EL25-49-000 · 2026-05-11 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
     v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation moves for leave and submits this answer1 to reject four arguments made by PJM and the Indicated PJM Transmission Owners in their response briefs.2 First, just and reasonable rules for large load interconnection cannot be delayed until the end of the decade and claims that such delays are “required”3 are belied both by PJM’s rush to adopt its own preferred “Connect and Manage” alternative and by the fact that other regions are managing to develop rules for interruptibility much more quickly. Second, the Federal Power Act (“FPA”) requires study requirements to be clearly written in the PJM Tariff because these study timelines and

methodologies significantly affect the provision of the new transmission services—and a lack of
1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213. Constellation respectfully submits there is good cause for the Commission to accept this answer as it is intended to aid the Commission in its decision-making. Unless otherwise defined, all capitalized terms have the same meaning as in PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”).
2 Reply Brief of PJM Interconnection, L.L.C. at 57 (Apr. 24, 2026) (“PJM Apr. 24 Response”); Reply Brief of the Indicated PJM Transmission Owners (Apr. 24, 2026) (“Indicated TO Apr. 24 Response”). The Indicated PJM Transmission Owners (“Transmission Owners”) that filed the Indicated TO Apr. 24 Response are the same subset of Transmission Owners in PJM that filed the February 23, 2026 Initial Brief and March 25, 2026 Reply.
3 PJM Apr. 24 Response at 57.

PDF page 2

2
clarity and resulting protracted delays (including delays due to refusals to study) are what instigated this proceeding in the first place. Third, draconian rules imposing disqualifications, suspensions and other unnecessary restrictions on the Commission’s new transmission services do not address any genuine “risks to reliability and resource adequacy”4 but instead merely limit access to, frustrate, and otherwise discriminate against these landmark services. Fourth, the Transmission Owners’ excessive Grid Reliance Charge has no basis in principle or precedent, while Constellation has proposed a just and reasonable replacement rate the Commission can readily adopt. In addition, there are several other areas in PJM’s response brief and revised Illustrative Tariff where clarification is needed or appropriate.

I. Three Years Is Not “Required” to Replace an Unlawful Rate
PJM claims “[a] June 1, 2029 effective date is required for the provision of these new, curtailable services.”5 At the same time, PJM is expediting its Connect and Manage interconnection framework to commence June 1, 2027, which would allow the interconnection of non-capacity backed loads that are potentially interruptible during capacity shortages, unless the load brings its own (new) generation.6 This, ironically, is a rebranded Option 7 from PJM’s show- cause filing, which the Commission rejected in favor of Interim Network Integration Transmission Service (“Interim NITS”).7 PJM did not seek rehearing on this point, yet PJM is nonetheless fast- tracking the version of interruptibility that the Commission rejected, while slow-boating the

4 Id. at 45.
5 Id. at 57.
6 PJM, Connect & Manage Exemption and Reliability Backstop Process Impacts, Connect and Manage Senior Task Force, at 2 (Apr. 28, 2026), 20260428-item-03---connect--manage-exemption-and-reliability-backstop-process- impacts-education---presentation.pdf (“Connect & Manage Presentation”).
7 December 18th Order, 193 FERC ¶ 61,217 at P 200 (“we direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to create a new interim, non-firm transmission service similar, but not identical, to PJM’s proposed option 7.”).

PDF page 3

3
version of interruptibility that the Commission required. That is unacceptable. It is simply not credible that PJM will take more than three years to implement Interim NITS allegedly due to “significant changes to PJM’s core Markets and Operations systems”8 but less than one year to commence Connect and Manage, a framework not clearly defined let alone demonstrated to be just and reasonable.

Accordingly, the Commission should promptly approve the rates and terms for Interim NITS, with Constellation’s focused modifications,9 and make them effective no later than October 1, 2026, so that service can begin no later than June 1, 2027, the same date that PJM plans to commence Connect and Manage. Adopting Interim NITS as soon as possible—for pending and future NITS applicants—should not be difficult. PJM “designed the new Interim NITS to basically be treated the same as regular, full NITS.”10

II. Study Procedures and Deadlines Must Be in the Tariff
The study procedures for the new transmission services must be identified clearly and spelled out in the tariff. Indeed, additional studies may not be needed at all to implement Interim NITS. As PJM states, it could determine that “the NITS study already conclusively answers the question of whether and how much Interim NITS may be provided” and grant Interim NITS “immediately.”11 PJM nevertheless argues, first, that its Illustrative Tariff properly details how

8 PJM Apr. 24 Response at 57.
9 Response Brief of Constellation Energy Generation, LLC at 7 (Apr. 24, 2026) (“Constellation Apr. 24 Response”); see also Reply Brief of Constellation Energy Generation, LLC at 14-25, 29 (Mar. 25, 2026) (“Constellation Mar. 25 Reply”).
10 PJM Apr. 24 Response at 1.
11 Id. at 27.

PDF page 4

4
PJM will study requests for new transmission services.12 Second, PJM claims that load integration studies are outside the scope of the Commission’s jurisdiction.13 Neither argument has merit.

A. The Commission Should Require Clear and Detailed Study Requirements to
be on File
The Illustrative Tariff does not contain any clear statement of what studies will be required for the new transmission services. Rather, it states merely that PJM will determine “whether additional studies are needed”14 for Interim NITS and “will coordinate with the affected Transmission Owner(s) to complete studies, including load integration studies”15 for Contract Demand Services. Contrary to PJM’s assertions, these vague statements do not come close to “appropriately detail[ing] PJM’s process, role, and standards for studying requests for these new transmission services.”16 Indeed, the only “detail” that can be gleaned from the Illustrative Tariff is that studies may be conducted. There is no indication of what type of studies will be conducted— other than the Transmission Owners’ load integration studies—or the methodologies PJM will use to assess whether the transmission system can “reliably” provide the new transmission services. These are not mere “implementation” details that are missing from the Illustrative Tariff. These terms directly affect eligibility for Interim NITS and Contract Demand Services, which clearly is a core requirement of the service.17 Requirements establishing the type of studies performed and methodologies used to assess whether PJM can provide the new transmission

12 Id. at 22.
13 Id. at 34.
14 Illustrative Tariff, Part XI, § 704.1.
15 Id. at § 710.3.
16 PJM Apr. 24 Response at 22.
17 December 18th Order, 193 FERC ¶ 61,217 at P 200 (“Moreover, this new service would be optional for an Eligible Customer seeking NITS on behalf of a Co-Located Load and would only be available to the extent PJM determines that it can provide some level of interim service reliably.”) (emphasis added).

