Motion for Leave to Answer and Answer of Enchanted Rock, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-located at Generating
Facilities
)
)
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
Docket No. EL25-20-000
(consolidated)
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
ENCHANTED ROCK, LLC
Pursuant to Rules 212 and 2131 of the Federal Energy Regulatory Commission (“FERC”
or “Commission”)’s rules of practice and procedure, Enchanted Rock, LLC (“ERock”2) submits this motion for leave to answer (“Motion”) and answer (“Answer”) in response to PJM
Interconnection, LLC (“PJM”)’s April 24, 2026 reply brief3 in the captioned proceedings
concerning, inter alia, the Commission’s December 18 Order.4
ERock submits this Answer to respond to several misleading and incorrect statements
made by PJM in their April 24 Reply Brief concerning PJM’s proposed implementation of
Interim Network Integration Transmission Service (“Interim NITS” 5). Moreover, for the
1 18 C.F.R. §§ 385.212, 385.213 (2025).
2 In April 2026, Enchanted Rock, LLC rebranded to “ERock” to reflect the evolution of the brand and its future.
3 Reply Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Apr. 24, 2026) (“April 24 Reply Brief”).4 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Order”); see also, 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al, Docket No. ER26-1479-000 (Feb. 23, 2026) (“PJM February 23 Compliance Filing”). 5 All capitalized terms not otherwise defined herein shall have the same meaning set forth in the PJM Open Access Transmission Tariff (“PJM Tariff”), or the Illustrative Language For New Tariff (“Illustrative Tariff”) filed with the Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Feb. 23, 2026) (“PJM Initial Brief”), as applicable.
PDF page 2
2
reasons stated below, and those stated in ERock’s March 25, 2026, reply brief and protest,6 PJM’s proposed implementation of Interim NITS conflicts with the December 18 Order’s directives requiring PJM to establish “a new interim, non-firm transmission service.”7
I. MOTION FOR LEAVE TO ANSWER
While Rule 213(a)(3) of the Commission’s rules of practice and procedure provides that an “answer may be made to any pleading, if not prohibited under paragraph (a)(2) of this section,”8 Rule 213(a)(2) precludes, as a matter of right, an answer to a protest or answer.9 The Commission, however, will permit such answers for good cause shown.10 Good cause exists when the response will assist the Commission in its decision-making process, such as by helping to explain the relevant issues or otherwise facilitating the development of the record.11 Good cause exists here to allow ERock to respond to the April 24 Reply Brief in order to address several erroneous arguments made by PJM, and to facilitate the development of the record.
II. ANSWER
A. PJM’s Proposed Implementation of Interim NITS Is Fundamentally Flawed
At the heart of PJM’s proposed implementation of Interim NITS lies a fundamental disconnect between what PJM is proposing and what the Commission directed PJM to implement in the December 18 Order. Notably, after finding that PJM’s existing tariff is unjust and unreasonable because, inter alia, “it does not include transmission services that reflect an
6 Reply Brief and Protest of Enchanted Rock, LLC, Docket Nos. EL25-49-000, et al. (Mar. 25, 2026) (the “ERock Protest”).7 See December 18 Order at P 160. 8 18 C.F.R. § 385.213(a)(3).9 Id. § 385.213(a)(2).10 See Transcontinental Gas Pipe Line Co., 158 FERC ¶ 61,125, at P 18 (2017).11 See id. (“Although the Commission’s Rules of Practice and Procedure do not permit answers to protests or answers to answers, we find good cause to waive our rules and accept the answers because they provide information that has assisted in our decision making process”); Midcontinent Indep. Sys. Operator, Inc., 161 FERC ¶ 61,056, at P 32 (2017) (“We will accept the answers . . . because they have provided information that assisted us in our decision making process.”).
