EL25-49-000 · 2026-04-24 · Indicated PJM Transmission Owners

Reply Brief of the Indicated PJM Transmission Owners

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
 )
Docket No. EL25-49-000
 )
Docket No. EL25-49-001
 )
Large Loads Co-Located at Generating Facilities )
Docket No. AD24-11-000
 )
Constellation Energy Generation, LLC

 )
Docket No. EL25-20-000
v.

 )
PJM Interconnection, L.L.C.
 )
(Consolidated)
REPLY BRIEF OF
THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to the Commission’s December 18, 2025 order in PJM Interconnection, L.L.C.,
193 FERC ¶ 61,217, at P 193 (2025) (“Order”), the Indicated PJM Transmission Owners
(collectively, the “PJM Transmission Owners”)1 submit this reply brief to parties’ responses to the initial briefs filed by PJM Interconnection, L.L.C. (“PJM Initial Brief”) and the PJM Transmission Owners (“PJM Transmission Owners Initial Brief”) on February 23, 2026 in the above-captioned proceedings.

1 For the purpose of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative.

PDF page 2

2
I. INTRODUCTION
The PJM Transmission Owners’ proposals in this proceeding are grounded in two main principles: (1) rates for the new services must be consistent with longstanding cost allocation principles, and (2) the new services must be implemented in a manner that does not compromise system reliability.  Co-Located Load2 customers must pay their fair share of transmission system costs, including those related to the benefits of being connected and synchronized with the extensive PJM Transmission System.  Otherwise, other ratepayers will be forced to subsidize Co- Located Load customers.  Additionally, reliability must be a key consideration of these new services, not a secondary issue or afterthought.  Co-Located Loads will be fully connected and synchronized with the transmission system, and can have serious impacts on the system.  The laudable goals of promoting speed to power and economic efficiency for data centers and other large load customers will not be well-served by implementing new transmission services in a manner that results in significant risks and uncertainty around the ongoing reliability of the system. Moreover, such a result risks undermining continued reliable service to existing customers. In this reply brief, the PJM Transmission Owners respond to a number of issues raised with respect to PJM’s proposed non-rate terms and conditions for the three new transmission services and their rate proposals for the new transmission services.  The PJM Transmission Owners express support for PJM’s proposed scope of the new transmission services, on the basis that they provide reasonable flexibility to Co-Located Load customers while recognizing the need to implement these new services in a reliable fashion.  They also respond to criticisms of PJM’s proposed study process, pointing out the important role that PJM Transmission Owners will continue to play with respect to conducting load-related studies, and explaining why allegations of potential PJM

2 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Open Access Transmission Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C.

PDF page 3

3
Transmission Owner discrimination are without merit.  The PJM Transmission Owners emphasize the importance of PJM’s strong operational penalties given the potential for large amounts of load to be secured from causing adverse system impacts based on the correct operation of control technologies and protection systems and provide further detail on their proposal for complementary financial penalties.

The PJM Transmission Owners also address criticisms of their rate proposals for the new transmission services.  Specifically, the PJM Transmission Owners rebut claims that their proposal to set the maximum rate for Non-Firm Contract Demand Service at the rate for Firm Contract Demand Service is unjust and unreasonable, explaining the superiority of this service relative to the existing Non-Firm Point-to-Point product and the need for further analysis prior to offering any rate discounts.  The PJM Transmission Owners further explain why their proposal for a Grid Reliance Charge is just and reasonable and consistent with cost allocation principles, given the benefits that the ongoing safe operation of the transmission system will provide to all Co-Located Load, regardless of on-site generation.

II. RESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND
CONDITIONS FOR THE NEW TRANSMISSION SERVICES
A. PJM has Appropriately Defined the Scope of Contract Demand and Interim
Network Integration Transmission Services
The PJM Transmission Owners support PJM’s proposals regarding the scope of Firm and Non-Firm Contract Demand Services and Interim Network Integration Transmission Service (“NITS”), including PJM’s proposal to restrict the use of Non-Firm Contract Demand Service to periods when on-site generation is on outage.3  In particular, the PJM Transmission Owners agree with PJM that Non-Firm Contract Demand Service is intended by the Commission to be a limited

3 PJM Initial Brief, Docket Nos. EL25-49, et al., Attachment B at P 17 (“Abdulsalam Affidavit”).

PDF page 4

4
service and is not a substitute for Firm Contract Demand Service or NITS for the portion of on- site load that will not be served by on-site generation.

Contrary to commenters’ assertions, there simply is no compelling reason for PJM not to restrict Non-Firm Contract Demand Service to periods where a Co-Located generating facility is on outage merely because the Commission did not limit the usage of Non-Firm Contract Demand Service to outages.4  Nor do commenters provide a compelling basis for Non-Firm Contract Demand Service to be available during non-outage conditions.  In the Order, the Commission explained that Non-Firm Contract Demand Service is intended to be an option for Eligible Customers seeking to use the transmission system on behalf of Co-Located Load in a more limited manner when on-site generation is not available to serve load.5

Limiting the use of Non-Firm Contract Demand Service is also necessary to ensure the reliable operation of the PJM transmission system, especially because PJM and the PJM Transmission Owners will be relying on increased uses of Special Protection Schemes (“SPS”), Remedial Action Schemes (“RAS”), and other control technologies and protective systems to ensure that on-site load that is not being planned from a transmission expansion or capacity standpoint can be operated reliably.  As PJM witness Dr. Sami Abdulsalam explains in his affidavit accompanying PJM’s Initial Brief, there are numerous operational and planning challenges associated with implementing Non-Firm Contract Demand Service.6  For instance, transmission

4 Reply Brief of Constellation Energy Generation, LLC, Docket Nos. EL25-49, et al., at 10-12 (filed Mar. 25, 2026) (“Constellation”); Reply Brief of Advanced Energy United and the Solar Energy Industries Association, Docket Nos. EL25-49, et al., at 3, 5-10 (filed Mar. 25, 2026); Reply Comments of Vistra Corp., Docket Nos. EL25-49, et al., at 25-26 (filed Mar. 25, 2026); Reply Brief of Eolian, L.P.; Antora Energy, Inc.; Calibrant Energy; Convergent Energy and Power; Mainspring Energy, Inc.; U.S. Energy Storage Coalition; and Verrus, LLC, Docket Nos. EL25-49, et al., at 6-7 (filed Mar. 25, 2026) (collectively, the “Joint Developers”).
5 Order at P 214.
6 PJM Initial Brief, Abdulsalam Affidavit at PP 9-12.

