the urgent need to address the impacts of load growth on the PJM system today, the Commission should require PJM to make the new tariff provisions related to the new transmission services effective sooner than June 1, 2029.”).
12 Initial Brief of PJM Interconnection, L.L.C. (Mar. 24, 2025) (proposing seven options for addressing Co-Location Arrangements). Even prior to PJM’s Initial Brief, in 2024 PJM had provided guidance on co-location issues. This guidance was featured in Constellation’s complaint that ultimately gave rise to the show cause proceeding. See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000 at 5 (Nov. 22, 2024) (citing PJM Guidance on Co-Located Load (March 22, 2024) (Updated April 17, 2024)) (“Constellation Complaint”).13 Vistra Mar. 25 Reply Comments at 11 (emphasis added); see also Joint Developer Mar. 25 Reply at 29-30 (“It is not clear why PJM will be able to implement its Connect and Manage proposal and SPP will be able to make non- firm conditional transmission service available this year while PJM claims to need 40 months to implement the new transmission services at issue in this proceeding.”); id. at Attachment A, Affidavit of Andrew Levitt and Aniruddh Mohan at 20:16-17 (“PJM can achieve implementation of all three services faster than proposed.”) (“Levitt & Mohan Affidavit”); id. at 21:27-22:2 (“Southwest Power Pool’s recent proposal to implement non-firm transmission service for load (CHILLS) by July 1, 2026 offers further evidence that such changes to dispatch can be implemented faster than envisaged by PJM.”).
PDF page 5
5
details forthcoming in future filings in this proceeding.”14 That is not compliance with the Commission’s directives. Complete and clear proposals are needed for parties to provide comment to ensure the new transmission services can work commercially as the Commission intended; that is particularly necessary in this proceeding given the demonstrated history of discriminatory treatment.
The Commission can accelerate interconnection of large loads by establishing separate
tracks for transmission services that can proceed on faster timelines.15 The Commission should establish a separate track to promptly approve the rates and terms for Interim NITS, including the study process, consistent with Constellation’s recommended modifications discussed below and in prior pleadings. The effective date should be no later than October 1, 2026, as our
recommendations are targeted only at critical issues that would delay or otherwise render meaningless the new transmission services. We have intentionally decided not to contest other elements of PJM’s and the Transmission Owners’ proposals that potentially concern us, so as to expeditiously complete these proceedings, timely implement new transmission services, and avoid protracted litigation.1614 Indicated TO Mar. 25 Reply at 12; see also id. (“The PJM Transmission Owners will also provide additional details on this proposal in future filings.”); Northern Virginia Electric Cooperative, Inc. March 25, 2026 Reply at 13 (“At this time, neither PJM nor the PJM Transmission Owners have a specific concept for the Commission to consider, but have committed to working together to explore penalty options.”); DCC Mar. 25 Reply at 8 (“DCC is also concerned that the proposed framework leaves numerous critical elements undefined or deferred.”); Constellation Mar. 25 Reply at 18-19 (discussing PJM and Transmission Owners “offer no proposal on a penalty charge”).15 See DCC Mar. 25 Reply at 9 (“PJM has not demonstrated that all elements of the proposed services must be deferred for several years, nor has it identified opportunities for phased or interim implementation. Given the immediate and growing demand for large load interconnection, the Commission should consider whether certain components of the framework can be implemented on an accelerated or staged basis to provide near-term benefits while longer-term systems are developed.”); Joint Developer Mar. 25 Reply at 9 (“For Non-Firm CDS and Interim NITS, the Commission should direct PJM to adopt an effective date as soon as practicable, based on a detailed projection of project schedule components, moving with urgency.”); Constellation Mar. 25, 2026 Reply (explaining the Commission should fast track Interim NITS).16 See supra note 3.
PDF page 6
6
II. New Transmission Services Should Be Supported, Not Discouraged or Made
“Meaningless”
The landmark December 18th Order directed PJM “to ensure that large loads are ‘able to
connect to the transmission system in a timely, orderly, and non-discriminatory manner.’”17 The majority of commenters agree that PJM’s and the Transmission Owners’ proposals are
fundamentally at odds with the Commission’s directive.18 The proposals restrict, delay,
discriminate, or otherwise discourage the use of Interim NITS and Contract Demand Services. The proposals produce the opposite effect of “releas[ing] the bottleneck of large load investments across the PJM footprint”19 and are contrary to the core requirement in the Federal Power Act that rates and terms be “just and reasonable.”20 Given the depth of PJM’s and the Transmission
Owners’ resistance,21 immediate Commission intervention is warranted. Without delay, the
17 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC ¶ 61,045 at P 2.