PDF page 3
3
Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the transmission system under certain conditions,”12 the Commission directed PJM to “establish three new transmission services that reflect that Eligible Customers taking service on behalf of Co-Located Load are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”13 Relevant here, one of the three new types of transmission services is intended to “allow Eligible Customers seeking to take NITS on behalf of Co-Located Load to, at their option, take a new interim, non-firm transmission service until all Network Upgrades necessary to provide NITS are complete.”14 Rather than proposing rules that would enable Eligible Customers to utilize this “new interim, non-firm transmission service,” the April 24 Reply Brief instead doubles down on PJM’s flawed position that would prohibit Co-Located Load from receiving any capacity or energy from a Co-Located Generating Facility while the Co-Located Load is taking Interim NITS (sometimes referred to herein as the “Proposed Interim NITS Limitation”).15 PJM’s Proposed Interim NITS Limitation, and its statements in its April 24 Reply Brief, make clear that PJM seeks to treat a Co-Located Generating Facility serving a Co-Located Load taking Interim NITS as a Capacity Resource that is fully deliverable to the PJM wholesale market during the interim period before “all Network Upgrades necessary to provide NITS are complete”16 and before the Co-Located Generating Facility even has an executed Generator Interconnection Agreement (“GIA”). PJM’s Proposed Interim NITS Limitation thus directly frustrates the Commission’s intention to allow a load taking interim, non-firm transmission service, and that is co-located
12 See December 18 Order at P 159.
13 See id. at P 160.14 See id. (emphasis added).15 See, e.g., ERock Protest at 2.16 See December 18 Order at P 160.
PDF page 4
4
with a generator, to be served by such generator before both the load and generator “‘graduate’ to full, front-of-meter service.”17
For these reasons, and the reasons discussed further herein and in the ERock Protest, PJM’s proposed implementation of Interim NITS clearly runs afoul of the Commission’s applicable directives in the December 18 Order and should be rejected by the Commission.
B. Responses to Specific PJM Statements and Arguments in the April 24 Reply Brief The fundamental disconnect between PJM’s proposed implementation of Interim NITS and the Commission’s applicable directives manifests in several of PJM’s statements and positions set forth in its April 24 Reply Brief, as addressed below.
First, PJM recognizes that the December 18 Order held that “when curtailed, Eligible Customers taking [Interim NITS] on behalf of Co-Located Loads may be able to continue to take energy from the Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”18 Rather than explaining why its tariff would not otherwise allow a Co- Located Load to take energy from a Co-Located Generating Facility (i.e., the Interconnection Customer), or even proposing new tariff language that would codify such prohibition, PJM instead states that it “thoroughly examined whether the Tariff should allow Interim NITS customers to directly take energy from the Co-Located Generating Facility when PJM has curtailed the Eligible Customer’s access to the Transmission System” and determined that it should not.19
PJM’s Proposed Interim NITS Limitation thus clearly departs from the Commission’s directive because PJM has not identified any tariff provisions that would not “otherwise allow” a
17 See December 18 Order. Commissioner Rosner, Concurring at P 11 (“Rosner Concurrence”).18 See April 24 Reply Brief at 16 (citing December 18 Order. at P 160 (emphasis added)).19 See April 24 Reply Brief at 16-17 (emphasis added).
PDF page 5
5
Co-Located Load from receiving any capacity or energy from a Co-Located Generating Facility while the Co-Located Load is taking Interim NITS. Moreover, for the reasons explained by ERock in its Protest, PJM’s Proposed Interim NITS Limitation would need to be codified in the PJM Tariff (PJM’s filed rate) in order to be effectuated because it is a practice, inter alia, “that affect[s] rates and service significantly, that [is] reasonably susceptible of specification, and that [is] not so generally understood in any contractual arrangement as to render recitation
superfluous.”20 Accordingly, for these reasons alone, the Commission should reject PJM’s Proposed Interim NITS Limitation.