PDF page 5

5
facilities serving large loads will likely have multiple feeders serving load, which will require protection systems with multiple measurements, logics and significant flexibility, adding complexity and reducing the reliability and overall security of the system.7  PJM witness Matthew Wharton provides further details regarding the operational complexities associated with implementing RASs.8  As Mr. Wharton explains, there is the possibility of interactions between RAS in a tightly coupled network such as PJM, increasing the possibility of misoperations.9  Mr. Wharton’s testimony details an incident where a failed lighting arrestor on a 230 kV transmission system led to the loss of 1,500 MW within the PJM region at multiple substations, which highlights the risk of having multiple RASs within a single area.10

Given these risks and challenges, Non-Firm Contract Demand Service cannot become a general substitute for firm service types such as NITS or Firm Contract Demand Service for load that is not intended or designed to be served from on-site generation under normal (i.e., non- outage) operating conditions.  Instead, Non-Firm Contract Demand Service should be limited to a supplemental service intended to provide as-available transmission capacity when such on-site generation is on outage.  This approach will properly balance flexibility for Co-Located Load customers to obtain needed firm or non-firm service depending on their mix of on-site load and generation, with the obligation to ensure that the system can continue to be operated reliably for the benefit of all customers.

In its Initial Brief and illustrative tariff records (“Illustrative Tariff”), PJM refers generally to “outages” and being “on outage” without further explanation.  PJM should clarify in any

7 Id. at P 11. 8 PJM Initial Brief, Attachment C at PP 15-26 (“Wharton Affidavit”).
9 PJM Initial Brief, Wharton Affidavit at PP 20-22.
10 Id. at P 21.

PDF page 6

6
effective tariff records that, for purposes of obtaining Non-Firm Contract Demand Service, an “outage” is limited to periods where a generator is offline due to a breakdown or maintenance issues, and does not cover other instances when a generator is not operating, such as when intermittent generation resources are unable to produce; when a co-located battery has depleted its available energy; or when a natural gas generator is unable to secure fuel.

B. PJM Appropriately did not Propose Changes to the Definition of Eligible
Customer
In their comments, Invenergy Renewables LLC and Invenergy Thermal LLC (together, “Invenergy”) request clarification on how the Commission and PJM view the definition of Eligible Customer in the PJM Open Access Transmission Tariff (“Tariff”) when applied to the co-located generator and co-located load.11  Specifically, whether a co-located generator would qualify as an Eligible Customer on behalf of a Co-Located Load, and whether a co-located generator’s status as an Eligible Customer depends on whether the co-location arrangement is in a jurisdiction that has mandated retail choice.12

In its Initial Brief, PJM appropriately proposed no changes to the definition of Eligible Customer.  PJM’s definition of Eligible Customer is essentially identical to the definition contained in the Commission’s pro forma Open Access Transmission Tariff.  Under that definition, an Eligible Customer can be an electric utility, a federal power marketing agency, or any person generating electric energy for sale for resale (i.e., making wholesale sales), as well as a retail customer taking unbundled transmission service pursuant to a state unbundling requirement.13  The

11 Comments of Invenergy Renewables LLC and Invenergy Thermal LLC, Docket Nos. EL25-49, et al., at 5- 6 (filed Mar. 16, 2026).
12 Id. at 5-6.
13 See FERC Pro Forma Open Access Transmission Tariff, definition of “Eligible Customer”; see also PJM Tariff, Section 1, definition of ”Eligible Customer.”

PDF page 7

7
answer to Invenergy’s questions would presumably depend on an individual co-located generator’s specific factual circumstances.  However, it seems unlikely that a co-located generator (as opposed to the load) would meet the definition of an Eligible Customer for purposes of obtaining Contract Demand Service.  The generator likely would not be seeking to procure transmission service in order for it to serve the on-site load, and instead would be selling its output directly to the on-site load at retail (or to its state licensed supplier).14  The ability of a Co-Located Load, or an entity representing the load, to qualify as an Eligible Customer would necessarily depend on whether the jurisdiction in which it is located has adopted retail choice, and the related criteria adopted by the state.  This is because the Commission does not assert jurisdiction over bundled sales and under Section 212(h), the Commission cannot mandate retail wheeling.15

C. The Commission Should not Mandate a Combined Interconnection and
Transmission Study Process for Co-Located Loads and Generation
Invenergy argues that the Commission and PJM should clarify how transmission and
generator interconnection study processes can work in tandem.16  In Invenergy’s view, developers and lenders will be reluctant to commit to projects without both sets of study results showing that the project is viable and identifying expected upgrade costs, and coordinated studies would better

14 Even if a co-located generator did qualify as an Eligible Customer, the PJM Transmission Owners caution the Commission not to create incentives for existing generators to exit the system in order to exclusively serve large loads.  The solution to capacity shortfall situations such as currently exists in PJM cannot be to simply to move the output of existing resources to serve new large loads at the expense of existing loads.
15 See 16 U.S.C. § 824k(h); see also Promoting Wholesale Competition Through Open Access Non- Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002).
16 Invenergy at 2-5.

PDF page 8

8
align generation and load, improve efficiency, reduce system costs, and provide the certainty needed for co-location projects to be financed and developed at scale.17

It is unclear what Invenergy is asking for here, but to the extent it is requesting a combined transmission and interconnection study process for Co-Located Load and generation, the Commission should decline.  PJM’s Initial Brief already sets forth a coordinated load and generation study process, with the PJM Transmission Owners conducting load integration studies and PJM performing generator interconnection and transmission service studies, when necessary. As the PJM Transmission Owners explain in their March 25, 2026, joint response to PJM’s Initial Brief, they are fully committed to continuing to work closely and collaboratively with PJM, as they do today on numerous matters, to ensure that large loads can be quickly and efficiently interconnected.18  In addition, the study process will be maximally efficient if the PJM Transmission Owners conduct load integrating studies first to ensure that the load additions can be reliably interconnected to the grid, which would then inform PJM’s generator interconnection and transmission service studies.19  Conducting load integration studies first will help avoid potential duplication of effort and expenses between PJM and the PJM Transmission Owners.20 Furthermore, requiring PJM to adopt a single study process goes well beyond the issues set for hearing by the Commission in the Order.  PJM and the PJM Transmission Owners have proposed a just and reasonable process for conducting the appropriate studies and ensuring they are completed quickly and efficiently, consistent with the Commission’s directives in the Order.

17 Id. at 4.
18 See Joint Response of the PJM Transmission Owners, Docket Nos. EL25-49, et al., at 6 (filed Mar. 25, 2026).
19 Id. at 6-7.
20 Id. at 7.

PDF page 9

9
There is no reason for the Commission to entertain proposals that go beyond those directives, such as requiring a single study process for Co-Located Loads.