PDF page 5

5
services reliably are “practices that affect rates and service significantly, that are realistically susceptible of specification, and that are not so generally understood in any contractual

arrangement as to render recitation superfluous.”18 PJM has a “statutory obligation to file
significant changes to its rates and ‘practices … affecting such rates.’”19 It is irrelevant whether stakeholders have the “fulsome opportunity to participate”20 in the development of PJM’s Manuals because including this material is part of PJM’s compliance obligation.21

Accordingly, the Commission should direct PJM to set forth clear and specific study
requirements in the Tariff. At a minimum, PJM should specify in its Tariff the violations that will be studied and the studies to be conducted for each, the deadline for completing each study and steps taken if study deadlines are not met, and defined remediation for specific violations found. The record in this long proceeding underscores that it is critical for these study rules and deadlines to be on file to effectuate the Commission’s and the Trump Administration’s commitment to

providing prompt service to large loads.22
18 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (emphasis in original). 19 Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804, 811 (D.C. Cir. 2007) (internal quotations omitted).
20 PJM Apr. 24 Response at 33.
21 See December 18th Order, 193 FERC ¶ 61,217 at P 219 (requesting briefing on rates, terms, and conditions for the new transmission services); see also Keyspan-Ravenswood, LLC v. FERC, 474 F.3d at 811 (“[T]he Commission provides no reason to believe that Ravenswood’s participation in such a stakeholder process relieved NYISO of its statutory obligation to file significant changes to its rates and ‘practices … affecting such rates.’”).
22 See, e.g., Constellation Complaint at 7 (“Exelon is refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled interconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, and forcing additional services to be procured.”); id. at 7-8. (“Exelon fulfilled its responsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear station, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center (‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies, insisting that Constellation or its potential customer must first apply for retail service and designate what sort of wholesale transmission service it will take from Exelon.”); id. at 8 (“projects are being held hostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); id. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”)

PDF page 6

6
B. Transmission Owner Load Integration Study Requirements are Unwritten
and Undisclosed Policies that Significantly Affect the Commission’s
Landmark Transmission Services
The Commission has jurisdiction to regulate load integration studies in connection with
jurisdictional transmission service. PJM is wrong to assert that “any ‘lack of detail’” regarding those studies is justified for jurisdictional reasons.23 The Commission has jurisdiction over all transmissions, including transmissions to end users.24 The courts have long held the Commission can regulate practices affecting rates within its jurisdiction, even if the Commission’s regulation touches upon state authority.25 Load integration studies, which determine “whether (and to what (citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully Isolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ refusal to cooperate … with reliability studies related to interconnection modifications.”); see also Constellation Energy Generation, LLC November 21, 2025 Supporting Comments, Docket No. RM26-4-000 at 3-4 (Nov. 21, 2025) (“Some Transmission Owners have simply refused to participate in PJM’s studies to analyze reliability impacts; and some, acting under unfiled interconnection study procedures, have changed their entire construct and timetable for processing load studies.”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., Docket Nos. EL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff to require this one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different configuration.”) (“Constellation Apr. 23, 2025 Answer”); id. at 14 (“What is more, regardless of what the Tariff actually says and does not say, some of the Indicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load agrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) (citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on LaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to complete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to Constellation by $15.3-$19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (2025) (“[T]here are allegations in the record that Exelon has delayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s concerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail distribution service.”).

23 PJM Apr. 24 Response at 34 (“at root, … Constellation’s complaints regarding the level of detail in PJM’s study procedures generally concern the Transmission Owner’s load integration studies”).
24 16 U.S.C. § 824(a); New York v. FERC, 535 U.S. 1, 20 (2002) (“[T]he FPA authorizes FERC’s jurisdiction over interstate transmissions, without regard to whether the transmissions are sold to a reseller or directly to a consumer.”); December 18th Order, 193 FERC ¶ 61,217 at PP 170, 173-74.
25 See, e.g., New Eng. Power Generators Ass’n v. FERC, 757 F.3d 283, 290-91 (D.C. Cir. 2014) (upholding the Commission’s mitigation of buyer-side market power as to out-of-market entrants as not “improperly regulating ‘facilities used for the generation of electric energy”); id. at 290 (“We have previously held that the Commission has jurisdiction to regulate certain parameters of the capacity market related to the price of capacity, even if those determinations touch on states’ authority.”); Conn. Dep’t of Pub. Util Control v. FERC, 569 F.3d 477, 481-83

PDF page 7

7
level)” the new transmission services can be reliably provided (that is, whether the new
transmission services are provided at all), easily fall within that scope.26
On rehearing, and on its own accord,27 the Commission should exercise its jurisdiction over the load integration studies needed to provide jurisdictional transmission service and direct those load integration studies to be on file.28 At a minimum, the PJM Tariff should specify the violations that will be studied and the studies to be conducted for each, the deadline for completing each study and steps taken if study deadlines are not met, and define remediation for specific violations found. Otherwise, the Commission risks neutering its December 18th Order by allowing

recalcitrant Transmission Owners an avenue to delay or disfavor the Commission’s new
transmission services.29
III. The Commission Should Reject Certain Proposed Strictures on the New Transmission
Services
PJM claims that its draconian disqualification and suspension scheme is necessary to
address “unique reliability and resource adequacy risks” of integrating large loads into PJM’s (upholding Commission’s authority to regulate the Installed Capacity Requirement, even if the requirement could necessitate the construction of facilities, a matter traditionally within the state’s jurisdiction); Municipalities of Groton v. FERC, 587 F.2d 1296, 1303 (D.C. Cir. 1978) (finding the Commission’s capacity deficiency charge does not encroach on state jurisdiction, even though it may “motivate [utilities] to develop sufficient capacity to meet their load requirements”).

26 Illustrative Tariff, Part XI, § 710.3 (“Transmission Provider will coordinate with the affected Transmission Owner(s) to complete studies, including load integration studies, which will provide data relevant to the determination of whether (and to what level as applicable) (i) Firm Contract Demand Transmission Service can be reliably provided and identify any necessary enhancements to the Transmission System to accommodate the requested level of service, and/or (ii) Non-Firm Contract Demand Transmission Services can be reliably provided.”)
27 16 U.S.C. § 825l(a) (upon a request for rehearing, “the Commission shall have power to grant or deny rehearing or to abrogate or modify its order without further hearing”).
28 16 U.S.C. § 824d(c) (“[E]very public utility shall file with the Commission … all rates and charges for any transmission or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.”); Fla. Mun. Power Agency v. Duke Energy Fla., LLC, 167 FERC ¶ 61,138, at P 43 (2019) (finding an “unwritten policy constitutes a practice that significantly affects the terms and conditions of transmission service … and, therefore, should have been filed with the Commission for Commission review.”).
29 See supra note 22.