Second, PJM avers that its Proposed Interim NITS Limitation is in line with the
December 18 Order’s requirement that Interim NITS be designed around the principles that “(1) the services are designed to serve loads that are ‘willing and able to control their withdrawals from the transmission system;’ and (2) the services are designed to allow PJM to maintain system reliability,”21 and that “Interim NITS will be curtailed when the system cannot support it in real time, whether with sufficient generation or transmission capacity.”22 But PJM’s argument misses the mark entirely, as the ability for a Co-Located Load to take energy and capacity from a Co-Located Generating Facility during the interim period before “all Network Upgrades
necessary to provide NITS are complete,”23 enables the Co-Located Load “to control their
20 See ERock Protest at 7 (citing Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,003, at P 69 & n.113 (2017) (citations and internal quotes omitted). See also, Sw. Power Pool, Inc., 170 FERC ¶ 61,125, at PP 35-36 & n.92 (2020) (noting that the filed rate doctrine “entitles customers to rely upon what is in a tariff, regardless of any ‘one-way’ assertions made by the utility outside of Commission filings.” (citing W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 24 (D.C. Cir. 2014) (rejecting the Commission’s argument that interconnection studies provided notice for financial responsibility for upgrades because the Commission provided “‘no reasoned explanation for expanding the notice exception to encompass such one-way assertions, especially since generators have no apparent way to challenge any costs such studies purport to assign’”)); Old Dominion Elec. Coop. v. FERC, 892 F.3d 1223, 1232 (D.C. Cir. 2018) (finding that a website statement at issue was not filed with the Commission, which “is required for all rate changes”)). 21 See April 24 Reply Brief at 17 (citations omitted).22 See id. 23 See December 18 Order at P 160.
PDF page 6
6
withdrawals from the transmission system.”24 Further, as made clear in Commissioner Rosner’s concurrence in the December 18 Order, the Commission knew that large load customers taking Interim NITS would only be “willing and able to control their withdrawals from the transmission system,” if they could rely upon their Co-Located Generating Facility during the interim period before necessary Network Upgrades are constructed.25 PJM’s Proposed Interim NITS Limitation thus directly contradicts the Commission’s directive for PJM to establish an interim, non-firm transmission service.
Third, PJM appears to believe that requiring the Co-Located Generating Facility to be
fully deliverable as a Capacity Resource during the interim period is necessary to “allow PJM to maintain system reliability.”26 PJM avers that allowing a Co-Located Generating Facility to serve a Co-Located Load utilizing Interim NITS would “remove the co-located generator from serving the Transmission System as a whole during emergency or pre-emergency conditions,”27 and states that “to the extent the co-located generator is a committed Capacity Resource, the PJM Region has first call on such resource’s energy to meet the region’s needs.”28 But PJM’s argument is inherently flawed because prior to the Co-Located Generating Facility completing PJM’s interconnection study process and receiving a GIA, it is not eligible to be a Capacity Resource.
24 See id. at P 204.25 See Rosner Concurrence at P 11 (“In exchange for increased speed, these loads will bear the risk of being curtailed when the grid is constrained until the transmission upgrades needed to provide service are constructed. But that doesn’t mean that the load will always have to shut down completely during peak periods. Rather, if the co- located load is paired with a new generator, and that generator is still waiting to begin its own front-of-meter service, the load can take service directly from the generator in the interim until both “graduate” to full, front-of-meter service.”) (emphasis added).26 See April 24 Reply Brief at 18. 27 See id. (emphasis removed).28 See id.
PDF page 7
7
ERock does not object to limiting a Co-Located Load from receiving any capacity or energy from a Co-Located Generating Facility during emergency conditions once the Co- Located Generating Facility has gone through the interconnection study process, has received a GIA, is a Capacity Resource, and the Co-Located Load receives firm service following the completion of necessary Network Upgrades.29 However, imposing such restrictions during the interim period prior to the Co-Located Generating Facility receiving a GIA, and prior to such Network Upgrades being completed, would not allow PJM to in fact call on the Co-Located Generating Facility as a Capacity Resource to meet any emergency. Further, such restrictions would render Interim NITS unworkable and conflict with the Commission’s directives regarding Interim NITS.30
Moreover, during the period in which the Co-Located Load operates on a non-firm basis, PJM can curtail the Co-Located Load during emergencies in order to maintain the reliability of the overall system, while the Co-Located Generating Facility can serve the Co-Located Load so that it does not go entirely offline. This arrangement enables PJM to maintain the overall reliability of the system while encouraging large loads to be curtailable by allowing them to rely on their Co-Located Generating Facility until both the load and generating facility “graduate” to full, front of meter service, as the Commission intended.31 This is not what PJM proposed. Further, forcing the Co-Located Generating Facility to be dispatched under emergency conditions during the interim period before it has completed the generation interconnection study process, has a GIA and is eligible to be a Capacity Resource, would not only conflict with the
29 See ERock Protest at 8 n. 29.30 See, e.g., ERock Protest at 8-10; Comments of the Data Center Coalition, Docket No. ER26-1479-000, at 6 (Mar. 16, 2026) (The Proposed Interim NITS Limitation “is unworkable because curtailment should limit use of the grid, not prevent the customer from using the colocated resource it supplied, which supports Interim NITS in the first place. If the customer cannot use that generation during curtailment, Interim NITS provides no practical value.”).31 See Rosner Concurrence at P 11.