Moreover, regardless of the study process ultimately adopted by PJM, it cannot be ignored or sidestepped that end-use load is still retail load and governed by existing load interconnection rules set forth in state jurisdictional tariffs and agreements.  There is no need for the Commission to entangle itself in questions regarding the division between its jurisdiction over interstate transmission matters and state jurisdiction over retail service in this proceeding.  The coordinated study approach proposed by PJM will provide a just and reasonable opportunity for Co-Located Load to interconnect and assess the appropriate type and level of transmission service that the customer wishes to obtain.  The PJM Transmission Owners commit to continue working closely with PJM to ensure the study process remains efficient and identifying any process improvements needed to do so.

D. PJM’s Study Proposal Does not Promote Discrimination Against Co-Located
Load Customers
Certain commenters assert that PJM’s study procedures for the new transmission services are too broad, lack detail, and do not address the terms and conditions for these new services with sufficient detail, clarity or consistency.21  The same commenters contend that the study procedures allow PJM and the PJM Transmission Owners too much discretion, which could result in delays and undue discrimination.22

While more detail regarding the study process for new transmission services, such as the relevant steps in the process, associated timelines for studies, and study fees, may be helpful, commenters’ concerns are overstated.  This is particularly true with respect to accusations that the

21 Constellation at 14-15; Vistra at 32, 37-38.
22 Constellation at 15-18; Vistra at 32-36, 38.

PDF page 10

10
PJM Transmission Owners will use the study process to discriminate against Co-Located Load or to deny co-location arrangements, or that references PJM Transmission Owner criteria as being insufficient.23

PJM’s Illustrative Tariff language appropriately provides that Transmission Owners will play a key role in this study process.  Transmission Owners will continue to have the responsibility for performing load integration studies related to the interconnection of any new or modified Co- Located Loads.24  Moreover, the design of any control technologies and protection systems will need to be closely coordinated with Transmission Owners in order to ensure they meet both PJM and PJM Transmission Owner criteria, as well as North American Electric Reliability Corporation (“NERC”) requirements.25  Given these considerations, it is appropriate and sufficient only to reference the need to incorporate each Transmission Owner’s related technical requirements in the Tariff.  Consistent with the Commission’s rule of reason,26 the Tariff need not include details of each Transmission Owner’s requirements.  The reference to studies conducted by the Transmission Owners that PJM will consider inherently must refer to the studies Transmission Owners will conduct in order to integrate load facilities.  The PJM Transmission Owners do not, however, oppose making this explicit in the Tariff.

23 For instance, Vistra notes that for Firm Contract Demand Service, PJM and the Transmission Owner “shall coordinate to study the effects” of providing service on the Transmission Owner’s system “pursuant to the applicable affected Transmission Owner requirements,” but states it is unclear what those requirements would be or where they are located.  Vistra at 33.
24 PJM Initial Brief, Attachment A at Section 710.3.
25 PJM Initial Brief at 60; see also infra Section II.E & n. 31.
26 See, e.g., City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (explaining that the rule of reason requires that tariffs include practices that “affect rates and services significantly,” “are realistically susceptible of specification,” and “are not so generally understood in any contractual arrangement as to render recitation superfluous”); Hectate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023) (“[E]ven specifiable practices that significantly affect rates need not be included if they are clearly implied by the tariff’s express terms.”).

PDF page 11

11
Claims that the PJM Transmission Owners will use their role in the study process and “natural monopoly market power” to delay and deny co-location arrangements or otherwise discriminate against Co-Located Load27 are baseless and speculative.  Contrary to Constellation’s assertions, there is no basis to simply assume that any PJM Transmission Owner would work to frustrate the intent of Commission-accepted tariff provisions.  Likewise, it is illogical that PJM Transmission Owners would have an incentive, financial or otherwise, to discriminate against Co- Located Loads in studying such arrangements, as any delay in implementing new Co-Located Loads will simply mean fewer retail and transmission customers on the system to be served by Transmission Owners.  Likewise, it makes no sense that the PJM Transmission Owners would eschew available tools, such as Co-Located Load arrangements, to the extent those arrangements support their obligation to ensure grid reliability.

E. The PJM Transmission Owners’ Proposed Criteria Relating to Special
Protection Schemes and Remedial Action Schemes are Just and Reasonable
In their initial brief, the PJM Transmission Owners proposed criteria to help address the potential adverse reliability impacts associated with a potentially substantial increase in reliance on SPS/RAS and other protection systems resulting from implementation of the new transmission services.28

In its reply brief, Constellation states that it agrees with the PJM Transmission Owners that all SPS and RAS should be fully redundant, as long as such redundancy is consistent with a two circuit breaker in a series example that it provides in its reply brief.29  The PJM Transmission Owners agree that the customer and Transmission Owner may own the circuit breaker(s) and

27 Constellation at 14; Vistra at 32.
28 PJM Transmission Owners Initial Brief at 23-25.
29 Constellation at 22.

PDF page 12

12
protection systems at their respective facilities.  However, the meaning of Constellation’s caveat is unclear because typical substation construction does not necessarily mean that there will ever only be two breakers in a series.  The terminals formed by the circuit breakers on each end of the conductors between a Transmission Owner’s and a customer’s facilities may be composed of one or more than one circuit breaker.  Regardless, it does not change the nature and design of the protection systems used to accomplish SPS and RAS.  The number of breakers will be determined by the Transmission Owner’s and customer’s design practices and budget, and the Transmission Owner’s technical criteria.

Constellation also states that it “agrees in principle with the fourth recommendation” asserted in the PJM TOs’ initial paper hearing brief,30 that “[a]ll SPS and RAS must fully meet PJM and PJM Transmission Owner technical criteria.”31  As Constellation acknowledges, PJM Manual 3 governs PJM’s procedures for reviewing RASs.32  Where Constellation and the PJM Transmission Owners diverge is Constellation’s assertion that “[n]ew technical criteria [in Manual 3] should not be established solely for Co-Located Loads.”33  Revisions or additions to Manual 3 to account for Co-Located Loads may be unavoidable due to technical characteristics of Co- Located Load.  However, to the extent new technical criteria in Manual 3, or any other manual, make sense to apply more broadly to participants other than Co-Located Load, the PJM Transmission Owners are amenable to that possibility.  But PJM and the PJM Transmission Owners should not be restricted from developing and implementing criteria applicable to Co- Located Load as a class, if those criteria are based on reasonable technical differences between

30 Id. at 23 (emphasis added).
31 Id. at 23 (citing PJM Transmission Owners Initial Brief at 23). 32 Id. at 23-24.  See PJM, PJM Manual 03: Transmission Operations (Mar. 4, 2026), https://www.pjm.com/- /media/DotCom/documents/manuals/m03.pdf (last visited Apr. 24, 2026).
33 Constellation at 24.

PDF page 13

13
Co-Located Loads and other facilities.  In particular, Manual 3 does not contemplate a potentially significantly expanded use of SPS/RAS to enable load to take transmission service without building transmission upgrades otherwise necessary to serve Co-Located Load.  To the extent Co- Located Load arrangements impose additional and distinct reliability challenges, there is no justification for limiting PJM’s and the PJM Transmission Owners’ ability to address those challenges through additional criteria, including those specific to Co-Located Load, through revisions to Manual 3 or otherwise.

