Exhibit No. PTO-0005Page 1 of 31
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
JOINT REBUTTAL TESTIMONY
OF
PETER BLAZUNAS, LANCE SCHAFER
AND
HANHAN HAMMER
I. INTRODUCTION
1
Q.
Please state your name, title, business address, and provide your professional 2
background and relevant experience.
3
A. [Blazunas] My name is Peter Blazunas, and my business address is 293 Boston Post Road 4
West, Marlborough, MA 01752. I am a Vice President with Concentric Energy Advisors, 5
Inc (“Concentric”). I am the same Peter Blazunas who sponsored Direct Joint Testimony 6
filed on February 23, 2026, in this proceeding.
7
[Schafer] My name is Lance Schafer, and my business address is 293 Boston Post 8
Road West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. I 9
am the same Lance Schafer who sponsored Direct Joint Testimony filed on February 23, 10
2026, in this proceeding.
11
PDF page 2
Exhibit No. PTO-0005Page 2 of 31
[Hammer] My name is Hanhan Hammer, and my business address is 293 Boston 1
Post Road West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. 2
I am the same Hanhan Hammer who sponsored Direct Joint Testimony filed on February 3
23, 2026, in this proceeding.
4
[Blazunas, Schafer, and Hammer] Our professional background and relevant 5
experience was provided in Exhibit No. PTO-0002 of our Direct Joint Testimony filed on 6
February 23, 2026, in this proceeding.
7
II. BACKGROUND
8
Q.
What is the background for this proceeding?
9
A. [Blazunas, Schafer, and Hammer] On December 18, 2025, the Commission issued its 10
order in PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 193 (2025) (“Order”). In 11
the Order, the Commission found that PJM’s Open Access Transmission Tariff (“Tariff”) 12
“is unjust and unreasonable because it does not contain provisions addressing with 13
sufficient clarity or consistency the rates, terms, and conditions of service that apply to 14
generators serving Co-Located Load and Eligible Customers taking transmission service 15
on behalf of Co-Located Load.”1 Specifically, the Commission found PJM’s Tariff “unjust 16
and unreasonable because it does not include types of transmission service that reflect 17
Eligible Customers taking service on behalf of Co-Located Loads that are willing and able 18
to limit their use of the transmission system under certain conditions.”2 19
The Commission ordered PJM to offer three new forms of transmission service 20
under its Tariff, and identified these three new forms of transmission service as: (i) Firm 21
1 Order at P 2.2 Id.
PDF page 3
Exhibit No. PTO-0005Page 3 of 31
Contract Demand transmission service (“Firm Contract Demand Service”); (ii) Non-Firm 1
Contract Demand transmission service (“Non-Firm Contract Demand Service”); and (iii) 2
interim, non-firm transmission service (usually referred to as “Interim NITS”). The 3
Commission also established a paper hearing to determine the just and reasonable rates, 4
terms, and conditions for these new transmission services. The paper hearing process 5
provides for initial briefs, responses to initial briefs, and replies to those responses. 6
III. PURPOSE OF TESTIMONY
7
Q.
What is the purpose of your testimony?
8
A. [Blazunas, Schafer, and Hammer] The purpose of our testimony is twofold. First, we 9
provide additional detail regarding a proposal to impose financial penalties for Eligible 10
Customers3 taking service on behalf of Co-Located Load that make unreserved use of the 11
transmission system. Second, we respond to certain criticisms made by parties in their reply 12
briefs regarding the rate designs proposed by the PJM Transmission Owners4 for the three 13
new transmission services required by the Order. This includes our responses to testimony 14
3 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C.4 For purposes of this testimony and the accompanying reply brief, the PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid- Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.
PDF page 4
Exhibit No. PTO-0005Page 4 of 31
accompanying the reply briefs filed by Constellation Energy Generation, LLC 1
(“Constellation”) and Vistra Corp. (“Vistra”) that address the PJM Transmission Owners’ 2
Grid Reliance Charge proposal.
3
IV. FINANCIAL PENALTY PROPOSAL
4
Q.
Should unreserved use penalties apply to Eligible Customers taking Firm Contract 5
Demand Service, Non-Firm Contract Demand Service, or Interim NITS on behalf of 6
Co-Located Load?
7
A. [Hammer] Yes. Robust penalty provisions are a necessary component of the new services 8
required by the Commission. First, and most importantly, any penalties must be sufficient 9
to meaningfully deter Co-Located Load customers from exceeding their contract demand 10
or Interim NITS limits and making unreserved use of the transmission system. Because 11
network upgrades are planned and built only to accommodate load covered by Firm 12
Contract Demand Service or NITS, it is crucial that Co-Located Loads respect their 13
contractual limits, including any related curtailment or other instructions from PJM. This 14
concern is particularly acute because many of these arrangements will likely involve 15
substantial amounts of load—hundreds, if not thousands of MW—being served by on-site 16
generation but still connected to the grid. If these limits are not respected, the reliability 17
consequences to the system—and to existing customers that rely on the reliable operation 18
of that system—could be severe.
19
Q.
Has PJM proposed any penalties?
20
A. [Hammer] Yes. PJM’s Initial Brief includes a table summarizing PJM’s proposed 21
operational penalties applicable to Eligible Customers taking service on behalf of Co- 22
PDF page 5
Exhibit No. PTO-0005Page 5 of 31
Located Load.5 PJM explains that it also supports a financial penalty in addition to its 1
proposed operational penalties and that it intends to work with the PJM Transmission 2
Owners to explore a financial penalty framework.6 Specifically, PJM states that 3
“[u]nreserved use penalties should apply to Eligible Customers taking Firm Contract 4
Demand Transmission Service, Non-Firm Contract Demand Transmission Service, or 5
Interim NITS on behalf of Co-Located Load.”7
6
The PJM Transmission Owners agree with PJM that the imposition of financial 7
penalties is appropriate, as any penalty regime should rely on both operational 8
consequences and complementary financial penalties. Although the PJM Transmission 9
Owners anticipate that operational penalties will provide the primary deterrent against 10
Eligible Customers serving Co-Located Load exceeding their reserved transmission 11
service use, financial penalties will play a valuable role in enhancing this deterrent as well 12
as ensuring the market and other ratepayers are made whole if an Eligible Customer serving 13
Co-Located Load exceeds its contract demand or Interim NITS limits.
14
Q.
Do the PJM Transmission Owners have a proposal for an appropriate penalty charge 15
to address any unreserved use of the PJM transmission system by an Eligible 16
Customer taking transmission service on behalf of a Co-Located load?