PDF page 8
8
December 18 Order, but would also unjustly and unduly discriminate against Co-Located Generating Facilities because it would impose obligations upon them that are not imposed upon similarly situated generators in PJM, i.e., generators that are in the process of being studied to be Capacity Resources but are not Co-Located Generating Facilities.32
Lastly, PJM argues that it would be illogical to allow Interim NITS customers to rely on their non-firm Co-Located Generating Facilities during emergencies when full NITS customers cannot. PJM goes so far as to argue that it is “illogical to grant this right to the transitional, temporary Interim NITS when such right is not available to full NITS customers.”33 But PJM has it backwards. Instead, it would be illogical for the Interim NITS customer not to be allowed to rely on its non-firm Co-located Generating Facility in order to remain online during emergencies when it is taking non-firm transmission service precisely because it is not taking firm transmission service under NITS.34
Further, it would be illogical (and not just and reasonable) to have a Co-Located Load taking Interim NITS bear the full capital and development risk of bringing a Co-Located Generating Facility online, only for PJM to dispatch their non-firm Co-Located Generating Facility for the benefit of other customers with firm NITS during emergencies – which is precisely when other customers with firm NITS are being served, but the non-firm, Interim NITS customer is being curtailed. PJM’s proposal would thus create an inequitable, unjust and
32 See also, Calpine Oneta Power, L.P., 119 FERC ¶ 61,177, at P 35 (2007) (“As we found in the September 26 Order and reaffirm below, AEP and Oneta are similarly situated. We also reaffirm our finding in the September 26 Order that it is unduly discriminatory for the transmission provider to pay AEP for its reactive power capability and deny payment to Oneta for its reactive power capability, because both entities are similarly situated.”) (citation omitted); Bluegrass Generation Company, L.L.C., 118 FERC ¶ 61,214, at P33 (2007) (noting that denying comparable treatment for similarly situated entities "constitute[s] undue discrimination.").33 See April 24 Reply Brief at 21.34 See Rosner Concurrence at P 11.
PDF page 9
9
unreasonable situation where firm NITS customers would receive emergency reliability benefits at the direct expense of Interim NITS customers.
III. CONCLUSION
PJM should not be allowed to openly flout the Commission’s unequivocal directives in the December 18 Order. The Commission required PJM to establish “a new interim, non-firm transmission service,”35 that will allow a load that is co-located with a generator to “take service directly from the generator in the interim until both ‘graduate’ to full, front-of-meter service” so that the load will not “always have to shut down completely during peak periods.”36 Rather than complying with these and related directives, PJM’s Proposed Interim NITS Limitation undercuts them. Accordingly, for the reasons set forth herein, ERock respectfully requests that the Commission grant its Motion, consider this Answer and prohibit PJM from imposing its Proposed Interim NITS Limitation.
Joel Yu
Senior Vice President, Policy & External
Affairs
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002
Jyu@enchantedrock.com
James Huang
Director, Wholesale Markets Policy
Enchanted Rock, LLC
1113 Vine Street, Suite 101
Houston, TX 77002
Jhuang@enchantedrock.com
Respectfully submitted,
/s/ Steven Shparber
Steven Shparber
Omar Bustami
Katie Bekel
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo, P.C.
555 12th Street NW, Suite 1100
Washington, D.C. 20004
(202) 434-7417
SShparber@mintz.com
OBustami@mintz.com
KBekel@mintz.com
Counsel to Enchanted Rock, LLC
Dated: May 7, 2026
35 See December 18 Order at P 160.
36 See Rosner Concurrence at P 11.