Additionally, Constellation’s request that the Commission reject the PJM Transmission Owners’ remaining recommendations is without merit.34 Constellation claims that these recommendations would treat Co-Located Loads differently without any legitimate basis. Constellation is wrong.  For instance, some PJM Transmission Owners already require protection on their facilities to ensure that existing customers with on-site generation do not backfeed the transmission system.  This also arises with respect to certain legacy networked distribution systems where the PJM Transmission Owner maintains a tripping scheme to ensure that power does not flow back onto the transmission system.  And both the PJM Transmission Owners and PJM have provided ample evidence explaining how the use of SPS and RAS in the context of Co-Located Load presents new and different challenges on the PJM system.35  No commenter, including Constellation, rebuts this evidence.  Moreover, the measures proposed by the PJM Transmission

34 Id. at 24-25.  These recommendations consist of (i) permitting Transmission Owners the option of requiring SPS or RAS on their side of the point of interconnection and permitting recovery of the associated costs; (ii) allowing Transmission Owners the option (which may or may not be exercised) of owning, operating and maintaining an SPS or RAS installed on the customer side of the point of interconnection; (iii) limiting the amount of load that can be covered by SPSs or RASs, and (iv) more frequent testing of SPS and RAS than is currently mandated by NERC reliability standards.  See PJM Transmission Owners Initial Brief at 23-24.
35 See PJM Transmission Owners Initial Brief at 22-25; see also PJM Initial Brief, Wharton Affidavit at PP 20- 26.

PDF page 14

14
Owners could be applicable to other customers—in addition to Co-Located Load—to the extent that the proliferation of SPS and RAS requires PJM-wide revisions to the relevant criteria. Relatedly, Vistra provides no convincing reason for the Commission to reject the PJM Transmission Owners’ recommendation that reasonable limits be imposed on the amount of load in specific geographic areas covered by SPS/RAS.36  As both PJM and the PJM Transmission Owners have explained, a heavy concentration of these protection systems in specific areas increases reliability risks based on potential failures on the system and the resulting potential for cascading outages.37  Vistra fails even to address, much less rebut, these explanations. Nevertheless, the PJM Transmission Owners recognize that to implement such limitations appropriately, further details and guidelines need to be developed, and welcome further engagement with stakeholders to assist PJM in doing so.

F. The PJM Transmission Owners Support PJM’s Proposed Operational
Penalties, and Provide Additional Details on Proposed Financial Penalties
1. PJM’s Operational Penalties are Just and Reasonable
The PJM Transmission Owners support the operational consequences and penalties
proposed by PJM that will apply to failures to follow load shedding/curtailment instructions and control technology and protection system misoperation.38  Robust operational penalty provisions are a necessary component of the new services because network upgrades are planned and built only to accommodate load covered by Firm Contract Demand Service or NITS.  Thus, it is crucial

36 Vistra at 27-28.
37 PJM Transmission Owners Initial Brief at 23; PJM Initial Brief, Wharton Affidavit at PP 21-22.
38 See PJM Initial Brief at 40-51.  PJM proposes penalties “applicable to Eligible Customers taking transmission service on behalf of a Co-Located Load using: (i) Firm Contract Demand Transmission Service; (ii) Non-Firm Contract Demand Transmission Service; and (iii) Interim NITS prior to automatically transitioning to NITS on behalf of a Co-Located Load.  PJM supports three different penalties applicable where such Eligible Customers:  (i) fail to follow established Load Shedding and Curtailment procedures; (ii) rely on necessary control technologies or protection systems in accordance with the PJM Manuals, which may include a RAS, that fail (i.e., misoperate) more than once; and (iii) makes unreserved use of the PJM Transmission System.”  Id. at 40.

PDF page 15

15
that Co-Located Loads respect their contractual limits.  This concern is particularly acute because these Co-Located Load arrangements likely will involve substantial amounts of load—hundreds, if not thousands of MW—being served by on-site generation but still connected to the grid.39  If these limits are not respected, the reliability consequences to the system—and to existing customers that depend on the reliable operation of that system—could be severe.40  Therefore, operational penalties must be structured to meaningfully deter load customers that exceed reserved service amounts.  PJM’s proposal appropriately achieves this purpose.

Constellation argues that PJM should simply adopt Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Load (“HILL”) process, which imposes only financial penalties.41  This argument is without merit.  First, SPP’s HILL proposal differs in a several pertinent respects from PJM’s proposal.  For example, unlike SPP’s HILL proposal, under PJM’s proposal Co-Located Load customers may be in the position of installing and operating their own control technologies and protection systems.42  Under such circumstances, it is appropriate and necessary that PJM have in place strong measures to ensure reliability and to incentivize customers to operate accordingly. Moreover, PJM and SPP are two different regions with different characteristics, including topology and proliferation of large loads.43  Financial penalties are proper but insufficient safeguards against adverse operational consequences of the sort proposed by PJM.

39 Joint Rebuttal Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer, Exhibit No. PTO-0005 at 4 (“Blazunas, Schafer, and Hammer Rebuttal Testimony”) .
40 Id. at 4.
41 Constellation at 19-21.
42 PJM Initial Brief at 43, 56; PJM Initial Brief, Attachment A at Sections 702.4, 705.5, 708(c), 710.4, 713.6.
43 See generally North American Electric Reliability Corporation, Long-Term Reliability Assessment (Jan. 2026), https://www.nerc.com/globalassets/our-work/assessments/nerc_ltra_2025.pdf; PJM, PJM Load Forecast Report (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load- report.pdf; Southwest Power Pool, 2025 Integrated Transmission Planning Assessment Report (Nov. 25, 2025), https://www.spp.org/media/2429/2025-itp-report-v10.pdf.  In addition, the level of retail competition and prevalence of independent generators in SPP differ substantially from those in PJM.

PDF page 16

16
The concerns raised regarding the liability of Co-Located Load customers for penalties associated with control technologies and protection systems operated by other parties, such as Transmission Owners44 miss the point.  The installation of redundant protection facilities by Transmission Owners on their own system should not serve as an excuse for customers to fail to properly maintain and operate their own equipment.  The failure to do so should be subject to the penalties proposed by PJM, regardless of whatever additional protection systems a Transmission Owner or other entity may install.