18 See Joint Developer Mar. 25 Reply at 31 (“Rather, they propose the minimum possible ambition to offer non-firm and contract transmission services …. The Commission should not allow this attempt to water down the Co-Location Order, which would prevent it from realizing its goals.”); id. at 2 (“PJM departs from the requirements and spirit of the Co-Location Order again and again, rendering the new transmission services commercially unworkable.”); DCC Mar. 25 Reply at 2 (“[T]he proposals introduce significant operational rigidity, limit flexibility, and create disincentives that will impede the development of co-located load and associated generation. This is fundamentally at odds with the Commission’s December directive.”); Geronimo Power, LLC March 25, 2026 Response Brief at 2- 3 (“[C]ertain proposals outlined in the initial brief filed by the PJM Transmission Owners run counter to the objectives outlined in the Commission’s order in this proceeding and will result in charges that do not reflect co- located loads’ actual impact on the grid, disincentivize large loads from co-locating with new generation resources, and ultimately extend the status quo in PJM that the Commission has found to be unjust and unreasonable.”); Enchanted Rock March, 25, 2026 Protest and Reply Brief at 2 (“PJM’s Proposed Interim NITS Limitation, if enacted, would make it commercially impractical for Eligible Customers to ever utilize Interim NITS to serve their Co-Located Load.”); Constellation Mar. 25 Reply at 10-30.19 FERC, News Release, FERC: Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid- operator-create-newrules-embrace-innovation-and?new= (quoting Chairman Swett).20 16 U.S.C. § 824d.21 Indicated TO Mar. 25 Reply at 2-3 (“Moreover, assuming that the new transmission services are ultimately required to be implemented, an action with which some PJM Transmission Owners strongly disagree ….”); see also Constellation April 8, 2026 Supplemental Protest, Docket Nos. ER26-1088-000, et al., at 3 (explaining that “[du]ring the week of March 30, 2026, [a] Transmission Owner informed Constellation that it would not study Constellation’s proposed design unless Constellation agreed to transfer ownership of the ring bus facilities to the Transmission Owner.”); Exelon Corporation April 14, 2026 Public Version of Answer, Docket Nos. ER26-1088-000, at 3-4
PDF page 7
7
Commission should issue an order promptly approving PJM’s proposed rates and terms for Interim NITS, with the following modifications:
• Establish a transitional mechanism for large loads with pending NITS applications
to apply for Interim NITS.22
• Establish clear and transparent rules on the studies performed by PJM and
mechanisms to prevent delay and discrimination by Transmission Owners,
including, as discussed below, studies to determine special protection schemes or
other remediation necessary to maintain system reliability.23
• Establish reasonable and not unduly discriminatory processes for determining
special protection schemes or other remediation that is required for Co-Location
Arrangements.24 As detailed below, remediation should be commensurate with the
need to protect the system from actual overloads and conditions that PJM cannot
mitigate through normal operations.
• Adopt the penalty scheme in Section 14.5 of Part II of the PJM Tariff for unreserved use by Non-Firm Point to Point Transmission Service and reject PJM’s proposal to
suspend and disqualify Eligible Customers for unreserved use of the transmission
system, measures that are not imposed on Non-Firm Point to Point Transmission
Service.25
• Reject PJM’s proposed requirement that an Eligible Customer provide PJM
authorization or certification from the Relevant Electric Retail Regulatory
Authority.26
In particular, the Commission should reject any proposal to delay allowing existing
generation to co-locate with large loads while accelerating the co-location of load with new
(stating Constellation’s allegations are “absurd” and “Exelon is totally supportive of service to new large loads, so long as the service is consistent with safe and reliable service, adheres to state and federal legal and regulatory requirements, and properly contributes to the services provided at both the transmission and distribution level.”) (emphasis added).
22 Constellation Mar. 25 Reply at 14.23 Id. at 14-18.24 Id. at 21-25. See also Exhibit 1 attached, the Affidavit of Michael Kormos (“Kormos Second Affidavit”), discussing purpose of special protection schemes and recommending PJM adopt its New Service Request Study Process and Regional Transmission Expansion Plan process to study reliability impacts of Co-Located Load requests and determine appropriate remediation.25 Id. 18-21.26 Constellation Mar. 25 Reply at 29.
PDF page 8
8
generation.27 Policies in favor of new resources are called “vintaging,” and they have long been discredited.28
In addition, the Commission should direct PJM and the Transmission Owners to course-
correct on the rates and terms for Contract Demand Services. The Commission should reject PJM’s narrowing of Non-Firm Contract Demand Service to outages of the co-located generator, which nearly every party filing reply comments agrees is “not consistent with the Commission’s definition” of the service.29 The Commission should adopt the cost-based and legally durable Grid Reliance Charge methodology proposed by electric market expert Zachary Ming over the
Transmission Owners’ flawed Grid Reliance Charge.30 And the Commission should deny PJM’s requirement to construct different feeders to take the new services.31 To allow more time if needed,
27 See Levitt & Mohan Affidavit at 21:8-11 (“If PJM’s concern regarding a capacity market shock that cannot be covered through an incremental auction is focused on existing co-located generation withdrawing from the capacity market, it should delay only that use case, while accelerating other use cases (i.e., co-location with new generation facilities).”).28 See Constellation Energy Generation, LLC December 5, 2025 Supporting Reply Comments, Docket No. RM26-4- 000, at 38-39; Constellation Energy Generation, LLC November 21, 2025 Supporting Comments, Docket No. RM26-4-000, at 16.29 Market Monitor Mar. 25 Reply at 5 (“The conditions for taking non-firm CDS identified by PJM … are not consistent with the Commission’s definition of non-firm CDS.”); see also Vistra Mar. 25 Reply Comments at 26 (“Nothing in the Commission’s Order suggested that Non-Firm Contract Demand Transmission Service should be so limited.”); DCC Mar. 25 Reply at 6 (“PJM’s proposal does not merely interpret the Commission’s directive—it materially narrows it. By constraining Non-Firm CDS to a limited outage-only function, PJM eliminates the very flexibility the Commission sought to introduce.”); Advanced Energy United and Solar Energy Industry Association March 25, 2026 Reply Brief at 3 (“PJM’s proposed Non-Firm Contract Demand Transmission Service departs materially from the Commission’s directives by restricting the service to periods when the colocated generating facility is on outage.”) (“United & SEIA Mar. 25 Reply”); Joint Developer Mar. 25 Reply at 7 (“Even if the Co- Location Order were unclear (which it is not), PJM has not offered an adequate rationale for limiting the availability of Non-Firm CDS to periods of generator outages.”); Constellation Mar. 25 Reply at 10-13 (“the Commission did not limit Eligible Customers to taking Non-Firm Contract Demand Service only at times when the Co-Located Generating Facility is on outage … [and] PJM’s justifications for limiting Non-Firm Contract Demand Service are unpersuasive”).30 Constellation Mar. 25 Reply at Att. 1.31 Id. at 29-30.