PDF page 8

8
Transmission System.30 Similarly, PJM claims that limiting Non-Firm Contract Demand Service to times when the Co-Located Generating Facility is on outage is “appropriate” because of unidentified “reliability and operational issues inherent in providing this service.”31 The Commission should reject both.

A. PJM’s Proposed Disqualification and Suspension Scheme is Not a Just,
Reasonable and Non-Discriminatory Replacement Rate
PJM fails to demonstrate that “unique reliability and resource adequacy risks” justify the extreme and unprecedented penalties PJM proposes with respect to the Commission’s new transmission services.

First, existing practice shows that PJM’s proposal is unwarranted. PJM Transmission Customers taking Non-Firm Point-To-Point Transmission Service are not subject to suspension or disqualification for unreserved use of the transmission system.32 PJM provides no reason why customers taking the new non-firm transmission services should be treated any differently. Notably, SPP proposes no suspension or disqualification of interruptible loads as part of its Conditional High Impact Large Loads Service (“CHILLS”).33 If SPP can manage interruptible loads without such draconian penalties, PJM should similarly be capable of doing so. Second, the one reliability incident that PJM highlights to defend its proposal—when “approximately 1,500 MW of data centers disconnected simultaneously and unexpectedly from the [Bulk Electric System] due to a transmission line fault in 2024”34—involved traditional grid

30 PJM Apr. 24 Response at 45.
31 Id. at 6.
32 Constellation Mar. 25 Reply at 19-20.
33 Id. 34 PJM Apr. 24 Response at 41-42.

PDF page 9

9
connected load, not a Co-Located Load.35 In fact, this incident illustrates how co-locating load with generation can provide benefits to the grid as compared to direct grid connections. As former PJM Chief Operating Officer Michael Kormos previously explained, “had those data centers been co-located with a generator (especially a nuclear generator), it is possible that the load would not have dropped offline as a result of the load being closer to the voltage source.”36 Third, PJM fails to explain how its resource adequacy concerns justify its disqualification and suspension scheme. To the extent PJM’s resource adequacy concerns stem from Interim NITS and Non-Firm Contract Demand Service being non-capacity backed,37 then PJM should have the same concern regarding the non-capacity backed loads that could be interconnected under its Connect and Manage framework and would be required to curtail during capacity shortfalls. But PJM has proposed no such penalties under the Connect and Manage framework, showing that PJM’s real agenda here is to discourage use of the transmission services it disfavors.38 Fourth, a four-month suspension is not “consistent” with NERC requirements as PJM claims.39 The NERC Reliability Standards that PJM cites—PRC-004-6 (Protection System Misoperation Identification and Correction) and PRC-012-2 (Remedial Action Schemes)—set forth a process for investigating whether protection systems misoperated and for developing a Corrective Action Plan if appropriate.40 Neither Reliability Standard, however, calls for suspension

35 Constellation Apr. 23, 2025 Answer, Exhibit 5, at ¶ 7 (Kormos Affidavit).
36 Id.
37 See infra pp. 13-14 (explaining the Commission rejected the previously proposed Option 7 that provided non- capacity backed loads would have been interconnected on the condition they would be curtailed before all other load during capacity shortfalls).
38 See generally Connect & Manage Presentation.
39 PJM Apr. 24 Response at 40.
40 See, e.g., Reliability Standard PRC-004-6, Protection System Misoperation and Identification, at R1 (“Each Transmission Owner, Generator Owner, and Distribution Provider that owns a BES interrupting device that operated

PDF page 10

10
or disqualification of service while an investigation is ongoing. Indeed, such a suspension would be fundamentally unjust and unreasonable, as it would deny the load a service to which it is entitled—potentially with ruinous economic consequences—without any finding of fault.

B. Limiting Non-Firm Contract Demand Service to Temporary Derates or
Outages Is Non-Compliant and Unreasonable
PJM claims it must limit Non-Firm Contract Demand Service to temporary derates or
outages because of “the inherent risks to the Transmission System and operational complexities associated with providing this service on a continuous basis.”41 Based on this logic, PJM should also limit Non-Firm Point-to-Point Transmission Service. PJM does not. Indeed, if the customer taking Non-Firm Point-to-Point Transmission Service is willing to pay through congestion, under the Transmission Loading Relief Procedure, PJM only curtails the service after all other measures have failed to maintain system reliability.42

The Transmission Owners’ attempt to support PJM’s limitation on Non-Firm Contract
Demand Service fares no better. Citing several of PJM’s unsubstantiated claims, Transmission Owners state, “facilities serving large loads will likely have multiple feeders serving load” that under the circumstances in Parts 1.1 through 1.3 shall, within 120 calendar days of the BES interrupting device operation, identify whether its Protection System component(s) caused a Misoperation ….”); id. at R5 (“Each Transmission Owner, Generator Owner, and Distribution Provider that owns the Protection System component(s) that caused the Misoperation shall, within 60 calendar days of first identifying a cause of the Misoperation: … Develop a Corrective Action Plan (CAP) for the identified Protection System component(s), and an evaluation of the CAP’s applicability to the entity’s other Protection Systems including other locations” or “Explain in a declaration why corrective actions are beyond the entity’s control or would not improve BES reliability, and that no further corrective actions will be taken.”); Reliability Standard PRC-012-2, Remedial Action Schemes, at R5 (“Each RAS-entity, within 120 full calendar days of a RAS operation or a failure of its RAS to operate when expected, or on a mutually agreed upon schedule with its reviewing Reliability Coordinator(s), shall” “Participate in analyzing the RAS operational performance to determine whether” the “System events and/or conditions appropriately triggered the RAS,” the “RAS responded as designed,” the “RAS was effective in mitigating BES performance issues it was designed to address,” or the “RAS operation resulted in any unintended or adverse BES response.”).

