EL25-49-000 · 2026-05-07 · Enchanted Rock, LLC

Motion for Leave to Answer and Answer of Enchanted Rock, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief

Text extracted from the eLibrary original (SHA-256 d6afed2ff23b2645…). Download the original from the official source.

Contents · 5 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 2
  2. II. ANSWER p. 2
  3. A. PJM’s Proposed Implementation of Interim NITS Is Fundamentally Flawed p. 2
  4. B. Responses to Specific PJM Statements and Arguments in the April 24 Reply Brief p. 4
  5. III. CONCLUSION p. 9

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER26-1479-000 (Feb. 23, 2026) (“PJM February 23 Compliance Filing”). 5 All capitalized terms not otherwise defined herein shall have the same meaning set forth in the PJM Open Access Transmission Tariff (“PJM Tariff”), or the Illustrative Language For New Tariff (“Illustrative Tariff”) filed with…
Read this passage Filed comments: Connecting load and generation

I. MOTION FOR LEAVE TO ANSWER

printed heading

I.
Read this passage

II. ANSWER

printed heading

II.
Read this passage

A. PJM’s Proposed Implementation of Interim NITS Is Fundamentally Flawed

printed heading · Topic match: Connecting load and generation

Operator, Inc., 161 FERC ¶ 61,056, at P 32 (2017) (“We will accept the answers . . . because they have provided information that assisted us in our decision making process.”). 3 Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals…
Read this passage Filed comments: Connecting load and generation

B. Responses to Specific PJM Statements and Arguments in the April 24 Reply Brief

printed heading · Topic match: Connecting load and generation

Further, such restrictions would render Interim NITS unworkable and conflict with the Commission’s directives regarding Interim NITS.30 Moreover, during the period in which the Co-Located Load operates on a non-firm basis, PJM can curtail the Co-Located Load during emergencies in order to maintain…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading

Accordingly, for the reasons set forth herein, ERock respectfully requests that the Commission grant its Motion, consider this Answer and prohibit PJM from imposing its Proposed Interim NITS Limitation.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 7th day of May 2026. /s/ Steven Shparber