PDF page 9
9
the Commission can establish the rates and terms of the new Contract Demand Services on a separate track.
A. The Commission Should Be on Guard for Opportunities that Allow for Undue
Discrimination and Continued Delay of Large Load-Interconnection.
Numerous service terms proposed by PJM and the Transmission Owners introduce
opportunities for undue discrimination that have stifled competition and barred the timely interconnection of loads to date.32 On reply, the Transmission Owners introduce several more, including proposing to replace “Delivery Point” in the Illustrative Tariff with “Point of Change in Ownership” to be “consistent” with PJM’s now-rejected definition of Co-Located Load and a host of other proposals that could also give Transmission Owners unfettered discretion.33 The proposal to replace “Delivery Point” with “Point of Change in Ownership” should be denied. Similar to PJM’s rejected definition of Co-Located Load, using Point of Change in Ownership in the Illustrative Tariff would risk “uncertainty or delays for parties in Co-Located Load configurations.”34 To make the Illustrative Tariff consistent with the definition of Co-Located Load, “Delivery Point” should be replaced with “Point of Interconnection.”
32 See Vistra Mar. 25 Reply at 4-5 (“The proposal appears to allow PJM and the Transmission Owners to determine, for each transmission service request, whether studies are required, which studies to conduct, the timeline for doing so, and how to prioritize different requests. That level of discretion creates textbook opportunities for the type of undue discrimination that the Order was intended to prevent.”); Constellation Mar. 25 Reply at 21-25 (discussing Transmission Owners’ recommendations on special protection schemes); see also supra note 21.33 Indicated TO Mar. 25 Reply at 19.34 PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at P 27 (2026).
PDF page 10
10
The Commission should also act to mitigate the Transmission Owners’ new proposals that could give them unfettered discretion over the timelines and technical requirements, including the following Transmission Owner requests:
• “Tariff should specify that Transmission Owners’ load integration studies will be completed first;”35
• “[T]he relevant Transmission Owner’s approval must be included in the process of allowing service to be reinstated” after service was suspended;36
• “[T]echnical requirements should also require an Eligible Customer to satisfy any applicable Transmission Owner-imposed technical requirements;”37
• “PJM Transmission Owners request that PJM add, as a condition precedent for receiving service, that the Eligible Customer satisfy any load-connection related requirements imposed by the applicable PJM Transmission Owner(s);”38 and
• “[T]he PJM Transmission Owners request that PJM add language to the list of information to be provided in an application for Firm Contract Demand
Transmission Service and/or Non-Firm Contract Demand Transmission Service to the effect that the customer has met applicable load interconnection study obligations.”39
It is possible that some of these proposed requirements, with sufficient transparency, standards and timelines, could be reasonable. However, without clarity with respect to the obligations on Eligible Customers, Co-Located Generators, and the Transmission Owners that currently function as gatekeepers for the implementation of these configurations, it is almost certain that the expedition desired by the Commission in issuing this landmark order will not be
35 Indicated TO Mar. 25 Reply at 6 (emphasis added).
36 Id. at 11 (emphasis added). 37 Id. at 13 (emphasis added). 38 Id. at 18 (emphasis added).39 Id. at 19 (emphasis added).
PDF page 11
11
achieved. The history of this proceeding suggests that the parties have widely disparate views of the appropriate process, timing, and obligations.40
The Commission can deter these delays and potential disputes with two simple solutions.
First, the Commission can direct PJM to establish deadlines for studies and other Transmission Owner approvals or consultation requirements. Deadlines are commonplace in PJM’s Tariff and
procedures.41 PJM should be able to adopt them here.
40 See, e.g., Constellation Complaint at 7 (“Exelon is refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled interconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, and forcing additional services to be procured.”); id. at 7-8. (“Exelon fulfilled its responsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear station, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center (‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); id. at 8 (“projects are being held hostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); id. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”) (citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully Isolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ refusal to cooperate … with reliability studies related to interconnection modifications.”); see also Constellation Energy Generation, LLC November 21, 2025 Supporting Comments, Docket No. RM26-4-000 at 3-4 (Nov. 21, 2025) (“Some Transmission Owners have simply refused to participate in PJM’s studies to analyze reliability impacts; and some, acting under unfiled interconnection study procedures, have changed their entire construct and timetable for processing load studies.”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., Docket Nos. EL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff to require this one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different configuration.”); id. at 14 (“What is more, regardless of what the Tariff actually says and does not say, some of the Indicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load agrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) (citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on LaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to complete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to Constellation by $15.3-$19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (2025) (“[T]here are allegations in the record that Exelon has delayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s concerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail distribution service.”).