2. Additional Detail Regarding PJM Transmission Owners’ Financial
Penalty Proposal
As set forth in their March 25 joint response, the PJM Transmission Owners are proposing financial penalties that will operate in a complementary fashion with PJM’s proposed operational penalties.45  The PJM Transmission Owners provide more detail on this proposal in the accompanying Blazunas, Schafer, and Hammer Rebuttal Testimony, as well as the accompanying Illustrative Tariff sheets.  As explained in the Blazunas, Schafer, and Hammer Rebuttal Testimony, the PJM Transmission Owners propose a financial penalty charge structure with two components:

(1) a base penalty charge, which applies to each individual hour in which the reserved transmission service limit is exceeded, and (2) a penalty ratchet, which applies when such exceedances occur repeatedly.46  When a Co-Located Load exceeds its reserved transmission service limit, which will include any reductions based on curtailments directed by PJM, the base penalty charge will be assessed for any hour in which at least one five-minute interval occurs during which a customer’s

44 See Response of the Data Center Coalition, Docket Nos. EL25-49, et al., at 8 (Mar. 25, 2026); Vistra at 30-
31. 45 Joint Response of the PJM Transmission Owners at 11-13.
46 Blazunas, Schafer, and Hammer Rebuttal Testimony at 6.

PDF page 17

17
metered load at the point of delivery exceeds its reserved transmission service.47  Such a five- minute interval is defined as an Exceedance Interval, and such an hour is defined as an Exceedance Hour.48  The base penalty charge will apply to each Exceedance Hour.49

The penalty rachet applies when multiple Exceedance Hours occur during a particular time period.50  It is designed to discourage recurring reliance on unreserved transmission capacity.51 Under the penalty rachet framework, the penalty charges escalate as the frequency of unreserved transmission use increases.52  Specifically, if more than one Exceedance Hour occurs on the same calendar day, an additional daily penalty applies.53  If exceedances occur on multiple calendar days within the same calendar week, an additional weekly penalty applies; likewise, if exceedances occur in multiple calendar weeks within the same calendar month, an additional monthly penalty applies.54  By progressively increasing the economic consequences of repeated penalties, the penalty ratchet reinforces the expectation that Co-Located Load customers manage their load in a manner consistent with their reserved transmission service limits.55

III. RESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE
PROPOSALS
As required by the Commission, the PJM Transmission Owners have proposed rates for Interim NITS, Firm Contract Demand Service, Non-Firm Contract Demand Service, and a Grid

47 Id. at 7.
48 Id. at 7.
49 Id. at 7.
50 Id. at 7.
51 Id.
52 Id.
53 Id.
54 Id.
55 Id.

PDF page 18

18
Reliance Charge.  Some parties support the PJM Transmission Owners rate proposals,56 while others raised issues regarding certain aspects of those proposals.  As discussed in their initial brief and below, the PJM Transmission Owners’ rate proposals are just and reasonable, and none of the criticisms in the March 25 filings support significant modifications to the proposed rates. In addition, the PJM Transmission Owners are including with this filing Illustrative Tariff sheets to provide additional detail regarding the implementation of their rate proposals.57 Testimony supporting these tariff revisions, as well as the PJM Transmission Owners’ responses to commenters, is included as Exhibit No. PTO-0005 to this reply brief.

A. The Proposed Contract Demand Rate Design is Just and Reasonable
The Firm Contract Demand Service rate will be calculated in a manner essentially identical to the existing NITS rates.58  Constellation notes that a number of PJM Transmission Owners do not use a single coincident peak to calculate their NITS rates.59  Constellation requests clarification that the Firm Contract Demand Service rate will be equal to the applicable Transmission Owner’s NITS rate calculated using that Transmission Owner’s methodology.60  The PJM Transmission Owners clarify that the zonal Firm Contract Demand rate will be calculated using that Transmission Owner’s specific methodology applicable to NITS customers.

Vistra incorrectly alleges that the PJM Transmission Owners fail to grapple with the question of whether it may be just and reasonable to apply the current zonal Non-Firm Point-to-

56 See Response of Northern Virginia Electric Cooperative, Inc., Docket Nos. EL25-49, et al., at 6-10 (filed Mar. 25, 2026); Reply Brief of Old Dominion Electric Cooperative, Docket Nos. EL25-49, et al., at 5, 8-10 (filed Mar. 25, 2026).
57 See Exhibit No. PTO-0006.
58 PJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer at 6.
59 Constellation at 31.
60 Id. at 31.

PDF page 19

19
Point (“PTP”) Service rates to Non-Firm Contract Demand Service, including whether Non-Firm Contract Demand Service is superior to Non-Firm PTP Service.61  In their Initial Brief, the PJM Transmission Owners explained why it would be unreasonable to simply apply the existing Non- Firm PTP rates to Non-Firm Contract Demand Service.62  That is, for many years in PJM, transmission customers have used Non-Firm PTP service exclusively to facilitate the delivery of specific generation to the PJM border, not for internal use.  The existing discounted Non-Firm PTP Service rate reflects historical use, and was certainly not intended, and is not appropriate, for Non- Firm Contract Demand Service, which (a) is intended to be a limited, supplemental service within PJM and (b) does not facilitate the delivery of specific generation to specific load over a contract path.63  In addition, Non-Firm Contract Demand Service is demonstrably superior to Non-Firm PTP service.  As discussed in the PJM Transmission Owners Initial Brief, Non-Firm Contract Demand Service has a superior curtailment priority relative to Non-Firm PTP.64 A few parties contend that the PJM Transmission Owners’ proposal to initially establish rates for Non-Firm Contract Demand Service based on the rates determined for Firm Contract Demand Service is inconsistent with principles of cost causation.65  The Joint Developers, for instance, argue that the PJM Transmission Owners should discount Non-Firm Contract Demand Service because Non-Firm Contract Demand customers will impose “lesser costs” on the grid.66 However, as noted in the Initial Brief, before determining whether a discount is appropriate for

61 Vistra at 16-17.
62 PJM Transmission Owners Initial Brief at 11-12.
63 Id. at 11 n. 30.
64 Id. at 12.
65 Joint Developers at 3, 20-23; Response Brief of Geronimo Power, LLC, Docket Nos. EL25-49, et al. at 6 (filed Mar. 25, 2026) (“Geronimo”).
66 Joint Developers at 20.