17
A. [Hammer] Yes. In addition to PJM’s proposed operational penalties for failure to curtail 18
upon instruction, the PJM Transmission Owners propose to apply financial penalties in 19
instances in which an Eligible Customer taking service on behalf of Co-Located Load 20
exceeds the authorized transmission service limits, as described in more detail below. The 21
5 PJM Initial Brief, Docket Nos. EL25-49, et al., at 41 (filed Feb. 23, 2026).6 Id. at 50.7 Id. at 51.
PDF page 6
Exhibit No. PTO-0005Page 6 of 31
authorized transmission service limits will include any reduction based on curtailments 1
directed by PJM.
2
Q.
Do the PJM Transmission Owners propose that the Commission adopt a separate 3
“Failure-to-Curtail” Financial Penalty?
4
A. [Hammer] No. The PJM Transmission Owners are not proposing that the Commission 5
adopt a separate “failure‑to‑curtail” financial penalty. Instead, failure to curtail should be 6
treated as a form of unreserved use and addressed through a single, unified unreserved use 7
financial penalty framework. Failure to curtail inherently results in unauthorized use of the 8
transmission system. As such, it is part of unreserved use and does not warrant a distinct 9
penalty mechanism. However, as indicated above, the financial penalties proposed here 10
will account for any failure to curtail by factoring any curtailments directed by PJM into 11
the determination of an Eligible Customer’s authorized transmission service limits. 12
Q.
Please describe the PJM Transmission Owners’ proposed financial penalties for 13
unreserved use.
14
A. [Hammer] The PJM Transmission Owners propose a financial penalty charge structure 15
for unreserved use with two components: (1) a base penalty charge, which applies to each 16
individual hour in which the reserved transmission service limit is exceeded, and (2) a 17
penalty ratchet, which applies when such exceedances occur repeatedly.
18
Q.
What is the base penalty charge?
19
A. [Hammer] As described in more detail below, when an Eligible Customer taking service 20
on behalf of Co-Located Load exceeds its reserved transmission service limit, the base 21
penalty charge will be assessed for any hour in which at least one five-minute interval 22
occurs during which a customer’s telemetered load at the Point of Delivery exceeds its 23
PDF page 7
Exhibit No. PTO-0005Page 7 of 31
reserved transmission service limit. This five-minute interval is defined as an Exceedance 1
Interval, and such an hour is defined as an Exceedance Hour. The base penalty charge will 2
apply to each Exceedance Hour.
3
Q.
What is the penalty rachet?
4
A. [Hammer] As described in more detail below, the penalty rachet applies when multiple 5
Exceedance Hours occur during a particular time period. It is designed to discourage 6
recurring reliance on unreserved transmission capacity. Under the penalty rachet 7
framework, the penalty charges escalate as the frequency of unreserved transmission use 8
increases. Specifically, if more than one Exceedance Hour occurs on the same calendar 9
day, an additional daily penalty applies. If exceedances occur on multiple calendar days 10
within the same calendar week, an additional weekly penalty applies. Likewise, if 11
exceedances occur in multiple calendar weeks within the same month, an additional 12
monthly penalty applies, and if exceedances occur in multiple months within the same year, 13
an additional yearly penalty applies. By progressively increasing the economic 14
consequences of repeated penalties, the penalty ratchet reinforces the expectation that 15
Eligible Customers taking service on behalf of Co-Located Load customers manage their 16
load in a manner consistent with their reserved transmission service.
17
Base Penalty Charge
18
Q.
Please describe the base penalty charge in more detail.
19
A. [Hammer] The base penalty charge will be assessed for any hour in which at least one 20
five-minute interval occurs during which a customer’s telemetered load at the Point of 21
Delivery exceeds its reserved transmission service limit. Such a five-minute interval is 22
defined as an Exceedance Interval, and such an hour is defined as an Exceedance Hour. 23
PDF page 8
Exhibit No. PTO-0005Page 8 of 31
The base penalty charge will apply to each Exceedance Hour. For purposes of determining 1
whether one or more exceedances have occurred, each five-minute interval beginning with 2
the first minute of each hour shall constitute a separate interval. Similarly, each hour from 3
0100 through 2400 shall constitute a separate hour. I explain the calculation of the reserved 4
transmission service limit and the base penalty charge in the following questions. 5
Q.
How is the reserved transmission service limit determined?
6
A. [Hammer] For an Eligible Customer taking only Firm Contract Demand Service, the 7
reserved transmission service limit will equal the Firm Contract Demand minus any 8
curtailed MW. For an Eligible Customer taking only Non-Firm Contract Demand Service, 9
the reserved transmission service limit will equal the approved Non-Firm Contract Demand 10
minus any curtailed MW. For an Eligible Customer taking Firm Contract Demand Service 11
and Non-Firm Contract Demand Service, the reserved transmission service limit will equal 12
the Firm Contract Demand plus the approved Non-Firm Contract Demand minus any 13
curtailed MW. For an Eligible Customer taking Interim NITS, the reserved transmission 14
service limit will equal the Interim NITS demand minus any curtailed MW. 15
Q.
How is the base penalty charge applied to each Exceedance Hour?
16
A. [Hammer] Under the PJM Transmission Owners’ proposal, the base penalty charge will 17
be applied to each Exceedance Hour and will be calculated as:
18
Hourly Exceedance MW × Equivalent Hourly Firm Contract Demand (“FCD”) rate × 19
number of Exceedance Intervals within the hour
20
Where:
21
Hourly Exceedance MW = Maximum telemetered load during the hour – Reserved 22
Transmission Service Limit for the hour
23
PDF page 9
Exhibit No. PTO-0005Page 9 of 31
Equivalent Hourly FCD rate = FCD rate / 8,760 hours
1
Q.
Why is the Firm Contract Demand Rate used as the basis for assessing the penalty? 2
A. [Hammer] The Firm Contract Demand rate is used as the basis for assessing the penalty 3
because, when a customer exceeds its reserved transmission service limit without 4
authorization, the excess usage effectively imposes firm‑level demand on the system. In 5
effect, the customer utilizes transmission facilities in the same manner as a firm load. 6
Q.
Can you provide an example to illustrate the application of the base penalty charge 7
concept?
8
A. [Hammer] Yes. The following example demonstrates the application of the base penalty 9
charge concept. This example is a hypothetical for illustration purposes only. 10
Firm Contract Demand (“FCD”) Rate is $72,000/MW-Year.
11
12
Equivalent Monthly FCD Rate: $6,000/MW-Month
13
Equivalent Weekly FCD Rate: $1,385/MW-Week
14
Equivalent Daily FCD Rate: $197.26/MW-Day
15
Equivalent Hourly FCD Rate: $8.22/MW-Hour
16
17
April 7, during Houring Ending (“HE”) 12:00 p.m., a Firm Contract Demand customer has 18
a total load of 500 MW and on-site generation of 400 MW. The customer has 100 MW 19
FCD and no approved Non-Firm Contract Demand for the hour.