41 Vistra Mar. 25 Reply at 34 (discussing timelines for generator interconnection requests).
PDF page 12
12
Second, the Commission should require PJM’s and Transmission Owners’ standards,
requirements, guidance, and practices on Co-Location Arrangements to be on file with the Commission on a standalone basis or reflected in PJM’s Tariff.42 Rules for Co-Location
Arrangements must be clearly stated and available as they “significantly affect rates, terms and conditions” of service and can be “readily susceptible to specification.”43 They cannot be hidden and subject to unilateral change without any notice or without any Commission oversight.44 In particular, the study process and standards applicable to Interim NITS requests should be the first priority. Interim NITS should be the easiest of the various new transmission services to implement for the reasons Constellation has discussed previously.45 Furthermore, many co- location requests are for front of the meter NITS, for which an Interim NITS option would provide immediate relief. PJM’s omission of any detail with respect to this study process does not comply with the Commission’s directive to provide additional record evidence to set the appropriate replacement rates, terms and conditions for Interim NITS.46 The Commission should direct PJM to file its study process for Interim NITS within 30 days.
42 Id. at 5 (“In directing further compliance, Vistra urges the Commission to provide as specific and detailed guidance as possible, in addition to setting tight compliance deadlines, to achieve the Commission’s laudable goal of providing the clarity needed to promote the expeditious interconnection of large loads.”); id. at 31 (“The study process in PJM’s proposal is flawed because it reserves for PJM and the Transmission Owners too much discretion to determine whether studies are required for a particular customer, which studies to conduct, the timeline for doing so, and how to prioritize different requests.”); id. at 32 (“[I]t reserves to PJM and the Transmission Owners unfettered discretion with respect to ‘the necessary steps that apply to Interconnection Customers seeking to serve Co-Located Load through a Co-Location Arrangement.’”).43 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018).44 See RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212, at P 38 (2026) (“The Commission does not review and approve PJM’s manuals, as they are not filed with the Commission. As a result, we have no statutory obligation to enforce the terms of Manual 14B.”) (citations omitted).45 See Constellation Mar. 25 Reply at 6-9.46 December 18th Order, 193 FERC ¶ 61,217 at P 219 & Ordering Para. (D).
PDF page 13
13
B. Without Intervention, the Commission’s Requirement for Special Protection Schemes is at Risk for Misuse
On balance, the Commission must be on guard for attempts by Transmission Owners to effectively block access to the new Interim NITS and Contract Demand Services. One proposal with the potential to continue to delay and thwart Co-Location Arrangements is the request that Co-Location Arrangements reflect Transmission Owners’ mandates for special protection schemes.47 In our Reply Brief, we explained that several recommendations on special protection schemes proposed in the Transmission Owners’ Initial Brief are “unsupported and unduly discriminatory towards Co-Located Load arrangements,” including recommendations to require double special protection schemes on both the customer and Transmission Owner side of the Point of Interconnection, to allow Transmission Owners to own an Eligible Customer’s special protection schemes, to limit the amount of load that can be covered by the special protection scheme, and to test special protection schemes for Co-Located Loads more frequently.48 Constellation explained “[p]rotection schemes ‘regularly employed on the PJM transmission system’ are not subject to these new requirements” and there is “no legitimate basis for treating Co-Located Load arrangements differently.”49
In their Reply Brief, the Transmission Owners continue to advocate that PJM “make clear that necessary control technologies and protection systems may (some would say should) be required on … both the customer’s side and the Transmission Owner’s side of the point of interconnection.”50 Like before, the recommendation that PJM impose double protection schemes
47 December 18th Order, 193 FERC ¶ 61,217 at P 205.48 Constellation Mar. 25 Reply at 24-25.49 Id. at 25 (quoting December 18th Order, 193 FERC ¶ 61,217 at P 205).50 Indicated TO Mar. 25 Reply at 8 (emphasis added).
PDF page 14
14
for Co-Located Loads as a default requirement is unsupported and unduly discriminatory. As Michael Kormos, PJM’s former Chief Operations Officer and Exelon’s Senior Vice President, explains in his Affidavit attached here, “there is no rational basis to require double special protection schemes by default”51 and, in fact, double special protection schemes52 would likely be appropriate only in “rare”53 situations. Put simply, always requiring double special protection schemes is not good utility practice.54
Given our concerns regarding discrimination,55 we elaborate further here on the need for PJM to establish a fair and transparent study process for determining the required special protection schemes to prevent further delays of Co-Location Arrangements and the effective blocking of large loads from taking the new transmission services. As Mr. Kormos recommends, PJM can develop a Co-Located Load request study process that leverages its existing generator
51 Kormos Second Affidavit at ¶ 7.52 The terms “special protection scheme,” “remedial action scheme, “special protection system,” and “system protection scheme” are used interchangeably. See NERC, Glossary of Terms Used in NERC Reliability Standards, at 49 (updated Apr. 1, 2026) (“NERC Glossary”) (stating the definition of “Special Protection System (Remedial Action Scheme)” is “See ‘Remedial Action Scheme’”); December 18th Order, 193 FERC ¶ 61,217 at P 204 (“special protection scheme, also known as a remedial action scheme”). We use the term “special protection scheme” to be consistent with the December 18th Order. Id. The Commission defines “special protection scheme” as “a plan designed to detect abnormal system conditions and to automatically take appropriate corrective action, to maintain system stability, acceptable system voltages, and acceptable facility loading.” Id. NERC defines “remedial action scheme” as “[a] scheme designed to detect predetermined System conditions and automatically take corrective actions that may include, but are not limited to, adjusting or tripping generation (MW and Mvar), tripping load, or reconfiguring a System(s).” NERC Glossary at 43-45. NERC identifies fourteen schemes and systems that are not considered a special protection scheme, including, “Schemes for automatic underfrequency load shedding (UFLS) and automatic undervoltage load shedding (UVLS) comprised of only distributed relays.” Id.53 Kormos Second Affidavit at ¶ 11; see also id. at ¶ 7 (“Double special protection schemes may be appropriate in some circumstances where the risks are so severe that redundancy is critical, but as I discuss below, that is more likely to be exception for Co-Location Arrangements than the rule.”).54 Id. at ¶ 7.55 See supra note 40.