PDF page 20

20
Non-Firm Contract Demand Service, and if so, at what level the discount should be set, the PJM Transmission Owners need to gather data on how Non-Firm Contract Demand Service customers are utilizing the service, taking into account the intended purpose of the service, and the effect of that utilization on the system.67  Thus, the PJM Transmission Owners will consider on a going- forward basis whether a discount is appropriate for Non-Firm Contract Demand Service based on system conditions and use patterns and, if so, the criteria and limits under which PJM will apply the discount.68  In short, the PJM Transmission Owners are preserving the ability to offer discounts, which is sufficient at this time to address the Joint Developers’ concerns.69

The Joint Developers argue that no further study or data gathering is necessary before offering a discount because the PJM Transmission Owners can have confidence that customers using Non-Firm Contract Demand Service will require fewer upgrades.70  However, it is far from certain what upgrades may be required for Non-Firm Contract Demand Service customers.  Indeed, it is possible that most or all Co-Located Load customers will take significant Firm Contract Demand Service, with only limited non-firm service.  This supports the PJM Transmission Owners’ explanation in their initial brief that further analysis is needed to determine whether a discount is appropriate for Non-Firm Contract Demand Service and, if so, what level of discount should be adopted, taking into account how customers are utilizing the service and the effect of that utilization on the system.71

67 PJM Transmission Owners Initial Brief at 13.
68 Id. at 13.  Any rate discount offered for Non-Firm Contract Demand Service would be offered by PJM based on rules and criteria established by the PJM Transmission Owners designed to incentivize the efficient use of Non- Firm Contract Demand Service and the transmission system.  Id.
69 Joint Developers at 20-23.
70 Id. at 21.
71 PJM Transmission Owners Initial Brief at 13.

PDF page 21

21
Finally, the Joint Developers’ concerns that the Non-Firm Contract Demand Service rate will discourage industrial development72 are exaggerated and misplaced.73  As the Commission has recognized, Non-Firm Contract Demand Service is intended as a limited service to cover periods when on-site generation is on outage, not a substitute for Firm Contract Demand Service or NITS.74  To the extent that Co-Located Load intends to rely on delivery of energy from the transmission system, rather than on-site generation, that load should be required to obtain firm service, either in the form of Firm Contract Demand Service or NITS.75

B. The Proposed Grid Reliance Charge Rate Design is Just and Reasonable
In their initial brief, the PJM Transmission Owners proposed a Grid Reliance Charge designed to reflect the costs of using the transmission system to deliver black start and regulation services.76  The Grid Reliance Charge also reflects the costs of providing the inherent benefits that all customers, including Contract Demand customers, receive as a result of their connection and synchronization to the grid.77  The PJM Transmission Owners proposed a methodology based on the portions of annual depreciation and operations and maintenance expenses that best capture the portions of a transmission owner’s revenue requirements relating to the ongoing reliable operation of the grid.78  Although nearly all of the commenters acknowledge that some Grid Reliance Charge is appropriate, a few parties contend that the PJM Transmission Owners’ proposed methodology

72 Joint Developers at 22-23.
73 Id. at 22-23 (“For example, . . . thermal energy storage resources must be able to take power when low-cost supply is available . . . at prices that reflect the lower cost of electricity and transmission service during such conditions.”).
74 Order at P 214.
75 Id. at P 160.
76 PJM Transmission Owners Initial Brief at 14-18.
77 Id. at 14.
78 Id. at 15-16.

PDF page 22

22
for determining the Grid Reliance Charge is unjust and unreasonable.  These claims are without merit.

Vistra and Geronimo are the only two parties that suggest no Grid Reliance Charge is necessary.  Geronimo claims that “not being islanded from the grid is not a benefit in and of itself”79 and argues that the PJM Transmission Owners did not provide any detail on what sort of “inherent benefits” will flow from the service associated with the Grid Reliance Charge.80  This claim is incorrect.  Being connected to the grid provides obvious benefits in terms of the ability to access resources that are not co-located with load if necessary, backing up co-located generation, and providing critical ancillary services to Co-Located Load, such as regulation and black start. These grid benefits also include delivering ancillary services and essential reliability services, such as frequency support, inertia, voltage stability, fault current capability, ride-through and protections coordination, and providing sufficient short-circuit capability.81  The PJM Transmission Owners are not aware of any existing or proposed Co-Located Load customers that are choosing to island their load and on-site generation.  Indeed, the Order directs PJM to provide three transmission-service pathways for Co-Located Loads, allowing those loads to take transmission service from the grid rather than requiring a fully islanded arrangement.  It follows that Co-Located Loads should share in the basic costs of operating and maintaining the grid upon which they rely.

Likewise, Geronimo incorrectly asserts that there are no costs associated with delivering black start and regulation services.82  In the Order, the Commission expressly recognized that rates

79 Geronimo at 11.
80 Id. at 11-12.
81 Rebuttal Testimony of Blazunas, Schafer, and Hammer at 16.
82 Geronimo at 12-14.

PDF page 23

23
may need to include an additional charge for delivering these services, in addition to the costs of the services themselves.83  This additional charge is appropriate because ancillary services such as black start and regulation provide no value without the ability to access the transmission system to obtain them.

Constellation contends that the proposed Grid Reliance Charge is not grounded in sound ratemaking and cost-causation principles based on the Grid Reliance Charge excluding and including certain cost categories.84  Namely, Constellation argues that the Grid Reliance Charge excludes reasonable costs, such as rate of return and taxes, while including unreasonable costs, such as the full costs of depreciation for facilities sized to meet PJM peak demand.85  Constellation is mistaken.  The PJM Transmission Owners’ proposed Grid Reliance Charge methodology is grounded in sound ratemaking and cost causation principles.  It represents an appropriate balance between fairly estimating the grid reliance benefits to Co-Located Load and the need to ensure the rate can be practically implemented.86  Practicality concerns are particularly pertinent here given the Commission’s desire to expedite the interconnection of data center loads.  This approach is also fully consistent with longstanding Commission and court precedent holding that cost allocation rules do not require exacting precision as long as they represent a comparison of the costs assessed to a party against the burdens imposed or benefits drawn.87  The PJM Transmission Owner’s Grid Reliance Charge proposal meets this standard.

83 Order at P 160.
84 Constellation at 25-27.
85 Id. at 25-27.
86 Rebuttal Testimony of Blazunas, Schafer, and Hammer at 16.
87 See, e.g., Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009); Transmission Plan. & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at P 504 and nn. 393, 435, 453 (2011) (citing to Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361 at 1369, 1371 (D.C. Cir. 2004) (explaining that cost causation “does not require exacting precision in a ratemaking agency’s allocation decisions.”)).

PDF page 24

24
 Attempting to determine the proportion of rate of return and taxes to include in the Grid Reliance Charge, as Constellation suggests,88 would necessarily entail the need to determine related proportions for all components (and all relevant FERC accounts in those components) of the Transmission Owner’s revenue requirement.  Such determinations would be extremely difficult to produce and would potentially result in a spurious level of precision because they would depend largely on subjective determinations including judgments based on the unique facts of each Co- Located Load arrangement.  Such determinations would be extremely challenging to implement on an ex ante basis and highly susceptible to disputes and challenges.  Moreover, although the base components included in the proposed Grid Reliance Charge calculation are limited to transmission depreciation and a percentage of transmission operations and maintenance expenses, the calculation also includes accounts related to day-to-day operational costs of the provision of grid reliance while maintaining a high level of transparency.  By excluding rate of return and taxes, the methodology produces a more conservative result focused on recovery of the costs necessary to support the ongoing reliable operation of the grid, rather than a return on investment. Constellation further challenges the PJM Transmission Owners’ proposal to include 100% of transmission depreciation expense in the calculation of the Grid Reliance Charge.89 Constellation witness Zachary Ming argues that it is inappropriate to include the “full depreciation costs for a variety of transmission components . . . that are sized to meet the actual peak demand requirements of the PJM system, even though customers paying the [Grid Reliance Charge], by definition, do not impose any demand or withdraw any energy from the PJM system . . . .”90  As the PJM Transmission Owners explain in the Initial Brief and related testimony, the Grid Reliance

88 Constellation at 11-12.
89 Id. at 26-27.
90 Id. at 27 (quoting Testimony of Zachary Ming at 12:5-10 (“Ming Testimony”)).