41 PJM Apr. 24 Response at 7.
42 PJM Manual 13, § 5.6.

PDF page 11

11
will “add[] complexity and reduc[e] the reliability and overall security of the system.”43 PJM and Transmission Owners continue to provide no justification or explanation for requiring multiple feeders.44

Transmission Owners also claim “there is the possibility of interactions between RAS in a tightly coupled network such as PJM, increasing the possibility of misoperations.”45 This circumstance is possible but unlikely. Multiple RAS in an area is a sign the transmission infrastructure is inadequate and the area has increased reliability risks. As Mr. Kormos explained, “[g]iven the increased reliability risks … most Co-Location Arrangements with new generation are unlikely to locate in areas without robust transmission.”46

IV. The Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor Precedent

The Commission should reject the Transmission Owners’ Grid Reliance Charge and adopt the minimum system method as recommended by electricity market expert Zachary Ming.47 The Transmission Owners’ Grid Reliance Charge is arbitrary and unmoored from cost causation principles. As Mr. Ming explains in his Reply Testimony in Attachment 1, the Transmission Owners’ proposal is “an improvised approach lacking any theoretical foundation and disconnected from any cost-causation principle, designed to produce an outcome that ‘feels right’ to the Transmission Owners.”48 Their proposal includes all the depreciation costs for the full cost of

43 Indicated TO Apr. 24 Response at 4-5.
44 Constellation Mar. 25 Reply at 30.
45 Indicated TO Apr. 24 Response at 5.
46 Constellation Apr. 24 Response, Exhibit 1, at ¶ 11 (“Second Affidavit of Michael Kormos”).
47 Constellation Mar. 25 Reply, Attachment 1 (“Ming Initial Testimony”).
48 See Reply Testimony of Zachary Ming at 10:18-20 (“Ming Reply Testimony”).

PDF page 12

12
sizing the transmission system components to serve peak load.49 This would force customers that do not impose demand on the grid to pay for transmission components that are sized to serve peak load.50 The Transmission Owners’ proposal also arbitrarily excludes costs related to rate of return and taxes.51

Constellation’s proposal leverages the minimum system method, a principled methodology grounded in precedent, to produce a just and reasonable rate that ensures Co-Located Loads pay their fair share of the transmission system based on how they actually use it—which is to receive ancillary services, not to draw power from the grid. The minimum system method is a “well- accepted framework for applying cost-causation principles.”52 It is not “extremely challenging to implement.”53 Numerous jurisdictions across North America have applied the minimum system method at the distribution level for decades.54 And as Mr. Ming explains, “[t]here is no reason that it cannot similarly be applied in the context of the transmission system—there has just not previously been any need to do so.”55

In his initial testimony, using publicly available data, Mr. Ming estimated that a minimum system yielding between 2% and 10% of actual system costs is reasonable, and he recommended a minimum transmission system of 6%.56 The Commission can adopt a Grid Reliance Charge based on 6%, or up to 10%, of the NITS rate as a reasonable rate that can be practically

49 Id. at 10:6-8.
50 Id. at 14:1-5.
51 Id. at 8:7-12.
52 Id. at 10:8-15.
53 Indicated TO Apr. 24 Response at 24.
54 Ming Reply Testimony at 18:7-11.
55 Id. at 14:12-14. 56 Ming Initial Testimony at 19:3-5; id. at 21:17-20.

PDF page 13

13
implemented. If the Commission believes there should be additional consideration of what constitutes a minimum system, the Commission can direct PJM to conduct a minimum system study. But the Commission should reject the Transmission Owners’ unsupported and inflated proposal.

V. Requested Clarifications of PJM’s Response Brief and Modifications to Revised Illustrative Tariff

There are five areas in PJM’s response brief and revised Illustrative Tariff where clarification is needed or appropriate.

First, PJM’s statement that an “Interim NITS customer would only be curtailed … if the system is in an unreliable state due to transmission system violations or capacity/reserve shortages”57 improperly conflates Interim NITS and the rejected Option 7.58 Under the rejected Option 7, non-capacity backed loads would have been interconnected on the condition they would be curtailed before all other load during capacity shortfalls.59 The Commission found this option “too broad and not sufficiently detailed to direct as a replacement rate.”60 No party, including PJM, sought rehearing challenging the Commission’s rejection. PJM now attempts to reinstate the “capacity/reserve shortage” curtailment criterion. But PJM failed to seek rehearing of this issue and cannot bypass the Federal Power Act’s rehearing requirements.61 The Commission should reject this attempt62 and direct PJM to revise Part XI, Section 705.2 of its Illustrative Tariff to

57 PJM Apr. 24 Response at 20 (emphasis added); see also id. 18 (“Interim NITS must be designed to allow PJM to maintain system reliability—both from a transmission and capacity perspective.”). 58 December 18th Order, 193 FERC ¶ 61,217 at P 202.
59 PJM Answer to February 2025 Show Cause at 18-19 (March 24, 2025).
60 December 18th Order, 193 FERC ¶ 61,217 at P 202.
61 16 U.S.C. § 825l(a).
62 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at P 27 (2026) (rejecting PJM attempt to change a Commission-directed definition through its compliance filing because, among other things, “no party, including

PDF page 14

14
specify that Interim NITS shall only be curtailed before Firm Contract Demand Service and NITS if the system is in an unreliable state due to transmission system violations. During capacity/reserve shortages, like all other loads, Co-Located Loads taking Interim NITS should only be curtailed after PJM has taken all real-time emergency procedure steps and still cannot provide adequate capacity to meet PJM’s load.

Second, Constellation supports PJM’s statement that “Eligible Customers serving Co- Located Loads with pending NITS applications would be able to apply for Interim NITS.”63 PJM should revise its Illustrative Tariff accordingly to clarify that large loads with currently pending NITS applications shall be studied for Interim NITS at the request of the load without the need to make a new or separate application, as long as such loads with pending NITS applications are Co- Located Loads that will be served by an Eligible Customer. PJM should add such language to Section 702.2 (Application Procedures) of Part XI of its Illustrative Tariff.

Third, PJM should add to the “Conditions Precedent for Receiving Service” in Part XI, Subpart A, Section 702.1 and Part XI, Subpart B, Section 710.1 the requirement that the Eligible Customer identify the Co-Located Arrangement, including the Customer Facilities that will be associated with the Co-Located Load for which the Eligible Customer is taking the service. If the Customer Facilities include an existing generator, certification that the existing generator supports the request should also be required. This clarification will ensure the Co-Located Load “is PJM, sought rehearing or clarification of this directive”); see also, e.g., Ne. Utils. Serv. Co., 74 FERC ¶ 61,355, at n.10 (1996).