PDF page 15
15
interconnection process and Regional Transmission Expansion Plan (“RTEP”) process.56 Three principles should guide PJM in adopting these existing frameworks.57
First, system studies of unauthorized use “should be standardized, transparent, and based on reasonable assumptions set ahead of time.”58 The absence of such provisions creates the exact circumstances that led to the Commission finding PJM’s Tariff unjust and unreasonable— “disparate treatment in PJM” where Transmission Owners take “different approaches to performing the necessary steps that apply to Interconnection Customers seeking to serve Co- Located Load through a Co-Location Arrangement.”59 PJM can adopt the standardized study processes used in its existing generator interconnection process and RTEP process and that determine whether a special protection scheme is needed in the first place. There are already well- established reliability tests in both the RTEP and the generator interconnection process that can evaluate whether a new request would create reliability criteria violations that need to be mitigated by a proposed special protection scheme.60
Second, criteria should be reasonable and transparent for PJM to assess system performance against.61 In the RTEP process, PJM assesses system performance against the mandatory planning requirements in NERC Reliability Standards, PJM’s own planning criteria, and individual Transmission Owner planning criteria reflected in each Transmission Owner’s
56 Kormos Second Affidavit at ¶ 12 (citing PJM Manuals 14A and 14B).57 Id. at ¶ 13.58 Id.59 December 18th Order, 193 FERC ¶ 61,217 at P 175.60 PJM Manual 14A, §§ 4.3-4.4.61 Kormos Second Affidavit at ¶ 14.
PDF page 16
16
Form No. 715. The current criteria should be leveraged to develop specific criteria regarding co- located load risk.62
Third, the special protection scheme that PJM requires an Eligible Customer to implement should be commensurate with the risks identified in the studies.63 While PJM has commonly used special protection systems for over 30 years,64 Mr. Kormos states “special protection schemes (above and beyond normal equipment protection) are not appropriate for every situation.”65 PJM only requires them when “appropriate,”66 that is, when studies identify “actual overloads and conditions that could cause cascading failures that PJM cannot mitigate through normal operations.”67 PJM does not use special protection schemes to mitigate contractual issues (such as unauthorized withdrawals).68 The appropriate remediation for Co-Location Arrangements will vary “depending on the Co-Location Arrangement, location of the co-located generator on the system, the robust nature of the system in the vicinity and other factors.”69 Mr. Kormos discusses the likely appropriate remediation for the following three examples to illustrate this variability.
• Example 1: a Co-Location Arrangement where the Co-Located Load is physically connected to an existing large generator that is connected to the Extra-High Voltage system (i.e., 345kV, 500 kV, or 765 kV) and the Co-Located Load is less than the generation at the site (i.e., a 2500 MW generator with 500 MW of load).70
• Example 2: a Co-Location Arrangement where the Co-Located Load is physically connected to an existing large generator that is connected to the Extra-High Voltage
62 See PJM Manual 14B at 116.63 Kormos Second Affidavit at ¶ 15.64 See PJM Manual 03 at Att. A (listing 14 remedial action schemes in PJM, two of which were installed pre-1995).65 Kormos Second Affidavit at ¶ 6. 66 PJM Manual 14B at 116.67 Kormos Second Affidavit at ¶ 5.68 Id.69 Id. at ¶ 8.70 Id. at ¶ 9.
PDF page 17
17
system and the Co-Located Load is equal to the generation at the site (i.e., a 700 MW generator physically connected with 700 MW of load).71
• Example 3: a Co-Location Arrangement where the Co-Located Load will be
physically connected to a new generator in an area without robust transmission.72 In Example 1, Mr. Kormos explains that “technical studies would likely show that the loss of the generator serving the Co-Located Load without the load immediately tripping (a net loss of 500 MW of generation) may have no reliability impact on the grid in all scenarios studied.”73 In that circumstance, Mr. Kormos posits that appropriate remediation could be to “simply have operating procedures to manually remove the load should the load not automatically disconnect after a generator trip with the ability, if required, for the Transmission Owner to remotely operate breakers to ensure the load is removed to prevent reliability issues.”74
In Example 2, Mr. Kormos states that “technical studies could show that the loss of the generation could cause unplanned withdrawals that result in some criteria violations but only cause contingency overloads or actual overloads that are still within short term ratings (i.e., 4-hour ratings) and within timeframes that allow normal operator actions.”75 In that circumstance, Mr. Kormos suggests the “appropriate remediation could include primary and secondary relaying to remove the load after a generation reduction and operating procedures to require manual load tripping with the ability of the Transmission Owner to remotely trip the load if the customer does not comply with a System Operator’s request.”7671 Id. at ¶ 10.72 Id. at ¶ 11.73 Id. at ¶ 9.74 Id.75 Id. at ¶ 10.76 Id.