PDF page 25

25
Charge includes 100% of the transmission depreciation expenses included in FERC Accounts 350- 359.91  This proposal is reasonable when considered in the overall context of the rate design methodology.  Although the transmission system is built to meet peak demand, the proposed Grid Reliance Charge rate design does not include the full revenue requirement associated with the transmission infrastructure put in place to meet peak demand, meaning that the full cost of that infrastructure is not recovered in the Grid Reliance Charge.  But even if a particular customer is not making use of the transmission system to deliver energy during the peak period(s), that customer still relies on the grid based on its on-site demand.  The PJM Transmission Owners’ proposed Grid Reliance Charge appropriately reflects that fact by including only costs associated with the continued operation of the transmission system.

Instead of the methodology proposed by the PJM Transmission Owners, Constellation’s witness Zachary Ming proposes a “minimum system” approach to calculating the Grid Reliance Charge.92  Under this proposal, the Grid Reliance Charge would be calculated using the “minimum system” method that some, but far from all, utilities use to determine customer-driven components of their distribution rates.  This approach would be based on determining the costs associated with the minimum size of all system components that could be used to recreate its system and connect each customer to the grid.93  Constellation’s proposal is unreasonable in the context of a Grid Reliance Charge, and if adopted, would end up shifting to other users of the system costs that are appropriately borne by Co-Located Load customers that will continue to rely on their interconnection to the transmission system.

91
PJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer at 21-22.

92 Constellation at 26-28; Ming Testimony at 14:2-15:2.
93 Mr. Ming addresses this proposal in greater detail and estimates a value between 2 and 10 percent of total system costs.  Constellation at 27-28; Ming Testimony at 21:17-20.

PDF page 26

26

As Mr. Ming acknowledges, although the “minimum system” method is sometimes used94 as a component of class cost of service studies for distribution systems, it is not used in transmission studies.95  As Mr. Schafer explains in the Blazunas, Schafer, and Hammer Rebuttal Testimony, the minimum system method is not used at the transmission level because the foundational premise of the method—that a definable portion of the system is built solely to connect customers largely independent of load—does not exist in transmission systems, which are planned and operated to serve bulk power flows and meet system-wide reliability criteria.96  In distribution studies, the minimum system study results are allocated to customer classes based on the count of customers, not on rate-class demand.97  Yet Mr. Ming nevertheless proposes to apply the results of the minimum system study to develop a demand-related charge – the Grid Reliance Charge.  Such an application is inconsistent with the methodology because the minimum system study develops a customer-related cost that is not intended to be billed on demand.98 Mr. Ming further proposes the minimum system methodology without concern for what the Grid Reliance Charge is designed to accomplish.  He states that “[w]ithin the context of electricity system ratemaking, [the minimum system] methodology [is] designed to calculate precisely the costs of constructing wires to connect all customers, i.e., customer-driven costs.”99 Mr. Ming adds that “[a] ‘minimum system’ is a theoretical electricity system designed only to

94 Indeed, the minimum system approach is not uniformly used even in distribution ratemaking.
95 Ming Testimony at 21:9-11 (“As discussed above, there is little to no precedent for applying the minimum system method to the transmission system, so there is relatively little available data upon which to benchmark results.”).
96 Blazunas, Schafer, and Hammer Rebuttal Testimony at 20.
97 Id. at 23.
98 Id. at 25.
99 Ming Testimony at 14:14-17.

PDF page 27

27
connect each customer and deliver a de minimis amount of power.”100  However, the simple goal of “connecting all customers” is quite different from recovering costs associated with delivery of black start, regulation and other ancillary services, which must be available under any system condition, along with the costs associated with a Co-Located Load’s continued reliance on the reliable operation of the transmission system.  Mr. Ming does not demonstrate that there is any correlation between the mere electrical connection of customers and the benefits a Co-Located Load receives from an on ongoing grid connection in proportion to its on-site load.  Without some link between the two, there is no justification for using a minimum system method to calculate the Grid Reliance Charge.  Further, the quoted portions above again highlight that the minimum system method is related to customer costs, not costs that should be recovered through demand charges.101  The minimum system method is simply not appropriate for use in developing the demand-based Grid Reliance Charge.  This contrasts with the PJM Transmission Owners’ proposal, which identifies the specific depreciation and operations and maintenance expense category that best captures the portions of a Transmission Owner’s revenue requirements relating to the ongoing reliable operation of the grid, and therefore the benefits that all customers interconnected with the system receive as a result.102

Mr. Ming’s position is that because no utilities use the “minimum system” method for transmission, the Commission must assume that the minimum system value is close to 0% for the transmission system, and therefore conclude that the PJM Transmission Owners’ proposed fixed

100 Ming Testimony at 14:19-20.
101 Blazunas, Schafer, and Hammer Rebuttal Testimony at 28.
102 See PJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer at 20-21; see also Blazunas, Schafer, and Hammer Rebuttal Testimony at 26-27.

PDF page 28

28
percentage should be much less than the proposed 25.8%.103  This reasoning is nonsensical.  The rational conclusion to draw here is that if no utilities use the “minimum system” method for transmission, then that method is irrelevant to this proceeding and it cannot be the basis for any inferences or conclusions with respect to the PJM Transmission Owners’ proposed Grid Reliance Charge methodology.104  The fact that the PJM Transmission Owner’s proposal resulted in a fixed percentage allocator higher than Constellation would prefer does not cause the underlying methodology to be unjust and unreasonable.