63 PJM Apr. 24 Response at 56; Constellation Mar. 25 Reply at 14.

PDF page 15

15
physically connected to the facilities of an existing or planned Customer Facility,” consistent with the definition of Co-Located Load.64

Fourth, PJM should remove Part XI, Section 710.1(vi) of the Illustrative Tariff requiring an Eligible Customer to “submit to the Transmission Provider an authorization or certification from its Relevant Electric Retail Regulatory Authority which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load.”65 This requirement is unworkable in existing state regulatory frameworks. It would be nonsensical for a generator to obtain special approval from a state commission in a retail competition state, and other non-competitive states have no procedures in place to seek approval.66 This provision would only serve to obstruct Co- Located Load Arrangements.

Fifth, Constellation supports PJM’s proposed revision to Part III, Section 29.2(x) of its Tariff. We propose one minor change to match the proposed intent.

For Eligible Customers taking service on behalf of Co-Located
Load: (1) a demonstration that the Co-Located Load on behalf of
which the Eligible Customer is seeking taking to obtain service and
the Co-Located Generating Facility are located on the same side of
the Delivery Point to the Transmission Provider’s Transmission
System as the Co-Located Load … 
64 December 18th Order, 193 FERC ¶ 61,217 at P 164; see also PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 at P 27 (affirming the Commission’s mandated definition of Co-Located Load).
65 Illustrative Tariff, Part XI, § 710.1(vi).
66 See Constellation Mar. 25 Reply at 29; Old Dominion Electric Cooperative Reply Brief at 7 (Mar. 25, 2026).

PDF page 16

16
CONCLUSION
For the reasons stated above, Constellation respectfully requests that the Commission accept this Answer and promptly approve the terms for Interim NITS, with Constellation’s focused modifications, effective October 1, 2026, with customers commencing service by June 1, 2027. Respectfully submitted,

/s/ Paul F. Wight

May 11, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
Seth T. Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC

PDF page 17

CERTIFICATE OF SERVICE
I hereby certify that I have on this 11th day of May, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025).

/s/ Sophia Browning

Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com

PDF page 18

ATTACHMENT 1
REPLY TESTIMONY OF ZACHARY MING

PDF page 19

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. EL25-49-001
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
Reply Testimony of Zachary Ming
Partner
Energy and Environmental Economics, Inc. (“E3”) On behalf of

Constellation Energy Generation, LLC (“Constellation”) May 11, 2026

PDF page 20

2
Table of Contents
1
Introduction … 3 2

Background … 6 3

Evaluation of Transmission Owners’ New Claims … 9
4
Response to Criticisms of E3 Proposal … 11 5

Summary … 19

PDF page 21

3
Constellation
1
2
Transmission Tariffs for Co-Located Load – Grid Reliance Charge 3

4
5
Reply Testimony of Zachary Ming, Partner, Energy and Environmental Economics, 6

Inc. (“E3”)
7
1
Introduction
8
Q1.
PLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS
9
ADDRESS.
10
A1.
My name is Zachary Ming. My current position is Partner at Energy and 11

Environmental Economics (“E3”). My business address is 44 Montgomery Street 12

Suite 1250, San Francisco, California 94104.
13
Q2.
PLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY.
14
A2.
I am filing this testimony as an independent expert, and it represents my own 15

positions
and
perspectives.
Constellation
Energy
Generation,
LLC
16
(“Constellation”) compensated for my testimony, but my compensation did not 17

depend on my conclusions.
18
Q3.
HAVE YOU PREVIOUSLY SUBMITTED TESTIMONY IN THIS
19
DOCKET?
20
A3.
Yes. I previously submitted testimony in this docket regarding the appropriate rate 21

designs that should be applied to different configurations of Co-Located Load.1 I 22

1 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49- 000, AD24-11-000, and EL25-20-000 (filed Apr. 23, 2025).

PDF page 22

4
also submitted testimony regarding the Transmission Owners’ proposal for 1

developing the Grid Reliance Charge at the outset of this paper hearing.2 2

Q4.
ARE YOUR QUALIFICATIONS THE SAME AS THOSE SET FORTH IN
3
YOUR PRIOR TESTIMONY IN THIS DOCKET?
4
A4.
My qualifications are the same as those set forth in my prior testimony in this docket 5

and include testimony before the Federal Energy Regulatory Commission 6

(“FERC”) and multiple state and provincial utility commissions.
7
Q5.
PLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY.
8
A5.
This testimony responds to the Reply Brief of the Indicated PJM Transmission 9

Owners (“Transmission Owners”), 3  including specifically the Joint Rebuttal 10

Testimony of Concentric Energy Advisors, Inc. (“Concentric”).4
11
First, I provide a brief review of both the Transmission Owners’ and my 12

positions and arguments regarding the proposed Grid Reliance Charge. Second, I 13

demonstrate that despite new arguments, the Transmission Owners’ proposal for 14

the Grid Reliance Charge is still unjust and unreasonable because it violates the 15

principles of cost causation adopted by FERC by charging Co-Located Load 16

customers for costs they do not impose on the system. Third, I respond to specific 17

criticisms of the Transmission Owners regarding my proposed Grid Reliance 18

Charge. In several cases, I demonstrate that the Transmission Owners’ criticisms 19

2 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49- 000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Mar. 25, 2026). 3 Reply Brief of the Indicated PJM Transmission Owners (Apr. 24, 2026) (“Indicated TO Apr. 24 Response”).
4 Exhibit No. PTO-0005 (Joint Rebuttal Testimony of Peter Blazunas, Lance Schafer and Hanhan Hammer).

PDF page 23

5
are more applicable to their own proposal than mine. I conclude by reiterating that 1

the Transmission Owners’ Grid Reliance Charge is unjust and unreasonable and 2

that my proposed Grid Reliance Charge is just and reasonable.
3

PDF page 24

6
2
Background
1
Q6.
WHAT WAS THE SUBJECT OF YOUR PRIOR TESTIMONY IN THIS
2
PROCEEDING?
3
A6.
The subject of my prior testimony in this proceeding related to the Transmission 4

Owners’ proposed new “Grid Reliance Charge” for Co-Located Load customers in 5

PJM. The Transmission Owners developed this charge in response to 6

Commissioner Chang’s guidance that “a just and reasonable replacement rate for 7

the new transmission services should reflect some form of minimum transmission 8

service charge, which would protect other customers against cost shifts resulting 9

from Co-Located Loads that rely upon the transmission system but do not directly 10

or meaningfully contribute to its costs via transmission service payments.”5 11

Q7.
DO YOU SUPPORT A GRID RELIANCE CHARGE?
12
A7.
Yes. I am aligned with the Transmission Owners that the concept of a Grid Reliance 13

Charge is appropriate to ensure that Co-Located Load customers that consume 14

ancillary services make a contribution to the cost of the wires that deliver these 15

services. However, I disagree with the Transmission Owners as to the method for 16

determining that charge and reach different conclusions about the amount of a 17

reasonable charge.
18
5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at P 9)..