PDF page 18
18
In Example 3, Mr. Kormos states, “technical studies would likely show that the system does not have the capability to handle large withdrawals under most conditions and identify significant criteria violations where actual overloads could cause a possible cascading event.”77 In such circumstance, Mr. Kormos suggests “a fully redundant special protection scheme located on both Eligible Customer Interconnection Facilities and Transmission Owner Interconnection Facilities could be appropriate.”78 Mr. Kormos, however, explains Co-Location Arrangements with new generation are “unlikely” to locate in areas without robust transmission, likely making the necessity for double special protection schemes to maintain reliability “rare.”79 Double special protection schemes should not be employed when other measures can maintain system reliability and real time monitoring can address any unexpected reliability issue.80
III. Critical Terms of Service Need Refinement
Several critical terms of service require further elaboration to make the new transmission services commercially workable. PJM should clarify how it will determine the future and real-time availability of Non-Firm Contract Demand Service.81 Consistent with the December 18th Order, Non-Firm Contract Demand Service should be available “when transmission capacity is available and not needed by firm customers.”8277 Id. at ¶ 11.78 Id.79 Id.80 Id. ¶ 16.81 Indicated TO Mar. 25 Reply at 4 (stating “it is not clear” if the study process for determining what level of Contract Demand Services can be provided is “meant to cover only the initial service study, or also subsequent determinations as to available Non-Firm capacity based on specific reservation requests”); Vistra Mar. 25 Reply at 31 (“the Commission should require PJM to clarify how it will assess whether non-firm service can occur “reliably”).82 December 18th Order, 193 FERC ¶ 61,217 at P 214.
PDF page 19
19
PJM should also clarify when and how Interim NITS and Non-Firm Contract Demand
Service will be curtailed.83 In doing so, PJM should not modify its curtailment order “so that Non- Firm Contract Demand Transmission Service load is curtailed prior to generation redispatch,” as recommended by the Transmission Owners.84 The Transmission Owners claim that modifying the curtailment order only for Non-Firm Contract Demand Service is necessary to address their concern that requiring Eligible Customers to pay redispatch costs “could result in cost shifts onto other customers because Eligible Customers may represent multiple load customers.”85 Generation redispatch, however, occurs all the time. If Non-Firm Contract Demand Service is curtailed in every instance, the product would be unusable. The curtailment order for Non-Firm Contract Demand Service should be the same as Non-Firm Point to Point Transmission. Only those Non- Firm Point to Point Transmission Service customers “not willing to pay through congestion,” that did not elect to pay redispatch costs, are required to curtail before generation redispatch. Without these clarifications, Eligible Customers and Co-Located Loads could be deterred from investing hundreds of millions of dollars on Co-Location Arrangements that would otherwise avoid unnecessary transmission upgrades to the benefit of all PJM customers, while
simultaneously contributing to our nation’s security and economic interests.
83 Indicated TO Mar. 25 Reply at 15 (“There should be load shedding practice guidelines applicable to Co-Located Load arrangements established by PJM.”); Joint Developer Mar. 25 Reply at 17 (“PJM’s proposed tariff does not provide adequate clarity regarding when and how Non-Firm CDS and Interim NITS shall be curtailed.”); United & SEIA Mar. 25 Reply at 12. (“PJM has provided no information about the conditions that would actually trigger curtailment of Interim NITS or Non-Firm Contract Demand Transmission Service in practice.”); id. at 11 (stating PJM discussion on its curtailment order is “contradictory” and “must be clarified and reconciled to confirm consistency with the Commission’s directive.”); DCC Mar. 25 Reply at 7 (“PJM’s proposal relies heavily on curtailment as a mechanism to maintain system reliability, but it does not provide sufficient clarity regarding how curtailment will be applied in practice.”).84 Indicated TO Mar. 25 Reply at 17.85 Id. at 17.
PDF page 20
20
CONCLUSION
WHEREFORE, Constellation respectfully requests that the Commission without delay issue an order (1) approving and making Interim NITS effective October 1, 2026, (2) directing PJM and the Transmission Owners to support new transmission services and rejecting attempts to restrict, delay, or otherwise discourage them and requiring oversight to ensure undue discrimination does not delay interconnection of large loads, and (3) directing PJM and the Transmission Owners to refine their proposals to provide sufficient certainty to make the new transmission services commercially workable.
Respectfully submitted,
/s/ Paul F. Wight
April 24, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
Seth T. Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 21
CERTIFICATE OF SERVICE
I hereby certify that I have on this 24th day of April, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025).