20
21
At 11:17 a.m., the customer experiences a sudden trip of 400 MW of on‑site generation. 22
While internal power controls immediately begin ramping down load and transferring 23
supply to backup generation, there is a brief delay before the protection systems fully 24
respond. As a result, the customer draws approximately 300 MW from the transmission 25
system for a period of seven minutes, from 11:17 a.m. to 11:24 a.m. (i.e., spanning two 26
five-minute intervals (11:15-11:20 a.m. and 11:20-11:25 a.m.)).
27
28
Because the customer’s telemetered load exceeded its 100 MW of reserved transmission 29
service limit during the HE 12:00 p.m., the HE 12:00 p.m. qualifies as an Exceedance Hour, 30
triggering a financial penalty.
31
32
For HE 12:00 p.m.:
33
Maximum telemetered load = 300 MW
34
Reserved Transmission Service Limit = 100 MW
35
Hourly Exceedance MW = 300 MW – 100 MW = 200 MW
36
PDF page 10
Exhibit No. PTO-0005Page 10 of 31
Hourly FCD Rate = $8.22/MW‑Hour
1
Number of Exceedance Intervals during the hour = 2
2
3
Base Penalty Charge for the HE 12:00 p.m.:
4
= 200 MW × $8.22/MW‑Hour x 2
5
= $3,288
6
7
This penalty charge is in addition to the customer’s existing obligation to pay for its 100 8
MW of FCD under its transmission service agreement.
9
10
Penalty Ratchet
11
Q.
Please describe the penalty ratchet in more detail.
12
A. [Hammer] The PJM Transmission Owners’ also propose a penalty ratchet to address 13
repeated exceedance behavior based on the frequency of unreserved use of the transmission 14
system. This penalty rachet is designed to discourage recurring reliance on unreserved 15
transmission capacity. Under this framework, the penalty rate escalates as the frequency of 16
unreserved transmission use increases. By progressively increasing the economic 17
consequences of repeated exceedances, the penalty ratchet reinforces the expectation that 18
Eligible Customers manage their Co-Located Load in a manner consistent with their 19
reserved transmission service limits.
20
Q.
Can you explain the overall mechanics of the penalty ratchet?
21
A. [Hammer] Yes. The penalty ratchet is based on an Eligible Customer’s exceedance pattern 22
and applies escalating FCD–equivalent rates as the frequency of unreserved transmission 23
use increases. Depending on whether exceedances occur within the same calendar day, 24
calendar week, calendar month, or calendar year, the penalty ratchet applies daily, weekly, 25
monthly, or annual penalty charges, respectively. Below is an overview of the penalty 26
ratchet:
27
28
PDF page 11
Exhibit No. PTO-0005Page 11 of 31
Exceedance Pattern
Penalty Rate Applied
Multiple Exceedance Hours in a single calendar day
Daily FCD-Equivalent Rate
Multiple Exceedance Days within a calendar week
Weekly FCD-Equivalent Rate
Multiple Exceedance Weeks within a calendar month
Monthly FCD-Equivalent Rate
Multiple Exceedance Months within a calendar year
FCD Annual Rate
1
Daily Penalty Charge
2
3
Q.
When does the Daily Penalty Charge apply, and how is it calculated?
4
A. [Hammer] The Daily Penalty Charge applies when multiple Exceedance Hours occur on 5
the same calendar day. In that circumstance, the Daily Penalty Charge is calculated as: 6
Maximum Hourly Exceedance MW during the calendar day
7
× Daily FCD-Equivalent Rate
8
× Number of Exceedance Hours in the calendar day
9
10
Q.
Can you provide an example of the Daily Penalty Charge?
11
A. [Hammer] Using the same example as in the base penalty charge section, assume the 12
customer exceeds its reserved transmission service limit in two separate hours on the same 13
calendar day (one exceedance at 10:30 a.m. and another at 11:15 p.m.). As I explained 14
above, each clock hour will be treated as a separate hour for purposes of this determination, 15
so even though these exceedances occurred within an hour of each other, they will be 16
treated as two Exceedance Hours. In that case:
17
Maximum Exceedance MW during the calendar day = 200 MW
18
Daily FCD Rate = $197.26/MW‑Day
19
Number of Exceedance Hours in the calendar day = 2
20
21
Daily Penalty Charge is calculated as:
22
23
200 MW× $197.26/MW‑Day x 2
24
= $78,904
25
26
The Daily Penalty Charge is assessed in addition to the base penalty charge applicable to 27
each individual Exceedance Hour.
28
PDF page 12
Exhibit No. PTO-0005Page 12 of 31
Weekly Penalty Charge
1
2
Q.
When does the Weekly Penalty Charge apply, and how is it calculated? 3
A. [Hammer] The Weekly Penalty Charge applies when Exceedance Hours occur on multiple 4
calendar days within the same calendar week. The Weekly Penalty Charge is calculated as: 5
Maximum Hourly Exceedance MW during the calendar week
6
× Weekly FCD-Equivalent Rate
7
× Number of Exceedance Days in the calendar week
8
9
Q.
Can you provide an example of the Weekly Penalty Charge?
10
A. [Hammer] Using the same example, assume the customer exceeds its reserved 11
transmission service limit in two different calendar days (Monday and Wednesday) within 12
the same calendar week. In that case:
13
Maximum Hourly Exceedance MW during the calendar week = 200 MW
14
Weekly FCD Rate= $1,385/MW‑Week
15
Number of Exceedance Days in a calendar week = 2
16
17
Weekly Penalty Charge is calculated as:
18
19
200 MW× $1,385/MW‑Week x 2
20
= $554,000
21
22
The Weekly Penalty Charge is assessed in addition to the base penalty charge and any 23
applicable Daily Penalty Charge.
24
Monthly Penalty Charge
25
26
Q.
When does the Monthly Penalty Charge apply, and how is it calculated? 27
A. [Hammer] The Monthly Penalty Charge applies when Exceedance Hours occur during 28
multiple calendar weeks within the same calendar month. The Monthly Penalty Charge is 29
calculated as:
30
Maximum Hourly Exceedance MW during the calendar month
31
× Monthly FCD-Equivalent Rate
32
× Number of Exceedance Weeks in the calendar month
33
PDF page 13
Exhibit No. PTO-0005Page 13 of 311
Q.
Can you provide an example of the Monthly Penalty Charge?