PDF page 25

7
Q8.
PLEASE EXPLAIN HOW YOU AND THE TRANSMISSION OWNERS
1
DIFFER REGARDING HOW THE GRID RELIANCE CHARGE SHOULD
2
BE CALCULATED.
3
A8.
Both the Transmission Owners and I seek to quantify the “the costs of delivering 4

ancillary services, including the delivery of black start and regulation.” 6  To 5

accomplish this, both the Transmission Owners and I seek to identify the percentage 6

of system costs required to deliver ancillary services. However, the Transmission 7

Owners and I are not aligned on 1) the methodology to determine this percentage 8

of system costs or 2) a reasonable value for this percentage.
9
With regard to methodology, the Transmission Owners use FERC Form 1 10

data to identify cost accounts that they assert “support grid reliance.” In doing so, 11

the Transmission Owners include certain costs related to depreciation and 12

Operation and Maintenance expenses (“O&M”) while excluding costs related to 13

return on rate base and taxes. Notably, the Transmission Owners include “100 14

percent of the transmission depreciation category.”7 I explain the flaws of this 15

assumption below. The Transmission Owners then divide the sum of their included 16

costs by the total transmission revenue requirement to produce a result of 25.8%. 17

In contrast, my proposed methodology to calculate the Grid Reliance 18

Charge leverages the established “minimum system” method to identify the portion 19

of costs that would be required to deliver ancillary services while excluding costs 20

that are incurred to size the system to serve peak demand. Dividing the cost of the 21

minimum system by the costs of a system sized to peak demand yields 6.2%. 22

6 Exhibit No. PTO-0001 at 17:12-13.
7 Id. at 21:11 to 22:1.

PDF page 26

8
Q9.
PLEASE
SUMMARIZE
THE
ARGUMENTS
IN
YOUR
PRIOR
1
TESTIMONY IN THIS PROCEEDING.
2
A9.
My prior testimony outlined that while the concept of a Grid Reliance Charge is 3

appropriate, the Transmission Owners’ proposed implementation of the Grid 4

Reliance Charge is unjust and unreasonable because it violates the principles of cost 5

causation by charging Co-Located Load customers for costs they do not impose on 6

the system. Specifically, because Co-Located Load customers that pay the Grid 7

Reliance Charge do not withdraw energy from the system, they do not contribute 8

to the sizing of transmission system components such as wires, towers, and 9

transformers to serve peak load. From a cost causation perspective, they should 10

therefore not be responsible for 100% of depreciation costs that include the full cost 11

of sizing transmission system components to serve peak load. Instead, the minimum 12

system method is a just and reasonable approach, because it provides a principled, 13

cost-causation basis for determining the portion of the system that is necessary to 14

provide ancillary services to Co-Located Load customers while excluding costs 15

related to sizing equipment to serve peak load.
16

PDF page 27

9
3
Evaluation of Transmission Owners’ New Claims
1
Q10.
WHAT NEW ASSERTIONS DO THE TRANSMISSION OWNERS MAKE
2
REGARDING THEIR PROPOSED METHODOLOGY?
3
A10.
The Transmission Owners assert that their proposed rate of 25.8% “represents an 4

appropriate balance between fairly estimating the grid reliance benefits to Co- 5

Located Load with the need to ensure the rate can be practically implemented.”8 6

They additionally state that their methodology is designed to produce a 7

“conservative result focused on recovery of the costs necessary to support the 8

ongoing reliable operation of the grid, rather than a return on investment.”9 Finally, 9

they justify their approach as one that can be “practically implemented” without 10

“exacting precision.”10
11
Q11.
DO THE TRANSMISSION OWNERS’ ASSERTIONS SUPPORT THEIR
12
PROPOSAL BEING JUST AND REASONABLE?
13
A11.
No. They fail to address the fundamental shortcoming of their proposal – a 14

transmission system built only to deliver ancillary services would be nowhere 15

near as large or expensive as a transmission system built to serve peak demand. 16

Customers that do not withdraw energy from the transmission system should not 17

be responsible for sharing 100% of depreciation costs when they are not causally 18

responsible for all of those costs.
19
8 Exhibit No. PTO-0005 at 16:8-10.
9 Indicated TO Apr. 24 Response at 24.
10 Id. at 23.

PDF page 28

10
The Transmission Owners implicitly acknowledge this point when they 1

state that “although the transmission system is built to meet peak demand, the 2

proposed Grid Reliance Charge rate design does not include the full revenue 3

requirement associated with the transmission infrastructure put in place to meet 4

peak demand.”11 However, they do not follow through on the implications of that 5

position. Instead, they propose Grid Reliance Charge customers to share in 100% 6

of depreciation costs for the “transmission infrastructure put in place to meet peak 7

demand,” and arbitrarily exclude costs related to rate of return and taxes. 8

That approach is entirely unmoored from a cost-causation analysis. After 9

all, whatever investments the Transmission Owners would need to make to deliver 10

ancillary services would necessarily incur costs associated with both rate of return 11

and taxes. Over a century of regulatory precedent confirms this point.12 Further, 12

there is no precedent by any utility in any proceeding that I am aware of that 13

distinguishes between depreciation on one hand and rate of return and taxes on the 14

other when it comes to the cost of delivering ancillary services. 15

In sum, the Transmission Owners’ proposal to include all depreciation costs 16

for transmission infrastructure, and then arbitrarily exclude the rate of return and 17

tax related to those costs, reveals what the proposal really is: an improvised 18

approach lacking any theoretical foundation and disconnected from any cost- 19

causation principle, designed to produce an outcome that “feels right” to the 20

Transmission Owners.
21
11 Id. at 25.
12 Bluefield Water Works & Improvement Co. v. Public Service Commission, 262 U.S. 679 (1923).