/s/ Sophia Browning
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
PDF page 22
EXHIBIT 1
AFFIDAVIT OF MICHAEL KORMOS
PDF page 23
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
AFFIDAVIT OF
MICHAEL KORMOS
April 24, 2026
I. QUALIFICATIONS AND OVERVIEW OF AFFIDAVIT
1. My name is Michael Kormos. My extensive professional experience includes transmission planning and operations as a senior executive at both PJM Interconnection, L.L.C. (“PJM”) and one of the largest transmission owners within the PJM region. I currently serve as an electric utility consultant helping industry participants develop transmission interconnection and transmission solutions and resolve issues related thereto. Until 2021, I was Sr. Vice President, Transmission & Compliance for Exelon Corporation, where I was responsible for the operations and long-term planning for transmission systems of Exelon utilities Atlantic City Electric, Baltimore Gas &
PDF page 24
2
Electric, ComEd, Delmarva Power, PECO, and PEPCO. In that role, I shaped Exelon and its utilities’ policy positions on issues related to the Federal Energy Regulatory Commission (“FERC”), Regional Transmission Organizations (“RTOs”), and national transmission matters.
2. Before joining Exelon, I spent 27 years at PJM. As PJM’s Chief Operations Officer, I was responsible for grid planning and operations and directly involved in implementing numerous significant FERC orders, including Order No. 1000, and supported the development and implementation of competitive wholesale markets in PJM. Earlier in my career at PJM, I oversaw an operational expansion that tripled the size of the system controlled by PJM. I also held management and engineering positions in transmission operations while at PJM.
3. I have been asked by Constellation Energy Generation, LLC (“Constellation”) to prepare an affidavit that responds to comments on special protection schemes in the Reply Brief filed by the Indicated Transmission Owners.1 In Section II, I rebut three assumptions the Indicated Transmission Owners imply about special protection schemes and discuss the general purpose of special protection schemes as well as how PJM currently determines the remediation necessary to maintain system reliability. In Section III, I recommend that PJM leverage its existing generator interconnection process and Regional Transmission Expansion Plan (“RTEP”) process as the model for studying and determining appropriate remediation for Co-Located Load requests.2 In
1 See Indicated Transmission Owners March 25, 2026 Reply Brief. The Indicated Transmission Owners that filed the March 25, 2026 Reply Brief are a subset of Transmission Owners in PJM, excluding Old Dominion Electric Cooperative, for example.2 See PJM Manual 14A and 14B.
PDF page 25
3
Section IV, I explain that real time monitoring can support PJM in addressing reliability risks caused by unreserved Co-Located Load use of the system.
II. PURPOSE OF SPECIAL PROTECTION SCHEMES AND PROCESS FOR SELECTING
APPROPRIATE REMEDIATION
4. The reply comments by Indicated Transmission Owners imply three incorrect assumptions about special protection schemes: (1) the purpose of special protection schemes is to “ensure that a Co-Located Load does not exceed its specified level of transmission service,”3 that is, to deter unreserved use; (2) special protection schemes “must be implemented”4 for all Co- Location Arrangements to maintain reliability; and (3) special protection schemes should be required on “both the customer’s side and the Transmission Owner’s side of the point of interconnection.”5 Below, I rebut each assumption in turn while explaining the purpose of special protection schemes and how PJM currently determines their necessity.
5. First, the purpose of special protection schemes is not to deter unreserved use of the transmission system. That is the purpose of penalties. Special protection schemes are intended to maintain reliability by protecting the system from actual overloads and conditions that could cause cascading failures that PJM cannot mitigate through normal operations. They are not intended to manage contractual requirements or mitigate conditions that PJM can manage through normal operations, such as contingency overloads that can be tolerated based on a four-
3 Indicated TO Mar. 25 Reply at 8.
4 Id.5 Id.
PDF page 26
4
hour transmission line rating specification6 or other conditions where PJM has adequate time and tools to maintain reliability.
6. Second, requiring special protection schemes by default for every Co-Location Arrangement is not good utility practice. While special protection schemes are commonly used,7 special protection schemes (above and beyond normal equipment protection) are not appropriate for every situation. This is because the technical studies that PJM conducts, which form the basis for remediation, do not always show that an interconnection request could result in a criteria violation that could lead to severe actual overloads and the need for immediate or instantaneous response to maintain reliability. Requirements for special protections schemes should reflect the basic principle that we should not require interventions that add technical complexity to the system when such interventions are not necessary, e.g., when the reliability risks do not merit such interventions. In short, special protection schemes should only be implemented when necessary.
7. Third, it is not good utility practice to always require Co-Location Arrangements to have special protection schemes on “both the customer’s side and the Transmission Owner’s side of the point of interconnection.”8 As I explain above, PJM studies do not always show that an interconnection of load could lead to an actual overload and in such cases a special protection scheme would be inadvisable. Double special protection schemes may be appropriate in some circumstances where the risks are so severe that redundancy is critical, but as I discuss below, that is more likely to be exception for Co-Location Arrangements than the rule. There is no
6 See PJM Manual 03, § 3.3.7 See id. at Att. A (listing 14 remedial action schemes in PJM). The term “remedial action scheme” has the same meaning as special protection scheme.8 Indicated TO Mar. 25 Reply at 8.
PDF page 27
5
rational basis to require double special protection schemes by default. To the extent that there are concerns about customers maintaining these schemes it would be more appropriate to handle these situations through NERC and Regional standards with the appropriate financial penalties for non-compliance as the industry does with the current special protection devices.