2
A. [Hammer] Using the same example, assume the customer exceeds its reserved 3
transmission service limit in two separate calendar weeks within the same calendar month. 4
In that case:
5
Maximum metered withdrawal during the month = 200 MW
6
Monthly FCD Rate = $6,000/MW‑Month
7
Number of Exceedance Weeks in a calendar month = 2
8
9
Monthly Penalty Charge:
10
11
200 MW × $6,000/MW‑Month x 2
12
= $2,400,000
13
14
The Monthly Penalty Charge is assessed in addition to the base, Daily, and Weekly Penalty 15
Charges.
16
Annual Penalty Charge
17
18
Q.
When does the Annual Penalty Charge apply, and how is it calculated? 19
A. [Hammer] The Annual Penalty Charge applies when Exceedance Hours occur during 20
multiple calendar months within the same calendar year. The Annual Penalty Charge is 21
calculated as:
22
Maximum Hourly Exceedance MW during the calendar year
23
× Annual FCD Rate
24
× Number of Exceedance Months in the calendar year
25
26
Q.
Can you provide an example of the Annual Penalty Charge?
27
A. [Hammer] Using the same example, assume the same customer exceeds its reserved 28
transmission service limit in two separate months within the same year. In that case: 29
Maximum Hourly Exceedance MW during a calendar year = 200 MW
30
FCD Rate = $72,000/MW‑Year
31
Number of Exceedance Weeks in a Year = 2
32
33
PDF page 14
Exhibit No. PTO-0005Page 14 of 31
Annual Penalty Charge is calculated as:
1
200 MW × $72,000/MW‑Year x 2
2
= $28.8 Million
3
4
The Annual Penalty Charge is accessed in addition to the Base Penalty Charge and all 5
applicable Daily, Weekly, and Monthly Penalty Charges.
6
Q.
What is the total penalty exposure under the calculations above?
7
A. [Hammer] In aggregate, if the Eligible Customer experiences two Exceedance Intervals 8
within a single hour, two hours within a single calendar day, two calendar days within a 9
single calendar week, and two calendar weeks within the same calendar month during two 10
months of the year (e.g., April and May), the total assessed financial penalty would be 11
approximately $36.5 million. The calculation supporting this total is summarized as 12
follows.
13
PDF page 15
Exhibit No. PTO-0005Page 15 of 3112
Q.
What do the PJM Transmission Owners propose to do with the revenues collected 3
from the financial penalties?
4
A. [Hammer] Revenues collected from daily, weekly, and monthly financial penalty charges 5
will be returned on a monthly basis to Eligible Customers taking NITS and Firm Contact 6
Demand Service that have not been penalized during the month as bill credits, based on 7
each Eligible Customer’s pro rata share of the Zone’s annual peak load based on the most 8
recent 12-month period ending October 31. Revenues collected from annual penalty 9
charges will be retuned on an annual basis to Eligible Customers taking NITS and Firm 10
Contract Demand Service that have not been penalized during the year as bill credits, based 11
(a) (b)
(c) (d)
(e) (f)
Unreserved Use Violations (200 MW):
No. of Exceedance Intervals
No. of Exceedance Hours
No. of Exceedance Days No. of Exceedance Weeks No. of Exceedance Months
(1) Tuesday, April 7, 2026 @ HE 12:00 p.m.
2
(2) Tuesday, April 7, 2026 @ HE 2:00 p.m.
2
(3) Wednesday, April 8, 2026 @ HE 12:00 p.m.
2
(4) Wednesday, April 8, 2026 @ HE 2:00 p.m.
2
(5) Tuesday, April 14, 2026 @ HE 12:00 p.m.
2
(6) Tuesday, April 14, 2026 @ HE 2:00 p.m.
2
(7) Wednesday, April 15, 2026 @ HE 12:00 p.m.
2
(8) Wednesday, April 15, 2026 @ HE 2:00 p.m.
2
(9) Thursday, May 7, 2026 @ HE 12:00 p.m.
2
(10) Thursday, May 7, 2026 @ HE 2:00 p.m.
2
(11) Friday, May 8, 2026 @ HE 12:00 p.m.
2
(12) Friday, May 8, 2026 @ HE 2:00 p.m.
2
(13) Thursday, May 14, 2026 @ HE 12:00 p.m.
2
(14) Thursday, May 14, 2026 @ HE 2:00 p.m.
2
(15) Friday, May 15, 2026 @ HE 12:00 p.m.
2
(16) Friday, May 15, 2026 @ HE 2:00 p.m.
2
(17) Base Charge (Exceedance Intervals)
32.00
(18) Maximum Hourly Exceedance MW
200.00
(19) Equivalent Hourly FCD Rate ($/MW-Hour)
$8.22
(20) Base Charge - Total
$52,602.74
(21) Daily Penalty Charge (Exceedance Hours)
16.00
(22) Maximum Hourly Exceedance MW (Day)
200.00
(23) Equivalent Daily FCD Rate ($/MW-Day)
197.26
$
(24) Daily Penalty Charge - Total
$631,232.88
(25) Weekly Penalty Charge (Exceedance Days)
8.00
(26) Maximum Hourly Exceedance MW (Week)
200.00
(27) Equivalent Weekly FCD Rate ($/MW-Week)
1,384.62
$
(28) Weekly Penalty Charge - Total
$2,215,384.62
(29) Monthly Penalty Charge (Exceedance Weeks)
4.00
(30) Maximum Hourly Exceedance MW (Month)
200.00
(31) Equivalent Monthly FCD Rate ($/MW-Month)
6,000.00
$
(32) Monthly Penalty Charge - Total
$4,800,000.00
(33) Annual Penalty Charge (Exceedance Months)
2.00
(34) Maximum Hourly Exceedance MW (Annual)
200.00
(35) FCD Rate ($/MW-Year)
72,000.00
$
(36) Annual Penalty Charge - Total
$28,800,000.00
(37) Penalty
$52,602.74
$631,232.88
$2,215,384.62
$4,800,000.00
$28,800,000.00
(38) Total Penalty
$36,499,220.23
1
1
2
2
2
2
1
1
1
1
2
2
2
2
2
2
2
2
PDF page 16
Exhibit No. PTO-0005Page 16 of 31
on each Eligible Customer’s pro rata share of the Zone’s annual peak load based on the 1
most recent 12-month period ending October 31.
2
V. GRID RELIANCE CHARGE
3
Q.