PDF page 29

11
4
Response to Criticisms of E3 Proposal
1
Q12.
DO THE TRANSMISSION OWNERS PROVIDE CRITICISMS OF YOUR
2
PROPOSED
MINIMUM
SYSTEM
METHODOLOGY
FOR
3
DETERMINING THE GRID RELIANCE CHARGE?
4
A12.
Yes. The Transmission Owners provide numerous criticisms of my proposal that I 5

respond to below.
6
Q13.
PLEASE RESPOND TO THE CRITICISM THAT THE MINIMUM
7
SYSTEM METHOD IS TOO COMPLEX.
8
A13.
The Transmission Owners claim that a minimum system method “would be 9

extremely difficult to produce and would potentially result in a spurious level of 10

precision because they would depend largely on subjective determinations.”13 This 11

assertion is unconvincing for two reasons. First, I have already produced an 12

estimate of 6.2% in my initial testimony. FERC could order PJM to use this 13

percentage as a reasonable rate that can be practically implemented. Second, my 14

proposal to use the minimum system method does not seek to apply more precision 15

than the Transmission Owners’ proposal but rather seeks to apply principles to 16

determining the costs associated with the delivery of ancillary services. If the 17

Transmission Owners or the Commission has concerns about how I reached the 18

6.2% estimate, then the right approach is to direct PJM to come up with its own 19

minimum system estimate—not discard the approach in favor of the Transmission 20

Owners’ arbitrary proposal.
21
13 Indicated TO Apr. 24 Response at 24.

PDF page 30

12
Q14.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
1
THAT THE MINIMUM SYSTEM METHOD IS INAPPROPRIATE IN THE
2
CONTEXT OF A GRID RELIANCE CHARGE.
3
A14.
The Transmission Owners broadly assert that the minimum system method is 4

inappropriate to apply within the context of the Grid Reliance Charge. 5

For example, they state that I “propose[] the minimum system methodology 6

without concern for what the Grid Reliance Charge is designed to accomplish.”14 7

However, I am using the minimum system method for exactly what the Grid 8

Reliance Charge is trying to accomplish – to isolate the portion of system costs that 9

Co-Located Load customers should contribute to as the foundation for a just and 10

reasonable rate. This is the same objective that the Transmission Owners purport to 11

share, although I am using a principled approach to determine these costs. 12

They also assert that I “[d]o not demonstrate that there is any correlation 13

between the mere electrical connection of customers and the benefits a Co-Located 14

Load receives from an … ongoing grid connection.”15 That is unfounded for two 15

reasons. First, these customers are not drawing power from the grid. Therefore, by 16

definition, they do not contribute to system components that are sized above 17

minimum levels. Second, while it is true that all customers derive “benefits” from 18

the grid, standard cost-of-service ratemaking does not attempt to charge customers 19

based on the benefits they receive but rather on the costs of providing service. This 20

is exactly what the minimum system framework does – it establishes a clear 21

14 Id. at 26.
15 Id. at 27.

PDF page 31

13
“correlation between the mere electrical connection of customers” and the costs of 1

serving a Co-Located Load customer.
2
The Transmission Owners also contend that I am “advocating for a
3
reclassification of a portion of PJM transmission costs as customer-related even 4

though this reclassification is not only inappropriate but contradicts standard 5

industry literature.”16 This is likewise unfounded. Nowhere do I advocate for any 6

reclassification of costs or changes to existing cost allocation methods already used 7

in PJM. I am simply proposing a method to quantify the cost of delivering ancillary 8

services.
9
Q15.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
10
THAT YOUR PROPOSAL “WOULD END UP SHIFTING TO OTHER
11
USERS OF THE SYSTEM COSTS THAT ARE APPROPRIATELY BORNE
12
BY CO-LOCATED LOAD CUSTOMERS.”17
13
A15.
This criticism not only is misplaced, but in fact the Transmission Owners’ proposal 14

is the one that inappropriately shifts costs—from other users of the system to Co- 15

Located Load customers. In the context of the electricity system, cost-shifting can 16

occur when certain customers do not pay their fair share of system costs, causing 17

those costs to be borne by other customers. The Transmission Owners’ claim of 18

cost-shifting relies on the assumption that their calculated rate is the appropriate 19

fair share that Co-Located Loads should pay, when it is in fact not the appropriate 20

fair share because it forces customers that do not impose demand on the grid to pay 21

16 Exhibit No. PTO-0005 at 18:2-4.
17 Indicated TO Apr. 24 Response at 25.

PDF page 32

14
for transmission components that are sized to serve peak demand. Instead, it would 1

be correct to say that the Transmission Owners’ proposal would shift costs to Co- 2

Located Load customers by forcing Co-Located Load customers to pay costs 3

associated with sizing up the grid to deliver energy, when Co-Located Load 4

customers do not cause those costs at all.
5
Q16.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
6
THAT THERE IS NOT PRECEDENT FOR APPLYING THE MINIMUM
7
SYSTEM METHOD IN THE CONTEXT OF THE TRANSMISSION
8
SYSTEM.
9
A16.
The Transmission Owners acknowledge the minimum system method has
10
precedent in the context of the distribution system. 18  It is a well-accepted 11

framework for applying cost-causation principles. There is no reason that it cannot 12

similarly be applied in the context of the transmission system—there has just not 13

previously been any need to do so. After all, this proceeding was designed to 14

address the emerging and somewhat novel challenge of interconnecting co-located 15

new large loads to the transmission system, which have grown rapidly in recent 16

years.19 To address this new problem, it is logical to use a minimum system method 17

that is well-accepted in an analogous context.
18
By contrast, the Transmission Owners’ proposal has no precedent that I am 19

aware of in any portion of the electricity sector (including distribution), by any 20

utility, in any geography. My approach has far greater precedential support than 21

18 Id. at 25.
19 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 65 (2025). (“the surge of interest in co-location arrangements in PJM has put before the Commission several significant and novel issues”).