8. Study results, and thus, the appropriate remediation necessary to maintain reliability, will vary depending on the Co-Location Arrangement, location of the co-located generator on the system, the robust nature of the system in the vicinity and other factors. Three examples of Co- Location Arrangements illustrate this point:
9. Example 1: a Co-Location Arrangement where the Co-Located Load is physically
connected to an existing large generator that is connected to the Extra-High Voltage system (i.e., 345kV, 500 kV, or 765 kV) and the Co-Located Load is less than the generation at the site (i.e., a 2500 MW generator with 500 MW of load).
In Example 1, technical studies would likely show that the loss of the generator serving the Co-Located Load without the load immediately tripping (a net loss of 500 MW of generation) may have no reliability impact on the grid in all scenarios studied. This is because the system supporting large generators is designed to handle all levels of potential generation dispatch and typically will handle small amounts of net withdrawals without issue. Large generators also typically provide significant inertia that can help the local grid avoid or minimize the impact of many anomalies. In this circumstance, the appropriate remediation to maintain reliability could likely be to simply have operating procedures to manually remove the load should the load not automatically disconnect after a generator trip with the ability, if required, for the Transmission Owner to remotely operate breakers to ensure the load is removed to prevent reliability issues. It is also quite likely that customers may choose to put relaying in place to automatically remove the load to avoid any possible financial penalties for unauthorized withdrawals and further increase reliability.
PDF page 28
6
10. Example 2: a Co-Location Arrangement where the Co-Located Load is physically connected to an existing large generator that is connected to the Extra-High Voltage system and the Co-Located Load is equal to the generation at the site (i.e., a 700 MW generator with 700 MW of load).
In Example 2, where the existing generation and Co-Located Load are equal, technical studies could show that the loss of the generation could cause unplanned withdrawals that result in some criteria violations but only cause contingency overloads or actual overloads that are still within short term ratings (i.e., 4-hour ratings) and within timeframes that allow normal operator actions. In this case, appropriate remediation could include primary and secondary relaying to remove the load after a generation reduction and operating procedures to require manual load tripping with the ability of the Transmission Owner to remotely trip the load if the customer does not comply with a System Operator’s request.
11. Example 3: a Co-Location Arrangement where the Co-Located Load will be physically connected to a new generator in an area without robust transmission.
In Example 3, technical studies would likely show that the system does not have the capability to handle large withdrawals under most conditions and identify significant criteria violations where actual overloads could cause a possible cascading event. In this situation, a fully redundant special protection scheme located on both Eligible Customer Interconnection Facilities and Transmission Owner Interconnection Facilities could be appropriate. Given the increased reliability risks, however, most Co-Location Arrangements with new generation are unlikely to locate in areas without robust transmission, making this example likely to be rare in practice.
III. A FAIR AND TRANSPARENT PROCESS FOR DETERMINING REMEDIATION MEASURES
12. I understand that PJM has not articulated the studies it will perform on Co-Located Load arrangements that would be the basis for determining the appropriate remediation necessary to maintain system reliability. Without additional clarification, PJM risks further delaying the interconnection of large loads and the potential of parties studying “extreme cases” to simply show
PDF page 29
7
violations, not actual reliability and stability risks. To ensure a fair and transparent process, PJM should develop a Co-Located Load request study process leveraging its existing generator interconnection study process and RTEP process as models.
13. Three principles should guide PJM in adapting its existing processes. First, system studies of unauthorized use should be standardized, transparent, and based on reasonable assumptions set ahead of time (and not guided by an opaque process and rules that differ from Transmission Owner to Transmission Owner). Like the generator interconnection study process, the study process for Co-Located Loads should be PJM-driven where most of the studies are all done based on RTO- wide processes and Transmission Owners have to justify any exception they require.
14. Second, PJM should develop criteria for PJM to assess system performance to establish acceptable/unacceptable levels of risk. These criteria should be based on the existing NERC and Regional standards used today to assess reliability risk.
15. Third, remediation should be commensurate with the level of risk identified in the studies. If the studies show no reliability issues, then no additional remediation should be required. This is not to say there is no protection. Interconnection facilities typically always include general protection schemes, such as equipment protection relaying and control devices.
IV. ADDITIONAL MEASURES TO ENSURE RELIABILITY
16. Some may argue that because planning models may not capture all possible situations that could present a reliability risk (which is true for all planning analysis), PJM should require special protection scheme for all Co-Location Arrangements. While some scenarios may go unstudied, the solution to ensuring adequate reliability and stability is not to over-mitigate. Rather, PJM should monitor in real-time and adjust remediation as necessary. Real-time monitoring is standard for a system operator. In fact, PJM proposes to monitor the Co-Located Load demand on the
PDF page 30
8
Transmission System.9 Real-time monitoring of Co-Located Load should also be simple for PJM to implement. Most standard metering equipment can provide real time telemetry. PJM needs to add the individual load and generation to the model and set-up the standard communications to receive the data. PJM already has standard process to do both on a routine basis. Including these resources should be no different than adding any other facility to the models.
17. This concludes my affidavit.
9 Initial Brief of PJM Interconnection, L.L.C. at 64 (Feb. 23, 2026).
PDF page 31
VERIFICATION
I declare under penalty of perjury that the foregoing Affidavit is true and correct to the best of my knowledge, information, and belief.
Executed this 24th day of April, 2026.
________________________
Michael Kormos