Constellation Witness Zachary Ming argues that the PJM Transmission Owners’ 4
proposed Grid Reliance Charge is “not grounded in sound ratemaking principles, 5
violates cost causation principles, and is unreasonably high.”8 How do you respond? 6
A. [Schafer] I disagree. The PJM Transmission Owners’ proposed Grid Reliance Charge 7
methodology represents an appropriate balance between fairly estimating the grid reliance 8
benefits to Co-Located Load with the need to ensure the rate can be practically 9
implemented. These grid benefits include delivering ancillary services and a suite 10
of essential reliability services, such as frequency support, inertia, voltage stability, fault 11
current capability, ride-through and protection coordination, and providing sufficient 12
short-circuit capability. Practicality concerns are particularly pertinent here given the 13
Commission’s desire to expedite the interconnection of data center loads. 14
Mr. Ming’s criticisms of the PJM Transmission Owners’ proposal are largely based 15
on his belief that Co-Located Load customers with zero demand should not be charged for 16
demand-driven transmission costs.9 Under this belief, Co-Located Load customers with 17
zero demand would not be allocated the cost of transmission infrastructure through a Grid 18
Reliance Charge because transmission costs are largely demand-driven.10
19
20
8 See Reply Brief of Constellation, Attachment 1, Testimony of Zachary Ming at 4:10-12 (“Ming Testimony”).9 Id. at 12:16-21.10 With respect to the notion that transmission costs are largely demand-driven, see, e.g., the National Association of Regulatory Utility Commissioners, Electric Utility Cost Allocation Manual (Jan. 1992), at Chapter 5. See also Lawrence J. Vogt, P.E., Electricity Pricing: Engineering Principles and Methodologies 522 (2009).
PDF page 17
Exhibit No. PTO-0005Page 17 of 31
Q.
What do you mean when you say that “transmission costs are largely demand- 1
driven?”
2
A. [Schafer] Transmission systems are planned, built, and operated to serve bulk power flows 3
and meet system-wide reliability criteria. Most transmission system investments and 4
associated costs are driven by the need to meet peak demand, not by the total volume of 5
energy delivered. Transmission facilities such as substations, lines, transformers, and 6
related equipment, are designed to serve maximum coincident peak demand plus required 7
reserve margins. Therefore, the primary cost drivers of the transmission system are largely 8
classified as demand-related rather than energy-usage related.
9
Q.
Does Mr. Ming believe that the concept of a Grid Reliance Charge is unreasonable? 10
A. [Schafer] No, he does not. In fact, he states “. . . it is reasonable for co-located load 11
customers to make some contribution to the cost of wires of the PJM system in the form of 12
a [Grid Reliance Charge].”11
13
Q.
Does Mr. Ming offer an alternative means for calculating the Grid Reliance Charge? 14
A. [Schafer] Yes. Similar to the PJM Transmission Owners’ proposal, Mr. Ming’s Grid 15
Reliance Charge is calculated as a percentage of the NITS rate. The percentage of the NITS 16
rate used to calculate the Grid Reliance Charge is referred to by Mr. Ming as the “Grid 17
Reliance Percentage Allocator.”12 As an alternative to the PJM Transmission Owners’ 18
proposed methodology for the calculation of the Grid Reliance Charge Fixed Percentage 19
Allocator, Mr. Ming proposes the adoption of the “minimum system” method.13 However, 20
11
Ming Testimony at 9:1-3.
12 In the Illustrative Tariff sheets filed by the PJM Transmission Owners, this is referred to as the Grid Reliance Fixed Percentage Allocator. See PJM Transmission Owners Reply Brief, Exhibit PTO-0006 (filed Apr. 24, 2026).13 Id. at 24:6-8.
PDF page 18
Exhibit No. PTO-0005Page 18 of 31
by proposing the minimum system method for the calculation of the Grid Reliance Charge 1
Fixed Percentage Allocator, Mr. Ming is advocating for a reclassification of a portion of 2
PJM transmission costs as customer-related even though this reclassification is not only 3
inappropriate but contradicts standard industry literature.14
4
Q.
What is the minimum system method?
5
A. [Schafer] The minimum system method is a cost allocation approach sometimes used in 6
electric distribution cost of service studies to distinguish between customer-related and 7
demand-related components of a portion of distribution plant investment. The method is 8
based on the principle that a portion of the distribution system must be constructed to serve 9
customers regardless of their level of demand, while additional investment is driven by the 10
magnitude of load served.
11
Under this method, a “minimum system” is defined as the lowest-cost configuration 12
of the distribution system that would be required to provide basic service to customers, 13
assuming minimal load requirements. This minimum system typically reflects the facilities 14
necessary to connect customers to the grid and ensure system operability, independent of 15
higher demand levels. The costs associated with this minimum system are classified as 16
customer-related, as they are incurred to serve customers regardless of their usage. 17
The customer-related portion of distribution plant investment identified through the 18
minimum system method is typically allocated on the basis of the number of customers in 19
each class, reflecting the premise that these costs are driven by customer count rather than 20
by demand or energy use.
21
14 See supra note 10.
PDF page 19
Exhibit No. PTO-0005Page 19 of 31
The remaining portion of distribution plant investment, representing the additional 1
capacity required to meet higher levels of demand, is classified as demand-related. These 2
costs are then allocated among customer classes based on appropriate demand allocators, 3
such as non-coincident peak demand.
4
Q.
Does Mr. Ming attempt to conduct a minimum system study for the PJM transmission 5
system to calculate the Grid Reliance Charge Fixed Percentage Allocator? 6
A. [Schafer] He claims to have done so. Mr. Ming states: “to approximate the cost of the 7
minimum system, I identified the relevant minimum system components and associated 8
unit costs and applied them to the component count estimate.”15
9
Q.
Does Mr. Ming present a true minimum system study for the PJM transmission 10
system?
11
A. [Schafer] No, he does not. This can be seen in his selection of minimum system 12
components, shown in Table 1 of his testimony.16 For example, Mr. Ming, when choosing 13
the minimum system component for transmission poles and transmission towers, chooses 14
“distribution wood pole[s].”17 In other words, Mr. Ming’s minimum system study assumes 15
that a minimum transmission system could be built with distribution wood poles. This 16
assumption violates the engineering reality of the transmission system. A distribution wood 17
pole cannot perform the function of a transmission structure in that it cannot support 18
required voltages, cannot meet clearance requirements, and cannot handle mechanical 19
loads (e.g., span length, conductor weight). The minimum system study establishes a 20
15 Ming Testimony at 19:14-16.16 Id. at 20:1. 17 Id.
PDF page 20
Exhibit No. PTO-0005Page 20 of 31
minimum feasible configuration of the same system that could actually provide the service 1
(at minimal load). Mr. Ming did not create such a minimum system. He substituted 2
distribution assets into a transmission function. In the context of a study that, for 3
methodological reasons, should never have been attempted in the first place, Mr. Ming’s 4
inclusion of distribution poles renders his results meaningless.
