Response Brief of Constellation Energy Generation, LLC
Text extracted from the eLibrary original (SHA-256 8cc4e22e2f25a851…). Download the original from the official source.
Contents · 9 sections
- I. Winning the AI Race Requires a Sprint, Not a Stroll
- II. New Transmission Services Should Be Supported, Not Discouraged or Made
- A. The Commission Should Be on Guard for Opportunities that Allow for Undue
- B. Without Intervention, the Commission’s Requirement for Special Protection
- III. Critical Terms of Service Need Refinement
- CONCLUSION
- I. QUALIFICATIONS AND OVERVIEW OF AFFIDAVIT
- II. PURPOSE OF SPECIAL PROTECTION SCHEMES AND PROCESS FOR SELECTING
- IV. ADDITIONAL MEASURES TO ENSURE RELIABILITY
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
EL25-20-000 (Consolidated) RESPONSE BRIEF OF CONSTELLATION ENERGY GENERATION, LLC Constellation1 submits this response brief to discuss three points with broad support in the reply briefs regarding how PJM and the Transmission Owners2 must modify their proposals to ensure compliance with the…Read this passage
I. Winning the AI Race Requires a Sprint, Not a Stroll
printed heading · Topic match: Connecting load and generation
March 25, 2026 Reply at 13 (“At this time, neither PJM nor the PJM Transmission Owners have a specific concept for the Commission to consider, but have committed to working together to explore penalty options.”); DCC Mar. 25 Reply at 8 (“DCC is also concerned that the proposed framework leaves…Read this passage Filed comments: Connecting load and generation
II. New Transmission Services Should Be Supported, Not Discouraged or Made
printed heading · Topic match: Connecting load and generation
See also Exhibit 1 attached, the Affidavit of Michael Kormos (“Kormos Second Affidavit”), discussing purpose of special protection schemes and recommending PJM adopt its New Service Request Study Process and Regional Transmission Expansion Plan process to study reliability impacts of Co-Located…Read this passage Filed comments: Connecting load and generation
A. The Commission Should Be on Guard for Opportunities that Allow for Undue
printed heading · Topic match: Connecting load and generation
Similar to PJM’s rejected definition of Co-Located Load, using Point of Change in Ownership in the Illustrative Tariff would risk “uncertainty or delays for parties in Co-Located Load configurations.”34 To make the Illustrative Tariff consistent with the definition of Co-Located Load, “Delivery…Read this passage Filed comments: Connecting load and generation
B. Without Intervention, the Commission’s Requirement for Special Protection
printed heading · Topic match: Connecting load and generation
Kormos discusses the likely appropriate remediation for the following three examples to illustrate this variability. • Example 1: a Co-Location Arrangement where the Co-Located Load is physically connected to an existing large generator that is connected to the Extra-High Voltage system (i.e.,…Read this passage Filed comments: Connecting load and generation
III. Critical Terms of Service Need Refinement
printed heading · Topic match: Reliability and curtailment
Without these clarifications, Eligible Customers and Co-Located Loads could be deterred from investing hundreds of millions of dollars on Co-Location Arrangements that would otherwise avoid unnecessary transmission upgrades to the benefit of all PJM customers, while simultaneously contributing to…Read this passage Filed comments: Reliability and curtailment
CONCLUSION
printed heading
CONCLUSION WHEREFORE, Constellation respectfully requests that the Commission without delay issue an order (1) approving and making Interim NITS effective October 1, 2026, (2) directing PJM and the Transmission Owners to support new transmission services and rejecting attempts to restrict, delay,…Read this passage
CERTIFICATE OF SERVICE
printed heading
Large Loads Co-Located at Generating Facilities Constellation Energy Generation, LLC v.Read this passage
I. QUALIFICATIONS AND OVERVIEW OF AFFIDAVIT
printed heading · Topic match: Connecting load and generation
In Section III, I recommend that PJM leverage its existing generator interconnection process and Regional Transmission Expansion Plan (“RTEP”) process as the model for studying and determining appropriate remediation for Co-Located Load requests.2 In 1 See Indicated Transmission Owners March 25,…Read this passage Filed comments: Connecting load and generation
II. PURPOSE OF SPECIAL PROTECTION SCHEMES AND PROCESS FOR SELECTING
printed heading · Topic match: Connecting load and generation
The reply comments by Indicated Transmission Owners imply three incorrect assumptions about special protection schemes: (1) the purpose of special protection schemes is to “ensure that a Co-Located Load does not exceed its specified level of transmission service,”3 that is, to deter unreserved use;…Read this passage Filed comments: Connecting load and generation
IV. ADDITIONAL MEASURES TO ENSURE RELIABILITY
printed heading · Topic match: Connecting load and generation
In fact, PJM proposes to monitor the Co-Located Load demand on the 8 Transmission System.9 Real-time monitoring of Co-Located Load should also be simple for PJM to implement.Read this passage Filed comments: Connecting load and generation