Mr. Ming further presents what he claims are the results of a minimum system study approach to the Grid Reliance Charge,105 but even if such an approach were theoretically legitimate, his implementation is fundamentally flawed.  This is evident from his selection of minimum system components.  For example, when choosing the minimum system component for transmission poles and transmission towers, Mr. Ming indicates the use of “distribution wood pole[s].”106  In other words, Mr. Ming’s minimum system study assumes that a minimum transmission system could be built with wood poles used for distribution system facilities.  This assumption disregards the engineering reality of the transmission system.  A distribution wood pole cannot perform the function of a transmission structure in that it cannot support required voltages, cannot meet clearance requirements, and cannot handle mechanical loads (e.g., span length, conductor weight).107

103
Mr. Ming admits that “no utilities that I am aware of classify any transmission costs to the customer cost driver,” and, based on this fact he assumes utilities are implicitly assuming “a minimum system value of 0% for the transmission system.”  Consequently, Mr. Ming concludes that “it is reasonable to assume that a proper minimum system study when applied to the transmission system would yield a value significantly lower than [the] 25.8%” that the PJM Transmission Owners propose for the initial fixed percentage.  See Ming Testimony at 18:11-15.

104 Blazunas, Schafer, and Hammer Rebuttal Testimony at 22-23.
105 Ming Testimony at 20:1 (Table 1). 106 Id. at 20:1, n.26 (Table 1).
107 Blazunas, Schafer, and Hammer Rebuttal Testimony at 19.

PDF page 29

29
Vistra also argues that the Grid Reliance Charge is unjust, unreasonable and unduly discriminatory, raising a number of claims.108  None of Vistra’s claims have any merit.  First, the PJM Transmission Owners’ proposal does not conflict with Order No. 888’s requirement to unbundle ancillary services from transmission service.109  Contrary to Vistra’s claim that the PJM Transmission Owners are proposing a new “undefined ancillary service,”110 the Grid Reliance Charge is not a new ancillary service.  Rather, it is a charge contemplated in the Order that is necessary to account for and recognize the benefits that Co-Located Load receives through its interconnection with the transmission grid and the delivery of black start and regulation services. As such, it is appropriately designed and recovered as a transmission service charge.111 Second, Vistra’s proposed alternative to the Grid Reliance Charge methodology also is without merit.  Vistra argues that, because only 0.5% of “PJM’s monthly billings” are related to black start and regulation charges, 0.5% is a reasonable proxy for the Grid Reliance Charge fixed percentage.112  This argument assumes that the 0.5% can be employed as the Grid Reliance Charge fixed percentage without considering the relationship between the percentage of billed revenue for black start and regulation and the costs of the transmission system used to deliver those ancillary services when needed, as well as to provide the benefits associated with an ongoing grid interconnection.113  In fact, there is no connection between the two metrics, making a comparison of the billings for black start and regulation service to the costs required to deliver those services

108 Vistra at 18-23.
109 Id. at 19-20. 110 Id. at 20.
111 Order, Chang Concurrence at P 9.
112 Vistra at 22 (quoting Affidavit of Rebecca Stadelmeyer at 11:12-14).
113 Blazunas, Schafer, and Hammer Rebuttal Testimony at 29.

PDF page 30

30
misleading at best.114  The fixed percentage is a function of the facilities and expenses related to the delivery of ancillary services; it is not associated with PJM’s billings for the actual ancillary services.115  Moreover, the purpose of the Grid Reliance Charge is not confined to recovering the costs associated with delivery of black start and regulation services, but rather, encompasses the full range of benefits that a Co-Located Load received by virtue of its continued interconnection to the grid.116

Third, Vistra is incorrect in its assertion that the PJM Transmission Owners’ proposal fails to account for Co-Located Load customers that take different levels of service.117  Under the PJM Transmission Owners’ rate proposal, customers taking some form of transmission delivery service (NITS, Firm or Non-Firm Contract Demand Service) will be charged only for that service, while customers that take no such transmission service will not be subject to such charges.  However, even if a customer never “pulls energy from the grid,” and only relies on black start and regulation service,118 and receives the inherent benefits that come with grid interconnection, providing these benefits still requires transmission infrastructure, which requires investment and expense.  The Grid Reliance Charge appropriately captures, with reasonable precision, the costs of the transmission necessary for the delivery of ancillary services to co-located loads, as the Commission recognized in the Order.119

114 Id. at 29.
115 Id.
116 Id. at 31.
117 Vistra at 21-22.
118 Id. at 21 (“[A] customer that is relying on the grid solely for regulation and black start service is demonstrably relying very little on the grid.”).
119 Order at P 183.  As with some other parties, if Vistra disagrees with this Commission finding, its path is to seek rehearing of the Order, not to challenge the PJM Transmission Owners’ proposed compliance.

PDF page 31

31
C. The PJM Transmission Owners’ Crediting Proposal Will not Create a Cost
Shift Among Customers
Vistra claims that the PJM Transmission Owners’ proposal to credit the revenues associated with the Grid Reliance Charge and Non-Firm Contract Demand Service to customers taking NITS and Firm Contract Demand Service will create unjustified cost shifts among customer classes.120  Vistra is incorrect.  First, the proposed credits relating to Non-Firm Contract Demand Service revenues are not subsidies but instead represent offsets that reduce the amount paid by firm service customers for the firm transmission service they receive.121  This is entirely appropriate as transmission rates are designed to recover the fixed costs of building and maintaining the system so as to provide service to firm customers.122  Therefore, the revenues received from Non-Firm Contract Demand Service are appropriately applied as a credit to offset those fixed costs.123  Absent such a credit, transmission owners would over-recover their revenue requirements.  Similarly, it is appropriate to provide firm service customers with credits representing the revenues received from the Grid Reliance Charge.  Those customers will be paying a rate that reflects the full embedded cost of the transmission system.124  Absent receiving a credit associated with the Grid Reliance Charge, those customers would be effectively double- charged for those services, which are already fully included in their firm service charge. Importantly, the crediting mechanism is fully consistent with previously approved crediting

120 Vistra at 23-25.
121 Blazunas, Schafer, and Hammer Rebuttal Testimony at 30.
122 Id. at 30.
123 Id. at 30.
124 Id. at 31.

PDF page 32

32
mechanisms in PJM’s Tariff, such as Section 27A, which credits Non-Firm PTP transmission service revenue to Network and Firm PTP transmission service customers.125

Finally, Vistra’s statement regarding the manner in which a PJM Transmission Owner or its affiliate passes along any bill credits it receives by virtue of its role as a transmission customer is irrelevant.126  Issues regarding the allocation of bill credits to retail customers are matters of state retail ratemaking, and beyond the scope of this specific proceeding and the Commission’s jurisdiction generally.

125 See PJM Tariff, Section 27A.
126 Vistra at 24-25.

PDF page 33

33
IV. CONCLUSION
The PJM Transmission Owners appreciate the opportunity to submit this reply brief to parties’ responses to the PJM and PJM Transmission Owners Initial Briefs.  The PJM Transmission Owners respectfully request that any subsequent Commission orders addressing these issues adopt the proposals and recommendations set forth herein.

Respectfully submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling

Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the PJM
  Transmission Owners
Dated:  April 24, 2026

PDF page 34

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, D.C., this 24th day of April 2026.

/s/ Daniel Klein