5
Q.
Even if Mr. Ming had appropriately conducted a minimum system study, would that 6
approach be reasonable for calculating the Grid Reliance Charge Fixed Percentage 7
Allocator?
8
A. [Schafer] No. The minimum system method is not an appropriate means for calculating 9
the Grid Reliance Charge Fixed Percentage Allocator at the transmission level. 10
Q.
Why is the minimum system method not an appropriate means for calculating the 11
Grid Reliance Charge Fixed Percentage Allocator at the transmission level? 12
A. [Schafer] The minimum system method is not an appropriate means for calculating the 13
Grid Reliance Charge Fixed Percentage Allocator at the transmission level because the 14
foundational premise of the method is incompatible with that calculation. That premise is 15
that a definable portion of the system is built solely to connect customers largely 16
independent of load.
17
Q.
Why is that premise not applicable to transmission systems?
18
A. [Schafer] The premise is not applicable to transmission systems because transmission 19
systems are not planned and built to connect customers independent of load. Rather, they 20
are planned, built and operated to move large amounts of electricity reliably, efficiently, 21
and economically from where it is produced to where it is consumed.
22
PDF page 21
Exhibit No. PTO-0005Page 21 of 31
Q.
Is Mr. Ming aware that the minimum system method is not used at the transmission 1
level?
2
A. [Schafer] Yes. He states in his testimony: “the minimum system method is generally not 3
used in the context of transmission system cost allocation and rate design.”18 4
Q.
How does Mr. Ming justify the adoption of the minimum system method at the 5
transmission level in this proceeding?
6
A. [Schafer] Mr. Ming attempts to justify his proposal to adopt the minimum system method 7
at the transmission level in this case by asserting that “[w]hile the minimum system method 8
is typically not used in the context of transmission cost allocation or ratemaking, the cost 9
of the minimum system is precisely the set of costs that a co-located load that benefits from 10
the existence of wires but imposes no demand on the grid should share.”19 11
Q.
What is wrong with Mr. Ming’s assertion?
12
A. [Schafer] Mr. Ming ignores the methodological inappropriateness of applying the 13
minimum system method to the transmission system, apparently attributing the industry- 14
standard exclusion of this method from transmission system cost of service analysis as 15
owing to the larger size and higher cost of transmission components. But it is not because 16
of the size or cost of the components that the minimum system method is excluded from 17
transmission system cost of service analysis but rather due to the fact that transmission 18
systems do not have a definable minimum, customer-driven component. Although Mr. 19
Ming acknowledges that the minimum system method is not used at the transmission level, 20
he nonetheless believes that the minimum system method, which is only used at the 21
18 See Ming Testimony at 16:9-10.19 Id. at 17:3-6.
PDF page 22
Exhibit No. PTO-0005Page 22 of 31
distribution level by some, but not all, utilities to define customer-related costs, would 1
somehow “precisely” identify the set of costs that a co-located customer imposing no load 2
on the grid should pay for grid reliance.20
3
Q.
How does Mr. Ming use the concept of the minimum system method to argue that the 4
PJM Transmission Owners’ proposed Grid Reliance Charge is too high?
5
A. [Schafer] Mr. Ming outlines the following relationship between the Grid Reliance Charge 6
and the minimum system method: 1) the minimum system method is not used at the 7
transmission level because the components are large and costly in relation to the minimum 8
system; 2) the fact that the minimum system method is not used implies that the minimum 9
system value is 0% for the transmission system; and 3) because the minimum system value 10
is 0%, it is “reasonable to assume that a proper minimum system study when applied to the 11
transmission system would yield a value significantly lower than 25.8%” (i.e., the PJM 12
Transmission Owner’s proposed initial Grid Reliance Charge Fixed Percentage 13
Allocator).21
14
Q.
Is this line of reasoning sensible?
15
A. [Schafer] Not at all. First, Mr. Ming once again ignores that there are methodological 16
reasons that the minimum system method is not used at the transmission level. Second, his 17
reasoning simply does not hold. Mr. Ming states “. . . no utilities that I am aware of classify 18
any transmission costs to the customer cost driver, meaning they are implicitly assuming a 19
minimum system value of 0% for the transmission system.”22 Therefore, according to Mr. 20
20 Id.21 Id. at 18:13-15.22 Id. at 18:11-13.
PDF page 23
Exhibit No. PTO-0005Page 23 of 31
Ming, because the minimum system method is not used at the transmission level, the 1
Commission must assume a minimum system value that is much lower than the 25.8% that 2
the PJM Transmission Owners calculated for the Grid Reliance Charge Fixed Percentage 3
Allocator. However, the only reasonable conclusion to the fact that the minimum system 4
method is not used at the transmission level is that that method and any results of that 5
method are entirely irrelevant to the assessment of a transmission-level charge, such as the 6
proposed Grid Reliance Charge.
7
Q.
How are the results of a distribution minimum system study used in a typical 8
distribution class cost of service study?
9
A. [Schafer] For the distribution plant accounts included in the study, the identified customer- 10
related portions of the account balances are allocated to customer classes based on the 11
count of customers. The identified demand-related portions of the account balances are 12
allocated to the customer classes with a demand allocator.
13
Q.
How does Mr. Ming propose to apply the percentage result of his minimum system 14
study?
15
A. [Schafer] He proposes to apply the result of his minimum system study, which he presents 16
as 6%, directly to the NITS rate as the Grid Reliance Charge Fixed Percentage Allocator.23 17
Q.
In a minimum system study for the distribution system, is the application of the 18
minimum system results similar to the application proposed by Mr. Ming? 19
A. [Schafer] No. The percentage of customer-related costs developed in the distribution 20
minimum system study is applied to the relevant distribution plant account balances. The 21
customer-related portion of the balance is then allocated to the customer classes based on 22
23
Id. at 25:3-4.
PDF page 24
Exhibit No. PTO-0005Page 24 of 31
the count of customers. The demand-related portion of the balance is then allocated to the 1
customer classes based on a measure of demand. The allocated balances are then included 2
in each customer class’s revenue requirement. The revenue requirement includes items 3
such as return on rate base, operations and maintenance expenses, depreciation, and taxes. 4
In other words, the minimum system study is performed in the context of the development 5
of the revenue requirement for customer-related and demand-related infrastructure. Mr. 6
Ming’s application of a percentage result from his minimum system study directly to NITS 7
is incompatible with the purpose of performing a minimum system study, because the 8
percentage he develops cannot be directly applied to the revenue requirement. 9
Q.
When Mr. Ming proposes to apply the results of his transmission minimum system 10
study directly to the NITS rate, is he violating cost causation principles that he 11
describes in his testimony?
