EL25-49-000 · 2026-04-24 · Indicated PJM Transmission Owners

Reply Brief of the Indicated PJM Transmission Owners

Text extracted from the eLibrary original (SHA-256 a74519a63be4a119…). Download the original from the official source.

Contents · 13 sections
  1. I. INTRODUCTION p. 2
  2. II. RESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND p. 3
  3. A. PJM has Appropriately Defined the Scope of Contract Demand and Interim p. 3
  4. B. PJM Appropriately did not Propose Changes to the Definition of Eligible p. 6
  5. C. The Commission Should not Mandate a Combined Interconnection and p. 7
  6. D. PJM’s Study Proposal Does not Promote Discrimination Against Co-Located p. 9
  7. E. The PJM Transmission Owners’ Proposed Criteria Relating to Special p. 11
  8. F. The PJM Transmission Owners Support PJM’s Proposed Operational p. 14
  9. III. RESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE p. 17
  10. A. The Proposed Contract Demand Rate Design is Just and Reasonable p. 18
  11. B. The Proposed Grid Reliance Charge Rate Design is Just and Reasonable p. 21
  12. C. The PJM Transmission Owners’ Crediting Proposal Will not Create a Cost p. 31
  13. IV. CONCLUSION p. 33

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.
Read this passage

I. INTRODUCTION

printed heading · Topic match: Cost allocation

INTRODUCTION The PJM Transmission Owners’ proposals in this proceeding are grounded in two main principles: (1) rates for the new services must be consistent with longstanding cost allocation principles, and (2) the new services must be implemented in a manner that does not compromise system…
Read this passage Filed comments: Cost allocation

II. RESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND

printed heading

RESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND CONDITIONS FOR THE NEW TRANSMISSION SERVICES
Read this passage

A. PJM has Appropriately Defined the Scope of Contract Demand and Interim

printed heading · Topic match: Connecting load and generation

This approach will properly balance flexibility for Co-Located Load customers to obtain needed firm or non-firm service depending on their mix of on-site load and generation, with the obligation to ensure that the system can continue to be operated reliably for the benefit of all customers.
Read this passage Filed comments: Connecting load and generation

B. PJM Appropriately did not Propose Changes to the Definition of Eligible

printed heading · Topic match: Connecting load and generation

The generator likely would not be seeking to procure transmission service in order for it to serve the on-site load, and instead would be selling its output directly to the on-site load at retail (or to its state licensed supplier).14 The ability of a Co-Located Load, or an entity representing the…
Read this passage Filed comments: Connecting load and generation

C. The Commission Should not Mandate a Combined Interconnection and

printed heading · Topic match: Retail and wholesale authority

There is no need for the Commission to entangle itself in questions regarding the division between its jurisdiction over interstate transmission matters and state jurisdiction over retail service in this proceeding.
Read this passage Filed comments: Retail and wholesale authority

D. PJM’s Study Proposal Does not Promote Discrimination Against Co-Located

printed heading · Topic match: Connecting load and generation

The reference to studies conducted by the Transmission Owners that PJM will consider inherently must refer to the studies Transmission Owners will conduct in order to integrate load facilities.
Read this passage Filed comments: Connecting load and generation

E. The PJM Transmission Owners’ Proposed Criteria Relating to Special

printed heading · Topic match: Connecting load and generation

Constellation also states that it “agrees in principle with the fourth recommendation” asserted in the PJM TOs’ initial paper hearing brief,30 that “[a]ll SPS and RAS must fully meet PJM and PJM Transmission Owner technical criteria.”31 As Constellation acknowledges, PJM Manual 3 governs PJM’s…
Read this passage Filed comments: Connecting load and generation

F. The PJM Transmission Owners Support PJM’s Proposed Operational

printed heading · Topic match: Connecting load and generation

PJM proposes penalties “applicable to Eligible Customers taking transmission service on behalf of a Co-Located Load using: (i) Firm Contract Demand Transmission Service; (ii) Non-Firm Contract Demand Transmission Service; and (iii) Interim NITS prior to automatically transitioning to NITS on behalf…
Read this passage Filed comments: Connecting load and generation

III. RESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE

printed heading

RESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE PROPOSALS As required by the Commission, the PJM Transmission Owners have proposed rates for Interim NITS, Firm Contract Demand Service, Non-Firm Contract Demand Service, and a Grid 47 Id. at 7. 48 Id. at 7. 49 Id. at 7. 50 Id. at 7. 51 Id.…
Read this passage

A. The Proposed Contract Demand Rate Design is Just and Reasonable

printed heading · Topic match: Connecting load and generation

The Proposed Contract Demand Rate Design is Just and Reasonable The Firm Contract Demand Service rate will be calculated in a manner essentially identical to the existing NITS rates.58 Constellation notes that a number of PJM Transmission Owners do not use a single coincident peak to calculate…
Read this passage Filed comments: Connecting load and generation

B. The Proposed Grid Reliance Charge Rate Design is Just and Reasonable

printed heading · Topic match: Connecting load and generation

Instead of the methodology proposed by the PJM Transmission Owners, Constellation’s witness Zachary Ming proposes a “minimum system” approach to calculating the Grid Reliance Charge.92 Under this proposal, the Grid Reliance Charge would be calculated using the “minimum system” method that some, but…
Read this passage Filed comments: Connecting load and generation

C. The PJM Transmission Owners’ Crediting Proposal Will not Create a Cost

printed heading · Topic match: Cost allocation

The PJM Transmission Owners’ Crediting Proposal Will not Create a Cost Shift Among Customers Vistra claims that the PJM Transmission Owners’ proposal to credit the revenues associated with the Grid Reliance Charge and Non-Firm Contract Demand Service to customers taking NITS and Firm Contract…
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

CONCLUSION The PJM Transmission Owners appreciate the opportunity to submit this reply brief to parties’ responses to the PJM and PJM Transmission Owners Initial Briefs.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 24th day of April 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005