PDF page 33

15
theirs. It is better to rely on principles and methods that have been used in other 1

applications rather than an arbitrary method with no precedent at all. 2

Q17.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
3
THAT YOUR ASSUMPTIONS IN DEVELOPING THE MINIMUM
4
SYSTEM RESULT “VIOLATE[S] THE ENGINEERING REALITY OF
5
THE TRANSMISSION SYSTEM.”20
6
A17.
The Transmission Owners posit that my “selection of minimum system components 7

… violates the engineering reality of the transmission system.”21 For example, they 8

state that “a distribution wood pole cannot perform the function of a transmission 9

structure in that it cannot support required voltages, cannot meet clearance 10

requirements, and cannot handle mechanical loads (e.g., span length, conductor 11

weight).”22
12
This criticism is not valid because a minimum system is a theoretical system 13

designed to deliver a de minimis amount of electricity as opposed to a system 14

designed to serve peak demand. As a result, everything is smaller in a minimum 15

system. Voltages are lower, conductors are lighter, etc. Therefore, transmission 16

structures do not need to be sized with the same clearance or to handle the 17

mechanical loads of today’s actual transmission system. Therefore, my 18

assumptions are entirely consistent with the engineering reality of a minimum 19

system.
20
20 Exhibit No. PTO-0005 at 19:17.
21 Id. at 19:12-17.
22 Indicated TO Apr. 24 Response at 28.

PDF page 34

16
If anything, my assumptions are conservatively high because they assume 1

the same number of conductor miles, structures, and substations as the current PJM 2

system. The existence of many of these components themselves are driven by 3

redundancies for contingencies associated with serving peak demand, so it is 4

actually possible that a minimum system would not only have smaller components 5

but also fewer components. Because my analysis does not assume fewer 6

components, it is conservatively high.
7
In any event, if the Transmission Owners disagree with what components 8

make up a minimum system, then they can provide an alternative proposal for the 9

components that should be considered under this methodology. Instead, they reject 10

the framework altogether. And if the Commission believes there should be further 11

consideration of what constitutes a minimum system, then (as my direct testimony 12

recommends) the Commission can order PJM to conduct a minimum system study. 13

PJM may have additional data that is not publicly available, and PJM may find it 14

appropriate to use different assumptions. While I calculated a 6.2% result, my direct 15

testimony acknowledges that a result as high as 10% may be reasonable. 16

Q18.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
17
THAT THE RESULTS OF THE MINIMUM SYSTEM METHOD ARE
18
“BASED ENTIRELY ON REPLACEMENT COST” AND “[DO] NOT
19
INCORPORATE
RATE OF RETURN,
TAXES,
DEPRECIATION,
20

PDF page 35

17
OPERATIONS AND MAINTENANCE, OR ANY OTHER ELEMENT OF
1
THE REVENUE REQUIREMENT.”23
2
A18.
These assertions reflect a misunderstanding of the minimum system method and 3

how its results should be used. The “replacement cost” that I use in my study is 4

equivalent to the “book cost” that seminal industry literature recommends.24 The 5

minimum system uses the ratio of replacement costs for both the minimum system 6

and actual system to identify what portion of the entire revenue requirement is 7

attributable to the minimum system. It does not omit any element of the revenue 8

requirement. Nonetheless, I appreciate the Transmission Owners highlighting the 9

importance of incorporating all elements of the revenue requirement, which their 10

method explicitly does not do. The Transmission Owners’ criticism would 11

therefore be more appropriately applied to their own proposal.
12
Q19.
PLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM
13
THAT IT NOT APPROPRIATE TO USE THE RESULTS OF THE
14
MINIMUM SYSTEM METHOD TO DEVELOP A DEMAND CHARGE
15
AND THAT APPLYING THE RESULTS OF THE MINIMUM SYSTEM
16
METHOD DIRECTLY TO THE NITS RATE “VIOLAT[ES] COST
17
CAUSATION PRINCIPLES.”25
18
A19.
The Transmission Owners’ criticism here appears to be largely based on the fact 19

that the minimum system method is typically used to identify customer-driven 20

costs. The fact that the results of a minimum system study can be used in this way 21

23 Exhibit No. PTO-0005 at 26:8-13.
24 NARUC, Electric Utility Cost Allocation Manual at 90-91 (1992).
25 Exhibit No. PTO-0005 at 24:11.

PDF page 36

18
does not mean that it can only be used in this way. As I have outlined extensively 1

above, the minimum system method provides a principled basis for isolating the 2

costs required to deliver ancillary services consistent with cost-causation principles. 3

Q20.
PLEASE RESPOND TO THE TRANSMISSION OWNERS' CRITICISM
4
THAT YOUR PROPOSED METHODOLOGY WOULD BE “EXTREMELY
5
CHALLENGING TO IMPLEMENT.”26
6
A20.
The Transmission Owners’ criticism is inconsistent with the minimum system 7

method's established track record. The method has been applied at the distribution 8

level across numerous jurisdictions across North America for decades, where 9

regulators have repeatedly found it to be both workable and sufficiently precise for 10

ratemaking purposes. Further, I have already developed a reasonable estimate of 11

the minimum system percentage outlined in my direct testimony. A methodology 12

with significant precedent for which a reasonable study has already been completed 13

should not be characterized as “extremely challenging to implement.” 14

15
26 Indicated TO Apr. 24 Response at 24.

PDF page 37

19
5
Summary
1
Q21.
PLEASE SUMMARIZE YOUR TESTIMONY.
2
A21.
Yes. The key takeaways of my testimony are:
3

The concept of a Grid Reliance Charge is reasonable to ensure that Co-Located 4

Load customers contribute to the cost of delivering ancillary services; 5


The Transmission Owners’ proposed Grid Reliance Charge is unjust and 6

unreasonable because it violates cost causation principles by charging Co- 7

Located Load customers for costs they do not impose on the system, namely 8

100% of depreciation costs that include the cost of sizing transmission system 9

components to serve peak load when Co-Located Load customers by definition 10

do not impose any load on the system;
11

The Transmission Owners’ proposal to compensate for this overcharging by 12

undercharging for rate of return and taxes is not “practical”, it is arbitrary and 13

unrelated to the cost of delivering ancillary services;
14

The Transmission Owners’ criticisms of my proposal to use the minimum 15

system method are without merit, and in several cases their criticisms are more 16

applicable to their own proposal than to mine; and
17

The minimum system method is a just and reasonable approach for calculating 18

the Grid Reliance Charge, because it provides a principled, cost-causation basis 19

for isolating the portion of the system necessary to deliver ancillary services. 20

PDF page 38

20
Q22.
DOES THIS CONCLUDE YOUR TESTIMONY?
1
A22.
Yes
2

PDF page 39

VERIFICATION
I declare under penalty of perjury that the foregoing Reply Testimony is true and correct to the best of my knowledge, information, and belief.

Executed this 11th day of May, 2026.
________________________
Zachary Ming