12
A. [Schafer] Yes. Mr. Ming states that “the Transmission Owners’ Grid Reliance Charge 13
proposal violates cost causation principles by charging for demand-driven transmission 14
costs that co-located customers with zero demand that their service does not cause.”24 Mr. 15
Ming conducts a minimum system study, identifies a portion of what he believes to be 16
customer-related cost, then recovers that customer-related cost via demand. In doing so, he 17
assigns customer-related costs to customers who did not cause that cost to be incurred. In 18
a distribution minimum system study, the customer-related cost is allocated on a per- 19
customer basis, i.e., the same amount is allocated to each customer regardless of their usage 20
of the system. Mr. Ming’s proposal clearly allocates more or less customer-related cost 21
24 Id. at 12:18-21.
PDF page 25
Exhibit No. PTO-0005Page 25 of 31
based on a customer’s load requirements. There is no justification for this in the context of 1
the methodology he has adopted.
2
Q.
Does Mr. Ming provide justification for the costs he includes in his minimum system 3
method?
4
A. [Schafer] No. Mr. Ming states that “co-located load customers receive ancillary services 5
from the existence of the wires that synchronize them to the rest of the PJM system.”25 He 6
then implies that including the full cost of the “wires” in a Grid Reliance Charge would be 7
inappropriate, since the full cost of the wires was incurred to meet peak demand. He then 8
concludes that using the minimum system method in order “to calculate precisely the costs 9
of constructing wires to connect all customers” is appropriate.26 From this argument, it 10
appears that Mr. Ming’s entire justification of the costs he includes in his minimum system 11
study is as follows: the costs underlying the Grid Reliance Charge are the same customer- 12
related costs necessary to connect all customers. He confirms this when he states: “[w]hile 13
the minimum system method is typically not used in the context of transmission cost 14
allocation or ratemaking, the cost of the minimum system is precisely the set of costs that 15
a co-located load that benefits from the existence of wires but imposes no demand on the 16
grid should share.27 The costs of the minimum system therefore provide a theoretically- 17
sound basis to calculate the Grid Reliance Charge.”28 Mr. Ming, however, fails to establish 18
the relationship between Grid Reliance Charge-related costs and the costs included in the 19
25 Id. at 14:7-8.26 Id. at 14:14-17.27 Id. at 17:3-6.28 Id. at 17:6-7.
PDF page 26
Exhibit No. PTO-0005Page 26 of 31
minimum system study. Moreover, as described above, he violates any supposed 1
“theoretically-sound basis” when he allocates customer-related costs on demand. 2
Q.
Mr. Ming criticizes the PJM Transmission Owners’ Grid Reliance Charge proposal 3
on the basis of the costs that were included or excluded from the methodology, such 4
as return on rate base and depreciation. Does Mr. Ming’s minimum system proposal 5
remedy his criticisms?
6
A. [Schafer] No. As shown in Table 1 of his testimony,29 Mr. Ming’s 6% minimum system 7
study result, which he proposes be applied directly to NITS, is based entirely on 8
replacement cost.30 In other words, his calculated 6% is the result of comparing the cost of 9
a “new” minimum transmission system to the cost of an entirely “new” transmission 10
system. Mr. Ming does not develop any greater detail than that. He does not incorporate 11
rate of return, taxes, depreciation, operations and maintenance, or any other element of the 12
revenue requirement.
13
Q.
Mr. Ming accuses the PJM Transmissions Owners of having provided little 14
justification for which costs are included or excluded from the Grid Reliance Charge. 15
How do you respond?
16
A. [Schafer] First, Mr. Ming’s criticism fails to acknowledge the account-by-account 17
justification of cost inclusion provided in Tables 1 and 2 of Exhibit No. PTO-0001.31 18
Second, Mr. Ming cites only two aspects of the inclusion/exclusion criteria in his testimony 19
without properly situating them in the context of the full proposal. In Exhibit No. PTO- 20
29 Id. at 20:1.30 Id. at 19:5-18. 31 PJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer at 20-21.
PDF page 27
Exhibit No. PTO-0005Page 27 of 31
0001, I provided multiple reasons as to why the PJM Transmission Owners’ Grid Reliance 1
Charge methodology is just and reasonable.32
2
Q.
Does the Grid Reliance Charge methodology proposed by the PJM Transmission 3
Owners result in a just and reasonable rate?
4
A. [Schafer] Yes. While the methodology includes certain costs and excludes others, it does 5
so in pursuit of the goal of developing a cost-based, transparent, and practically 6
implementable calculation that relies on publicly available data. Mr. Ming claims that the 7
PJM Transmission Owners’ Grid Reliance Charge methodology is not grounded in sound 8
ratemaking and cost-causation principles because of the exclusion of certain items such as 9
return on rate base.33 However, it is notable that in his own proposal, not only does he not 10
include return on rate base, but he does not calculate any specific element of the revenue 11
requirement. His proposed Grid Reliance Charge Fixed Percentage Allocator is entirely 12
based on the ratio of the cost of a theoretical “new” transmission minimum system to the 13
cost of an entirely “new” transmission system.
14
Q.
Please summarize your response to Constellation Witness Zachary Ming.
15
A. [Schafer] Mr. Ming’s critique of the proposed Grid Reliance Charge is internally 16
inconsistent and unsupported by accepted ratemaking practice. Although he agrees that 17
co‑located customers should pay a Grid Reliance Charge, he provides little justification for 18
his proposed minimum system study solution. The minimum system method is not used 19
for transmission cost of service analysis because transmission systems are built to serve 20
32 Id. at 24-25.33 Ming Testimony at 11:18-12:1.
PDF page 28
Exhibit No. PTO-0005Page 28 of 31
bulk power flows and reliability needs and do not have a separable, customer‑driven 1
“minimum system” component.
2
Despite acknowledging that the minimum system method is inappropriate at the 3
transmission level, Mr. Ming nonetheless applies it using assumptions that are not feasible 4
from an engineering standpoint and that substitute distribution facilities for transmission 5
infrastructure. His analysis also omits basic elements of the revenue requirement and 6
proposes to inappropriately recover what he describes as customer‑related costs through 7
demand charges, contrary to the very cost‑causation principles he evokes. Mr. Ming’s 8
estimates of what he believes to be a reasonable level of Grid Reliance Charge must be 9
rejected, as his proposal is methodologically unsound.
10
Q.
Vistra Witness Rebecca Stadelmeyer also challenges the PJM Transmission Owners’ 11
proposed calculation of the Grid Reliance Charge Fixed Percentage Allocator. What 12
is Ms. Stadelmeyer’s alternative proposal?
13
A. [Schafer] Ms. Stadelmeyer believes that the Grid Reliance Charge Fixed Percentage 14
Allocator should be based on the benefits customers receive from the grid in supporting 15
black start and regulation service only.34 Accordingly, she proposes that the percentage be 16
based on PJM’s monthly billings for black start and regulation charges.35 17
Q.
What is wrong with this alternative proposal for the calculation of the Grid Reliance 18
Charge Fixed Percentage Allocator?
19
A. [Schafer] Ms. Stadelmeyer’s alternative calculation of the Grid Reliance Charge Fixed 20
Percentage Allocator is based on the ratio of PJM’s monthly black start and regulation 21
34 See Response Brief of Vistra, Attachment A, Affidavit of Rebecca Stadelmeyer at 12:8-11 (“Stadelmeyer Affidavit”).35 Vistra at 22-23; Stadelmeyer Affidavit at 11:4-12:4.
PDF page 29
Exhibit No. PTO-0005Page 29 of 31
billings to total monthly billings.36 In other words, rather than attempting to identify costs 1
underlying grid reliance (or any subset of grid reliance, such as black start or regulation 2
service), Ms. Stadelmeyer simply lowers the PJM Transmission Owners’ proposed Grid 3
Reliance Charge with a sales ratio.
4
Q.
Why was it inappropriate for Ms. Stadelmeyer to simply lower the PJM Transmission 5
Owners’ proposed Grid Reliance Charge with a sales ratio?
6
A. [Schafer] As noted above, Ms. Stadelmeyer’s sales ratio represents the ratio of black start 7
and regulation service monthly billings to total monthly billings. This sales ratio does not 8
represent the transmission costs that underlie grid reliance, and thus is not a reasonable 9
proxy for the Grid Reliance Charge Fixed Percentage Allocator. There is no relationship 10
between the percentage of billed revenues for black start and regulation and the costs of 11
the transmission system used to deliver those services. Indeed, a comparison of the billings 12
for black start and regulation service to the costs required to deliver those services is 13
meaningless. As the Commission has stated, the Grid Reliance Charge and thus the Grid 14
Reliance Charge Fixed Percentage Allocator is a function of the facilities and expenses 15
related to the delivery of ancillary services; they are not associated with PJM’s billings for 16
the actual ancillary services.37 In short, Ms. Stadelmeyer does not justify the supposed 17
relationship between her sales ratio and the transmission cost of delivering ancillary 18
services. For this reason, her alternative proposal is unreasonable.
19
20
36 Id.37 Order at P 183.
PDF page 30
Exhibit No. PTO-0005Page 30 of 31
Q.
Ms. Stadelmeyer also states that the proposed Grid Reliance Charge will shift costs 1
inappropriately between classes because it will allow NITS customers to pay less than 2
they currently do for a superior product compared to either Firm Contract Demand 3
Service or Non-Firm Contract Demand Service. Do you agree?
4
A. [Blazunas] No. Ms. Stadelmeyer bases her statement on two erroneous arguments. First, 5
she argues that the proposed Grid Reliance Charge calculation and credit allocation process 6
result in subsidies from Non-Firm Contract Demand Service customers to customers 7
receiving service via NITS.38 Her characterization of the bill credits that flow from Non- 8
Firm Contract Demand Service to both NITS and Firm Contract Demand Service 9
customers, however, is inaccurate. The bill credits are not subsidies but instead represent 10
offsets that reduce the amount paid by firm customers (i.e., customers receiving service 11
either through NITS or Firm Contract Demand Service) for the firm transmission service 12
they receive. This is entirely appropriate. Rates are designed to recover the fixed costs of 13
building and maintaining the system so as to provide service to firm customers and so the 14
revenues received from Non-Firm Contract Demand Service, which is only provided in 15
instances where it can be accommodated by the system and is interruptible, are used to 16
offset those fixed costs.
17
Second, Ms. Stadelmeyer argues that the proposed Grid Reliance Charge
18
calculation and credit allocation also result in transmission charges that are not 19
commensurate with the benefits received by different types of customers.39 In particular, 20
she takes issue with the application of the proposed Grid Reliance Charge to Non-Firm 21
38 Stadelmeyer Affidavit at 8:8-10.39 Id. at 8:10-11.
PDF page 31
Exhibit No. PTO-0005Page 31 of 31
Contract Demand Service when no service or only de minimis service is taken.40 According 1
to Ms. Stadelmeyer, the current proposed Grid Reliance Charge calculation and application 2
does not accurately reflect the benefits received by Non-Firm Contract Demand Service 3
customers,41 which she asserts are limited to black start and regulation services only.42 This 4
assertion, however, fails to reflect the operational and reliability benefits a customer 5
receives from a connection to the grid. These grid benefits include delivering ancillary 6
services and a suite of essential reliability services, such as frequency support, inertia, 7
voltage stability, fault current capability, ride-through and protection coordination, 8
and providing sufficient short-circuit capability. As discussed above, the proposed Grid 9
Reliance Charge methodology results in a just and reasonable rate that appropriately 10
reflects the value of these benefits.
11
Q.
Does this complete your testimony at this time?
12
A. [Blazunas, Schafer, and Hammer] Yes.
13
40 Id. at 9:2-5.41 Id. at 9:4-5.42 Id. at 10:6-9.
PDF page 32
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
P.ll\,f Irrtercontrection. I-.L.C.. et ul
Docket No. EL25-4q-000
L)ocket No. EL25-,-tq-00 i
l.arge Loads Co-Located at Generating Facilities
Constellation F.nergv Generation. LLC
\.
P"l M Interconnectior.r" I.. L.Cl.
(Consolidated)
DECLARATION OF PETER BLAZUI{AS
I deposc and state under penaltl, of perjun' that the fbregoing exhihits \\ere preparecl c-,r assembled by' rne or under m-v direction. and that I have read the foregoing questions and ansr,vers iabeled as m\ testimonl,: that if asked the same questions my ans\&iers in response lr,oul,l be as shor,vn: and that the facts contained in mv ans\tr-ers are true to the best ol' mv knor,r,ledge. infbrmation. and beliel.
April 24.2
)
)
)
)
)
)
)
)
Dockel No. AD24-11-000
Dccket }io. EL2--s -2 0-000
PDF page 33
[No extractable text on this page.]
PDF page 34
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
DECLARATION OF HANHAN HAMMER
I depose and state under penalty of perjury that the foregoing exhibits were prepared or assembled by me or under my direction, and that I have read the foregoing questions and answers labeled as my testimony: that if asked the same questions my answers in response would be as shown; and that the facts contained in my answers are true to the best of my knowledge, information, and belief.
April 24, 2026